A method for starting a skin bowl air extraction pump under high negative pressure and a gas detection method

By installing a sealing body and using a solenoid valve to control the vacuum pump, the problem of low efficiency of the vacuum pump under high negative pressure environment is solved, and efficient and stable gas detection is achieved, meeting the detection needs of coal mines.

CN116877397BActive Publication Date: 2026-11-24CHONGQING XINLIYUAN TECH CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310842224.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-07-11
Publication Date
2026-11-24
Estimated Expiration
2043-07-11

AI Technical Summary

Technical Problem

Under high negative pressure, the efficiency of the vacuum pump is low and it is difficult to start, resulting in low and unstable gas detection efficiency, which makes it difficult to meet the detection needs of the coal mining industry.

Method used

The structure employs a sealed body to enclose the cup-shaped air pump, connecting its air inlet to the negative pressure pipeline under test. This ensures that the cup-shaped air pump operates under the same pressure environment. The sealing body and heat dissipation fins improve heat dissipation, and the air path is controlled by a solenoid valve to achieve stable air extraction and testing.

Benefits of technology

It improves extraction efficiency and detection accuracy, shortens detection time, extends equipment life, and meets the detection requirements under high negative pressure environments in coal mines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116877397B_ABST
    Figure CN116877397B_ABST
Patent Text Reader

Abstract

This invention discloses a method for starting a vacuum pump under high negative pressure and a gas detection method. In the vacuum pump starting method, before starting, a vacuum pump assembly with the following structure is obtained: a base and a vacuum pump mounted on the base. The base is provided with a sealing body that encloses the vacuum pump. The inlet and outlet of the vacuum pump extend outside the sealing body, and the inner cavity of the sealing body is connected to the inlet of the vacuum pump. During startup, the inlet of the vacuum pump is connected to the negative pressure pipe to be tested through a pipe, and the vacuum pump is started. Both the vacuum pump starting method and the gas detection method of this invention have advantages such as improved pumping efficiency and shortened detection time under high negative pressure environments.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of coal mining technology, and in particular to a method for starting a vacuum pump under high negative pressure and a gas detection method. Background Technology

[0002] Methane gas is commonly extracted during coal mining. It can be used as fuel and a raw material for producing substances such as hydrogen. Therefore, it is necessary to collect and transport methane gas during mining. Monitoring the gas concentration (CH4, CO, O2, etc.) within the pipeline is essential during pipeline transport. To obtain sufficient samples, a vacuum pump is typically used to extract the gas from the pipeline. However, the significant negative pressure inside the pipeline (-50kPa to -80kPa, relative to standard atmospheric pressure) greatly reduces the efficiency of the vacuum pump and increases the difficulty of starting it. Furthermore, due to national and coal industry standards regarding the power requirements of electrical equipment in coal mining environments, it is not easy to replace the pump with a more powerful one. This significantly prolongs the extraction time, reduces detection efficiency, and may even prevent the pump from starting, thus making it impossible to measure the gas concentration under high negative pressure. Summary of the Invention

[0003] In view of the shortcomings of the prior art, the technical problem to be solved by the present invention is: how to provide a method for starting a cup-type air pump and a gas detection method that can improve the pumping efficiency, shorten the detection time and is easy to start under high negative pressure environment.

[0004] To solve the above-mentioned technical problems, the present invention adopts the following technical solution: A method for starting a vacuum pump under high negative pressure is characterized by first obtaining a vacuum pump assembly with the following structure: a base and a vacuum pump mounted on the base; a sealing body is provided on the base to enclose the vacuum pump; the air inlet and outlet of the vacuum pump extend outside the sealing body; and the inner cavity of the sealing body is connected to the air inlet of the vacuum pump. During startup, the air inlet of the vacuum pump is connected to the negative pressure pipe to be measured via a pipe, and the vacuum pump is then started.

[0005] In the above method, because the vacuum pump is enclosed in a sealed body, and the inner cavity of the sealed body is connected to the air inlet of the vacuum pump, which in turn is connected to the negative pressure pipeline being tested, the vacuum pump operates under the same pressure environment within the sealed body as the negative pressure pipeline. This pressure consistency between the inside and outside of the vacuum pump makes startup easier. Furthermore, because the vacuum pump always operates under the same pressure as the negative pressure pipeline, its output power is lower and more stable, resulting in higher pumping efficiency and faster gas detection, thus improving detection efficiency. Additionally, the increased and stable suction flow also improves detection accuracy. Moreover, the vacuum pump's long-term operation in a low-pressure-difference environment also extends its service life.

[0006] Furthermore, the sealing body is integrally sealed onto the cup-shaped air pump and the base. The sealing body has a connection port that communicates with the inner cavity. The air inlet of the cup-shaped air pump is provided with a T-junction, and the connection port is connected to the T-junction through an air pipe.

[0007] The integrated encapsulation structure not only achieves reliable sealing of the vacuum pump, but also allows the vacuum pump to be directly fixed to the base.

[0008] Furthermore, the sealing body is a sealing cover that is fastened to the base, and a sealing ring is provided between the sealing cover and the base; the sealing cover has two air nozzles that communicate with the inner cavity, and the air outlet of the leather cup vacuum pump is connected to one of the air nozzles.

[0009] In this way, the air inlet of the cup-shaped vacuum pump is located directly inside the sealing cover. When pumping air, the air inlet of the cup-shaped vacuum pump draws air from the inner cavity of the sealing cover, reducing the pressure in the inner cavity. The gas in the negative pressure pipeline to be tested flows into the sealing cover through the air nozzle.

[0010] Furthermore, the sealing body is provided with heat dissipation fins.

[0011] The vacuum pump generates heat during operation. By installing heat dissipation fins on the sealed body, the heat dissipation of the vacuum pump under sealed conditions can be improved.

[0012] A gas detection method under high negative pressure is characterized by first obtaining a detection system with the following structure: an inlet pipe, an inlet filter, a pump assembly, a gas sensor module for detecting gas concentration, and an outlet pipe are sequentially connected along the gas path; the pump assembly includes a base and a cup-shaped pump mounted on the base, the base being provided with a sealing body that encloses the cup-shaped pump, the inlet and outlet of the cup-shaped pump extending outside the sealing body and connected to the inlet filter and the gas sensor module respectively via gas pipes, and the inner cavity of the sealing body communicating with the inlet of the cup-shaped pump; during detection, the inlet pipe and outlet pipe are first connected to the negative pressure pipeline to be tested, and the cup-shaped pump is started to perform gas extraction detection.

[0013] In summary, the pump start-up method and gas detection method of the present invention have the advantages of improving pumping efficiency and shortening detection time under high negative pressure environment. Attached Figure Description

[0014] Figure 1 This is a schematic diagram of the gas flow rate and concentration measuring device in Example 1.

[0015] Figure 2 This is a schematic diagram of the gas path structure in Example 1.

[0016] Figure 3 This is a schematic diagram of the internal structure of the rear shell of Example 1.

[0017] Figure 4 This is a schematic diagram of the internal structure of the front cover in Example 1.

[0018] Figure 5 and Figure 6 This is a schematic diagram of the structure of the first and second filters in Example 1.

[0019] Figure 7 This is a schematic diagram of the gas sensor module in Example 1.

[0020] Figure 8 This is a schematic diagram of the air pump assembly in Example 2.

[0021] Figure 9 This is a schematic diagram of the gas path structure in Example 3.

[0022] Figure 10 This is a schematic diagram of the air pump assembly in Example 3. Detailed Implementation

[0023] The present invention will be further described in detail below with reference to an embodiment of the present invention.

[0024] Example 1: like Figure 1 and Figure 2 As shown, a gas flow rate and concentration measuring device under high negative pressure environment in a pipeline includes a rear housing 7 with an opening on one side and a front cover 8. The front cover 8 is located on the side of the rear housing 7 away from the opening and covers the rear housing 7. A flow rate detection module 1 and a concentration detection module 2 are arranged inside the rear housing 7 and the front cover 8. The flow rate detection module 1 includes a Pitot tube assembly 11 and a differential pressure element 12 for detecting total pressure and static pressure data. The Pitot tube assembly 11 includes a total pressure tube and a static pressure tube arranged side by side. The tubes are connected to the corresponding differential pressure elements 12 via pipelines; the concentration detection module 2 includes an inlet pipe 21 and an outlet pipe 22 arranged side by side with the total pressure pipe and the static pressure pipe, and the inlet pipe 21 and the outlet pipe 22 are connected in sequence via pipelines to a first inlet filter 23, a pump assembly 24 and a gas sensor module 25 for detecting gas concentration; in this embodiment, a protective sleeve 17 is installed on the rear housing 7, and the protective sleeve 17 is fitted onto the total pressure pipe, the static pressure pipe, the inlet pipe 21 and the outlet pipe 22.

[0025] The concentration detection module 2 further includes a first solenoid valve 26 and a second solenoid valve 27. The first solenoid valve 26 is connected between the gas sensor module 25 and the outlet pipe 22, and is used to control the gas flow between the gas sensor module 25 and the outlet pipe 22. The second solenoid valve 27 is connected between the first inlet filter 23 and the pump assembly 24. The second solenoid valve 27 also has a vent to the atmosphere, and is used to switch the pump assembly 24 to be connected to the first inlet filter 23 or to the atmosphere. To prevent impurities from entering the pump assembly, a second inlet filter 29 is also provided in the gas path between the second solenoid valve 27 and the pump assembly 24.

[0026] The flow rate detection module 1 further includes a fourth solenoid valve 13 and a fifth solenoid valve 14. The fourth solenoid valve 13 and the fifth solenoid valve 14 are respectively connected between the total pressure pipe and the static pressure pipe and the corresponding differential pressure element 12. The fourth solenoid valve 13 and the fifth solenoid valve 14 also have interconnected ports. The fourth solenoid valve 13 is used to switch the differential pressure element 12 to connect to the corresponding total pressure pipe or the port, and the fifth solenoid valve 14 is used to switch the differential pressure element 12 to connect to the corresponding static pressure pipe or the port.

[0027] During measurement, the total pressure pipe, static pressure pipe, inlet pipe, and outlet pipe, arranged side-by-side, are all inserted into the gas pipeline. Gas flow rate is measured first, followed by gas concentration. Since the flow rate measurement process requires no external interference with the gas within the pipeline, it does not affect the gas state, including local gas concentration. After the flow rate measurement is completed, the extraction pump assembly is activated to extract gas from the gas pipeline. Because coal mine gas pipelines contain a significant amount of impurities, a first intake filter is installed between the inlet pipe and the extraction pump assembly to filter these impurities. This prevents impurities from clogging the gas path, increasing reliability and extending the equipment's lifespan. The filtered gas then flows through the gas sensor module for gas concentration measurement.

[0028] Specifically, to ensure accuracy during flow velocity measurement, the differential pressure element needs to be zeroed before measurement. This is achieved by connecting the differential pressure element to the connection port via the fourth and fifth solenoid valves, ensuring communication between the total pressure and static pressure detection terminals. During flow velocity measurement, the total pressure and static pressure pipes are connected to their respective differential pressure elements via the fourth and fifth solenoid valves, thus enabling flow velocity measurement.

[0029] Since the measuring device in this embodiment is always located outside the gas pipeline during use, and the suction pump assembly needs to extract gas from the pipeline under negative pressure, the two sides of the suction pump assembly's diaphragm experience a large pressure difference (the pressure difference between atmospheric pressure and the negative pressure in the pipeline). This makes it difficult to start and efficiently extract gas even when the suction pump assembly's power meets national and coal mining industry standards. To ensure reliable start-up of the suction pump assembly, based on the above structure, during concentration measurement, the first and second solenoid valves can be closed first, cutting off the gas path between the gas sensor module and the outlet pipe, and connecting the suction pump assembly to the atmosphere. This ensures that the suction pump assembly and its inlet section are under atmospheric pressure, reducing the pressure difference on both sides of the diaphragm. The suction pump assembly is then started to extract gas, increasing the pressure in the gas sensor module. After reaching a first set time or pressure, the first solenoid valve is opened, connecting the gas path between the gas sensor module and the outlet pipe, releasing the pressure in the gas sensor module, and maintaining a pressure higher than the pipeline pressure. This stabilizes the airflow rate in the gas sensor module. After the second set time is reached, the second solenoid valve is opened to connect the air pump assembly to the first air intake filter, keeping the pressure of the gas sensor module higher than the pipeline pressure. This not only maintains the stability of the airflow but also blows out the original air inside the gas sensor module, allowing the gas to flow more smoothly through the gas sensor module and making the gas concentration detection more accurate.

[0030] Both the first intake filter 23 and the second intake filter 29 include a base plate 4 and a cover plate 5 that are interlocked. The base plate 4 has a recessed positioning groove 41, and a first filter chamber 42 is recessed in the center of the positioning groove 41. The base plate 4 has a first air inlet that communicates with the first filter chamber 42. The cover plate 5 has a protruding positioning platform 51 that matches the positioning groove 41. The positioning platform 51 has a recessed second filter chamber 52 in the center. The positioning platform 51 also has a surrounding element. The first filter chamber 42 is provided with a sealing groove 53, and a sealing ring is provided in the sealing groove 53. The cover plate 5 has a second air port that communicates with the second filter chamber 52. Both the first filter chamber 42 and the second filter chamber 52 have protruding air guide columns, and multiple air guide columns are distributed at intervals in both the first filter chamber 42 and the second filter chamber 52. The positioning platform 51 is fitted into the positioning groove 41, and a waterproof and breathable membrane separating the first filter chamber 42 and the second filter chamber 52 is sandwiched between them.

[0031] The positioning groove 41, the first filter chamber 42, the positioning platform 51, and the second filter chamber 52 are all circular. The air guide column is arranged in multiple layers in a ring along the axis of the corresponding first filter chamber 42 and second filter chamber 52. The first air port and the second air port are respectively arranged radially along the first filter chamber 42 and the second filter chamber 52, and the projections of the first air port and the second air port in the thickness direction of the base plate 4 are staggered.

[0032] During filtration, the gas containing impurities and water vapor enters from the first or second air inlet. Under the obstruction of the distributed air guide columns, it disperses in the first or second filter chamber and passes through the waterproof and breathable membrane to the other side. The impurities and water vapor in the gas are trapped by the waterproof and breathable membrane.

[0033] In this embodiment, as Figure 5 and Figure 6 As shown, the first intake filter 23 and the second intake filter 29 are stacked on top of each other, and the cover plate of the first intake filter 23 and the base plate of the second intake filter 29 are integral structures.

[0034] Because the gas pipeline contains many impurities, and the concentration detection process requires gas extraction via a vacuum pump assembly, many impurities are drawn into the intake pipe, eventually accumulating in the gas path between the first intake filter and the intake pipe, causing blockage. Therefore, the concentration detection module 2 also includes a normally closed third solenoid valve 28. One end of the third solenoid valve 28 is connected to the gas path between the second solenoid valve 27 and the first intake filter 23, and the other end is open to the atmosphere.

[0035] After the concentration measurement is completed, the second solenoid valve is closed to cut off the air inlet of the second solenoid valve, and the third solenoid valve is opened to connect the air outlet of the first air inlet filter to the atmosphere. The pressure difference is used to allow the outside air to flow back into the gas pipeline through the third solenoid valve, the first air inlet filter and the air inlet pipe, thereby achieving backflushing of the first air inlet filter and the air inlet pipe and blowing the impurities back into the gas pipeline.

[0036] During flow velocity measurement, although the gas in the gas pipeline is not actively extracted, the openings of the total pressure pipe and the static pressure pipe are completely open in order to ensure the accuracy of the flow velocity measurement. Impurities in the gas pipeline will slowly enter under the action of airflow and eventually remain in the total pressure pipe or the static pressure pipe, causing blockage. This will affect the accuracy of subsequent flow velocity measurement and the service life of the equipment.

[0037] Therefore, the flow rate detection module 1 further includes a sixth solenoid valve 15 and a seventh solenoid valve 16. One end of the sixth solenoid valve 15 is connected to the air passage between the static pressure pipe and the fifth solenoid valve 14, and the other end is connected to the atmosphere. One end of the seventh solenoid valve 16 is connected to the air passage between the total pressure pipe and the fourth solenoid valve 13, and the other end is connected to the atmosphere. Through the sixth and seventh solenoid valves, the total pressure pipe and the static pressure pipe can be directly connected to the atmosphere, and atmospheric pressure can be used to introduce outside air into the gas pipeline to backflush the air intake pipe.

[0038] To prevent dust from entering from the atmosphere from causing secondary pollution to the gas path, the ends of the sixth solenoid valve 15, the seventh solenoid valve 16, the second solenoid valve 27, and the third solenoid valve 28 that are connected to the atmosphere are connected to a vacuum filter 3.

[0039] In this embodiment, as Figure 3 and Figure 4 As shown, the first intake filter 23, the second intake filter 29 and the vacuum filter 3 are all disposed inside the rear housing 7, and the first solenoid valve 26, the second solenoid valve 27, the third solenoid valve 28, the fourth solenoid valve, the fifth solenoid valve, the sixth solenoid valve, the air pump assembly 24 and the gas sensor module 25 are all mounted on the back of the rear housing 7.

[0040] like Figure 7 As shown, the gas sensor module 25 includes a rectangular substrate with a vent hole extending along its length and gas nozzles extending from both ends of the vent hole. The substrate has multiple sensor mounting seats arranged along its length, and the bottom of each sensor mounting seat is connected to the vent hole. Sensors (not shown in the figure) for detecting CH4 concentration, CO concentration, and O2 concentration are respectively mounted on the sensor mounting seats.

[0041] The working procedure for measuring gas flow rate and concentration using this embodiment is as follows: 1. By default, all solenoid valves are not energized: the first solenoid valve 26 is closed by default, and the air pump outlet is closed; the third solenoid valve 28 is closed by default; the second solenoid valve 27 is connected to the atmosphere and the air pump assembly by default; the sixth solenoid valve 15 is closed by default; the fourth solenoid valve 13 and the fifth solenoid valve 14 are connected to each other by default; and the seventh solenoid valve 16 is closed by default.

[0042] 2. Power on the equipment, zero the differential pressure element, open the fourth solenoid valve 13 and the fifth solenoid valve 14, and start measuring the flow rate, temperature and pressure for 15 seconds.

[0043] 3. After the flow rate, temperature and pressure measurements are completed, close the fourth solenoid valve 13 and the fifth solenoid valve 14.

[0044] 4. With the gas supply connected to the atmosphere, start the air pump assembly and detect the increase in internal pressure of the gas sensor module to ensure smooth start-up of the air pump, with a delay of 200ms; open the first solenoid valve 26, and the gas sensor module releases pressure to a level higher than the pipeline pressure, with a delay of 200ms, stabilizing the air flow rate within the gas sensor module to ensure stable operation of the air pump assembly; open the second solenoid valve 27, and the air intake of the air pump assembly changes from the atmosphere to the pipeline. Due to the lower pressure in the gas pipeline, the internal pressure of the gas sensor module will continue to decrease, but it will remain higher than the pipeline pressure under the action of the air pump assembly.

[0045] 5. The gas extraction pump assembly maintains a stable rate (stable operation) to extract gas from the pipeline. Keep the gas extraction pump running continuously for 20 seconds until the gas concentration stabilizes before taking a measurement to ensure the accuracy of gas concentration detection. After a delay of 5 to 10 seconds, take the average value of the measurement results.

[0046] 6. Turn off the air pump assembly and all solenoid valves to complete the measurement.

[0047] Alternatively, the pipeline can be cleaned separately by opening the third solenoid valve 28, the sixth solenoid valve 15, and the seventh solenoid valve 16 in sequence.

[0048] Example 2: The main difference between this embodiment and Embodiment 1 is: In Example 1, in order for the air pump assembly 24 to start smoothly, it is necessary to switch the solenoid valve and the air circuit multiple times. It is also necessary to delay the air pumping to ensure that the air pumped in when starting the air pump is reliably discharged, so as to ensure the stability of the gas concentration extracted subsequently. This results in a long detection time and complex control.

[0049] Therefore, in this embodiment, as Figure 8 As shown, the vacuum pump assembly 24 includes a base 61 and a cup vacuum pump 62 mounted on the base 61. The base 61 is provided with a sealing body 63 that seals and encloses the cup vacuum pump 62. The air inlet and outlet of the cup vacuum pump 62 extend outside the sealing body 63 and are connected to the air inlet filter 23 and the gas sensor module 25 respectively through air pipes. The inner cavity of the sealing body 63 is connected to the air inlet of the cup vacuum pump 62.

[0050] Because the vacuum pump is enclosed in a sealed body, and the inner cavity of the sealed body is connected to the pump's inlet, which in turn connects to the negative pressure pipeline being tested, the vacuum pump operates under the same pressure environment within the sealed body as the pipeline. This pressure consistency facilitates easier startup. Furthermore, since the vacuum pump operates at the same pressure as the pipeline, its output power is more stable, resulting in higher pumping efficiency and faster gas detection. The increased and stable suction flow also improves detection accuracy. Finally, the vacuum pump's long-term operation in a low-pressure-difference environment extends its service life.

[0051] In this embodiment, the sealing body 63 is a sealing cover that is fastened to the base 61. A sealing ring is provided between the sealing cover and the base 61, and it is fixedly installed on the base 61 by bolts. The sealing cover has two air nozzles that communicate with the inner cavity. The air outlet of the cup vacuum pump 62 is connected to one of the air nozzles, and the air inlet of the cup vacuum pump 62 is located inside the sealing cover.

[0052] During evacuation, the air inlet of the cup-shaped vacuum pump draws air from the inner cavity of the sealing cover, thereby further reducing the pressure in the inner cavity. The gas in the negative pressure pipeline under test flows into the sealing cover through the air nozzle under the action of pressure difference, which can ensure that the cup-shaped vacuum pump is in a low-pressure environment, reduce the pressure difference acting on the cup, and ensure the working efficiency of the cup-shaped vacuum pump.

[0053] In a specific implementation, the sealing body 63 can also adopt another structure, namely, the sealing body 63 is integrally encapsulated on the cup-shaped vacuum pump 62 and the base 61. The sealing body 63 has a connection port that communicates with the inner cavity, and the air inlet of the cup-shaped vacuum pump 62 is provided with a T-junction. The connection port is connected to the T-junction through an air pipe. The integral encapsulation structure can achieve both reliable sealing of the cup-shaped vacuum pump and direct fixation of the cup-shaped vacuum pump to the base.

[0054] Example 3: The main difference between this embodiment and Embodiment 2 is: like Figure 9 As shown, the concentration detection module 2 further includes a first solenoid valve 26 and a second solenoid valve 27. The first solenoid valve 26 is connected between the gas sensor module 25 and the gas outlet pipe 22, and is used to control the gas flow between the gas sensor module 25 and the gas outlet pipe 22. The second solenoid valve 27 is connected between the first air inlet filter 23 and the air pump assembly 24, and is used to control the gas flow between the first air inlet filter 23 and the air pump assembly 24. like Figure 10 As shown, the sealing body 63 is a sealing cover that is fastened to the base 61. A sealing ring is provided between the sealing cover and the base 61 and it is fixedly installed on the base 61 by bolts. The sealing cover has three air nozzles that communicate with the inner cavity. The air outlet of the cup vacuum pump 62 is connected to one of the air nozzles, and the air inlet of the cup vacuum pump 62 is located inside the sealing cover.

[0055] The nozzle on the sealing body 63 connected to the air outlet is connected to the gas sensor module 25 through a pipeline. The other two nozzles are distributed on both sides of the sealing body 63. One nozzle is connected to the second solenoid valve 27 through a pipeline, and the other nozzle is connected to the second air inlet filter 29, the third solenoid valve 28 and the vacuum filter 3 in sequence through a pipeline. The vacuum filter 3 is the same as the atmosphere.

[0056] The working procedure for measuring gas flow rate and concentration using this embodiment is as follows: 1. In the default state, all solenoid valves are not energized: the first solenoid valve 26 and the second solenoid valve 27 are closed by default; the third solenoid valve 28 is open by default, connecting to the atmosphere and the air pump assembly; everything else is the same as in Example 1, and the measurement steps for flow rate, temperature and pressure are the same as in Example 1, and will not be repeated here.

[0057] 2. Start the air pump assembly, and the internal pressure of the gas sensor module increases; after a 200ms delay, the first solenoid valve 26 opens, and the gas sensor module releases pressure to a level higher than the pipeline pressure; after a 200ms delay, the second solenoid valve 27 and the third solenoid valve 28 open (energized), and the air intake of the air pump assembly changes from the atmosphere to the pipeline, and the internal pressure of the gas sensor module continues to decrease and remains higher than the pipeline pressure.

[0058] 3. Keep the air pump running for 20 seconds. After the gas concentration stabilizes, take the measurement and wait for 5 to 10 seconds. Take the average value of the measurement results.

[0059] 4. Turn off the air pump assembly and all solenoid valves to complete the measurement.

[0060] In this embodiment, when cleaning the gas path for gas concentration detection, the second solenoid valve 27 is opened. Under atmospheric pressure, outside air passes through the vacuum filter 3, the third solenoid valve 28, and the second intake filter 29 in sequence, enters the sealing body 63 through one of the air nozzles, flows through the inner cavity of the sealing body, and flows out through the air nozzle on the other side. Then, it passes through the second solenoid valve 27, the first intake filter 23, and the intake pipe 21 in sequence and enters the gas pipeline.

[0061] The vacuum pump inevitably generates heat during operation. Sealing the vacuum pump within a sealed enclosure reduces its heat dissipation efficiency. However, during the backflushing cleaning process described above, outside air flows into the sealed enclosure 63 from one side and out from the other, allowing for ample contact and heat exchange with the vacuum pump. This significantly reduces heat loss from the sealed enclosure 63, effectively cooling the vacuum pump while simultaneously performing the backflushing cleaning.

[0062] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A method for starting a vacuum pump under high negative pressure, characterized in that, First, obtain a vacuum pump assembly with the following structure, including a base (61) and a cup vacuum pump (62) mounted on the base (61). The base (61) is provided with a sealing body (63) that seals and encloses the cup vacuum pump (62). The sealing body (63) has three air nozzles that communicate with the inner cavity. The air inlet of the cup-shaped air pump (62) is located inside the sealing body (63). The air outlet of the cup-shaped air pump (62) is connected to one of the air nozzles and connected to the negative pressure pipeline to be tested through the first solenoid valve (26). One of the other two air nozzles is connected to the negative pressure pipeline to be tested through the second solenoid valve (27), and the other is connected to the atmosphere through the third solenoid valve (28). When starting, the first solenoid valve (26) and the second solenoid valve (27) are closed, and the third solenoid valve (28) is opened to connect the atmosphere and the air pump assembly; the cup-shaped air pump (62) is started to increase the pressure at the outlet end; After a first set time delay, the first solenoid valve (26) is opened, releasing the pressure at the outlet end to a level higher than the pressure of the negative pressure pipeline to be tested; After a second set time delay, the second solenoid valve (27) is opened and the third solenoid valve (28) is disconnected from the atmosphere, so that the air intake of the air pump assembly is changed from the atmosphere to the negative pressure pipeline to be tested. The pressure at the air extraction end continues to decrease and remains higher than the pressure of the negative pressure pipeline to be tested, thus completing the start-up.

2. The method for starting a vacuum pump under high negative pressure as described in claim 1, characterized in that, The first setting time and the second setting time are both 200ms.

3. The method for starting a vacuum pump under high negative pressure as described in claim 1, characterized in that, The third solenoid valve (28) has a vacuum filter (3) connected to one end that is open to the atmosphere.

4. The method for starting a vacuum pump under high negative pressure as described in claim 1, characterized in that, The sealing body (63) is a sealing cover that is fastened to the base (61). A sealing ring is provided between the sealing cover and the base (61), and it is fixedly installed on the base (61) by bolts.

5. A gas detection method under high negative pressure, characterized in that, First, obtain a detection system with the following structure, including an air inlet pipe (21), a first air inlet filter (23), a pump assembly (24), a gas sensor module (25) for detecting gas concentration, and an outlet pipe (22) connected sequentially along the gas path. The vacuum pump assembly (24) includes a base (61) and a cup vacuum pump (62) mounted on the base (61). The base (61) is provided with a sealing body (63) that seals and encloses the cup vacuum pump (62). The sealing body (63) has three air nozzles that communicate with the inner cavity. The air inlet of the cup vacuum pump (62) is located inside the sealing body (63). The air outlet of the cup vacuum pump (62) is connected to one of the air nozzles and connected to the gas sensor module (25). A first solenoid valve (26) is connected between the gas sensor module (25) and the air outlet pipe (22). One of the other two air nozzles is connected to the first air intake filter (23) through a second solenoid valve (27), and the other is connected to the atmosphere through a second air intake filter (29) and a third solenoid valve (28). During testing, the air inlet pipe (21) and air outlet pipe (22) are connected to the negative pressure pipeline to be tested; the first solenoid valve (26) and the second solenoid valve (27) are closed first, and the third solenoid valve (28) is opened. Start the vacuum pump (62) to increase the internal pressure of the gas sensor module (25); after a first set time, open the first solenoid valve (26) to release the internal pressure of the gas sensor module (25) to a level higher than the pressure of the negative pressure pipeline to be measured; After a second set time delay, the second solenoid valve (27) is opened and the connection between the third solenoid valve (28) and the atmosphere is cut off, so that the air intake of the air pump assembly (24) is changed from the atmosphere to the negative pressure pipeline to be tested, and the internal pressure of the gas sensor module (25) is kept higher than the pressure of the negative pressure pipeline to be tested for air pumping detection; after detection, the leather cup air pump (62) is turned off, the second solenoid valve (27) is opened and the third solenoid valve (28) is opened to connect to the atmosphere for backflushing and heat dissipation.