Construction method of waterproof lightning protection clamp assembly of aluminum plate curtain wall

CN116722509BActive Publication Date: 2026-10-09GAOCHENG LIANNAN CONSTR INSTALLATION CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310625156.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-05-30
Publication Date
2026-10-09
Estimated Expiration
2043-05-30

AI Technical Summary

Benefits of technology

[0025] The waterproof lightning protection clip assembly of this invention adds a waterproof cover and a waterproof gasket, and uses weather-resistant sealant for bonding or sealing of the joint gaps, effectively solving the water leakage problem caused by shrinkage or cracking of the weather-resistant sealant in the past. It adopts the construction method of rebar installation, which can quickly install the lightning protection pole and solves the problem of the expansion sleeve being difficult to adjust, making it easy to straighten. In addition, the lower fastener of the lightning protection fastener is threaded to the lightning protection pole, which facilitates the installation of aluminum panel curtain walls, waterproof gaskets and waterproof covers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116722509B_ABST
    Figure CN116722509B_ABST
Patent Text Reader

Abstract

The application discloses a kind of construction methods of aluminum plate curtain wall waterproof lightning protection clamp subassembly, it is related to the technical field of engineering construction method, specifically includes the following steps: S1 according to the positioning of outer wall vertical aluminum plate curtain wall line control;S2 punch, plant lightning rod;S3 horizontal aluminum plate curtain wall cutting, installation, glue;S4 install waterproof gasket and waterproof cover, glue again;S5 carry out water test;S6 install lightning belt round steel, adjust.The application adopts the construction mode of planting bar, fast plants lightning rod, solves the situation that previous expansion sleeve is not good adjustment, is convenient to straighten;Waterproof cover and waterproof gasket are increased, and are bonded by weatherproof sealant and the sealing of gap at spigot, effectively solve the leakage problem caused by weatherproof sealant shrinkage or cracking.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the technical field of engineering construction methods, specifically to a construction method for an aluminum panel curtain wall waterproof lightning protection clip assembly. Background Technology

[0002] Traditional lightning protection clips typically consist of a pole, an upper clip, a lower clip, and an expansion sleeve. The lower clip is connected to one end of the pole, and the upper clip is installed to the lower clip using screws and nuts. An expansion sleeve is installed on the threaded part of the other end of the pole, with nuts and plugs at both ends. The pole with the expansion sleeve is fixed within the building structure and inserted into the aluminum curtain wall. However, during construction, the aluminum curtain wall needs to be cut with corresponding insertion holes for the lightning protection pole. To facilitate construction, the holes are often large, leaving empty spaces inside. To facilitate applying sealant, workers often use waste paper or supports to prop up these holes. Due to the thermal expansion and contraction of the weather-resistant sealant, cracks form, creating holes or gaps of varying sizes in the aluminum panel. In summer, with heavy rainfall, this can lead to leaks, causing widespread dampness on the exterior wall and consequently, dampness on the interior ceiling. Furthermore, the expansion sleeve is difficult to align perfectly after installation. Therefore, the applicant proposes a construction method for a waterproof lightning protection clip assembly to address these problems. Summary of the Invention

[0003] The technical problem to be solved by the present invention is to provide a construction method for an aluminum panel curtain wall waterproof lightning protection clip assembly, which addresses the above-mentioned shortcomings of the prior art.

[0004] To achieve its purpose, the present invention adopts the following technical solution:

[0005] A construction method for a waterproof lightning protection clip assembly for an aluminum panel curtain wall, the lightning protection clip assembly including a lightning protection pole, a lightning protection fastener, a waterproof cover and a waterproof gasket, the lightning protection fastener including an upper fastener, a lower fastener and a connecting rod, the lower fastener being fixedly connected to an internal threaded rod on one side, the internal threaded rod being provided with an internal thread, and the end of the lightning protection pole being provided with an external thread;

[0006] The construction method for the above-mentioned lightning protection clip assembly includes the following steps:

[0007] S1 Lay out the control line: Based on the positioning of the vertical aluminum panel curtain wall, measure the center line control point of the horizontal aluminum panel curtain wall, and lay out the center control line based on the control point;

[0008] S2 Lightning Protection Pole Installation: Drill holes with a power drill, clean the holes with a blower, run the wire, and use epoxy anchoring adhesive to install the lightning protection pole in the hole;

[0009] S3 Installation of Horizontal Aluminum Panel Curtain Wall: Weld the curtain wall frame, cut out corresponding slots on the aluminum panel according to the position of the lightning protection pole, and then install the aluminum panel horizontally on the lightning protection pole. Apply weather-resistant sealant in the slot gaps to bond the horizontal aluminum panel to the lightning protection pole.

[0010] S4 Installation of Waterproof Gaskets and Waterproof Covers: After applying weather-resistant sealant to the waterproof gasket, insert it into the lightning rod and attach it to the horizontal aluminum curtain wall panel. Press the waterproof gasket until the weather-resistant sealant is squeezed out of the waterproof gasket. Then insert the waterproof cover into the lightning rod and apply weather-resistant sealant to the connection between the upper opening of the waterproof cover and the lightning rod, and the connection between the lower opening of the waterproof cover and the aluminum curtain wall panel.

[0011] S5 undergoes a water spray test: After the weather-resistant sealant has cured, perform a water spray treatment; if there is no leakage, it is acceptable.

[0012] S6 Installation of Lightning Protection Strip Round Steel: Install lightning protection fasteners at the end of the lightning protection pole, and thread the lightning protection strip round steel between the lower fastener and the upper fastener.

[0013] Preferably, step S1, which involves releasing the control line, is as follows:

[0014] S1.1 Measure the position of the center line of the horizontal component from the vertical aluminum curtain wall panel of the exterior wall inward and mark it;

[0015] S1.2 Draw the construction line, mark the centerline control points according to the construction line, and use a chalk line to mark the centerline.

[0016] Preferably, in step S2:

[0017] S2.1 According to the requirements of the lightning protection specification, a lightning protection clamp shall be installed at a distance of no more than 1 meter. The corresponding holes shall be drilled in sequence using a 220V handheld impact drill. The drill bit of the impact drill shall be one size larger than the diameter of the lightning protection pole.

[0018] S2.2 Use a 220V hair dryer to clean the holes;

[0019] S2.3 Fill the handheld glue gun with epoxy injection adhesive and inject it into the hole. After curing, proceed to the next step.

[0020] Preferably, the maximum diameter of the aluminum plate cutting slot in step S3 is ≤50mm.

[0021] Preferably, step S6, which involves installing the round steel strip for the lightning protection belt, is as follows:

[0022] S6.1 Install a fastener at the end of the lightning protection pole, that is, tighten the internal thread of the internal thread rod with the external thread of the lightning protection pole;

[0023] S6.2 Straighten the round steel of the lightning protection strip. Place the round steel of the lightning protection strip on the lower fastener, and then fasten the upper fastener on top of the round steel of the lightning protection strip. Tighten the screws and nuts to the lower fastener and adjust the position of the round steel of the lightning protection strip to make it form a straight line.

[0024] The beneficial effects of this invention are:

[0025] The waterproof lightning protection clip assembly of this invention adds a waterproof cover and a waterproof gasket, and uses weather-resistant sealant for bonding or sealing of the joint gaps, effectively solving the water leakage problem caused by shrinkage or cracking of the weather-resistant sealant in the past. It adopts the construction method of rebar installation, which can quickly install the lightning protection pole and solves the problem of the expansion sleeve being difficult to adjust, making it easy to straighten. In addition, the lower fastener of the lightning protection fastener is threaded to the lightning protection pole, which facilitates the installation of aluminum panel curtain walls, waterproof gaskets and waterproof covers. Attached Figure Description

[0026] For ease of explanation, the present invention will be described in detail below with reference to specific embodiments and accompanying drawings.

[0027] Figure 1 This is a flowchart of the construction steps in this embodiment;

[0028] Figure 2 This is a schematic diagram of the structure and installation of the lightning protection clamp assembly in this embodiment.

[0029] In the picture:

[0030] 1-Lightning protection pole;

[0031] 2-Lightning protection fastener; 201-Upper fastener; 202-Lower fastener; 203-Connecting rod;

[0032] 3-Waterproof cover; 301-Top plate; 302-Side plate;

[0033] 4-Waterproof gasket; 5-Aluminum panel curtain wall; 6-Building structure. Detailed Implementation

[0034] The following are specific embodiments of the present invention described in conjunction with the accompanying drawings, further illustrating the technical solutions of the present invention. However, the present invention is not limited to these embodiments. Specific details, such as particular configurations and components, are provided in the following description merely to aid in a comprehensive understanding of the embodiments of the present invention. Therefore, those skilled in the art should understand that various changes and modifications can be made to the embodiments described herein without departing from the scope and spirit of the present invention. Furthermore, for clarity and brevity, descriptions of known functions and structures have been omitted.

[0035] It should be noted that, unless otherwise specified, the embodiments and features described in this invention can be combined with each other.

[0036] like Figure 2 The example shown is a waterproof lightning protection clip assembly, which includes a lightning protection pole 1, a lightning protection fastener 2, a waterproof cover 3, and a waterproof gasket 4. The lightning protection fastener 2 includes an upper fastener 201, a lower fastener 202, and a connecting rod 203. An internal threaded rod is fixedly connected to one side of the lower fastener 202. The internal threaded rod is provided with an internal thread, and the end of the lightning protection pole 1 is provided with an external thread.

[0037] like Figure 1 The above-mentioned lightning protection clip assembly is shown in the following steps:

[0038] S1 Lay out the control line: Based on the positioning of the vertical aluminum panel curtain wall 5, measure the center line control point of the horizontal aluminum panel curtain wall 5, and lay out the center control line based on the control point;

[0039] S2 Lightning Protection Pole 1: Drill holes with a power drill, clean the holes with a blower, pull the wire, and plant the lightning protection pole 1 in the holes using epoxy anchoring adhesive.

[0040] S3 Installation of horizontal aluminum panel curtain wall 5: Weld the curtain wall frame, cut out the corresponding slots on the aluminum panel according to the position of the lightning rod 1, and then install the aluminum panel horizontally on the lightning rod 1. Apply weather-resistant sealant in the slot gaps to bond the horizontal aluminum panel to the lightning rod 1.

[0041] S4 Installation of Waterproof Gasket 4 and Waterproof Cover 3: After applying weather-resistant sealant to the waterproof gasket 4, insert it into the lightning rod 1 and stick it on the horizontal curtain wall aluminum panel. Press the waterproof gasket until the weather-resistant sealant is squeezed out of the waterproof gasket. Then insert the waterproof cover 3 into the lightning rod 1. Apply weather-resistant sealant to the connection between the upper opening of the waterproof cover 3 and the lightning rod 1, and the connection between the lower opening of the waterproof cover 3 and the aluminum panel curtain wall 5.

[0042] S5 undergoes a water spray test: After the weather-resistant sealant has cured, perform a water spray treatment; if there is no leakage, it is acceptable.

[0043] S6 Installation of lightning protection strip round steel: Install lightning protection fastener 2 at the end of lightning protection pole 1, and thread the lightning protection strip round steel between the lower fastener 202 and the upper fastener 201.

[0044] The specific steps for releasing the control line in step S1 of this embodiment are as follows:

[0045] S1.1 Measure the position of the center line of the horizontal component from the vertical aluminum curtain wall panel of the exterior wall inward and mark it;

[0046] S1.2 Draw the construction line, mark the centerline control points according to the construction line, and use a chalk line to mark the centerline.

[0047] The specific steps for planting the lightning protection pole 1 in step S2 of this embodiment are as follows:

[0048] S2.1 According to the requirements of the lightning protection specification, a lightning protection clamp shall be installed at a distance of no more than 1 meter. The corresponding holes shall be drilled in sequence using a 220V handheld impact drill. The drill bit of the impact drill shall be one size larger than the diameter of the lightning protection pole 1.

[0049] S2.2 Use a 220V hair dryer to clean the holes;

[0050] S2.3 Fill the handheld glue gun with epoxy injection adhesive and inject it into the hole. After curing, proceed to the next step.

[0051] In step S3 of this embodiment, the maximum diameter of the aluminum plate cutting slot is ≤50mm.

[0052] The specific steps for installing the lightning protection strip round steel in step S6 of this embodiment are as follows:

[0053] S6.1 Install the lower fastener 202 at the end of the lightning protection pole 1, that is, tighten the internal thread of the internal thread rod with the external thread of the lightning protection pole 1;

[0054] S6.2 Straighten the lightning protection strip round steel. Place the lightning protection strip round steel on the lower fastener 202, and then fasten the upper fastener 201 on top of the lightning protection strip round steel. Tighten the screws and nuts to the lower fastener 202 and adjust the position of the lightning protection strip round steel to form a straight line.

[0055] It should be noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to limit the exemplary embodiments according to this application. As used herein, the singular form is intended to include the plural form as well, unless the context clearly indicates otherwise. Furthermore, it should be understood that when the terms "comprising" and / or "including" are used in this specification, they indicate the presence of features, steps, operations, devices, components, and / or combinations thereof.

[0056] In the description of this application, it should be understood that the terms "upper" and "lower" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.

[0057] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one of that feature. In the description of this application, "multiple" means at least two, such as two, three, etc., unless otherwise explicitly specified.

[0058] The specific embodiments described herein are merely illustrative examples of the spirit of this application. Those skilled in the art to which this application pertains may make various modifications or additions to the described specific embodiments or use similar methods to substitute them, without departing from the spirit of this application or exceeding the scope defined by the appended claims.

Claims

1. A construction method for a waterproof lightning protection clip assembly for aluminum panel curtain walls, characterized in that, The lightning protection clamp assembly includes a lightning protection pole (1), a lightning protection fastener (2), a waterproof cover (3), and a waterproof gasket (4). The lightning protection fastener (2) includes an upper fastener (201), a lower fastener (202), and a connecting rod (203). The lower fastener (202) is fixedly connected to an internal thread rod on one side. The internal thread rod is provided with an internal thread, and the end of the lightning protection pole (1) is provided with an external thread. The construction method for the above-mentioned lightning protection clip assembly includes the following steps: S1 Release the control line: Based on the positioning of the vertical aluminum panel curtain wall (5), measure the center line control point of the horizontal aluminum panel curtain wall (5), and release the center control line based on the control point; S2 Planting of lightning protection poles (1): Drill holes with a hand drill, clean the holes with a blower, pull the wire, and plant the lightning protection poles (1) in the holes using epoxy anchoring adhesive; S3 Installation of horizontal aluminum panel curtain wall (5): Weld the curtain wall frame, cut out the corresponding slots on the aluminum plate according to the position of the lightning rod (1), and then install the aluminum plate horizontally on the lightning rod (1). Apply weather-resistant sealant in the slot gaps to bond the horizontal aluminum plate to the lightning rod (1). S4 Install waterproof gasket (4) and waterproof cover (3): After applying weather-resistant sealant to the waterproof gasket (4), insert it into the lightning rod (1) and stick it on the horizontal curtain wall aluminum plate. Press the waterproof gasket until the weather-resistant sealant is squeezed out of the waterproof gasket. Then insert the waterproof cover (3) into the lightning rod (1) and apply weather-resistant sealant at the connection between the upper opening of the waterproof cover (3) and the lightning rod (1) and the connection between the lower opening of the waterproof cover (3) and the aluminum plate curtain wall (5). S5 undergoes a water spray test: After the weather-resistant sealant has cured, perform a water spray treatment; if there is no leakage, it is acceptable. S6 Install lightning protection strip round steel: Install lightning protection fastener (2) at the end of lightning protection pole (1) and thread the lightning protection strip round steel between the lower fastener (202) and the upper fastener (201).

2. The construction method of the aluminum panel curtain wall waterproof lightning protection clip assembly according to claim 1, characterized in that, The steps for releasing the control line in step S1 are as follows: S1.1 Measure the position of the center line of the horizontal component from the vertical aluminum curtain wall panel of the exterior wall inward and mark it; S1.2 Draw the construction line, mark the centerline control points according to the construction line, and use a chalk line to mark the centerline.

3. The construction method of an aluminum panel curtain wall waterproof lightning protection clip assembly according to claim 1, characterized in that, In step S2: S2.1 According to the requirements of the lightning protection specification, a lightning protection clamp shall be installed at a distance of no more than 1 meter. The corresponding holes shall be drilled in sequence using a 220V handheld impact drill. The drill bit of the impact drill shall be one size larger than the diameter of the lightning protection pole (1). S2.2 Use a 220V hair dryer to clean the holes; S2.3 Fill the handheld glue gun with epoxy injection adhesive and inject it into the hole. After curing, proceed to the next step.

4. The construction method of an aluminum panel curtain wall waterproof lightning protection clip assembly according to claim 1, characterized in that, In step S3, the maximum diameter of the aluminum plate cutting slot is ≤50mm.

5. The construction method of an aluminum panel curtain wall waterproof lightning protection clip assembly according to claim 1, characterized in that, The steps for installing the lightning protection strip round steel in step S6 are as follows: S6.1 Install the lower fastener (202) at the end of the lightning protection pole (1), that is, tighten the internal thread of the internal thread rod with the external thread of the lightning protection pole (1); S6.2 Straighten the lightning protection strip round steel. Place the lightning protection strip round steel on the lower fastener (202), and then fasten the upper fastener (201) on top of the lightning protection strip round steel. Tighten the screws and nuts to the lower fastener (202) and adjust the position of the lightning protection strip round steel to form a straight line.