Method for installing composite profile, storage medium and electronic device
By determining the installation line along the vertical direction on the inner wall of the tunnel and fixing the arch section and side section of the composite profile, combined with the circulating grouting method and sealing the connection parts, the problem of low efficiency in tunnel reinforcement construction was solved, achieving efficient reinforcement in a limited space and time, and improving the tunnel's deformation resistance and safety.
Patent Information
- Application Number
- CN202310745789.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-21
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-06-21
AI Technical Summary
Existing technologies make it difficult to efficiently construct reinforcement structures within a limited space and time without affecting the normal operation of existing lines and equipment within the tunnel.
The composite profile installation method involves first determining the installation line on the inner wall of the tunnel along the direction perpendicular to the tunnel extension, and then opening a central positioning hole at the intersection. The arch section and side section are fixed along the installation line, and then grouting and sealing of the connection parts are carried out by circulating grouting.
It improves the installation efficiency of composite profiles, ensures that tunnel reinforcement construction is completed within a limited time, enhances the tunnel's resistance to deformation, reduces defects, ensures traffic safety, and extends the tunnel's service life.
Smart Images

Figure CN116771375B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to tunnel construction technology, particularly to the installation technology of composite profiles, and more specifically, to the installation method, storage medium, and electronic equipment of composite profiles. Background Technology
[0002] With the rapid development of national economic construction, various highway, railway, and subway tunnel facilities are becoming increasingly common. During long-term operation, these tunnel facilities inevitably develop various defects due to factors such as material aging, operating environment changes, and external environmental factors. These defects mainly manifest as cracks, water leakage, spalling, and convergence deformation. For example, cracks of varying depths appear on the surface of the tunnel lining, water leakage occurs around the cracks, or the lining rings and longitudinal joints open, and the cross-section converges and deforms. The continuous development of these defects damages the integrity of the tunnel structure, reduces the load-bearing capacity of the tunnel structure, and also poses hidden dangers to the safe operation of trains. It is urgent to treat these tunnel defects.
[0003] In realizing the concept of this invention, the inventors discovered at least the following problems in the related technologies: the space in the tunnel area to be reinforced is limited, making construction difficult, especially with a short construction period, and the tunnel reinforcement construction cannot affect the normal operation of the original lines and equipment inside the tunnel. Currently, it is difficult to efficiently construct related reinforcement structures and installation processes within a limited space and time without affecting the normal operation of the original lines and equipment inside the tunnel, and to meet the requirements of the tunnel operation and management unit for tunnel reinforcement. Summary of the Invention
[0004] In view of this, the technical problem to be solved by the present invention is to provide an installation method, storage medium and electronic device for composite profiles, which solves the problem in the related technology that it is difficult to efficiently construct reinforcement structures and installation processes in a limited space and within a limited construction time without affecting the normal operation of the original lines and equipment in the tunnel.
[0005] To address the aforementioned technical problems, a specific embodiment of the present invention provides a method for installing a composite profile, comprising: determining an installation line on the inner wall of a tunnel perpendicular to the tunnel's extension direction; opening a first central positioning hole at the intersection of the installation line and the arch line of the inner wall of the tunnel; fixing the arch section of the composite profile onto the first central positioning hole along the installation line, wherein the composite profile is composed of the arch section, a left side section, and a right side section; and fixing the left side section and the right side section of the composite profile onto the inner wall of the tunnel along the installation line.
[0006] Another aspect of the present invention provides a computer-readable storage medium storing computer-executable instructions, which, when executed by a processor, are used to implement the method of the present invention.
[0007] Another aspect of the present invention provides a computer program, which includes computer-executable instructions that, when executed, implement the method of the present invention.
[0008] Another aspect of the present invention provides an electronic device, including one or more processors and a storage device, wherein the storage device is used to store executable instructions, which, when executed by the processor, implement the method of the present invention.
[0009] According to the above embodiments of the present invention, by first determining the installation position of the arch section of the composite profile and following the principle of installing the arch section first and then the two side sections of the composite profile, the problems of low installation efficiency and slow construction of composite profiles in related technologies can be solved at least partially. Therefore, it is possible to achieve the technical effect of efficient construction in a limited space and within a limited construction time without affecting the normal operation of the original lines and equipment in the tunnel.
[0010] It should be understood that the above general description and the following specific embodiments are merely exemplary and illustrative, and do not limit the scope of the invention. Attached Figure Description
[0011] The accompanying drawings, which are part of the specification of this invention, illustrate exemplary embodiments of the invention. The drawings, together with the description in the specification, serve to illustrate the principles of the invention.
[0012] Figure 1 This is a schematic diagram of a composite profile installed on the inner wall of a tunnel, as provided in a specific embodiment of the present invention.
[0013] Figure 2 This is a first schematic flowchart illustrating an installation method for a composite profile, provided as a specific embodiment of the present invention.
[0014] Figure 3 This is a second schematic flowchart illustrating an installation method for a composite profile, provided as a specific embodiment of the present invention.
[0015] Figure 4 This is a flowchart illustrating a circulating grouting method provided in a specific embodiment of the present invention.
[0016] Figure 5 The third schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0017] Figure 6 This is a schematic flowchart illustrating a sealing composite profile connection part provided for a specific embodiment of the present invention.
[0018] Figure 7The fourth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0019] Figure 8 The fifth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0020] Figure 9 The sixth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0021] Figure 10 This is a schematic flowchart illustrating the processing of handholes and misalignments on the inner wall of a tunnel, provided as a specific embodiment of the present invention.
[0022] Figure 11 The seventh schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0023] Figure 12 The eighth schematic flowchart illustrates an installation method for a composite profile, provided as a specific embodiment of the present invention.
[0024] Figure 13 The ninth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0025] Figure 14 The tenth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0026] Explanation of reference numerals in the attached figures:
[0027] T tunnel inner wall U-shaped arch section
[0028] L left segment R right segment
[0029] C First center positioning hole H Fixing hole Detailed Implementation
[0030] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the spirit of the contents disclosed in the present invention will be clearly explained below with reference to the accompanying drawings and detailed description. After understanding the embodiments of the present invention, any person skilled in the art can make changes and modifications based on the technology taught in the present invention without departing from the spirit and scope of the present invention.
[0031] The illustrative embodiments and descriptions of the present invention are used to explain the invention, but are not intended to limit the invention. Furthermore, elements / components using the same or similar reference numerals in the drawings and embodiments are used to represent the same or similar parts.
[0032] The terms "first," "second," etc., used in this document are not intended to specifically refer to order or sequence, nor are they intended to limit the invention. They are merely used to distinguish elements or operations described using the same technical terms.
[0033] The directional terms used in this article, such as up, down, left, right, front, or back, are for reference only when referring to the accompanying drawings. Therefore, the use of directional terms is for illustrative purposes and not to limit this work.
[0034] The terms “include,” “including,” “have,” “contain,” etc., used in this article are all open-ended terms, meaning that they include but are not limited to.
[0035] The term "and / or" as used herein includes any or all of the things mentioned.
[0036] The term "multiple" in this article includes "two" and "more than two"; the term "multiple groups" in this article includes "two groups" and "more than two groups".
[0037] The terms "approximately," "about," etc., used herein are intended to modify any quantity or error that may vary slightly, but these slight variations or errors do not change the essence of the quantity or error. Generally, the range of slight variations or errors modified by such terms may be 20% in some embodiments, 10% in others, 5% in still others, or other values. Those skilled in the art should understand that the aforementioned values can be adjusted according to actual needs and are not limited thereto.
[0038] All terms used herein (including technical and scientific terms) have the meanings commonly understood by those skilled in the art, unless otherwise defined. It should be noted that the terms used herein are to be interpreted in a manner consistent with the context of this specification, and not in an idealized or overly rigid way.
[0039] When expressions such as "at least one of A, B, and C" are used, they should generally be interpreted in accordance with the meaning commonly understood by those skilled in the art (e.g., "a system having at least one of A, B, and C" should include, but is not limited to, systems having A alone, having B alone, having C alone, having A and B, having A and C, having B and C, and / or having A, B, and C, etc.). When expressions such as "at least one of A, B, or C" are used, they should generally be interpreted in accordance with the meaning commonly understood by those skilled in the art (e.g., "a system having at least one of A, B, or C" should include, but is not limited to, systems having A alone, having B alone, having C alone, having A and B, having A and C, having B and C, and / or having A, B, and C, etc.). Those skilled in the art should also understand that any conjunction and / or phrase that substantially arbitrarily indicates two or more optional items, whether in the specification, claims, or drawings, should be understood to indicate the possibility of including one of these items, either of these items, or both items. For example, the phrase “A or B” should be understood as including the possibility of “A” or “B”, or “A and B”.
[0040] Figure 1 This is a schematic diagram of a composite profile installed on the inner wall of a tunnel, as provided in a specific embodiment of the present invention.
[0041] like Figure 1 As shown, the composite profile can be composed of an arch section U, a left section L, and a right section R. The left section L can be composed of at least one composite profile sub-segment, and the right section R can also be composed of at least one composite profile sub-segment. The composite profile is fixed to the tunnel inner wall T to reinforce the tunnel lining, reduce the occurrence of lining defects, and ensure traffic safety and the tunnel's service life. The arch section U is fixed using reinforcing bolts through the first central positioning hole C, and the left section L and right section R are fixed using reinforcing bolts through the fixing holes H. For technicians in this field, a thorough understanding and learning of the product characteristics, installation conditions, installation procedures, and quality assurance measures of prefabricated composite profiles is an important prerequisite for ensuring the high quality, high efficiency, and comprehensive safety of prefabricated composite profiles.
[0042] Figure 2 This is a first schematic flowchart illustrating an installation method for a composite profile, provided as a specific embodiment of the present invention.
[0043] like Figure 2 As shown, the installation method for composite profiles may include the following operations S101 to S104:
[0044] In operation S101: Determine an installation line on the inner wall of the tunnel along the direction perpendicular to the tunnel extension.
[0045] In embodiments of the present invention, the tunnel inner wall, i.e., the tunnel interior lining, has an installation line along which is approximately semi-circular or larger than semi-circular. Composite profiles can be installed along this installation line.
[0046] Then, in operation S102: a first center positioning hole is opened at the intersection of the installation line and the arch line of the tunnel inner wall.
[0047] In embodiments of the present invention, the arch line of the tunnel inner wall extends along the tunnel direction and may be a straight line or a curve. An intersection point is formed between the installation line and the arch line, and this intersection point can be used as the first center positioning hole.
[0048] Secondly, in operation S103: the arch section of the composite profile is fixed to the first central positioning hole along the installation line, wherein the composite profile is composed of the arch section, the left side section and the right side section.
[0049] In embodiments of the present invention, the arch section can be fixed to the tunnel inner wall along the installation line using bolts through the first central positioning hole. In addition to the first central positioning hole, the arch section can be further reinforced through fixing holes. The composite profile can be composed of the arch section, the left side section, and the right side section. The left side section and / or the right side section can further be composed of one, two, or more composite profile sub-segments. The composite profile can include at least one of grouted metal cavities, grouted composite profiles, non-grouted metal cavities, and non-grouted composite profiles. The cross-sectional shape of the composite profile can include at least one of circular, triangular, square, rectangular, polygonal, U-shaped, and trapezoidal shapes.
[0050] Next, in operation S104: fix the left and right sections of the composite profile to the inner wall of the tunnel along the installation line.
[0051] In an embodiment of the present invention, the left side segment is connected to the arch segment, and the right side segment is also connected to the arch segment. The arch segment, the left side segment, and the right side segment are connected end to end and fixed to the inner wall of the tunnel along the installation line.
[0052] In embodiments of the present invention, the arched section is installed first, followed by the side sections. For example, the arched section can be installed first, then the left side section, and then the right side section. Alternatively, the arched section can be installed first, then the right side section, and then the left side section. Or, the arched section can be installed first, followed by the left and right side sections simultaneously, i.e., the work proceeds synchronously from the arched section towards both ends. This significantly shortens the construction time of the composite profile, improves construction efficiency, and enables efficient construction within a limited timeframe.
[0053] Figure 3 This is a second schematic flowchart illustrating an installation method for a composite profile, provided as a specific embodiment of the present invention.
[0054] like Figure 3 As shown, after operation S104 fixes the left and right sections of the composite profile to the inner wall of the tunnel along the installation line, the installation method of the composite profile may further include:
[0055] In operation S105: Grout is injected into the composite profile using the circulating grouting method.
[0056] In embodiments of the present invention, if the composite profile is a grouting metal cavity or a grouting composite profile, grout can be injected into the composite profile using a circulating grouting method (i.e., circulating grouting method). The grout can be mortar, a cement-sand mixture, chemical fillers, etc. Using the circulating grouting method to inject grout into the composite profile can fully fill it, enhancing its compressive strength. Installing grouted composite profiles inside the tunnel can improve the tunnel's resistance to deformation, reduce the occurrence of lining defects, ensure traffic safety, and extend the tunnel's service life.
[0057] Figure 4 This is a flowchart illustrating a circulating grouting method provided in a specific embodiment of the present invention.
[0058] like Figure 4 As shown, operation S105 involves injecting grout into the composite profile using a circulating grouting method, and may include the following operations S105-1 to S105-2:
[0059] In operation S105-1: continuously inject grout into the inlet of the composite profile until no air bubbles appear at the outlet of the composite profile.
[0060] In an embodiment of the present invention, grout is continuously injected into the inlet of the composite profile. After the cavity of the composite profile is filled with filler, grout will emerge from the outlet of the composite profile, accompanied by the appearance of air bubbles (bubbling). If grout is continuously injected into the inlet of the composite profile, only grout will emerge from the outlet of the composite profile, and no more air bubbles will emerge, indicating that the filler in the composite profile has been compacted.
[0061] Next, in operation S105-1: close the slurry outlet and the slurry inlet in sequence.
[0062] In an embodiment of the present invention, when the slurry outlet of the composite profile only emits slurry and not bubbles, the slurry outlet is closed first, and then the slurry inlet is closed to prevent gas from entering the composite profile and to ensure that the filler inside the composite profile is in a dense state.
[0063] In the embodiments of the present invention, no air bubbles appear at the grout outlet of the composite profile, indicating that the filler inside the composite profile has been compacted. After the filler solidifies, there are no air holes, ensuring that the composite profile is filled densely, thereby enhancing the compressive strength of the composite profile, improving the tunnel's resistance to deformation, reducing the occurrence of lining defects inside the tunnel, ensuring traffic safety, and extending the service life of the tunnel.
[0064] Figure 5 The third schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0065] like Figure 5 As shown, before grouting the composite profile using the circulating grouting method in operation S105, the installation method of the composite profile may further include:
[0066] Operation S106: Seal the connection between the arch section, the left side section and the right side section.
[0067] In the embodiments of the present invention, the connection between the sealed arch section, the left side section and the right side section can prevent grout leakage when grouting the composite profile, ensure that the composite profile is fully filled, enhance the compressive strength of the composite profile, and improve the tunnel's resistance to deformation by installing the grouted composite profile in the tunnel, reduce the occurrence of lining defects inside the tunnel, ensure traffic safety and extend the service life of the tunnel.
[0068] Figure 6 This is a schematic flowchart illustrating a sealing composite profile connection part provided for a specific embodiment of the present invention.
[0069] like Figure 6 As shown, operation S106, which seals the connection between the arch section, the left side section, and the right side section, may include the following operations S106-1 to S106-3:
[0070] In operation S106-1: the fiber cloth is soaked in structural adhesive.
[0071] In embodiments of the present invention, the fiber cloth may include carbon fiber, basalt fiber, glass fiber, and cotton fiber, etc. Basalt fiber is both non-conductive and corrosion-resistant, therefore basalt fiber is preferred for the fiber cloth. Immersing the fiber cloth in structural adhesive, or applying structural adhesive to the fiber cloth, allows for better sealing of the connection points between the arch section, the left side section, and the right side section.
[0072] Next, in operation S106-2: wrap the connecting part with a fiber cloth.
[0073] In embodiments of the present invention, the fiber cloth is wrapped around the connecting part once, twice, or several times, or more than once, to achieve complete wrapping of the connecting part.
[0074] Then, in operation S106-3: use a reinforcing plate to seal and wrap the connection part of the fiber cloth.
[0075] In embodiments of the present invention, a reinforcing plate is installed outside the fiber cloth; the reinforcing plate can be a cover plate. One end of the reinforcing plate is fixed to one side of the connection portion, and the other end of the reinforcing plate is fixed to the other side of the connection portion. For example, one end of the reinforcing plate is fixed to the arch section, and the other end of the reinforcing plate is fixed to the left side section, thereby achieving complete wrapping of the connection portion and improving the support capacity of the composite profile.
[0076] In embodiments of the present invention, the connecting parts are wrapped with fiber cloth to prevent grout leakage during cyclic grouting of the composite profile, ensuring that the composite profile is fully filled. The connecting parts wrapped with fiber cloth are encapsulated with reinforcing plates, enhancing the compressive strength of the composite profile. Installing the grouted composite profile inside the tunnel can significantly improve the tunnel's deformation resistance, reduce the occurrence of lining defects, ensure traffic safety, and extend the tunnel's service life.
[0077] Figure 7 The fourth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0078] like Figure 7 As shown, after operation S101 determines an installation line on the inner wall of the tunnel perpendicular to the tunnel extension direction, the installation method of the composite profile may also include the following operations:
[0079] In operation S107: an auxiliary installation line is determined on the inner wall of the tunnel near the installation line, perpendicular to the tunnel extension direction.
[0080] In embodiments of the present invention, the auxiliary mounting line is also called the spare mounting line. The auxiliary mounting line is close to the mounting line and parallel to the mounting line. For example, the auxiliary mounting line is spaced 1 cm to 5 cm apart from the mounting line.
[0081] After operation S102 involves drilling the first center positioning hole at the intersection of the installation line and the arch line of the tunnel inner wall, the installation method of the composite profile may further include the following operations:
[0082] In operation S108: When a metal object is encountered when the first center positioning hole is opened at the intersection of the installation line and the arch line of the tunnel inner wall, a second center positioning hole is opened at the intersection of the auxiliary installation line and the arch line of the tunnel inner wall.
[0083] In embodiments of the present invention, if a metal object is encountered when the first central positioning hole is opened, a second central positioning hole needs to be opened at the intersection of the auxiliary installation line and the arch line of the tunnel inner wall. The tunnel lining is typically composed of reinforced concrete; if a hole in the tunnel lining encounters reinforcing steel, the hole needs to be re-drilled at a different location.
[0084] Then, in operation S109: the arch section of the composite profile is fixed on the second central positioning hole along the auxiliary installation line, wherein the composite profile is composed of the arch section, the left side section and the right side section.
[0085] In this embodiment of the invention, the arch section is installed first along the auxiliary installation line, followed by the left and right side sections. This significantly shortens the construction time of the composite profile, improves construction efficiency, and enables efficient construction within a limited construction time.
[0086] Next, in operation S1010: fix the left and right sections of the composite profile to the inner wall of the tunnel along the auxiliary installation line.
[0087] In the embodiments of the present invention, the composite profiles are installed in the order of first installing the arch section and then installing the side sections. This allows for rapid installation along the auxiliary installation line without any deviation, resulting in high installation efficiency and strong load-bearing capacity of the composite profiles.
[0088] In an embodiment of the present invention, after determining the installation line, an auxiliary installation line is determined on the inner wall of the tunnel near the installation line, perpendicular to the tunnel extension direction. Once the first central positioning hole encounters a metal object, a second central positioning hole can be directly opened at the intersection of the auxiliary installation line and the arch line of the inner wall of the tunnel. The composite profile is then installed along the auxiliary installation line to reinforce the tunnel, greatly shortening the construction time of the composite profile, improving construction efficiency, and enabling efficient construction within a limited construction time.
[0089] Figure 8 The fifth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0090] like Figure 8 As shown, before operation S103 fixes the arched section of the composite profile onto the first central positioning hole along the installation line, the installation method of the composite profile may further include the following operation S1011:
[0091] In operation S1011: process the inner wall of the tunnel along the installation line.
[0092] In embodiments of the present invention, the tunnel inner wall is treated along the installation line, for example, by cleaning or / and sanding the tunnel inner wall along the installation line, resulting in a tighter fit between the composite profile and the tunnel inner wall. Applying structural adhesive to the contact surface between the composite profile and the tunnel inner wall further strengthens the bond between them.
[0093] In embodiments of the present invention, operation S1011, which processes the tunnel inner wall along the installation line, may include the following operations:
[0094] Clean or grind the inner wall of the tunnel along the installation line.
[0095] In embodiments of the present invention, after cleaning or grinding the inner wall of the tunnel along the installation line, the composite profile adheres more tightly to the inner wall of the tunnel. If structural adhesive is applied to the contact surface between the composite profile and the inner wall of the tunnel, the adhesion between the composite profile and the inner wall of the tunnel is even stronger. When grinding the inner wall of the tunnel, the depth should not exceed 0.5 mm to avoid damaging the original load-bearing capacity of the tunnel lining.
[0096] Figure 9 The sixth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0097] like Figure 9 As shown, before operation S103, which fixes the arched section of the composite profile onto the first central positioning hole along the installation line, the installation method of the composite profile may further include the following operation S1012:
[0098] In operation S1012: process the handholes and misalignments on the inner wall of the tunnel along the installation line.
[0099] In embodiments of the present invention, misalignment refers to an unevenness between tunnel segments (i.e., the tunnel lining) caused by tunnel deformation. The manholes and misalignments on the tunnel wall are addressed along the installation line; for example, the manholes can be sealed with filler to correct the misalignment. The filler may include structural adhesive, mortar, basalt fiber, etc. Mortar may include epoxy mortar, etc. Basalt fiber is preferred because it is non-conductive and durable.
[0100] In embodiments of the present invention, handholes and misalignments on the inner wall of the tunnel are treated along the installation line, and the composite profile is fully fitted to the inner wall of the tunnel. If structural adhesive is applied to the contact surface between the composite profile and the inner wall of the tunnel, the composite profile and the inner wall of the tunnel will bond more tightly, the compressive strength of the composite profile will be enhanced, the deformation resistance of the tunnel can be significantly improved, the occurrence of lining defects inside the tunnel can be reduced, traffic safety can be ensured, and the service life of the tunnel can be extended.
[0101] Figure 10 This is a schematic flowchart illustrating the processing of handholes and misalignments on the inner wall of a tunnel, provided as a specific embodiment of the present invention.
[0102] like Figure 10 As shown, the process of handling handholes and misalignments on the inner wall of the tunnel along the installation line in operation S1012 may include the following operations S1012-1 to S1012-2:
[0103] In operation S1012-1: the hand hole is sealed with filler.
[0104] In embodiments of the present invention, structural adhesives, mortar, quick-drying cement, basalt fiber, and other fillers can be used to seal the manholes. If the manhole location is covered by more than half of the composite profile, the manhole on the segment (i.e., the tunnel lining) covered by the composite profile is sealed with filler. To prevent the sealant from falling off due to vibration during operation after pre-sealing, this work must be carried out simultaneously with the installation of the composite profile; if the manhole location is partially obscured by the composite profile by less than half, sealing is not required after the composite profile is installed.
[0105] Then, in operation S1012-2: the misalignment is filled with filler.
[0106] In embodiments of the present invention, structural adhesives, mortar, quick-drying cement, basalt fibers, and other fillers can be used to fill misalignments. If the misalignment is less than or equal to 10 mm, structural adhesive can be used to fill and compact it. If the misalignment is greater than 10 mm, a special shim can be used to fill and compact it.
[0107] In embodiments of the present invention, the manholes and misalignments on the inner wall of the tunnel are treated along the installation line, the composite profile fits more tightly with the inner wall of the tunnel, the compressive strength of the composite profile is enhanced, which can significantly improve the tunnel's resistance to deformation, reduce the occurrence of lining defects inside the tunnel, ensure traffic safety, and extend the service life of the tunnel.
[0108] Figure 11 The seventh schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0109] like Figure 11 As shown, before operation S103, which fixes the arched section of the composite profile onto the first central positioning hole along the installation line, the installation method of the composite profile may further include the following operation S1013:
[0110] In operation S1013: Structural adhesive is applied to the side of the composite profile near the inner wall of the tunnel, wherein, in the tunnel extension direction, the thickness of the structural adhesive applied at the middle of the side of the composite profile is greater than the thickness of the structural adhesive applied at both sides.
[0111] In embodiments of the present invention, the thickness of the structural adhesive applied to the middle of the side of the composite profile in the tunnel extension direction is greater than the thickness of the structural adhesive applied to the two sides. This ensures that the adhesive is compacted after the composite profile is installed, thereby enhancing the compressive strength of the composite profile. Typically, the resulting adhesive thickness is not less than 5 mm.
[0112] Figure 12 The eighth schematic flowchart illustrates an installation method for a composite profile, provided as a specific embodiment of the present invention.
[0113] like Figure 12As shown, before operation S103, which fixes the arched section of the composite profile onto the first central positioning hole along the installation line, the installation method of the composite profile may further include the following operation S1014:
[0114] In operation S1014: Mark the installation position of the composite profile at a prominent location on the arch line, the left side section, and the right side section.
[0115] In embodiments of the present invention, the left segment and / or the right segment may be composed of one, two, or more composite material sub-segments. For example, the left segment may consist of one composite material sub-segment, and the right segment may consist of two composite material sub-segments. Alternatively, the left segment may consist of two composite material sub-segments, and the right segment may consist of two composite material sub-segments. Another example is that the left segment may consist of three composite material sub-segments, and the right segment may consist of two composite material sub-segments.
[0116] In embodiments of the present invention, the ring numbers of the composite profiles are marked at prominent locations on the arch line, left side section, and right side section, and the profiles are stacked according to their ring numbers. Marking the installation positions of the composite profiles at prominent locations on the arch line, left side section, and right side section allows construction workers to quickly identify whether the composite profile section is the arch line, the left side section, or the right side section, improving installation efficiency and reducing the likelihood of incorrect installation, thus enabling efficient construction within a limited construction time window.
[0117] Figure 13 The ninth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0118] like Figure 13 As shown, before operation S103, which fixes the arched section of the composite profile onto the first central positioning hole along the installation line, the installation method of the composite profile may further include the following operation S1015:
[0119] In operation S1015: clean the dust in the first center positioning hole and fill the first center positioning hole with anchoring adhesive.
[0120] In embodiments of the present invention, a cleaning brush can be inserted into the first central positioning hole to stir up floating dust and other debris. Then, a blower can be used to blow the dust out of the hole. This process can be repeated several times to thoroughly clean the dust from the hole. After cleaning the dust from the first central positioning hole and filling it with anchoring adhesive, the bolts will not loosen or fall out due to train vibrations. This prevents safety risks associated with installing composite profiles on the tunnel wall and enhances the compressive strength of the composite profiles. Filling the first central positioning hole with anchoring adhesive also prevents rust and water from leaking out of the reinforcing steel, thus avoiding contamination of the train and the tunnel.
[0121] Figure 14 The tenth schematic flowchart illustrates a method for installing composite profiles according to a specific embodiment of the present invention.
[0122] like Figure 14 As shown, before operation S104, which fixes the left and right sections of the composite profile to the tunnel inner wall along the installation line, the installation method of the composite profile may further include the following operation S1016:
[0123] In operation S1016: clean the dust in all the fixing holes and fill the fixing holes with anchoring adhesive, wherein the fixing holes are used to fix the arch section, the left side section and the right side section.
[0124] In the embodiments of this invention, both the central positioning hole and the fixing hole are anchor bolt holes. All mounting holes except the central positioning hole are fixing holes, used to fix the arch section, left side section, and right side section. A cleaning brush can be inserted into the fixing hole to stir up dust and other debris, and then a blower can be used to blow the dust out of the hole. This process can be repeated several times to thoroughly clean the dust from the hole. After cleaning all the dust from the fixing holes and filling them with anchoring adhesive, the bolts will not fall out due to train vibrations or other reasons. This prevents safety risks associated with installing composite profiles on the tunnel wall and enhances the compressive strength of the composite profiles.
[0125] According to embodiments of the present invention, the method flow according to embodiments of the present invention can be implemented as a computer software program. For example, embodiments of the present invention include a computer program product comprising a computer program carried on a computer-readable storage medium, the computer program containing program code for performing the method shown in the flowchart. According to embodiments of the present invention, the electronic devices, devices, apparatuses, modules, units, etc., described above can be implemented by computer program modules.
[0126] The present invention also provides a computer-readable storage medium, which may be included in the device / apparatus / system described in the above embodiments; or it may exist independently and not assembled into the device / apparatus / system. The computer-readable storage medium carries one or more programs, which, when executed, implement the method according to the embodiments of the present invention.
[0127] According to embodiments of the present invention, the computer-readable storage medium may be a non-volatile computer-readable storage medium, such as including, but not limited to: portable computer disks, hard disks, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM or flash memory), portable compact disk read-only memory (CD-ROM), optical storage devices, magnetic storage devices, or any suitable combination thereof. In the present invention, the computer-readable storage medium may be any tangible medium containing or storing a program that can be used by or in conjunction with an instruction execution system, apparatus, or device.
[0128] The flowcharts and block diagrams in the accompanying drawings illustrate the architecture, functionality, and operation of possible implementations of systems, methods, and computer program products according to various embodiments of the present invention. In this regard, each block in a flowchart or block diagram may represent a module, segment, or portion of code containing one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions indicated in the blocks may occur in a different order than those indicated in the drawings. For example, two consecutively indicated blocks may actually be executed substantially in parallel, and they may sometimes be executed in reverse order, depending on the functions involved. It should also be noted that each block in a block diagram or flowchart, and combinations of blocks in a block diagram or flowchart, may be implemented using a dedicated hardware-based system that performs the specified function or operation, or using a combination of dedicated hardware and computer instructions.
[0129] Those skilled in the art will understand that the features described in the various embodiments and / or claims of the present invention can be combined or combined in various ways, even if such combinations or combinations are not explicitly described in the present invention. In particular, the features described in the various embodiments and / or claims of the present invention can be combined or combined in various ways without departing from the spirit and teachings of the present invention. All such combinations and / or combinations fall within the scope of the present invention.
[0130] The embodiments of the present invention have been described above. However, these embodiments are merely illustrative and not intended to limit the scope of the invention. Although various embodiments have been described above, this does not mean that the measures in the various embodiments cannot be used advantageously in combination. The scope of the invention is defined by the appended claims and their equivalents. Various substitutions and modifications can be made by those skilled in the art without departing from the scope of the invention, and all such substitutions and modifications should fall within the scope of the invention.
Claims
1. A method for installing composite profiles, characterized in that, The method includes: An installation line is determined on the inner wall of the tunnel along a direction perpendicular to the tunnel's extension. A first central positioning hole is opened at the intersection of the installation line and the arch line of the tunnel inner wall; The arched section of the composite profile is fixed to the first central positioning hole along the installation line, wherein the composite profile is composed of the arched section, the left side section, and the right side section; and The left and right sections of the composite profile are fixed to the inner wall of the tunnel along the installation line; Sealing the connection between the arch section, the left side section, and the right side section includes: soaking fiber cloth in structural adhesive; wrapping the connection with fiber cloth; and encapsulating the connection with reinforcing plates. Grout is injected into the composite profile using a circulating grouting method; After determining an installation line on the inner wall of the tunnel perpendicular to the tunnel's extension direction, the method further includes: Near the installation line on the inner wall of the tunnel, an auxiliary installation line is determined along the direction perpendicular to the tunnel extension. The auxiliary installation line is parallel to the installation line and is spaced 1 to 5 centimeters apart from the installation line. After the step of drilling the first center positioning hole at the intersection of the installation line and the arch line of the tunnel inner wall, the method further includes: When a metal object is encountered at the intersection of the installation line and the arch line of the tunnel inner wall, a second center positioning hole is opened at the intersection of the auxiliary installation line and the arch line of the tunnel inner wall. The arched section of the composite profile is fixed to the second central positioning hole along the auxiliary installation line, wherein the composite profile consists of the arched section, the left side section, and the right side section; and The left and right sections of the composite profile are fixed to the inner wall of the tunnel along the auxiliary installation line.
2. The installation method according to claim 1, characterized in that, The steps of injecting grout into the composite profile using the circulating grouting method include: Continuously inject grout into the inlet of the composite profile until no air bubbles appear at the outlet; and Close the slurry outlet and the slurry inlet in sequence.
3. The installation method according to claim 1, characterized in that, Before the step of fixing the arched section of the composite profile to the first central positioning hole along the installation line, the method further includes: The tunnel interior wall is treated along the installation line.
4. The installation method according to claim 3, characterized in that, The step of processing the tunnel inner wall along the installation line includes: Clean the inner wall of the tunnel along the installation line.
5. The installation method according to claim 1, characterized in that, Before the step of fixing the arched section of the composite profile to the first central positioning hole along the installation line, the method further includes: Handholes and misalignments on the inner wall of the tunnel are processed along the installation line.
6. The installation method according to claim 5, characterized in that, The steps of processing handholes and misalignments on the tunnel inner wall along the installation line include: The handhole was sealed with filler; and The misalignment was filled using filler material.
7. The installation method according to claim 1, characterized in that, Before the step of fixing the arched section of the composite profile to the first central positioning hole along the installation line, the method further includes: Structural adhesive is applied to the side of the composite profile near the inner wall of the tunnel, wherein, in the tunnel extension direction, the thickness of the structural adhesive applied at the middle of the side of the composite profile is greater than the thickness of the structural adhesive applied at both sides.
8. The installation method according to claim 1, characterized in that, Before the step of fixing the arched section of the composite profile to the first central positioning hole along the installation line, the method further includes: The installation positions of the composite profile are marked at prominent locations on the arch line, the left side section, and the right side section.
9. The installation method according to claim 8, characterized in that, The left segment and / or the right segment are composed of at least one composite profile sub-segment.
10. The installation method according to claim 1, characterized in that, Before the step of fixing the arched section of the composite profile to the first central positioning hole along the installation line, the method further includes: Clean the dust from the first central positioning hole and fill the first central positioning hole with anchoring adhesive.
11. The installation method according to claim 1, characterized in that, Before the step of fixing the left and right sections of the composite profile to the tunnel inner wall along the installation line, the method further includes: Clean the dust from all the fixing holes and fill them with anchoring adhesive. The fixing holes are used to fix the arch section, the left side section and the right side section.
12. A computer-readable storage medium having executable instructions stored thereon, which, when executed by a processor, implement the method according to any one of claims 1 to 11.
13. An electronic device, comprising: One or more processors; A storage device for storing executable instructions, which, when executed by the processor, implement the method according to any one of claims 1 to 11.
Citation Information
Patent Citations
Tunnel lining structure reinforcing method
CN114961773A
Construction method of non-standard high-strength composite steel ring for tunnel reinforcement in subway operation skylight period
CN115898452A