Distilled water production method of cleaning apparatus and cleaning apparatus
By setting a heating device to control the distillation temperature range in the cleaning equipment, the problems of odor and efficiency during the distillation process of the cleaning equipment are solved, achieving efficient distillation of water while avoiding the generation of odors from solute evaporation.
Patent Information
- Application Number
- CN202311004619.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2022-09-20
- Filing Date
- 2023-08-09
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-08-09
AI Technical Summary
During the distillation of wastewater, excessively high temperatures in cleaning equipment can produce odors, while excessively low temperatures can affect distillation efficiency.
The heating device controls the wastewater to a distillation temperature range, with the lower limit of the range not less than the boiling point of water and the upper limit less than the minimum boiling point of each solute. The heating process is precisely controlled by a temperature sensor and controller to prevent the solute from evaporating and producing an odor.
It improves distillation efficiency, avoids the generation of odors, and ensures that water in wastewater evaporates effectively while solute does not evaporate.
Smart Images

Figure CN116849566B_ABST
Abstract
Description
[0001] This application claims priority to Chinese Patent Application No. 202211145737.3, filed on September 20, 2022, entitled “Control Method for Base Station and Base Station Having the Same”, the entire contents of which are incorporated herein by reference. Technical Field
[0002] This application belongs to the field of home cleaning, and particularly relates to a distillation method for water production in a cleaning device and the cleaning device itself. Background Technology
[0003] Cleaning equipment includes sweepers, floor scrubbers, sweeper-mop combos, vacuum cleaners, and vacuum cleaning devices. In related technologies, during the distillation of wastewater, excessively high distillation temperatures can easily produce unpleasant odors, while excessively low distillation temperatures can negatively impact distillation efficiency. Summary of the Invention
[0004] This application aims to address at least one of the technical problems existing in the prior art. To this end, this application proposes a distillation water purification method and cleaning equipment, which can ensure wastewater distillation efficiency and avoid the generation of odors during wastewater distillation.
[0005] In a first aspect, this application provides a method for distilling water using a cleaning device, the cleaning device including a wastewater tank and a heating device disposed in the wastewater tank, the method comprising:
[0006] When performing water distillation, the heating device is controlled to heat the wastewater in the wastewater tank to the distillation temperature range; wherein...
[0007] The lower limit of the distillation temperature range is not less than the boiling point of water in the wastewater, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the wastewater.
[0008] According to one embodiment of this application, the distillation temperature range is determined as follows:
[0009] Determine the composition of each solute in the wastewater;
[0010] Determine the boiling point of each solute component;
[0011] To determine the boiling point of water in wastewater;
[0012] The distillation temperature range is determined based on the minimum value of the boiling point of water and the boiling points of each of the solutes.
[0013] According to one embodiment of this application, controlling the heating device to heat the wastewater in the wastewater tank to a distillation temperature range includes:
[0014] The heating device is controlled to heat the sewage in the sewage tank to the target distillation temperature within the distillation temperature range.
[0015] According to one embodiment of this application, the target distillation temperature is determined as follows:
[0016] The midpoint of the distillation temperature range is taken as the target distillation temperature.
[0017] According to one embodiment of this application, the target distillation temperature is determined as follows:
[0018] Based on the test results, the target distillation temperature is determined from the distillation temperature range. The test results are the results after the wastewater is heated to the temperature in the distillation temperature range and heated for the target duration. The test results include the amount of remaining wastewater and / or the odor intensity.
[0019] According to one embodiment of this application, determining the target distillation temperature from the distillation temperature range based on test results includes:
[0020] Multiple test temperatures are selected from the distillation temperature range;
[0021] The test results are obtained after the wastewater is heated to each of the specified test temperatures and for the target heating time.
[0022] The test temperature at which the odor intensity is lowest and / or the amount of residual wastewater is lowest among the test results is taken as the target distillation temperature.
[0023] According to one embodiment of this application, determining the target distillation temperature from the distillation temperature range based on test results includes:
[0024] The current test temperature is obtained from the distillation temperature range and the test is performed.
[0025] Obtain the current test result after heating the wastewater to the current test temperature and for the target heating time;
[0026] Based on the current test result and the current test temperature, the next test temperature is obtained;
[0027] The next test temperature is taken as the current test temperature, and the process returns to the step of obtaining the current test temperature from the distillation temperature range for testing, until the temperature test stop condition is met.
[0028] The temperature of the last test is taken as the target distillation temperature.
[0029] According to one embodiment of this application, obtaining the next test temperature based on the current test result and the current test temperature includes:
[0030] If it is determined that the amount of residual wastewater in the current test result is greater than the target amount of wastewater, and / or the odor intensity is less than the target odor intensity, the current test temperature is increased within the distillation temperature range to obtain the next test temperature;
[0031] If it is determined that the amount of residual wastewater in the current test result is less than the target amount of wastewater, and / or the odor intensity is greater than the target odor intensity, the current test temperature is reduced within the distillation temperature range to obtain the next test temperature.
[0032] According to one embodiment of this application, obtaining the current test temperature from the distillation temperature range for testing includes:
[0033] The current test temperature range is obtained from the distillation temperature range, and the median value of the current test temperature range is used as the current test temperature for testing. The first test temperature range is the distillation temperature range.
[0034] The step of obtaining the next test temperature based on the current test result and the current test temperature includes:
[0035] Based on the current test result and the current test temperature, determine the next test temperature range from the current test temperature range, and take the midpoint of the next test temperature range as the next test temperature.
[0036] According to one embodiment of this application, determining the next test temperature range from the current test temperature range based on the current test result and the current test temperature includes:
[0037] If it is determined that the amount of residual wastewater in the current test result is greater than the target amount of wastewater and / or the odor intensity is less than the target odor intensity, the temperature range between the current test temperature and the upper limit of the current test temperature range shall be used as the next test temperature range.
[0038] If it is determined that the amount of residual wastewater in the current test result is less than the target amount of wastewater, and / or the odor intensity is greater than the target odor intensity, the temperature range between the lower limit of the current test temperature range and the current test temperature shall be used as the next test temperature range.
[0039] According to one embodiment of this application, the lower limit of the distillation temperature range is not less than the boiling point of water in the wastewater at the target altitude, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the wastewater at the target altitude, wherein the target altitude is the altitude of the area where the distillation water production is performed.
[0040] Secondly, this application provides a cleaning device, which includes a controller, a wastewater tank, a heating device disposed in the wastewater tank, and a temperature sensor disposed in the wastewater tank, wherein the controller is communicatively connected to the heating device and the temperature sensor respectively;
[0041] The temperature sensor is used to detect the temperature of the wastewater in the wastewater tank;
[0042] The heating device is used to heat the sewage in the sewage tank to the distillation temperature range, wherein the lower limit of the distillation temperature range is not less than the boiling point of water in the sewage, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the sewage.
[0043] The controller is used to control the heating device to heat the sewage in the sewage tank to the distillation temperature range when performing distillation water production.
[0044] According to one embodiment of this application, the cleaning equipment further includes a stirrer disposed in the sewage tank, and the controller is communicatively connected to the stirrer;
[0045] The agitator is used to agitate the sewage and / or impurities in the sewage tank;
[0046] The controller is also used to control the operation of the stirrer.
[0047] According to one embodiment of this application, the cleaning equipment further includes a dust collection device connected to the sewage tank and a dust collection fan disposed at the dust collection device, wherein the controller is communicatively connected to the dust collection fan;
[0048] The dust collection fan is used to draw impurities from the wastewater tank into the dust collection device;
[0049] The controller is also used to control the operation of the dust collection fan.
[0050] According to the distillation water purification method and cleaning equipment of this application, wastewater is heated to a distillation temperature range that is not less than the boiling point of water in the wastewater, so as to ensure that the distillation temperature of the wastewater is not less than the boiling point of water in the wastewater, thus ensuring the distillation efficiency of the wastewater. In addition, the distillation temperature range is less than the minimum boiling point of each solute in the wastewater, so as to ensure that the distillation temperature of the wastewater is lower than the boiling point of each solute in the wastewater, thus avoiding the generation of odors.
[0051] Additional aspects and advantages of this application will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of this application. Attached Figure Description
[0052] The above and / or additional aspects and advantages of this application will become apparent and readily understood from the description of the embodiments taken in conjunction with the following drawings, in which:
[0053] Figure 1 This is one of the structural schematic diagrams of the cleaning equipment provided in the embodiments of this application;
[0054] Figure 2 This is a schematic flowchart of the water distillation method for the cleaning equipment provided in the embodiments of this application;
[0055] Figure 3 This is a signal waveform diagram of the distillation water purification method of the cleaning equipment provided in the embodiments of this application;
[0056] Figure 4 This is an oscillation waveform diagram in the distillation water purification method of the cleaning equipment provided in the embodiments of this application;
[0057] Figure 5 This is a second schematic diagram of the structure of the cleaning equipment provided in the embodiments of this application;
[0058] Figure 6 This is the third schematic diagram of the cleaning equipment provided in the embodiments of this application;
[0059] Figure 7 This is the fourth structural schematic diagram of the cleaning equipment provided in the embodiments of this application;
[0060] Figure 8 This is the fifth schematic diagram of the cleaning equipment provided in the embodiments of this application;
[0061] Figure 9 This is the sixth schematic diagram of the cleaning equipment provided in the embodiments of this application. Detailed Implementation
[0062] The technical solutions of the embodiments of this application will be clearly described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this application. All other embodiments obtained by those skilled in the art based on the embodiments of this application are within the scope of protection of this application.
[0063] The terms "first," "second," etc., used in the specification and claims of this application are used to distinguish similar objects and not to describe a specific order or sequence. It should be understood that such use of data can be interchanged where appropriate so that embodiments of this application can be implemented in orders other than those illustrated or described herein, and the objects distinguished by "first," "second," etc., are generally of the same class and the number of objects is not limited; for example, a first object can be one or more. Furthermore, in the specification and claims, "and / or" indicates at least one of the connected objects, and the character " / " generally indicates that the preceding and following objects are in an "or" relationship.
[0064] The following is in conjunction with the appendix Figure 1 To be continued Figure 9 The distillation water production method and cleaning equipment provided in this application will be described in detail through specific embodiments and application scenarios.
[0065] The distillation method for water purification in cleaning equipment can be applied to the cleaning equipment, and can be executed by the hardware or software within the cleaning equipment.
[0066] The distillation water production method for cleaning equipment provided in this application embodiment can be executed by the cleaning equipment or a functional module or entity in the cleaning equipment that can realize the method. The cleaning equipment mentioned in this application embodiment includes, but is not limited to, sweepers, floor scrubbers, sweeping and mopping machines, vacuum cleaners, vacuum cleaning devices, etc.
[0067] The distillation water purification method for cleaning equipment provided in this application embodiment can be applied to, for example... Figure 1 The cleaning equipment shown. For example... Figure 1 As shown, the cleaning equipment includes a wastewater tank 11, a clean water tank 12, a cooling assembly 15, a heating device 13, a temperature sensor 132, and a controller 40. The heating device 13 and the temperature sensor 132 are both located in the wastewater tank 11. The cooling assembly 15 is connected between the wastewater tank 11 and the clean water tank 12. The controller 40 is communicatively connected to the cooling assembly 15, the heating device 13, and the temperature sensor 132.
[0068] The cleaning equipment includes a base station and / or a self-propelled robot. The wastewater tank 11, clean water tank 12, cooling assembly 15, heating device 13, temperature sensor 132, and controller 40 can be installed on the base station, on the self-propelled robot, or on both.
[0069] When performing water distillation, temperature sensor 132 monitors the temperature of the wastewater in wastewater tank 11 in real time. Based on the temperature detected by temperature sensor 132, controller 40 adjusts the heating power of heating device 1 to heat the wastewater in wastewater tank 11 to the distillation temperature range, causing the wastewater to generate steam that enters cooling component 15. Controller 40 controls cooling component 15 to condense the steam into liquid water (i.e., clean water) and delivers the clean water to clean water tank 12. The wastewater in wastewater tank 11 is generated after cleaning by the self-propelled robot, while the clean water in clean water tank 12 can be used for cleaning by the self-propelled robot.
[0070] like Figure 2 As shown, this application provides a method for distilling water using a cleaning device, which is then applied to... Figure 1 The method of distilling water using the controller 40 in this cleaning device is illustrated using step 100.
[0071] Step 100: When performing distillation to produce water, control the heating device to heat the wastewater in the wastewater tank to the distillation temperature range; wherein, the lower limit of the distillation temperature range is not less than the boiling point of water in the wastewater, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the wastewater.
[0072] The cleaning equipment can be equipped with a distillation mode. In this mode, the cleaning equipment can perform distillation, which means producing clean water from the wastewater in the wastewater tank 11. When performing distillation, the controller 40 controls the heating device 13 to heat the wastewater in the wastewater tank 11 to generate water vapor, which enters the cooling component 15. The controller 40 controls the cooling component 15 to condense the water vapor into liquid water (i.e., clean water) and delivers the clean water to the clean water tank 12.
[0073] When performing distillation to produce water, the controller 40 controls the heating device 13 to heat the wastewater in the wastewater tank 11 to the distillation temperature range. Since wastewater includes water and various solutes, the boiling points of water and various solutes in the wastewater are different, and the boiling point of water in the wastewater is lower than the boiling points of various solutes. The solutes in the wastewater may include odorous substances (such as cleaning solutions), which will produce an odor when evaporated at high temperatures. Therefore, the distillation temperature range can be set between the minimum boiling point of water in the wastewater and the minimum boiling point of each solute, so that when the wastewater is heated to this distillation temperature range, the water in the wastewater evaporates into water vapor, while the various solutes in the wastewater do not evaporate.
[0074] In this embodiment, the lower limit of the distillation temperature range is set to be no less than the boiling point of water in the wastewater, to ensure that the water in the wastewater can evaporate into water vapor when heated to this distillation temperature range, thereby improving the distillation efficiency of the wastewater. At the same time, the upper limit of the distillation temperature range is set to be less than the minimum boiling point of each solute in the wastewater, to ensure that the various solutes in the wastewater will not evaporate when heated to this distillation temperature range, thus avoiding the generation of odors from solute evaporation.
[0075] The distillation temperature range can be determined by other equipment (non-clean equipment) or clean equipment.
[0076] In some embodiments, the distillation temperature range can be determined by other equipment (non-cleaning equipment). That is, other equipment determines the distillation temperature range based on the solutes that may be present in the wastewater, and the cleaning equipment obtains and stores the distillation temperature range from the other equipment. In this embodiment, the distillation temperature range is a fixed value. When the cleaning equipment performs distillation to produce water, it can directly control the heating device 13 to heat the wastewater in the wastewater tank 11 to the distillation temperature range.
[0077] In some embodiments, the distillation temperature range can be determined by the cleaning equipment. Specifically, the cleaning equipment determines the distillation temperature range based on the solute in the wastewater in the wastewater tank 11 and stores it in its memory. In this embodiment, the distillation temperature range can be a dynamic value; that is, the distillation temperature range determined by the cleaning equipment may differ depending on the solute in the wastewater in the wastewater tank 11. When performing distillation for water production, the cleaning equipment can first determine the distillation temperature range based on the solute in the wastewater in the wastewater tank 11, and then control the heating device 13 to heat the wastewater in the wastewater tank 11 to that distillation temperature range.
[0078] In some embodiments, the distillation temperature range is determined as follows:
[0079] Determine the composition of each solute in the wastewater;
[0080] Determine the boiling point of each solute component;
[0081] To determine the boiling point of water in wastewater;
[0082] The distillation temperature range is determined based on the minimum boiling point of water and the boiling points of each solute.
[0083] Taking the distillation temperature range determined by the controller 40 in the cleaning equipment as an example, the controller 40 first detects various solutes in the wastewater, such as oil and particulate impurities, then analyzes the solute composition of each solute and determines the boiling point of each solute based on its composition. The controller 40 determines the distillation temperature range based on the boiling point of water and the minimum boiling point of the solute in the wastewater. For example, if the boiling point of water in the wastewater is 100℃ and the minimum boiling point of the solute is 110℃, the upper limit of the distillation temperature range can be slightly lower than the minimum boiling point of the solute, such as a range of 100℃ to 109℃. It should be noted that solutes in the wastewater may cause the boiling point of the wastewater to rise. To ensure distillation efficiency, the lower limit of the distillation temperature range can be slightly higher than the boiling point of water, such as a range of 102℃ to 109℃.
[0084] In some embodiments, the lower limit of the distillation temperature range is not less than the boiling point of water in the wastewater at the target altitude, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the wastewater at the target altitude. The target altitude is the altitude of the area where the water distillation is performed.
[0085] The boiling point of water in wastewater varies at different altitudes, as do the boiling points of various solutes. There are two ways to determine the distillation temperature range at the target altitude. One method is to first determine the target altitude of the area where water distillation will be performed, then obtain the boiling points of water and solutes in the wastewater at that altitude to determine the distillation temperature range. The other method is to first determine the distillation temperature range at zero altitude based on the boiling points of water and solutes in the wastewater at zero altitude, and then convert this range to the target altitude using the altitude-temperature conversion formula.
[0086] In some embodiments, the heating device in step 100 heats the wastewater in the wastewater tank to a distillation temperature range, including:
[0087] The heating device is controlled to heat the wastewater in the wastewater tank to the target distillation temperature within the distillation temperature range.
[0088] It should be noted that due to the instability of the heating device 13, when the controller 40 controls the heating device 13 to heat the sewage in the sewage tank to the distillation temperature range, the sewage temperature may fluctuate slightly around the distillation temperature range, meaning the sewage temperature may be lower or higher than the distillation temperature range. Therefore, in this embodiment, an optimal distillation temperature, i.e., the target distillation temperature, is selected from the distillation temperature range. The controller 40 controls the heating device 13 to heat the sewage in the sewage tank 11 to the target distillation temperature, so that the sewage temperature only fluctuates slightly around the target distillation temperature and does not fall below or exceed the distillation temperature range, ensuring distillation efficiency and effectively avoiding the generation of odors.
[0089] The target distillation temperature can be determined by other equipment (non-cleaning equipment). That is, after other equipment determines the distillation temperature range, the target distillation temperature is determined from the distillation temperature range, and the cleaning equipment obtains the target distillation temperature from the other equipment and stores it. Alternatively, the target distillation temperature can be determined by the cleaning equipment. That is, after the cleaning equipment determines the distillation temperature range based on the wastewater in wastewater tank 11, the target distillation temperature is determined from the distillation temperature range.
[0090] In some embodiments, the target distillation temperature is determined as follows:
[0091] The midpoint of the distillation temperature range is used as the target distillation temperature.
[0092] Taking the example of the target distillation temperature being determined by the controller 40 in the cleaning equipment, the controller 40 uses the midpoint of the distillation temperature range as the target distillation temperature, ensuring that the wastewater temperature fluctuates only within a small range of the target distillation temperature and does not exceed the distillation temperature range. For example, if the distillation temperature range is 102°C to 109°C, the target distillation temperature can be 105°C.
[0093] In some embodiments, the target distillation temperature is determined as follows:
[0094] Based on the test results, the target distillation temperature is determined from the distillation temperature range. The test results are obtained when the wastewater is heated to the target heating parameters. The target heating parameters include the temperature in the distillation temperature range and the target heating time. The test results include the amount of residual wastewater and / or odor intensity.
[0095] The controller 40 controls the heating device 13 to perform multiple tests on the wastewater. It should be noted that the wastewater can be divided into multiple equal portions, ensuring that each portion has the same moisture content and solute composition. Multiple tests can refer to testing multiple portions of wastewater separately. In each test, the controller 40 controls the heating device 13 to heat the wastewater to a specific temperature within the distillation temperature range and heats it for the same duration (i.e., the target duration) to obtain the test results. Different tests may have different heating temperatures but the same heating duration, resulting in different test results. The test results include the amount of remaining wastewater and / or odor intensity. The amount of remaining wastewater refers to the amount of wastewater remaining after heating and evaporation, and the odor intensity refers to the intensity of the odor produced by the heating and evaporation of the wastewater.
[0096] In some embodiments, determining a target distillation temperature from a distillation temperature range based on test results includes:
[0097] Select multiple test temperatures from the distillation temperature range;
[0098] The test results were obtained after the wastewater was heated to each test temperature and for the target heating time.
[0099] The test temperature with the lowest odor intensity and / or the lowest amount of residual wastewater in the test results is taken as the target distillation temperature.
[0100] In this embodiment, the controller 40 can select a temperature from the distillation temperature range as the test temperature at fixed intervals, starting from the lower limit of the distillation temperature range, thereby obtaining multiple test temperatures. The controller 40 controls the heating device 13 to heat multiple samples of wastewater to different test temperatures and heat them for the same duration (i.e., the target duration), obtaining multiple test results. The controller 40 compares the multiple test results and selects the test temperature with the lowest odor intensity and / or the lowest amount of remaining wastewater as the target distillation temperature. It should be noted that when the test results include both the amount of remaining wastewater and the odor intensity, the test temperature with the lowest odor intensity and the lowest amount of remaining wastewater is selected as the target distillation temperature to avoid the generation of odors while improving wastewater distillation efficiency.
[0101] In some embodiments, determining a target distillation temperature from a distillation temperature range includes:
[0102] The current test temperature is obtained from the distillation temperature range for testing;
[0103] Obtain the current test result after heating the wastewater to the current test temperature and for the target heating time;
[0104] Based on the current test result and the current test temperature, the next test temperature will be determined.
[0105] The next test temperature is used as the current test temperature. The process returns to the step of obtaining the current test temperature from the distillation temperature range and conducting the test until the temperature test stop condition is met.
[0106] Use the temperature of the last test as the target distillation temperature.
[0107] In the nth test (n≥1), the controller 40 first obtains the nth test temperature from the distillation temperature range. The first test temperature can be a randomly selected temperature from the distillation temperature range. The controller 40 controls the heating device 13 to heat a sample of wastewater to the nth test temperature for the target heating time, obtaining the nth test result. Based on the nth test result and the nth test temperature, the controller 40 determines the (n+1)th test temperature from the distillation temperature range. After obtaining the (n+1)th test temperature, the controller 40 controls the heating device 13 to heat another sample of wastewater to the (n+1)th test temperature for the target heating time, obtaining the (n+1)th test result. Based on the (n+1)th test result and the (n+1)th test temperature, the controller 40 determines the (n+2)th test temperature from the distillation temperature range. The above steps are repeated until the temperature test stop condition is met.
[0108] The temperature test stopping condition refers to the conditions that must be met to stop the temperature test. The temperature test stopping condition may include the odor intensity in the test results being the minimum odor intensity, and / or the residual wastewater volume in the test results being the minimum residual wastewater volume. In other words, when the odor intensity and / or residual wastewater volume are determined to be the minimum in the Nth test result, the temperature test stopping condition is met, i.e., the temperature test is stopped, and the Nth test temperature is taken as the target distillation temperature.
[0109] In some embodiments, the next test temperature is obtained based on the current test result and the current test temperature, including:
[0110] If it is determined that the amount of residual wastewater in the current test result is greater than the target amount of wastewater, and / or the odor intensity is less than the target odor intensity, the current test temperature is increased within the distillation temperature range to obtain the next test temperature;
[0111] If the amount of residual wastewater in the current test result is less than the target amount of wastewater, and / or the odor intensity is greater than the target odor intensity, the current test temperature is reduced within the distillation temperature range to obtain the next test temperature.
[0112] If the amount of residual wastewater in the nth test result is greater than the target amount of wastewater, and / or the odor intensity is less than the target odor intensity, then the distillation temperature is increased within the distillation temperature range, and the increased test temperature is the (n+1)th test temperature. If the amount of residual wastewater in the nth test result is less than the target amount of wastewater, and / or the odor intensity is greater than the target odor intensity, then the distillation temperature is decreased within the distillation temperature range, and the decreased test temperature is the (n+1)th test temperature. The controller 40 adjusts the test temperature to find the test temperature with the minimum odor intensity and / or minimum amount of residual wastewater (such as the Nth test temperature), and uses the Nth test temperature as the target distillation temperature.
[0113] In some embodiments, obtaining the current test temperature from the distillation temperature range for testing includes:
[0114] Obtain the current test temperature range from the distillation temperature range, and use the median value of the current test temperature range as the current test temperature for testing. The first test temperature range is the distillation temperature range.
[0115] Based on the current test results and the current test temperature, the next test temperature is determined, including:
[0116] Based on the current test result and the current test temperature, determine the next test temperature range from the current test temperature range, and take the midpoint of the next test temperature range as the next test temperature.
[0117] In the nth test, the controller 40 first obtains the nth test temperature range from the distillation temperature range. The first test temperature range is the distillation temperature range. The controller 40 takes the midpoint of the nth test temperature range as the nth test temperature and controls the heating device 13 to heat a sample of wastewater to the nth test temperature for the target heating time, thus obtaining the nth test result. Based on the nth test result and the nth test temperature, the controller 40 determines the (n+1)th test temperature range from the nth test temperature range and takes the midpoint of the (n+1)th test temperature range as the (n+1)th test temperature. The controller 40 then controls the heating device 13 to heat another sample of wastewater to the (n+1)th test temperature for the target heating time, thus obtaining the (n+1)th test result. Based on the (n+1)th test result and the (n+1)th test temperature, the controller 40 determines the (n+2)th test temperature range from the (n+1)th test temperature range and takes the midpoint of the (n+2)th test temperature range as the (n+2)th test temperature. Repeat the above steps until the temperature test stops.
[0118] In some embodiments, determining the next test temperature range from the current test temperature range based on the current test result and the current test temperature includes:
[0119] If it is determined that the amount of residual wastewater in the current test result is greater than the target amount of wastewater and / or the odor intensity is less than the target odor intensity, the temperature range between the current test temperature and the upper limit of the current test temperature range shall be used as the next test temperature range.
[0120] If the amount of residual wastewater in the current test result is less than the target amount of wastewater, and / or the odor intensity is greater than the target odor intensity, the temperature range between the lower limit of the current test temperature range and the current test temperature will be used as the next test temperature range.
[0121] If the amount of residual wastewater in the nth test result is greater than the target amount of wastewater, and / or the odor intensity is less than the target odor intensity, then the controller 40 uses the temperature range between the nth test temperature and the upper limit of the nth test temperature range as the (n+1)th test temperature range; if the amount of residual wastewater in the nth test result is less than the target amount of wastewater, and / or the odor intensity is greater than the target odor intensity, then the controller 40 uses the temperature range between the lower limit of the nth test temperature range and the nth test temperature as the (n+1)th test temperature range. By adjusting the test temperature range, the test temperature with the minimum odor intensity and / or minimum amount of residual wastewater in the test results (such as the Nth test temperature) is found, and the Nth test temperature is used as the target distillation temperature.
[0122] According to the distillation water purification method of the cleaning equipment provided in the embodiments of this application, the sewage is heated to a distillation temperature range. This distillation temperature range is not less than the boiling point of water in the sewage, so that the distillation temperature of the sewage is not less than the boiling point of water, ensuring the distillation efficiency of the sewage. In addition, the distillation temperature range is less than the minimum boiling point of each solute in the sewage, so that the distillation temperature of the sewage is lower than the boiling point of each solute in the sewage, avoiding the generation of odor.
[0123] In some embodiments, the step of controlling the heating device to heat the wastewater in the wastewater tank to a target distillation temperature within the distillation temperature range includes:
[0124] Real-time acquisition of wastewater temperature and temperature change rate;
[0125] The heating power of the heating device is adjusted based on the temperature and temperature change rate of the wastewater, with the target distillation temperature as the control target.
[0126] During the process of the controller 40 controlling the heating device 13 to heat the sewage in the sewage tank 11, the temperature sensor 132 detects the temperature of the sewage in real time. The controller 40 calculates the rate of temperature change of the sewage based on the real-time temperature detected by the temperature sensor 132. The rate of temperature change is the difference in temperature change over a fixed period of time. For example, if the temperature of the sewage is detected once every moment from the moment the controller 40 starts controlling the heating device 13 to heat the sewage in the sewage tank 11, the interval between two adjacent moments is the aforementioned fixed period of time.
[0127] It should be noted that the temperature change rate may not be calculated at the first moment (i.e., the moment when the heating device 13 starts heating the sewage in the sewage tank 11), or the temperature change rate at the first moment may be 0. Starting from the second moment, the temperature change rate at the i-th moment is the difference between the temperature of the sewage at the i-th moment and the temperature at the (i-1)-th moment, where i > 1. For example, if the interval between two adjacent moments is 1 second, the temperature change rate of the sewage can be the temperature change difference per second.
[0128] In this embodiment, the heating power of the heating device 13 is adjusted according to the temperature and temperature change rate of the wastewater. When the temperature of the wastewater differs significantly from the target distillation temperature, the temperature change rate of the wastewater is increased, that is, the heating power of the heating device 13 is increased to quickly raise the temperature of the wastewater. When the temperature of the wastewater is close to the target distillation temperature, the temperature change rate of the wastewater is reduced, that is, the heating power of the heating device 13 is reduced, so as to avoid the temperature of the wastewater from exceeding the target distillation temperature significantly, thereby avoiding the evaporation of solutes in the wastewater and the generation of odors.
[0129] In some embodiments, the step of adjusting the heating power of the heating device based on the temperature and temperature change rate of the wastewater, with a target distillation temperature as the control target, includes:
[0130] Obtain the current heating power of the heating device at the current moment;
[0131] Based on the current heating power, the current temperature of the wastewater, and the current rate of temperature change, and with the target distillation temperature as the control target, the heating power of the heating device at the next moment is determined;
[0132] Adjust the heating power of the heating device to the heating power of the next moment;
[0133] Use the heating power at the next moment as the current heating power, return to the step of obtaining the current heating power of the heating device at the current moment, until the power adjustment stop condition is met.
[0134] When the controller 40 starts heating the wastewater in the wastewater tank 11 with the heating device 13, since the temperature of the wastewater in the wastewater tank 11 differs significantly from the target distillation temperature, the controller 40 can adjust the heating power of the heating device 13 to its maximum heating power. That is, the heating power of the heating device 13 at the first moment can be its maximum heating power. Then, the controller 40 can control the heating device 13 to operate at its maximum heating power until the second moment, that is, the heating power of the heating device 13 at the second moment is also its maximum heating power.
[0135] Starting from the second moment, the controller 40 determines the heating power of the heating device 13 at the (i+1)th moment based on the heating power at the i-th moment, the temperature of the wastewater at the i-th moment, and the rate of temperature change. The determination of the heating power at the (i+1)th moment is based on the target distillation temperature as the control target, so that the temperature of the wastewater changes toward the target distillation temperature by adjusting the heating power of the heating device 13.
[0136] The controller 40 controls the heating device 13 to continue heating the wastewater in the wastewater tank 11 at the heating power at time i+1, and obtains the temperature and temperature change rate of the wastewater at time i+1. Based on the heating power at time i+1 and the temperature and temperature change rate of the wastewater at time i+1, the controller determines the heating power of the heating device 13 at time i+2, with the target distillation temperature as the control target, and controls the heating device 13 to continue heating the wastewater in the wastewater tank 11 at the heating power at time i+2. The above steps are repeated until the power adjustment stop condition is met.
[0137] The power adjustment stopping condition can include the wastewater temperature reaching the target distillation temperature, and the wastewater temperature change rate not exceeding the target change rate. The target change rate can be set relatively small, i.e., the target change rate can be 0 or close to 0. For example, if at time I, the temperature sensor 132 detects that the wastewater temperature has reached the target distillation temperature, and the controller 40 determines that the wastewater temperature change rate is less than the target change rate, then the controller 40 stops adjusting the heating power of the heating device 13 and controls the heating device 13 to continue heating the wastewater in the wastewater tank 11 at the heating power at time I.
[0138] After the controller 40 stops adjusting the heating power of the heating device 13, the temperature sensor 132 continues to monitor the temperature of the wastewater in real time, and the controller 40 calculates the rate of temperature change of the wastewater in real time. When the controller 40 detects that the temperature and rate of temperature change of the wastewater do not meet the power adjustment stop condition, that is, when the temperature of the wastewater is different from the target distillation temperature or the rate of temperature change of the wastewater is greater than the target rate of change, the controller 40 readjusts the heating power of the heating device 13 according to the temperature and rate of temperature change of the wastewater, with the target distillation temperature as the control target, so as to ensure that the temperature of the wastewater is stable at the target distillation temperature, or fluctuates slightly within a range near the target distillation temperature.
[0139] In some embodiments, the step of adjusting the heating power of the heating device based on the temperature and temperature change rate of the wastewater, with a target distillation temperature as the control target, includes:
[0140] Given that the temperature of the wastewater is lower than the reference temperature, determine the target reference rate of change of the wastewater temperature, where the reference temperature is lower than the target distillation temperature.
[0141] Adjust the heating power of the heating device based on the deviation between the rate of temperature change of the wastewater and the target reference rate of temperature change.
[0142] The reference temperature can be set to a value close to the target distillation temperature. For example, if the target distillation temperature is 105℃, the reference temperature can be 104.5℃.
[0143] When the temperature of the wastewater is lower than the reference temperature, the controller 40 can use a constant rate of change control method to adjust the heating power of the heating device 13. The constant rate of change control method means controlling the temperature change rate of the wastewater to be a reference rate of change (a fixed value) or to fluctuate within a small range around the reference rate of change.
[0144] In some embodiments, the controller 40 may set a reference rate of change. When the temperature of the wastewater is lower than the reference temperature, the controller 40 acquires the reference rate of change (i.e., the target reference rate of change), and adjusts the heating power of the heating device 13 according to the deviation between the wastewater temperature change rate and the target reference rate of change, so that the temperature of the wastewater can quickly approach the reference temperature.
[0145] In some embodiments, the controller 40 can set multiple reference change rates and multiple reference temperature ranges, and establish a one-to-one correspondence between the multiple reference change rates and the multiple reference temperature ranges, so that each reference temperature range corresponds to a reference change rate. When the temperature of the wastewater is within different reference temperature ranges, different reference change rates are selected as target reference change rates.
[0146] The steps for determining the target reference rate of change corresponding to the temperature of wastewater include:
[0147] Determine the target reference temperature range to which the wastewater temperature belongs from multiple reference temperature ranges; the reference temperature range is lower than the reference temperature.
[0148] Based on the correspondence between the reference temperature range and the reference rate of change, determine the target reference rate of change corresponding to the target reference temperature range.
[0149] When the wastewater temperature is lower than the reference temperature, the controller 40 first determines the target reference temperature range to which the wastewater temperature belongs from multiple reference temperature ranges. Then, based on the one-to-one correspondence between multiple reference temperature ranges and multiple reference change rates, it determines the target reference change rate corresponding to the target reference temperature range. This target reference change rate is the target reference change rate corresponding to the wastewater temperature. The controller 40 adjusts the heating power of the heating device 13 according to the deviation between the wastewater temperature change rate and the target reference change rate, so that the wastewater temperature can quickly approach the reference temperature.
[0150] In some embodiments, the temperature within the reference temperature range is negatively correlated with the corresponding reference rate of change. In other words, the higher the temperature within the reference temperature range, the lower the corresponding reference rate of change, resulting in the wastewater temperature being closer to the reference temperature and the wastewater temperature rate of change being smaller. This allows for a rapid increase in wastewater temperature while preventing excessive temperature fluctuations that could significantly exceed the target distillation temperature.
[0151] For example, the target distillation temperature is 105℃, and the reference temperature is 104.5℃. The controller 40 sets four reference temperature ranges, namely the first reference temperature range to the fourth reference temperature range, and sets the corresponding reference change rate for each of the four reference temperature ranges. Specifically, the first reference temperature range is between 25℃ and 70℃, with a corresponding reference change rate of 1℃ / s; the second reference temperature range is between 70℃ and 85℃, with a corresponding reference change rate of 0.6℃ / s; the third reference temperature range is between 85℃ and 95℃, with a corresponding reference change rate of 0.4℃ / s; and the fourth reference temperature range is between 95℃ and 104.5℃, with a corresponding reference change rate of 0.1℃ / s.
[0152] In some embodiments, the step of adjusting the heating power of the heating device based on the deviation between the rate of change of wastewater temperature and a target reference rate of change includes:
[0153] If it is determined that the temperature change rate of the wastewater is greater than the target reference change rate, a first adjustment amount is determined based on the deviation between the temperature change rate of the wastewater and the target reference change rate, and the heating power of the heating device is reduced by the first adjustment amount.
[0154] If the temperature change rate of the wastewater is determined to be less than the target reference change rate, a second adjustment amount is determined based on the deviation between the temperature change rate of the wastewater and the target reference change rate, and the heating power of the heating device is increased by the second adjustment amount.
[0155] When the wastewater temperature is lower than the reference temperature, the controller 40 compares the wastewater temperature change rate with the target reference change rate in real time. If the wastewater temperature change rate is greater than the target reference change rate, it indicates that the wastewater temperature change is too large. To prevent the wastewater temperature from significantly exceeding the target distillation temperature, the heating power of the heating device 13 is reduced. The amount of reduction in the heating power of the heating device 13 (i.e., the first adjustment amount) is determined based on the deviation between the wastewater temperature change rate and the target reference change rate. The deviation is positively correlated with the first adjustment amount; that is, the larger the deviation, the larger the first adjustment amount, and the smaller the deviation, the smaller the first adjustment amount. After determining the first adjustment amount, the current heating power of the heating device 13 is reduced by the first adjustment amount.
[0156] If the rate of temperature change of the wastewater is less than the target reference rate of change, it indicates that the temperature change of the wastewater is too small. To quickly increase the temperature of the wastewater, the heating power of the heating device 13 is increased. The amount of increase in the heating power of the heating device 13 (i.e., the second adjustment amount) is determined based on the deviation between the rate of temperature change of the wastewater and the target reference rate of change. The deviation in the rate of change is positively correlated with the second adjustment amount; that is, the larger the deviation in the rate of change, the larger the second adjustment amount, and the smaller the deviation in the rate of change, the smaller the second adjustment amount. After determining the second adjustment amount, the current heating power of the heating device 13 is increased by the second adjustment amount.
[0157] In some embodiments, the step of adjusting the heating power of the heating device based on the temperature of the wastewater and the rate of temperature change, with a target distillation temperature as the control target, further includes:
[0158] Given that the temperature of the wastewater is between the reference temperature and the target distillation temperature, a third adjustment amount is determined based on the temperature deviation between the wastewater temperature and the target distillation temperature. The heating power of the heating device is then increased by the third adjustment amount, and the temperature deviation is positively correlated with the third adjustment amount.
[0159] When the wastewater temperature is determined to be between the reference temperature and the target distillation temperature, the controller 40 can use a constant temperature control method to adjust the heating power of the heating device 13. The constant temperature control method refers to controlling the wastewater temperature to be at or near the target distillation temperature.
[0160] When the wastewater temperature is determined to be between the reference temperature and the target distillation temperature, the controller 40 calculates the temperature deviation between the wastewater temperature and the target distillation temperature in real time, and determines a third adjustment amount based on this temperature deviation. The third adjustment amount is positively correlated with the temperature deviation; that is, the smaller the temperature deviation, the smaller the third adjustment amount, and the larger the temperature deviation, the larger the third adjustment amount.
[0161] As the temperature of the wastewater gets closer and closer to the target distillation temperature, the temperature deviation between the wastewater temperature and the target distillation temperature becomes smaller and smaller. The third adjustment amount becomes smaller and smaller, that is, the increase in the heating power of the heating device 13 becomes smaller and smaller, so that when the temperature of the wastewater reaches the target distillation temperature, the increase in the heating power of the heating device 13 (i.e., the third adjustment amount) is exactly 0, that is, the adjustment of the heating power of the heating device 13 is stopped.
[0162] In some embodiments, the step of adjusting the heating power of the heating device based on the temperature of the wastewater and the rate of temperature change, with a target distillation temperature as the control target, further includes:
[0163] After determining that the wastewater temperature has reached the target distillation temperature for the first time, the heating power of the heating device is adjusted according to the temperature deviation between the wastewater temperature and the target distillation temperature.
[0164] When the wastewater temperature reaches the target distillation temperature for the first time, the controller 40 stops adjusting the heating power of the heating device 13, but the temperature sensor 132 continues to monitor the wastewater temperature in real time. The controller 40 compares the wastewater temperature with the target distillation temperature in real time. If the wastewater temperature differs from the target distillation temperature, the controller 40 readjusts the heating power of the heating device 13 based on the temperature deviation between the wastewater temperature and the target distillation temperature, thereby ensuring that the wastewater temperature remains stable at the target distillation temperature, or fluctuates slightly within a range around the target distillation temperature.
[0165] In some embodiments, the step of adjusting the heating power of the heating device based on the temperature deviation between the wastewater temperature and the target distillation temperature includes:
[0166] If it is determined that the temperature of the wastewater is greater than the target distillation temperature, a fourth adjustment amount is determined based on the temperature deviation between the wastewater temperature and the target distillation temperature, and the heating power of the heating device is reduced by the fourth adjustment amount.
[0167] If the temperature of the wastewater is determined to be lower than the target distillation temperature, a fifth adjustment amount is determined based on the temperature deviation between the wastewater temperature and the target distillation temperature, and the heating power of the heating device is increased by the fifth adjustment amount.
[0168] After the wastewater temperature reaches the target distillation temperature for the first time, the controller 40 compares the wastewater temperature with the target distillation temperature in real time. If the wastewater temperature is higher than the target distillation temperature, it indicates that the wastewater temperature is too high, and the controller 40 reduces the heating power of the heating device 13. The amount of reduction in the heating power of the heating device 13 (i.e., the fourth adjustment amount) is determined based on the temperature deviation between the wastewater temperature and the target distillation temperature. This temperature deviation is positively correlated with the fourth adjustment amount; that is, the larger the temperature deviation, the larger the fourth adjustment amount, and the smaller the temperature deviation, the smaller the fourth adjustment amount. After determining the fourth adjustment amount, the current heating power of the heating device 13 is reduced by the fourth adjustment amount.
[0169] If the wastewater temperature is lower than the target distillation temperature, it indicates that the wastewater temperature is too low, and the controller 40 increases the heating power of the heating device 13. The amount of increase in the heating power of the heating device 13 (i.e., the fifth adjustment amount) is determined based on the temperature deviation between the wastewater temperature and the target distillation temperature. This temperature deviation is positively correlated with the fifth adjustment amount; that is, the larger the temperature deviation, the larger the fifth adjustment amount, and the smaller the temperature deviation, the smaller the fifth adjustment amount. After determining the fifth adjustment amount, the current heating power of the heating device 13 is increased by the fifth adjustment amount.
[0170] In some embodiments, combined with Figure 5As shown, the cleaning equipment also includes a power controller 131, which is communicatively connected to the heating device 13. The step of adjusting the heating power of the heating device includes:
[0171] Based on the linear relationship between heating power and control parameters, determine the target control parameters corresponding to the target heating power;
[0172] Based on the target control parameters, the power controller outputs a signal to the heating device, causing the heating device to heat the sewage in the sewage tank at the target heating power.
[0173] The heating power is the power of the heating device 13 to heat the sewage in the sewage tank 11, and the control parameter is the parameter that controls the operating state of the power controller 131. The heating power of the heating device 13 is controlled by the power controller 131. Through the control parameter, the controller 40 can control the operating state of the power controller 131, thereby controlling the heating power of the heating device 13.
[0174] The linear relationship between heating power and control parameters can be preset. The target heating power is the heating power that the heating device 13 needs to achieve when heating the sewage in the sewage tank 11. After determining the target heating power to be achieved by the heating device, the controller 40 can directly determine the target control parameters corresponding to the target heating power based on the linear relationship between heating power and control parameters. Here, linear relationship means a straight line relationship or a relationship that approaches a straight line relationship.
[0175] After determining the target control parameters corresponding to the target heating power, the controller 40 controls the operating state of the power controller 131 according to the target control parameters, thereby controlling the output signal of the power controller 131 to the heating device 13. This output signal is used to control the heating power of the heating device 13 to the target heating power, so that the heating device 13 heats the sewage in the sewage tank 11 at the target heating power.
[0176] In related technologies, the heating power and control parameters have a non-linear relationship. After determining the target heating power, it is impossible to quickly and accurately determine the target control parameters corresponding to the target heating power based on this non-linear relationship, thus making it impossible to quickly and accurately control the heating power of the heating device 13.
[0177] In this embodiment, a linear relationship between heating power and control parameters is established so that after determining the target heating power, the target control parameters corresponding to the target heating power can be quickly and accurately determined based on this linear relationship. Then, based on the target control parameters, the heating power of the heating device can be quickly and accurately controlled to the target heating power.
[0178] In some embodiments, the power controller 131 may be an adapter or a thyristor, etc. When the power controller 131 is an adapter, the control parameters may be the current and / or voltage of the adapter; when the power controller 131 is a thyristor, the control parameters may be the duty cycle of the thyristor.
[0179] The embodiments of this application will be described in detail below, taking the power controller 131 as a thyristor as an example.
[0180] The power controller 131 is a thyristor, and the control parameter is the duty cycle of the thyristor. The duty cycle is the ratio of the on-time of the thyristor in one control cycle to the control cycle. This control cycle includes multiple reference cycles, each reference cycle being half a cycle of the AC signal, which is the input signal of the thyristor.
[0181] In related technologies, the control cycle of a thyristor is one reference cycle, which is half a cycle of an AC signal. The relationship between the conduction time of the thyristor and the heating power within one reference cycle is a non-linear curve. However, the control cycle of the thyristor in this application includes multiple reference cycles, and the relationship between the conduction time of the thyristor and the heating power within these multiple reference cycles is a linear curve.
[0182] In some embodiments, the control period is determined as follows:
[0183] Starting from a single reference cycle, for each additional reference cycle, determine the relationship curve between the conduction time of the thyristor and the heating power;
[0184] When the linearity of the relationship curve is less than the target linearity, determine the number of reference periods corresponding to the relationship curve;
[0185] Use this number of reference periods as a control period.
[0186] Starting with a single reference cycle, the controller 40 increases the reference cycles sequentially. For each additional reference cycle, the controller 40 determines the relationship between the conduction time of the thyristor and the heating power over all current reference cycles. For example, when increasing to m reference cycles, the controller 40 determines the relationship between the conduction time of the thyristor and the heating power over m reference cycles, where m > 1. The linearity of the relationship curve corresponding to m reference cycles is compared with the target linearity. If the linearity of the relationship curve corresponding to m reference cycles is greater than the target linearity, another reference cycle is added, i.e., to m+1 reference cycles. The controller 40 then determines the relationship between the conduction time of the thyristor and the heating power over m+1 reference cycles and compares the linearity of the relationship curve corresponding to m+1 reference cycles with the target linearity. This process is repeated until the linearity of the relationship curve corresponding to M reference cycles is less than the target linearity, where M ≥ m.
[0187] When the linearity of the relationship curve corresponding to M reference cycles is determined to be less than the target linearity, the controller 40 uses the M reference cycles as a control cycle, ensuring that the linearity of the relationship curve between the conduction time of the thyristor and the heating power within this control cycle is less than the target linearity. This target linearity can be set relatively small so that the relationship curve between the conduction time of the thyristor and the heating power within this control cycle is a linear curve or approaches a linear curve, thereby obtaining a linear relationship between the duty cycle of the thyristor and the heating power.
[0188] In some embodiments, a linear relationship between the heating power and the duty cycle of the thyristor is determined based on the rated power of the heating device.
[0189] The ratio of the heating power of the heating device 13 to the duty cycle of the thyristor is the rated power of the heating device 13, which is a fixed value. When determining the target duty cycle corresponding to the target heating power, the controller 40 divides the target heating power by the rated power of the heating device 13 to obtain the target duty cycle.
[0190] In some embodiments, the control parameter is the duty cycle of the thyristor, and the target control parameter is the target duty cycle corresponding to the target heating power. The step of controlling the power controller to output a signal to the heating device according to the target control parameter includes:
[0191] Based on the target duty cycle, determine the conduction period of the thyristor within the control cycle;
[0192] The thyristor is controlled to conduct during the conduction period so that it outputs a signal to the heating device during the conduction period.
[0193] The controller 40 determines the target on-time of the thyristor within the control cycle based on the target duty cycle, and then determines the on-time period of the thyristor within the control cycle based on the target on-time. The on-time period can be any period within the control cycle, as long as the duration of the on-time period is the target on-time.
[0194] In some embodiments, to ensure precise control of the thyristor, the controller 40 sets the conduction period at the end of the control cycle, meaning the end time of the conduction period coincides with the end time of the control cycle. When determining the conduction period, the controller 40 can first use the end time of the control cycle as the end time of the conduction period, and then determine the start time of the conduction period within the control cycle, so that the duration between the start time and the end time of the conduction period is the target conduction duration.
[0195] After determining the conduction period, the controller 40 controls the thyristor to conduct during the conduction period, so as to output an AC signal (the input signal of the thyristor) to the heating device 13. It should be noted that the thyristor is off during the non-conducting period and does not output a signal to the heating device 13. The controller 40 controls the signal output to the heating device 13 by controlling the duty cycle of the thyristor, that is, controlling the duration of the conduction period of the thyristor within the control cycle (i.e., the conduction duration), thereby controlling the heating power of the heating device 13.
[0196] In some embodiments, the step of controlling the thyristor to conduct during the conduction period includes:
[0197] At the beginning of the conduction period, a trigger signal is sent to the thyristor to control the thyristor to conduct;
[0198] During the conduction period, each time the voltage of the input signal to the thyristor is determined to be zero, a trigger signal is sent to the thyristor to control the thyristor to continue conducting.
[0199] A thyristor has the characteristic of turning on based on a trigger signal, but automatically turning off at a zero-crossing point (i.e., when the voltage of the thyristor's input signal is zero). Therefore, at the beginning of the conduction period, the controller 40 sends a trigger signal to the thyristor to control its conduction. To prevent the thyristor from turning off at a zero-crossing point during the conduction period, the controller 40 detects whether the thyristor has crossed a zero point, that is, whether the voltage of the thyristor's input signal is zero. When the controller 40 detects that the voltage of the thyristor's input signal is zero, it sends a trigger signal to the thyristor to control it to continue conducting.
[0200] A detection module can be used to detect whether the voltage of the input signal of the thyristor is zero. The detection module is connected to the input signal (AC signal) of the thyristor and may include an optocoupler. When the input signal is in the positive half-axis, the stepped-down voltage is higher than the voltage drop of the LED inside the optocoupler, triggering the optocoupler to output a polarity voltage, causing the detection module to output a high-level zero-crossing signal to the controller 40. When the input signal is in the negative half-axis, the stepped-down voltage is opposite to the diode, the diode is in reverse cutoff, there is no current in the LED inside the optocoupler, the optocoupler is triggered to output a high-impedance state, causing the detection module to output a low-level zero-crossing signal to the controller 40. Therefore, the controller 40 can determine the phase of the thyristor's input signal by determining the edge of the zero-crossing signal, and thus determine whether the voltage of the thyristor's input signal is zero. When the zero-crossing signal changes from high to low, or from low to high, the controller 40 determines that the voltage of the thyristor's input signal is zero.
[0201] like Figure 3As shown, the waveform of the input signal to the thyristor is a sine wave. The period of the input signal is 2π, the reference period T0 is π, and the control period T1 of the thyristor includes 10 reference periods, i.e., the control period T1 is 10π. The waveform of the zero-crossing signal is a square wave, and it is high when the input signal of the thyristor is on the positive half-axis and low when it is on the negative half-axis. The waveform of the trigger signal is a square wave, and when the trigger signal is high, it controls the thyristor to conduct. The waveform of the output signal of the thyristor is a sine wave, and when the thyristor is on, the output signal is consistent with its input signal.
[0202] For example, based on the linear relationship between heating power and control parameters, controller 40 determines that the target duty cycle corresponding to the target heating power is 25%. Based on the target duty cycle and control period T1, controller 40 can deduce that the conduction duration of the thyristor within control period T1 is 2.5π. Controller 40 determines that the conduction period of the thyristor within control period T1 is the last 2.5π of control period T1, i.e. Figure 3 The values t1 to t4 are defined as follows: t1 is the start time of the conduction period, t4 is the end time of the conduction period, and t4 is also the end time of the control cycle T1.
[0203] During the time interval from t0 (the start time of control cycle T1) to t1, the trigger signal is low, the thyristor is off, and the thyristor does not output a signal to the heating device 13. At time t1, the controller 40 sends a high-level trigger signal to the thyristor to control it to conduct, causing the thyristor to output a signal to the heating device 13. During the time interval from t1 to t2, the zero-crossing signal is low, the voltage of the thyristor's input signal is not zero, and the thyristor remains on. At time t2, the zero-crossing signal changes from low to high, the thyristor crosses the zero point, the voltage of the thyristor's input signal is zero, causing the thyristor to turn off. Therefore, at time t2, the controller 40 sends a high-level trigger signal to the thyristor to control it to continue conducting, causing the thyristor to continue outputting a signal to the heating device 13. During the time interval from t2 to t3, the zero-crossing signal is high, the voltage of the thyristor's input signal is not zero, and the thyristor remains on. At time t3, the zero-crossing signal changes from high to low. The thyristor crosses zero, meaning the voltage of its input signal is zero, causing the thyristor to turn off. Therefore, at time t3, the controller 40 sends a high-level trigger signal to the thyristor to keep it conducting, allowing it to continue outputting a signal to the heating device 13. During the time interval t3 to t4, the zero-crossing signal is low, and the thyristor's input signal is not zero, so the thyristor remains on. At time t4, the zero-crossing signal changes from low to high, and the thyristor crosses zero, meaning the voltage of its input signal is zero, causing the thyristor to turn off. At this time, the controller 40 determines whether to send a high-level touch signal to the thyristor based on the conduction period in the next control cycle.
[0204] In some embodiments, the method further includes:
[0205] The heating power of the heating device is obtained when the temperature of the wastewater reaches the target distillation temperature;
[0206] Determine the average heating power of the heating device over the target duration based on the heating power.
[0207] When the heating power shows a decreasing trend within the target duration and the average heating power is less than the target power, it is determined that the sewage tank has burned dry.
[0208] From the moment the wastewater temperature first reaches the target distillation temperature, the controller 40 acquires the heating power of the heating device in real time. For example, the moment when the wastewater temperature first reaches the target distillation temperature is taken as the first moment, and the heating power of the heating device 13 is acquired at every moment starting from the first moment.
[0209] In some embodiments, the step of obtaining the heating power of the heating device includes:
[0210] Obtain the duty cycle of the thyristor;
[0211] The heating power of the heating device is obtained based on the duty cycle of the thyristor and the rated power of the heating device.
[0212] The controller 40 controls the signal output by the thyristor to the heating device 13 by controlling the duty cycle of the thyristor, thereby controlling the heating power of the heating device 13. The duty cycle of the thyristor is the ratio of the conduction time of the thyristor within a control cycle to the control cycle itself. By setting the control cycle of the thyristor, the duty cycle of the thyristor and the heating power of the heating device 13 can be linearly related, and the ratio of the heating power of the heating device 13 to the duty cycle of the thyristor is the rated power of the heating device 13, which is a fixed value. After obtaining the duty cycle of the thyristor, the controller 40 multiplies the duty cycle of the thyristor by the rated power of the heating device 13 to obtain the heating power of the heating device 13.
[0213] The target duration is a predetermined fixed duration. The controller 40 calculates the average heating power of the heating device 13 within the target duration based on its heating power. For example, starting from the moment when the wastewater temperature first reaches the target distillation temperature as the first moment, the controller 40 acquires the heating power of the heating device 13 at every moment. The controller 40 calculates the average heating power of the heating device 13 at all moments within the target duration; this average value is the average heating power within the target duration.
[0214] The target duration refers to the time between a point in time prior to the current point and the current point. For example, if the current point is point p (p > 1), and the duration between the first point and point p is the target duration, then the controller 40 calculates the average heating power between the first point and point p. Starting from point p, the controller 40 calculates the average heating power within a target duration for each heating power value acquired. After acquiring the heating power at point p+1, the controller 40 calculates the average heating power between the second point and point p+1; after acquiring the heating power at point p+2, it calculates the average heating power between the third point and point p+2, and so on.
[0215] The target power is a predetermined heating power. Starting from time p, the controller 40 detects the trend of heating power change within the target duration and compares the average heating power within the target duration with the target power. If the heating power shows a decreasing trend within the target duration, and the average heating power within the target duration is less than the target power, then it is determined that the wastewater tank 11 has burned dry.
[0216] For example, at time p, the controller 40 detects the trend of heating power change from time 1 to time p (target duration). If the heating power at each time from time 1 to time p is less than the heating power at the previous time, it is determined that the heating power shows a decreasing trend from time 1 to time p; otherwise, it is determined that the heating power does not show a decreasing trend from time 1 to time p. Simultaneously, the controller 40 detects whether the average heating power from time 1 to time p (target duration) is less than the target power. If the heating power shows a decreasing trend from time 1 to time p, and the average heating power from time 1 to time p is less than the target power, it is determined that the wastewater tank 11 has burned out. Otherwise, at time p+1, the controller 40 continues to detect the trend of heating power change from time 2 to time p+1 (target duration), and simultaneously detects whether the average heating power from time 2 to time p+1 is less than the target power. This detection is repeated until the heating power shows a decreasing trend within a target duration, and the average heating power within that target duration is less than the target power, at which point the wastewater tank 11 is determined to have burned out.
[0217] This embodiment combines the heating power of the heating device and the average heating power within the target time to detect burn-out. When the heating power shows a decreasing trend within the target time and the average heating power is less than the target power, it is determined that the sewage tank is burn-out, so as to accurately detect the burn-out time of the sewage tank and ensure high safety performance.
[0218] In some embodiments, the target power is the heating power of the heating device 13 when it dry-burns the wastewater tank 11 to the target distillation temperature. The wastewater tank 11 contains no medium. The controller 40 controls the heating device 13 to heat the wastewater tank 11, and the temperature sensor 132 monitors the temperature of the wastewater tank 11 in real time. When the controller 40 detects that the wastewater tank 11 has reached the target distillation temperature, it acquires the heating power of the heating device 13 at this time and uses this heating power as the target power. The target power can be between 60W and 120W.
[0219] It should be noted that when there is moisture in the wastewater tank 11, the controller 40 controls the heating device 13 to heat the wastewater tank 11, causing the moisture to evaporate into water vapor. Since moisture evaporation carries away a large amount of heat, the heating power of the heating device 13 needs to be set relatively high in order to heat the wastewater tank 11 to the target distillation temperature. When there is no moisture in the wastewater tank 11, the controller 40 controls the heating device 13 to heat the wastewater tank 11. Since no moisture evaporates from the wastewater tank 11, it does not carry away a large amount of heat, and the heating device 13 can use a smaller heating power to heat the wastewater tank 11 to the target distillation temperature. Therefore, as the amount of water evaporated in the wastewater tank 11 gradually decreases, the heating power of the heating device 13 gradually decreases. When the heating power of the heating device 13 decreases to the target power, it indicates that the wastewater tank 11 is dry-burning.
[0220] However, there are errors in the detection of heating power and sewage temperature. If only the heating power of the heating device 13 is compared with the target power, it may lead to inaccurate detection of burning dryness and may also cause safety issues. Therefore, this application also sets a target time. Based on the trend of heating power change within the target time, the average heating power within the target time is compared with the target power to detect whether the sewage tank 11 has burned dryness.
[0221] In some embodiments, the target duration is determined as follows:
[0222] When the temperature of the wastewater reaches the target distillation temperature, determine the oscillation waveform of the heating power of the heating device as a function of time;
[0223] The oscillation period in which the amplitude difference first appears to be less than the target difference is determined. The amplitude difference is the difference between the maximum amplitude and the minimum amplitude in the oscillation period.
[0224] Determine the target duration based on the oscillation period.
[0225] When the wastewater temperature first reaches the target distillation temperature, the controller 40 acquires the heating power of the heating device 11 in real time and determines the oscillation waveform of the heating power of the heating device 11 over time. As time changes, the oscillation period in this waveform becomes larger and larger, while the amplitude difference within the oscillation period becomes smaller and smaller.
[0226] The controller 40 calculates the amplitude difference in each oscillation cycle of the oscillation waveform sequentially. When the first oscillation cycle in the oscillation waveform appears with an amplitude difference less than the target difference, the controller 40 determines the target duration based on that oscillation cycle. For example... Figure 4 As shown, the fourth oscillation cycle (i.e., the time period from 3T to 4T) is the oscillation cycle in which the amplitude difference first appears to be less than the target difference. The target duration is determined based on the fourth oscillation cycle (i.e., the time period from 3T to 4T).
[0227] In some embodiments, the target duration is a multiple of the oscillation period, i.e., the target duration is... Figure 4 The target duration is a multiple of the fourth oscillation period (i.e., the time period from 3T to 4T), which can be one to four times. For example, if the fourth oscillation period (i.e., the time period from 3T to 4T) is 50s, the target duration can be 50s, 100s, 150s, or 200s.
[0228] In some embodiments, the target duration is the time between the start time of the oscillation waveform and the end time of the oscillation cycle. The start time of the oscillation waveform is the moment when the temperature of the wastewater first reaches the target distillation temperature, and the end time of the oscillation cycle is... Figure 4The end time of the fourth oscillation cycle (i.e., the time period from 3T to 4T). For example, the target duration is between 50s and 200s.
[0229] This embodiment combines the heating power of the heating device and the average heating power within the target time to detect burn-out. When the heating power shows a decreasing trend within the target time and the average heating power is less than the target power, it is determined that the sewage tank is burn-out, so as to accurately detect the burn-out time of the sewage tank and ensure high safety performance.
[0230] The distillation water production method using a cleaning device provided in this application embodiment can be implemented by the cleaning device itself. This application embodiment uses a cleaning device performing the distillation water production method as an example to illustrate the cleaning device provided in this application embodiment.
[0231] This application also provides a cleaning device. For example... Figure 1 As shown, the cleaning equipment includes a controller 40, a wastewater tank 11, a heating device 13 installed in the wastewater tank 11, and a temperature sensor 132 installed in the wastewater tank 11. The controller 40 is communicatively connected to the heating device 13 and the temperature sensor 132.
[0232] Temperature sensor 132 is used to detect the temperature of the sewage in sewage tank 11.
[0233] The heating device 13 is used to heat the sewage in the sewage tank 11 to the distillation temperature range. The lower limit of the distillation temperature range is not less than the boiling point of water in the sewage, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the sewage.
[0234] The controller 40 is used to control the heating device 13 to heat the sewage in the sewage tank 11 to the distillation temperature range when performing distillation water production.
[0235] In some embodiments, the controller 40 is also configured to control the heating device 13 to heat the wastewater in the wastewater tank 11 to a target distillation temperature within the distillation temperature range.
[0236] In some embodiments, the controller 40 is further configured to use the midpoint of the distillation temperature range as the target distillation temperature.
[0237] In some embodiments, the controller 40 is further configured to determine a target distillation temperature from the distillation temperature range based on the test results, wherein the test results are the results after the wastewater is heated to the temperature in the distillation temperature range and heated for a target duration, and the test results include the amount of remaining wastewater and / or odor intensity.
[0238] In some embodiments, the controller 40 is further configured to select multiple test temperatures from the distillation temperature range; obtain test results after heating wastewater to each test temperature and for a target heating time; and take the test temperature with the lowest odor intensity and / or the lowest amount of remaining wastewater in the test results as the target distillation temperature.
[0239] In some embodiments, the controller 40 is further configured to obtain the current test temperature from the distillation temperature range for testing; obtain the current test result after the wastewater is heated to the current test temperature and heated for a target duration; obtain the next test temperature based on the current test result and the current test temperature; use the next test temperature as the current test temperature, return to the step of obtaining the current test temperature from the distillation temperature range for testing, until the temperature test stop condition is met; and use the last test temperature as the target distillation temperature.
[0240] In some embodiments, the controller 40 is further configured to, when determining that the amount of residual wastewater in the current test result is greater than the target amount of wastewater and / or the odor intensity is less than the target odor intensity, increase the current test temperature within the distillation temperature range to obtain the next test temperature; and when determining that the amount of residual wastewater in the current test result is less than the target amount of wastewater and / or the odor intensity is greater than the target odor intensity, decrease the current test temperature within the distillation temperature range to obtain the next test temperature.
[0241] In some embodiments, the controller 40 is further configured to obtain the current test temperature range from the distillation temperature range, and use the median value of the current test temperature range as the current test temperature for testing, wherein the first test temperature range is the distillation temperature range.
[0242] In some embodiments, the controller 40 is further configured to determine the next test temperature range from the current test temperature range based on the current test result and the current test temperature, and to use the median value of the next test temperature range as the next test temperature.
[0243] In some embodiments, the controller 40 is further configured to, when determining that the amount of residual wastewater in the current test result is greater than the target amount of wastewater and / or the odor intensity is less than the target odor intensity, use the temperature range between the current test temperature and the upper limit of the current test temperature range as the next test temperature range; and when determining that the amount of residual wastewater in the current test result is less than the target amount of wastewater and / or the odor intensity is greater than the target odor intensity, use the temperature range between the lower limit of the current test temperature range and the current test temperature as the next test temperature range.
[0244] In some embodiments, the lower limit of the distillation temperature range is not less than the boiling point of water in the wastewater at the target altitude, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the wastewater at the target altitude. The target altitude is the altitude of the area where the water distillation is performed.
[0245] In some embodiments, combined with Figures 5 to 8 As shown, the heating device 13 can be located on the outside of the sewage tank 11, or it can be located inside the sewage tank 11, or it can be located both on the outside and inside the sewage tank 11. That is, the specific location of the heating device 13 can be determined according to the actual layout and is not limited here. For example... Figure 5 The heating device 13 is located at the bottom outside the sewage tank 11. The heating device 13 can be constructed as a commonly used heating device such as a heating wire or an electromagnetic heating device.
[0246] In some embodiments, the temperature sensor 132 may be located on the outside of the sewage tank 11, or it may be located inside the sewage tank 11, or it may be located both on the outside and inside the sewage tank 11. That is, the specific location of the temperature sensor 132 can be determined based on accurately detecting the temperature of the sewage in the sewage tank 11, and is not limited here. For example... Figure 5 The temperature sensor 132 is located at the bottom outside the sewage tank 11.
[0247] In some embodiments, the cleaning equipment further includes a refrigerant circulation system 20. The refrigerant circulation system 20 includes a compressor 21, an evaporator 22, a condenser 23, and a throttling element 24 forming a refrigerant circulation path, with the evaporator 22 defining a cooling assembly 15. That is, the compressor 21, evaporator 22, condenser 23, and throttling element 24 constitute the refrigerant circulation path, and the evaporator 22 defines the cooling assembly 15, meaning the cooling assembly 15 is located within the refrigerant circulation system 20. This facilitates the circulation of refrigerant within the circulation path and allows the cooling assembly 15 to continuously condense water vapor, thereby improving the cooling effect of the cooling assembly 15.
[0248] The principle of the refrigerant circulation system is as follows: the compressor 21 compresses the refrigerant into a high-temperature and high-pressure gaseous refrigerant. The gaseous refrigerant enters the condenser 23 and dissipates heat under the action of the heat dissipation fins and the fan. Then it enters the throttling element 24. The throttling element 24 reduces the pressure of the high-pressure gaseous refrigerant and converts it into a low-temperature liquid refrigerant, which enters the evaporator 22. The high-temperature water vapor condenses and liquefies in the low-temperature environment of the evaporator 22 to form clear water.
[0249] In some embodiments, the cleaning equipment further includes an agitator 17 disposed in the wastewater tank 11, the agitator 17 being located at the bottom inside the wastewater tank 11. The controller 40 is communicatively connected to the agitator 17. The agitator 17 is used to agitate the wastewater and / or impurities in the wastewater tank 11. The controller 40 is also used to control the operation of the agitator.
[0250] When performing water distillation, the controller 40 controls the heating device 13 to heat the wastewater in the wastewater tank 11 while simultaneously controlling the stirrer 17 to agitate the wastewater in the tank 11, accelerating the evaporation of water and improving the efficiency of water distillation. After stopping water distillation, the controller 40 can continue to control the heating device 13 to dry the wastewater tank 11. During the drying of the wastewater tank 11, the controller 40 can control the stirrer to agitate the impurities in the tank 11, accelerating the evaporation of moisture from the impurities and improving the drying efficiency.
[0251] In some embodiments, the cleaning equipment further includes a steam pipe 14 having an air inlet 141 and a steam valve 142 disposed within the steam pipe 14. The steam pipe 14 is connected between the wastewater tank 11 and the cooling assembly 15, and the controller 40 is communicatively connected to the steam valve 142. The cooling assembly 15 may be disposed on the outer wall of the steam pipe 14, inside the steam pipe 14, or at the outlet of the steam pipe 14.
[0252] The steam valve 142 is used to switch between a first valve position and a second valve position, wherein in the first valve position, the sewage tank 11 is connected to the steam pipe 14; and in the second valve position, the air inlet 141 is connected to the steam pipe 14.
[0253] The controller 40 is also used to control the steam valve 142 to switch between the first valve position and the second valve position.
[0254] Steam valve 142 can be located below air inlet 141. Controller 40 controls the switching of steam valve 142 between a first valve position and a second valve position, thereby controlling the connection between steam pipe 14, air inlet 141, and wastewater tank 11. When controller 40 controls steam valve 142 to switch to the first valve position (e.g., controlling steam valve 142 at a vertical angle), steam pipe 14 is disconnected from wastewater tank 11, and air inlet 141 is connected to steam pipe 14. Water vapor in the air enters cooling assembly 15 through steam pipe 14 to perform air-to-water conversion. When controller 40 controls steam valve 142 to switch to the second valve position (e.g., controlling steam valve 142 at a horizontal angle), steam pipe 14 is connected to wastewater tank 11, and air inlet 141 is disconnected from steam pipe 14. Water vapor generated in wastewater tank 11 enters cooling assembly 15 through steam pipe 14 to perform distillation-to-water conversion.
[0255] In some embodiments, the wastewater tank 11 is provided with an air inlet, and the controller 40 is also used to control the opening or closing of the air inlet. The controller 40 can control the air inlet to remain open continuously, or it can control the air inlet to remain open during the water distillation process. During the water distillation process, keeping the air inlet open allows air to enter the wastewater tank 11 through the air inlet to balance the air pressure after the wastewater tank 11 heats up and generates water vapor. At this time, the amount of air entering is relatively small, and the air can blow the water vapor generated by the wastewater tank 11 into the steam pipe 14. In some embodiments, air may not enter the steam pipe 14, as long as heating continues for a period of time to generate water vapor is sufficient.
[0256] In some embodiments, the cleaning equipment further includes a dust collection device 181 connected to the wastewater tank 11 and a dust collection fan 182 located at the dust collection device 181, and the controller 40 is also communicatively connected to the dust collection fan 182.
[0257] The dust collection fan 182 is used to draw impurities from the sewage tank 11 into the dust collection device 181.
[0258] Controller 40 is also used to control the operation of dust collection fan 182.
[0259] After drying stops, the controller 40 controls the dust collection fan 182 to draw impurities from the wastewater tank 11 into the dust collection device 181 to prevent the accumulation of impurities in the wastewater tank 11. During operation of the dust collection fan 182, the controller 40 can also control the agitator 17 to break up the impurities in the wastewater tank 11, making it easier for the broken-up impurities to be drawn into the dust collection device 181 by the dust collection fan 182. Additionally, during operation of the dust collection fan 182, the controller 40 can also control the steam valve 142 to switch off the steam pipe 14 from the wastewater tank 11, preventing impurities from entering the steam pipe 14.
[0260] In some embodiments, the cleaning equipment further includes a transfer wastewater tank 16, which is connected to the wastewater tank 11. The transfer wastewater tank is used to transport wastewater to the wastewater tank 11.
[0261] In some embodiments, a vacuum pump may be provided in the transfer sewage tank 16, and the controller 40 is also communicatively connected to the vacuum pump. The vacuum pump is used to draw sewage into the transfer sewage tank 16, and the controller 40 is also used to control the vacuum pump to draw sewage into the transfer sewage tank 16.
[0262] For example, when there is wastewater in the self-moving robot, a vacuum pump can be used to extract the wastewater from the self-moving robot into a transfer wastewater tank 16. Since the wastewater tank 11 requires heating, hot steam cannot be extracted by vacuuming to allow the wastewater in the self-moving robot to enter. Therefore, the transfer wastewater tank 16 ensures the extraction of wastewater from the self-moving robot. Moreover, the wastewater tank 11 requires heating, which limits its volume. The transfer wastewater tank 16 increases the volume of wastewater it can hold.
[0263] In some embodiments, the wastewater tank 11 may be located below the transfer wastewater tank 16, with the outlet of the transfer wastewater tank 16 facing the inlet of the wastewater tank 11. A control valve may be installed at the outlet of the transfer wastewater tank 16, and the controller 40 is also communicatively connected to the control valve. The control valve is used to switch between a first valve position and a second valve position, and the controller 40 is used to control the control valve to switch between the first valve position and the second valve position. Specifically, in the first valve position of the control valve, the transfer wastewater tank 16 is closed from the wastewater tank 11, and the controller 40 controls a vacuum pump to extract the air from the transfer wastewater tank 16, so that the wastewater from the self-propelled robot is drawn into the transfer wastewater tank 16; in the second valve position of the control valve, the transfer wastewater tank 16 is connected to the wastewater tank 11, and the wastewater in the transfer wastewater tank 16 flows into the wastewater tank 11 under the action of gravity.
[0264] In some embodiments, the cleaning equipment further includes a transfer clean water tank 19 connected between the cooling assembly 15 and the clean water tank 12. The transfer clean water tank 19 is used to collect condensed liquid water for conveying the condensed liquid water to the clean water tank 12.
[0265] In some embodiments, a vacuum pump can be installed at the clean water tank 12, and the vacuum pump is communicatively connected to the controller 40. The vacuum pump is used to draw clean water from the intermediate clean water tank 19 to the clean water tank 12, and the controller 40 controls the vacuum pump to draw clean water from the intermediate clean water tank 19 to the clean water tank 12 to replenish the clean water tank 12. The intermediate clean water tank 19 can improve the cleaning equipment's capacity to store clean water, allowing the cleaning equipment to store more clean water.
[0266] According to the cleaning equipment provided in the embodiments of this application, the sewage is heated to a distillation temperature range, which is not less than the boiling point of water in the sewage, so that the distillation temperature of the sewage is not less than the boiling point of water in the sewage, thus ensuring the distillation efficiency of the sewage. In addition, the distillation temperature range is less than the minimum boiling point of each solute in the sewage, so that the distillation temperature of the sewage is lower than the boiling point of each solute in the sewage, thus avoiding the generation of odor.
[0267] Accordingly, such as Figure 9As shown in the illustration, this application also provides a cleaning device, including a self-moving robot 30 and / or a cleaning base station 10. The self-moving robot 30 and / or the cleaning base station 10 includes a wastewater tank 11, a clean water tank 12, a cooling assembly 15, a heating device 13, a temperature sensor 132, and a controller 40. This embodiment achieves the same technical effects as the cleaning device described above, and to avoid repetition, it will not be described again here.
[0268] Accordingly, this application also provides a cleaning device, including a self-moving robot and / or a cleaning base station. The self-moving robot and / or the cleaning base station includes a memory and a processor. The memory stores a computer program, and the processor executes the computer program to implement the various processes of the above-described water control method and achieves the same technical effect. To avoid repetition, it will not be described again here.
[0269] It should be noted that, in this document, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes that element. Furthermore, it should be noted that the scope of the methods and apparatuses in the embodiments of this application is not limited to performing functions in the order shown or discussed, but may also include performing functions substantially simultaneously or in the reverse order, depending on the functions involved. For example, the described methods may be performed in a different order than described, and various steps may be added, omitted, or combined. Additionally, features described with reference to certain examples may be combined in other examples.
[0270] Through the above description of the embodiments, those skilled in the art can clearly understand that the methods of the above embodiments can be implemented by means of software plus necessary general-purpose hardware platforms. Of course, they can also be implemented by hardware, but in many cases the former is a better implementation method. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, can be embodied in the form of a computer software product. This computer software product is stored in a storage medium (such as ROM / RAM, magnetic disk, optical disk) and includes several instructions to cause a terminal (which may be a mobile phone, computer, server, or network device, etc.) to execute the methods described in the various embodiments of this application.
[0271] The embodiments of this application have been described above with reference to the accompanying drawings. However, this application is not limited to the specific embodiments described above. The specific embodiments described above are merely illustrative and not restrictive. Those skilled in the art can make many other forms under the guidance of this application without departing from the spirit and scope of the claims, and all of these forms are within the protection scope of this application.
[0272] In the description of this specification, the references to terms such as "one embodiment," "some embodiments," "illustrative embodiment," "example," "specific example," or "some examples," etc., indicate that a specific feature, structure, material, or characteristic described in connection with that embodiment or example is included in at least one embodiment or example of this application. In this specification, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.
[0273] Although embodiments of this application have been shown and described, those skilled in the art will understand that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of this application, the scope of which is defined by the claims and their equivalents.
Claims
1. A distillation water production method for cleaning an apparatus, characterized by, The cleaning device comprises a sewage tank and a heating device arranged in the sewage tank, and the method comprises: In the case of performing distillation water production, the heating device is controlled to heat the sewage in the sewage tank to a distillation temperature interval; wherein, The lower limit value of the distillation temperature interval is not less than the boiling point of water in the sewage, and the upper limit value of the distillation temperature interval is less than the minimum value of the boiling points of various solutes in the sewage; The control of the heating device to heat the sewage in the sewage tank to the distillation temperature interval comprises: controlling the heating device to heat the sewage in the sewage tank to a target distillation temperature in the distillation temperature interval; The target distillation temperature is determined from the distillation temperature interval according to test results, the test results being test results after heating the sewage to a temperature in the distillation temperature interval and for a target heating time, the test results including residual sewage amount and / or odor intensity.
2. The distillation water production method of a cleaning apparatus according to claim 1, characterized by, The distillation temperature interval is determined by: Determining each solute component in the sewage; Determining the boiling point of each solute component; Obtaining the boiling point of water in the sewage; According to the boiling point of water and the minimum value of each solute boiling point, the distillation temperature interval is determined.
3. The distillation water production method of a cleaning apparatus according to claim 1, wherein, The target distillation temperature is determined by: Taking the middle value of the distillation temperature interval as the target distillation temperature.
4. The distillation water production method of a cleaning apparatus according to claim 1, wherein, The determination of the target distillation temperature from the distillation temperature interval according to the test results comprises: Selecting a plurality of test temperatures from the distillation temperature interval; Obtaining test results obtained after heating the sewage to each test temperature and for a target heating time; Taking the test temperature with the smallest odor intensity and / or the smallest residual sewage amount in the test results as the target distillation temperature.
5. The distillation water production method of a cleaning apparatus according to claim 1, wherein, The determination of the target distillation temperature from the distillation temperature interval according to the test results comprises: Obtaining a current test temperature from the distillation temperature interval for testing; Obtaining a current test result after heating the sewage to the current test temperature and for a target heating time; According to the current test result and the current test temperature, a next test temperature is obtained; Taking the next test temperature as the current test temperature, returning to the step of obtaining the current test temperature from the distillation temperature interval for testing until the temperature test stop condition is met; Taking the last test temperature as the target distillation temperature.
6. The distillation water production method of a cleaning apparatus according to claim 5, wherein, The determination of the next test temperature according to the current test result and the current test temperature comprises: In the case where it is determined that the residual sewage amount in the current test result is greater than the target sewage amount, and / or the odor intensity is less than the target odor intensity, the current test temperature is increased within the distillation temperature interval to obtain the next test temperature; In the case where it is determined that the residual sewage amount in the current test result is less than the target sewage amount, and / or the odor intensity is greater than the target odor intensity, the current test temperature is decreased within the distillation temperature interval to obtain the next test temperature.
7. The distillation water production method of a cleaning apparatus according to claim 5, wherein The obtaining of the current test temperature from the distillation temperature interval for testing comprises: The current test temperature range is obtained from the distillation temperature range, and the median value of the current test temperature range is used as the current test temperature for testing. The first test temperature range is the distillation temperature range. The step of obtaining the next test temperature based on the current test result and the current test temperature includes: Based on the current test result and the current test temperature, determine the next test temperature range from the current test temperature range, and take the midpoint of the next test temperature range as the next test temperature.
8. The distillation water production method of a cleaning apparatus according to claim 7, wherein, The step of determining the next test temperature range from the current test temperature range based on the current test result and the current test temperature includes: If it is determined that the amount of residual wastewater in the current test result is greater than the target amount of wastewater and / or the odor intensity is less than the target odor intensity, the temperature range between the current test temperature and the upper limit of the current test temperature range shall be used as the next test temperature range. If it is determined that the amount of residual wastewater in the current test result is less than the target amount of wastewater, and / or the odor intensity is greater than the target odor intensity, the temperature range between the lower limit of the current test temperature range and the current test temperature shall be used as the next test temperature range.
9. The distillation water production method of a cleaning apparatus according to claim 1, wherein, The lower limit of the distillation temperature range is not less than the boiling point of water in the wastewater at the target altitude, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the wastewater at the target altitude. The target altitude is the altitude of the area where the distillation water production is performed.
10. A cleaning apparatus for carrying out the method according to any one of claims 1 to 9, characterized in that The cleaning equipment includes a controller, a wastewater tank, a heating device installed in the wastewater tank, and a temperature sensor installed in the wastewater tank. The controller is communicatively connected to the heating device and the temperature sensor, respectively. The temperature sensor is used to detect the temperature of the wastewater in the wastewater tank; The heating device is used to heat the sewage in the sewage tank to the distillation temperature range, wherein the lower limit of the distillation temperature range is not less than the boiling point of water in the sewage, and the upper limit of the distillation temperature range is less than the minimum boiling point of each solute in the sewage. The controller is used to control the heating device to heat the sewage in the sewage tank to the distillation temperature range when performing distillation water production.
11. The cleaning apparatus of claim 10, wherein, The cleaning equipment also includes a stirrer installed in the sewage tank, and the controller is communicatively connected to the stirrer; The agitator is used to agitate the sewage and / or impurities in the sewage tank; The controller is also used to control the operation of the stirrer.
12. The cleaning apparatus of claim 10, wherein, The cleaning equipment also includes a dust collection device connected to the sewage tank and a dust collection fan located at the dust collection device, and the controller is communicatively connected to the dust collection fan; The dust collection fan is used to draw impurities from the wastewater tank into the dust collection device; The controller is also used to control the operation of the dust collection fan.
Citation Information
Patent Citations
Wet cleaning apparatus with a dirty liquid tank
CN107752923A
Method and installation for distilling liquid
CN113396002A