Construction quality control method for spliced joint of new and old bridges based on vibration coordination recognition
By installing acceleration sensors and data acquisition stations at the bottom of the bridge side beams, the bridge vibration can be monitored and analyzed in real time, solving the problem of construction quality control at the joint between new and old bridges. This enables precise control of the joint construction quality and determination of traffic opening time without interrupting traffic.
Patent Information
- Application Number
- CN202210281517.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-03-21
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2042-03-21
AI Technical Summary
Without disrupting traffic, it is difficult to control the construction quality of the joints between new and old bridges, especially the degradation of concrete performance and vibration characteristics, which leads to initial damage and performance degradation of the joint structure.
Accelerometers were installed at the bottom of the side beams of the existing old bridge and the widened new bridge. The bridge vibration was monitored in real time using data acquisition stations and wireless networks. The computer analysis determined when the vibration amplitude was consistent and traffic was opened to ensure the vibration coordination between the old and new bridges. The spring-mass-damping system of the accelerometer was used for vibration identification and data transmission.
It enables effective control of the construction quality of bridge joints without interrupting traffic, ensuring concrete quality, accurately determining traffic opening times, reducing costs, and facilitating installation.
Smart Images

Figure CN116818088B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the technical field of bridge joint connection in bridge expansion and widening projects, specifically involving a construction quality control method for the joint between old and new bridges based on vibration compatibility identification. Background Technology
[0002] In recent years, bridge widening has become a common structural form in highway reconstruction and expansion projects, often requiring wet joints between newly constructed widened bridges and existing bridges. To ensure safe and smooth highway traffic during construction, the joint connection between new and old bridges must be carried out without interrupting traffic. However, vehicle vibrations and their coupling with the bridge often directly affect the construction quality of the joint. The main challenges in controlling the construction quality of widened bridge joints without interrupting traffic are as follows: First, when constructing wet joints without interrupting traffic, the concrete at the joint location experiences significant degradation due to vehicle disturbance caused by the random traffic-bridge coupling vibration. Second, even if a temporary rigid connection is used between the new widened bridge and the existing old bridge before construction, it is impossible to completely guarantee uniform vibration on both sides of the joint during construction. Third, due to differences in structural performance between the new and old bridges and the degradation of the old bridge's performance, the vibration characteristics of widened bridges are difficult to analyze through theoretical calculations or finite element simulations. For the reasons mentioned above, without interrupting road traffic, the construction quality of joints in widened bridges is highly susceptible to disturbance from vehicles, leading to initial concrete damage and performance degradation in the joint structure. Therefore, it is urgent to develop methods for controlling joint quality during the construction of widened bridge joints. Summary of the Invention
[0003] The purpose of this invention is to provide a method for construction quality control of splice joints between new and old bridges based on vibration compatibility identification.
[0004] The objective of this invention is achieved through the following technical solution:
[0005] A construction quality control method for the splice joints of old and new bridges based on vibration compatibility identification, the construction quality control method specifically includes the following steps:
[0006] (a) A new bridge is constructed by casting a concrete pour on one side of the existing old bridge. Then, an integral layer of the old bridge and an integral layer of the new bridge are cast on the existing old bridge and the new bridge, respectively. A wet joint of the bridge is left between the existing old bridge and the new bridge.
[0007] (b) Then, accelerometers are installed at the bottom of the side beams of both the existing old bridge and the widened new bridge, and the accelerometers are connected to the data acquisition station using data cables. Then, concrete is poured into the wet joint of the widened bridge to form a widened bridge.
[0008] (c) Then, without interrupting traffic on the existing old bridge, the relevant vibration monitoring data collected by the data acquisition station via the accelerometer is transmitted to the analysis computer via a wireless network, and the opening time of traffic on the widened new bridge is determined through relevant calculation and analysis.
[0009] In step (b), when pouring concrete in the wet joint of the widened bridge, the side beams of the existing old bridge and the widened new bridge near the wet joint of the widened bridge are temporarily rigidly connected along the longitudinal direction of the bridge to ensure that the deformation difference of the side plates on both sides is relatively small during the pouring of the concrete for the wet joint of the widened bridge.
[0010] In step (b), the acceleration sensor is located at the mid-span position at the bottom of the side beam and on both sides of the mid-span position.
[0011] The acceleration sensor is located at the mid-span position at the bottom of the side beam and 5m to both sides of the mid-span position.
[0012] In step (b), the accelerometer is installed using epoxy resin adhesive to ensure that its installation position does not shift during use.
[0013] The data acquisition station has data receiving, data storage, and data transmission functions. Its data receiving function can receive acceleration data collected from the accelerometer via a data cable; its data storage function can save relevant data obtained from the accelerometer; and its data transmission function can transmit the data stored at the data acquisition station to the analysis computer via a wireless network.
[0014] The data acquisition station is equipped with a 48V lead-acid battery to provide the power required by the accelerometer and the data acquisition station.
[0015] The acceleration sensor employs a spring-mass-damping system.
[0016] In step (c), the acceleration sensor acquires the vertical acceleration at the corresponding measuring points on the upper beams of the existing old bridge and the widened new bridge.
[0017] In step (c), the analysis computer analyzes and determines the vibration amplitude of the existing old bridge and the widened new bridge. When the difference in vibration amplitude between the existing old bridge and the widened new bridge is less than 1 mm, traffic can be opened on the widened new bridge.
[0018] The vibration amplitude is calculated in the following way:
[0019] The equation of motion for the accelerometer particle under the action of the base acceleration (which can be considered as the acceleration at the bottom of the instrument base, i.e., the vertical acceleration supported by the instrument casing) is as follows:
[0020]
[0021] In the formula, m is the mass of the spring-mass-damping system in the accelerometer, c is the damping coefficient of the spring-mass-damping system in the accelerometer, k is the spring stiffness of the spring-mass-damping system in the accelerometer, and u(t) is the relative displacement of the mass in the accelerometer. The velocity of the particles in the accelerometer. The acceleration of a particle in an accelerometer. The base acceleration;
[0022] Since the actual measured acceleration motion time history is arbitrarily variable and contains a series of simple harmonic components distributed in a certain frequency band, we can first analyze the components of one simple harmonic component of the accelerometer. Then, the formula for calculating the base acceleration of the accelerometer is:
[0023]
[0024] In the formula: Let ω be the amplitude of the ground motion acceleration, ω be the angular frequency, and t be the time.
[0025] Combining equations (I) and (II) (specifically, substituting equation II into equation I and dividing both sides by m yields a homogeneous differential equation, from which the general and particular solutions can be directly obtained; solving the general and particular solutions simultaneously and substituting them into the original differential equation yields the complete solution, i.e., equation III), the relative displacement u(t) of the accelerometer particle is calculated as follows:
[0026]
[0027] In the formula: R d ω is the power amplification factor, ζ is the damping ratio, and ω / ω n φ is the frequency ratio, φ is the phase angle, and ω is the external load frequency. n It is the natural circular frequency.
[0028] The working principle of this invention is as follows: When widening and connecting bridges during reconstruction and expansion without interrupting traffic, the vibration characteristics at the joint locations of the widened bridges are monitored by collecting relevant data such as vibration monitoring and vibration response identification. This ensures coordinated vibration and deformation between the widened new bridge and the existing old bridge, achieving quality control of the bridge joint construction. Based on this, the timing for opening the new bridge to traffic is rationally determined. This invention is applicable to bridge reconstruction and widening projects of all levels of highways, especially for lateral connection construction between existing and new bridges. It can achieve quality control of the bridge joints without interrupting traffic on the existing old bridge, solving the problem of performance degradation caused by traffic disturbances at the bridge joints during reconstruction and expansion, and providing a basis for opening the new bridge to traffic.
[0029] Compared with the prior art, the present invention has the following advantages:
[0030] 1. A single device can be used to monitor and identify the vibration of widened bridges in real time.
[0031] 2. This method uses wireless data transmission, which enables remote monitoring of vibration of bridges that have been widened.
[0032] 3. This method can effectively control the quality of the joint concrete by monitoring the vibration of the widened bridge.
[0033] 4. This method, through the analysis of vibration time history data, can more accurately determine the opening time of the widened new bridge to traffic.
[0034] 5. The complete set of equipment involved in this invention has low cost, can be reused, and is easy to install and construct. Attached Figure Description
[0035] Figure 1 A schematic diagram of the cross-sectional layout of the vibration monitoring device for a bridge widening project.
[0036] Figure 2 A schematic diagram of the plan layout of the vibration monitoring device for the widened bridge;
[0037] Figure 3 A schematic diagram of the plan layout of the vibration monitoring device for the widened bridge;
[0038] Figure 4 This is a schematic diagram of data transmission for vibration monitoring of a bridge that has been widened.
[0039] In the diagram: 1-Existing old bridge; 2-Wide new bridge; 3-Integrated layer of old bridge; 4-Integrated layer of new bridge; 5-Wide wet joint of bridge; 6-Acceleration sensor; 7-Data cable; 8-Data acquisition station; 9-Wireless network; 10-Analysis computer. Detailed Implementation
[0040] The present invention will now be described in detail with reference to the accompanying drawings and specific embodiments.
[0041] Example
[0042] A method for construction quality control of splice joints between new and old bridges based on vibration compatibility identification, specifically including the following steps:
[0043] (a) A new bridge 2 is constructed on one side of the existing old bridge 1. Then, an integrated layer 3 of the old bridge and an integrated layer 4 of the new bridge are constructed on the existing old bridge 1 and the new bridge 2 respectively. A wet joint 5 of the bridge 2 is left between the existing old bridge 1 and the new bridge 2.
[0044] (b) Accelerometers 6 are then installed at the bottom of the side beams of both the existing old bridge 1 and the widened new bridge 2. The accelerometers 6 employ a spring-mass-damping system and are connected to a data acquisition station 8 via a data cable 7. The data acquisition station 8 has data receiving, data storage, and data transmission functions and is equipped with a 48V lead-acid battery. Then, a temporary rigid connection is made between the side beams of the existing old bridge 1 and the widened new bridge 2 near the wet joint 5 of the widened bridge along the longitudinal direction of the bridge. Concrete is then poured into the wet joint 5 of the widened bridge. Figure 1 , 2 As shown in Figure 3, specifically, the acceleration sensor 6 is installed by epoxy resin adhesive and is located at the mid-span position and on both sides of the mid-span position at the bottom of the side beam. In this embodiment, three acceleration sensors are installed on the old bridge 1 and three acceleration sensors are also installed on the widened new bridge 2. The acceleration sensor 6 is located at the mid-span position and 5m on both sides of the mid-span position at the bottom of the side beam.
[0045] (c) Then, without interrupting traffic on the existing old bridge 1, the relevant vibration monitoring data collected by the data acquisition station 8 via the accelerometer 6 is transmitted to the analysis computer 10 using the wireless network 9. The accelerometer 6 acquires the vertical acceleration at the corresponding measuring points on the upper side beams of the existing old bridge 1 and the widened new bridge 2. Through relevant calculations and analysis, the vibration amplitudes of the existing old bridge 1 and the widened new bridge 2 are determined to decide the opening time of traffic on the widened new bridge 2. When the difference in vibration amplitude between the existing old bridge 1 and the widened new bridge 2 is less than 1 mm, traffic on the widened new bridge 2 can be opened. The data transmission is as follows: Figure 4 As shown, the vibration amplitude is specifically calculated in the following way:
[0046] The equation of motion for the 6 particles of the accelerometer under the action of the base acceleration is:
[0047]
[0048] In the formula, m is the mass of the spring-mass-damping system in the accelerometer (6), c is the damping coefficient of the spring-mass-damping system in the accelerometer (6), k is the spring stiffness of the spring-mass-damping system in the accelerometer (6), and u(t) is the relative displacement of the mass in the accelerometer. The velocity of the particles in the accelerometer. The acceleration of a particle in an accelerometer. The base acceleration;
[0049] The formula for calculating the base acceleration is:
[0050]
[0051] In the formula: Let ω be the amplitude of the ground motion acceleration, ω be the angular frequency, and t be the time.
[0052] Combining equations (I) and (II), the relative displacement u(t) of the 6 mass points of the accelerometer is calculated as follows:
[0053]
[0054] In the formula: R d ω is the power amplification factor, ζ is the damping ratio, and ω / ω n φ is the frequency ratio, φ is the phase angle, and ω is the external load frequency. n It is the natural circular frequency.
[0055] The above description of the embodiments is provided to enable those skilled in the art to understand and use the invention. It will be apparent to those skilled in the art that various modifications can be made to these embodiments, and the general principles described herein can be applied to other embodiments without inventive effort. Therefore, the present invention is not limited to the above embodiments, and any improvements and modifications made by those skilled in the art based on the disclosure of the present invention without departing from the scope of the invention should be within the protection scope of the present invention.
Claims
1. A method for construction quality control of splice joints between new and old bridges based on vibration compatibility identification, characterized in that, The construction quality control method specifically includes the following steps: (a) A new bridge (2) is constructed on one side of the existing old bridge (1). Then, an integrated layer (3) of the old bridge and an integrated layer (4) of the new bridge are constructed on the existing old bridge (1) and the new bridge (2), respectively. A wet joint (5) of the bridge is left between the existing old bridge (1) and the new bridge (2). (b) Then, accelerometers (6) are installed at the bottom of the side beams of the existing old bridge (1) and the widened new bridge (2), and the accelerometers (6) are connected to the data acquisition station (8) using data cable (7). Then, concrete is poured in the wet joint (5) of the widened bridge. (c) Then, without interrupting traffic on the existing old bridge (1), the relevant vibration monitoring data collected by the data acquisition station (8) via the acceleration sensor (6) is transmitted to the analysis computer (10) using the wireless network (9), and the opening time of traffic on the widened new bridge (2) is determined through relevant calculation and analysis. In step (c), the accelerometer (6) acquires the vertical acceleration at the corresponding measuring points on the upper beams of the existing old bridge (1) and the widened new bridge (2); In step (c), the analysis computer (10) analyzes and determines the vibration amplitude of the existing old bridge (1) and the widened new bridge (2). When the difference in vibration amplitude between the existing old bridge (1) and the widened new bridge (2) is less than 1 mm, traffic can be opened on the widened new bridge (2). The vibration amplitude is calculated in the following way: The equation of motion of the accelerometer particle (6) under the action of the base acceleration is: , in, For the mass of the spring-mass-damping system in the accelerometer (6), Let be the damping coefficient of the spring-mass-damped system in the accelerometer (6). For the spring stiffness of the spring-mass-damping system in the accelerometer (6), The relative displacement of particles in the accelerometer. The velocity of the particles in the accelerometer. The acceleration of a particle in an accelerometer. The base acceleration; The formula for calculating the base acceleration is: , in, The amplitude of ground motion acceleration. It is the angular frequency. For time; The relative displacement of the particle of the accelerometer (6) was calculated. for: , in, This is the power amplification factor. For the damping ratio, For frequency ratio, The phase angle, For the frequency of external load, It is the natural circular frequency.
2. The method for construction quality control of splice joints between old and new bridges based on vibration compatibility identification according to claim 1, characterized in that, In step (b), when pouring concrete in the wet joint (5) of the bridge, the side beams of the existing old bridge (1) and the new bridge (2) near the wet joint (5) of the bridge are temporarily rigidly connected along the longitudinal direction of the bridge.
3. The method for construction quality control of splice joints between old and new bridges based on vibration compatibility identification according to claim 1, characterized in that, In step (b), the acceleration sensor (6) is located at the mid-span position at the bottom of the side beam and on both sides of the mid-span position.
4. The method for construction quality control of splice joints between old and new bridges based on vibration compatibility identification according to claim 3, characterized in that, The acceleration sensor (6) is located at the mid-span position at the bottom of the side beam and 5m on both sides of the mid-span position.
5. The method for construction quality control of splice joints between old and new bridges based on vibration compatibility identification according to claim 1, characterized in that, In step (b), the accelerometer (6) is installed using epoxy resin adhesive.
6. The method for construction quality control of splice joints between old and new bridges based on vibration compatibility identification according to claim 1, characterized in that, The data acquisition station (8) has data receiving, data storage and data sending functions.
7. The method for construction quality control of splice joints between old and new bridges based on vibration compatibility identification according to claim 1, characterized in that, The data acquisition station (8) is equipped with its own 48V lead-acid battery.
Citation Information
Patent Citations
Bridge splicing seam vehicle-induced vibration deformation monitoring and control system and method
CN113916146A
Construction method of reconstruction, extension and widening bridge joint connecting structure without interrupting traffic
CN116815653A
Lightweight spliced wide bridge vibration monitoring system for cooperative work performance intelligent perception
CN122042169A