Method, device and readable storage medium for scheduling maintenance work order
By using knowledge graphs to calculate similarity and installation/maintenance personnel evaluation information in work order scheduling, the problem of unreasonable work order scheduling in the past has been solved, and efficient allocation of installation/maintenance work orders has been achieved.
Patent Information
- Application Number
- CN202210472801.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-04-29
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2042-04-29
AI Technical Summary
The existing work order scheduling method is unreasonable, resulting in low work order allocation efficiency, requiring manual transfer of work orders, and making it impossible to process installation and maintenance tasks in a timely manner.
By acquiring the attribute information of the installation and maintenance work orders to be scheduled, calculating the similarity using historical installation and maintenance work order data in the knowledge graph database, determining the target installation and maintenance team and personnel, and combining the evaluation information and capability values of the installation and maintenance personnel, selecting the most suitable installation and maintenance personnel to carry out on-site construction.
This improved the rationality and efficiency of work order scheduling, reduced the workload of unreasonable work order assignments and manual work order transfers, and ensured that installation and maintenance tasks were completed on time.
Smart Images

Figure CN117035246B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of artificial intelligence technology, and in particular to a method, apparatus, device, and readable storage medium for scheduling installation and maintenance work orders. Background Technology
[0002] The intelligent work order scheduling method refers to a method that uses a work order scheduling center to centrally schedule and select the most suitable installation and maintenance personnel for on-site construction of installation and maintenance work orders.
[0003] The existing work order scheduling method is to select the nearest installation and maintenance worker whose remaining capacity meets the workload of the new installation and maintenance work order and is based on the remaining capacity of the installation and maintenance personnel and the distance between the current location of the installation and maintenance personnel and the new installation and maintenance location.
[0004] However, existing solutions are prone to errors and inconsistencies in work order scheduling, which reduces the efficiency of work order scheduling. For example, if an installation or maintenance address is assigned to an address that is not within the jurisdiction of the installation or maintenance personnel, work orders that are assigned inappropriately need to be manually reassigned by the installation or maintenance personnel, resulting in low work order scheduling efficiency. Summary of the Invention
[0005] This application provides a method, apparatus, device, and readable storage medium for scheduling installation and maintenance work orders, in order to solve the defects of unreasonable work order scheduling in the prior art and achieve efficient scheduling of installation and maintenance work orders.
[0006] In a first aspect, embodiments of this application provide a method for scheduling installation and maintenance work orders, including:
[0007] Obtain the first attribute information from the installation and maintenance work order to be scheduled, wherein the first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0008] Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0009] Determine the similarity between the first attribute information and each of the second attribute information;
[0010] In one embodiment, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the plurality of historical installation and maintenance work orders, and the target installation and maintenance group includes at least one installation and maintenance personnel;
[0011] The target installation and maintenance personnel are identified from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
[0012] In one embodiment, determining the target installation and maintenance group from the installation and maintenance groups corresponding to each of the plurality of historical installation and maintenance work orders based on the similarity of each of the second attribute information includes:
[0013] The similarity of each of the second attribute information is sorted in descending order to determine the first historical installation and maintenance work order corresponding to the first preset number of second attribute information.
[0014] Determine the installation and maintenance group corresponding to each of the first preset number of first historical installation and maintenance work orders;
[0015] The maintenance group that appears most frequently is identified as the target maintenance group.
[0016] In one embodiment, determining the target maintenance personnel from the target maintenance group includes:
[0017] Based on the first evaluation information of each installation and maintenance personnel in the target installation and maintenance group, determine the recommendation index of each installation and maintenance personnel;
[0018] The recommendation index of each installation and maintenance personnel is sorted in descending order to determine the installation and maintenance personnel corresponding to the first second preset number of recommendation indices;
[0019] The target installation and maintenance personnel are determined based on the installation and maintenance capability value and available installation and maintenance time of each of the first two preset number of recommendation indices.
[0020] In one embodiment, determining the recommendation index for each installation and maintenance personnel based on the first evaluation information of each personnel in the target installation and maintenance group includes:
[0021] The recommendation index for each installation and maintenance personnel is determined according to the following formula:
[0022] f(P,T)=C1·g(X(P,T))+C2·h(Y(P,T))
[0023] Where T is the installation and maintenance work order, P is the installation and maintenance personnel corresponding to the installation and maintenance work order; g is the indicator function affecting customer satisfaction, h is the installation and maintenance efficiency indicator function, C1 is the customer satisfaction indicator weight coefficient, C2 is the installation and maintenance efficiency indicator weight coefficient; f(P,T) is the recommendation index of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; X(P,T) is the satisfaction indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; Y(P,T) is the installation and maintenance efficiency indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T.
[0024] In one embodiment, the first attribute information also includes installation and maintenance time information;
[0025] The step of determining the target installation and maintenance personnel based on the installation and maintenance capability value and available installation and maintenance time of each of the first second preset number of recommendation indices includes:
[0026] Based on the installation and maintenance capability values of the installation and maintenance personnel corresponding to the first second preset number of recommendation indices, determine the installation and maintenance personnel whose installation and maintenance capability values are greater than the preset values;
[0027] Match the available installation and maintenance time of installation and maintenance personnel whose installation and maintenance capability value is greater than the preset value with the installation and maintenance time information;
[0028] The successfully matched installation and maintenance personnel are identified as the target installation and maintenance personnel. In one embodiment, before retrieving the knowledge graphs corresponding to multiple historical installation and maintenance work orders from the knowledge graph library, the method further includes:
[0029] Information is extracted from multiple historical installation and maintenance work orders and the corresponding installation and maintenance information for each of the multiple historical installation and maintenance work orders, to obtain the installation and maintenance location information, installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order;
[0030] Based on the installation and maintenance location information, the installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order, a knowledge graph corresponding to each historical installation and maintenance work order is constructed.
[0031] In one embodiment, after determining the target equipment maintenance personnel from the target equipment maintenance group, the method further includes:
[0032] Based on the installation and maintenance location information of the installation and maintenance work order to be scheduled, the target installation and maintenance personnel and the target installation and maintenance group, and the corresponding customer information, a knowledge graph corresponding to the installation and maintenance work order to be scheduled is constructed.
[0033] Add the knowledge graph corresponding to the installation and maintenance work order to be scheduled to the knowledge graph library.
[0034] In one embodiment, after sending the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel, the method further includes:
[0035] Receive the second evaluation information sent by the terminal for the target installation and maintenance personnel;
[0036] The first evaluation information of the target maintenance personnel is updated based on the second evaluation information.
[0037] Secondly, embodiments of this application provide a scheduling device for installation and maintenance work orders, comprising:
[0038] The acquisition unit is used to acquire the first attribute information in the installation and maintenance work order to be scheduled, the first attribute information including the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0039] The acquisition unit is also used to acquire the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library;
[0040] The determining unit is used to determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graph corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0041] The determining unit is further configured to determine the similarity between the first attribute information and each of the second attribute information;
[0042] The determining unit is further configured to determine a target installation and maintenance group from the installation and maintenance groups corresponding to each of the plurality of historical installation and maintenance work orders based on the similarity of each of the second attribute information, wherein the target installation and maintenance group includes at least one installation and maintenance personnel.
[0043] The determining unit is further configured to determine the target maintenance personnel from the target maintenance group;
[0044] The sending unit is used to send the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel.
[0045] Thirdly, embodiments of this application provide a terminal, including a memory, a transceiver, and a processor;
[0046] A memory for storing computer programs; a transceiver for sending and receiving data under the control of the processor; and a processor for reading the computer programs from the memory and performing the following operations:
[0047] Obtain the first attribute information from the installation and maintenance work order to be scheduled, wherein the first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0048] Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0049] Determine the similarity between the first attribute information and each of the second attribute information;
[0050] Based on the similarity of each of the second attribute information, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel.
[0051] The target installation and maintenance personnel are identified from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
[0052] Fourthly, embodiments of this application provide an electronic device, including a processor and a memory storing a computer program, wherein the processor executes the program to implement the steps of the installation and maintenance work order scheduling method described in the first aspect.
[0053] Fifthly, embodiments of this application provide a computer program product, including a computer program that, when executed by a processor, implements the steps of the installation and maintenance work order scheduling method described in the first aspect.
[0054] The installation and maintenance work order scheduling method, apparatus, equipment, and readable storage medium provided in this application embodiment obtain first attribute information from the installation and maintenance work order to be scheduled, and obtain second attribute information corresponding to each historical installation and maintenance work order through the knowledge graph corresponding to each of the multiple historical installation and maintenance work orders. Then, the target installation and maintenance group is determined by calculating the similarity between the first attribute information and the second attribute information, and the final target installation and maintenance personnel are determined based on the target installation and maintenance group. Since both the first attribute information and the second attribute information include installation and maintenance location information, and historical installation and maintenance work orders can reflect which areas the installation and maintenance personnel have previously installed and maintained, the accuracy of the installation and maintenance work orders to be scheduled can be improved by using historical installation and maintenance work orders. This can reduce the situation where the installation and maintenance address does not fall within the jurisdiction of the installation and maintenance personnel, thereby improving the rationality and efficiency of work order scheduling. Attached Figure Description
[0055] To more clearly illustrate the technical solutions in this invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of this invention. For those skilled in the art, other drawings can be obtained from these drawings without creative effort.
[0056] Figure 1 This is one of the flowcharts illustrating the scheduling method for installation and maintenance work orders provided in the embodiments of this application;
[0057] Figure 2 This is a second flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application embodiment;
[0058] Figure 3 This is the third flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application embodiment;
[0059] Figure 4 This is the fourth flowchart illustrating the scheduling method for installation and maintenance work orders provided in the embodiments of this application;
[0060] Figure 5 This is the fifth flowchart illustrating the scheduling method for installation and maintenance work orders provided in the embodiments of this application;
[0061] Figure 6 This is a schematic diagram of a knowledge graph triple provided in an embodiment of this application;
[0062] Figure 7 This is a schematic diagram of the home broadband installation knowledge graph provided in the embodiments of this application;
[0063] Figure 8 This is the sixth flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application embodiment;
[0064] Figure 9 This is the seventh flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application embodiment;
[0065] Figure 10 This is the eighth flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application embodiment;
[0066] Figure 11 This is a schematic diagram of the terminal structure provided in the embodiments of this application;
[0067] Figure 12 This is a schematic diagram of the structure of the electronic device provided in the embodiments of this application. Detailed Implementation
[0068] To make the objectives, technical solutions, and advantages of this application clearer, the technical solutions of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0069] This application applies to broadband installation and maintenance scenarios for telecom operators. Operators have high requirements for broadband installation and maintenance services; installations generally need to be completed within 3 working days, and faults must be repaired within 12 hours. Therefore, new tasks such as broadband installation and fault maintenance may arise that must be handled on the same day, especially during peak periods like winter and summer vacations, requiring immediate dispatch of new work orders to on-site installation and maintenance personnel. Current work order scheduling only selects the nearest installation and maintenance personnel whose remaining capacity meets the workload of the new work order based on the personnel's capabilities and the new installation / maintenance location. However, this scheduling method is flawed in cases where the work order address is outside the personnel's jurisdiction, requiring them to reassign the work order to other personnel, thus increasing the workload of unnecessary work order reassignments and reducing work order distribution efficiency.
[0070] The goal of the work order scheduling provided in this application embodiment is to centrally schedule work orders through a work order scheduling center, select the most suitable installation and maintenance personnel for on-site construction, and reduce situations such as unreasonable work order scheduling requiring manual transfer of work orders, untimely installation, and low work order scheduling efficiency.
[0071] Based on this, embodiments of this application provide a method for scheduling installation and maintenance work orders. Figure 1 This is one of the flowcharts illustrating the scheduling method for installation and maintenance work orders provided in this application. The execution entity of this method is a scheduling device for installation and maintenance work orders, which can be integrated into a terminal or electronic device. Figure 1 As shown, the method includes the following steps:
[0072] Step 101: Obtain the first attribute information from the installation and maintenance work order to be scheduled. The first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0073] Specifically, the installation and maintenance location information includes the location area and the geographical environment. The location area refers to the area corresponding to the address where the installation and maintenance personnel for the work order to be dispatched need to provide on-site repairs. For example, if the installation and maintenance address is: Room D, Building C, Community B, District A, Guangzhou, then since Community B belongs to District A of Guangzhou, the location area is District A. The geographical environment refers to the specific environment corresponding to this area, which includes: urban areas, rural areas, urban-rural fringe areas, urban villages, etc. Since each installation and maintenance personnel has their own assigned area of responsibility, and different environments are under the exclusive jurisdiction of different personnel, the installation and maintenance location information, which combines the location area and the geographical environment, can be used as the information for obtaining work orders to be dispatched, thus improving the rationality and efficiency of work order dispatch.
[0074] Step 102: Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0075] Specifically, each installation and maintenance work order corresponds to a knowledge graph, and the knowledge graphs corresponding to all installation and maintenance work orders constitute a knowledge graph library. Each historical installation and maintenance work order corresponds to a second attribute information, and multiple historical installation and maintenance work orders correspond to multiple second attribute information. The meaning of the installation and maintenance location information included in the second attribute information is the same as the meaning of the installation and maintenance location information included in the first attribute information in step 101, and will not be repeated here.
[0076] Knowledge graphs are composed of knowledge links and are essentially semantic networks. Nodes represent entities, and edges consist of attributes or relationships. In the knowledge graph corresponding to historical installation and maintenance work orders, entities include customers, installation addresses, installation and maintenance personnel, installation and maintenance teams, and equipment. Relationships reflect the relationships between entities in the knowledge graph, and attributes can depict entities in a more three-dimensional and complete way. Knowledge graphs aim to describe various entities or concepts and their relationships in the real world. They have certain advantages in expanding entity information and strengthening the connections between entities. Moreover, entities contain rich descriptive knowledge, providing rich reference and decision-making basis for recommending installation and maintenance personnel. The knowledge graph library provided in this application embodiment stores the semantic relationships between historical installation and maintenance work order data and on-site installation and maintenance personnel, the semantic relationships between customers and installation and maintenance addresses, the semantic relationships between customers and installation and maintenance personnel, the semantic relationships between customers and installation and maintenance equipment, the semantic relationships between installation and maintenance personnel and installation and maintenance teams, and the semantic relationships between installation and maintenance efficiency.
[0077] Step 103: Determine the similarity between the first attribute information and each of the second attribute information.
[0078] Specifically, in this embodiment, the installation and maintenance personnel's group is determined based on the similarity of the newly added installation and maintenance work order to be scheduled, and the installation and maintenance personnel under that group are marked as candidate target installation and maintenance personnel. Specifically, the similarity can be calculated to determine how the installation and maintenance work order to be scheduled is assigned based on the historical assignment of installation and maintenance work orders. For example, for a historical installation and maintenance work order, if the installation and maintenance personnel in installation and maintenance group a have provided installation and maintenance services to customer b corresponding to that historical work order, and the installation and maintenance address is Room D, Building C, Community B, District A, Guangzhou, and the newly added installation and maintenance work order's customer c also requests installation and maintenance at the address of Building C, Community B, District A, Guangzhou, then the dispatch center will determine the installation and maintenance group to which the newly added installation and maintenance work order to be scheduled is assigned based on historical installation and maintenance work orders: that is, installation and maintenance group a is used as the installation and maintenance group for the newly added installation and maintenance work order to be scheduled.
[0079] By determining the similarity between the first attribute information and each second attribute information separately, multiple similarity scores are obtained. That is, each second attribute information corresponds to a similarity score obtained by comparing it with the first attribute information. For example, the similarity between the scheduled installation / maintenance work order S0 and the historical installation / maintenance work order S1 is T1, the similarity between the scheduled installation / maintenance work order S0 and the historical installation / maintenance work order S2 is T2, the similarity between the scheduled installation / maintenance work order S0 and the historical installation / maintenance work order S3 is T3, and so on. N The similarity is T N Then there will be N similarity scores T.
[0080] The method for calculating similarity is as follows:
[0081] Obtain the key information (location and geographical environment) corresponding to the first attribute information, and convert this key information into a first vector; obtain the key information (location and geographical environment) corresponding to the second attribute information, convert this key information into a second vector, and then use the Tanimoto method to calculate the similarity between the first vector and the second vector. The formula for calculating the similarity is as follows:
[0082]
[0083] Here, A and B are two entity vectors. Tanimoto similarity is often used to calculate the similarity of document data. Its value ranges from [0,1]. It is 1 when there is complete overlap and 0 when there is no overlap. The closer it is to 1, the higher the similarity.
[0084] The method provided in this application adopts Tanimoto similarity because the vector element values have no relative magnitude relationship. The similarity between entity vectors A and B is calculated using the above formula. The closer the similarity measurement result is to 1, the more similar the entity vectors are, and the closer the relationship between the two in the knowledge graph is considered. Conversely, it means that the semantic similarity between the two is lower and the relationship in the knowledge graph is more distant.
[0085] Similarity calculation utilizes representation learning algorithms to convert key entities and attributes of installation events in the knowledge graph database into vectors, thus quantifying the knowledge graph. The Tanimoto method is then used to calculate the similarity between entities. Key entities and attributes for similarity calculation include the city / premises where the installation was applied for, the application area, customer type, and installation / maintenance group. When converting to vectors, the city / premises and customer type are enumerated values, the application area is converted to an area ID, and the installation / maintenance group is retained as a string. For example, ('Guangzhou', 'Community B', 'VIP User', 'Installation / Maintenance Group B') is converted into the vector (4401, 403194758, 1, 'Installation / Maintenance Group B'), where 4401 is the city / premises enumeration value corresponding to 'Guangzhou', 403194758 is the area ID of 'Community B' managed by the resource system, and 1 is the 'VIP User' enumeration value.
[0086] Step 104: Based on the similarity of each of the second attribute information, determine the target installation and maintenance group from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel.
[0087] Specifically, each installation and maintenance personnel belongs to a specific installation and maintenance group, and each group typically includes several personnel. Before assigning a specific personnel to an installation and maintenance work order, it is first necessary to identify the corresponding installation and maintenance group. Since each historical installation and maintenance work order corresponds to one group, it is necessary to first determine the target group from among the groups corresponding to multiple historical work orders, and then select candidate personnel from that target group.
[0088] Step 105: Determine the target installation and maintenance personnel from the target installation and maintenance group, and send the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel.
[0089] Specifically, after candidate installation and maintenance personnel are identified from the target installation and maintenance group, the final target installation and maintenance personnel are determined from the candidate group. The scheduled installation and maintenance work order is then sent to the terminal corresponding to the final target installation and maintenance personnel. This terminal can be a mobile phone, tablet, or other device capable of receiving the scheduled installation and maintenance work order information. The scheduled installation and maintenance work order includes information such as: customer, installation and maintenance address, and installation and maintenance equipment.
[0090] The installation and maintenance work order scheduling method, apparatus, equipment, and readable storage medium provided in this application embodiment obtain first attribute information from the installation and maintenance work order to be scheduled, and obtain second attribute information corresponding to each historical installation and maintenance work order through the knowledge graph corresponding to each of the multiple historical installation and maintenance work orders. Then, the target installation and maintenance group is determined by calculating the similarity between the first attribute information and the second attribute information, and the final target installation and maintenance personnel are determined based on the target installation and maintenance group. Since both the first attribute information and the second attribute information include installation and maintenance location information, and historical installation and maintenance work orders can reflect which areas the installation and maintenance personnel have previously installed and maintained, the accuracy of the installation and maintenance work orders to be scheduled can be improved by using historical installation and maintenance work orders. This can reduce the situation where the installation and maintenance address does not fall within the jurisdiction of the installation and maintenance personnel, thereby improving the rationality and efficiency of work order scheduling.
[0091] Furthermore, the scheduling method provided in this application uses a knowledge graph to store the semantic relationship between historical installation and maintenance work order data and on-site installation and maintenance personnel. Then, it extracts key information from the knowledge graph database to calculate similarity, which improves both the efficiency and accuracy of similarity calculation.
[0092] Furthermore, Figure 2 This is the second flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application embodiment. This application embodiment... Figure 1 Based on the illustrated embodiment, the implementation process of determining the target installation and maintenance group from the installation and maintenance groups corresponding to multiple historical installation and maintenance work orders according to the similarity of each second attribute information is explained in detail, such as... Figure 2 As shown, the method includes the following steps:
[0093] Step 201: Sort the similarity of each second attribute information in descending order, and determine the first historical installation and maintenance work order corresponding to the first preset number of second attribute information.
[0094] Specifically, since there are multiple historical installation and maintenance work orders, there are also multiple second attribute information corresponding to these multiple historical installation and maintenance work orders, and there are also multiple similarities. In this embodiment of the application, the historical installation and maintenance work orders corresponding to the top-ranked similarities (i.e., the first preset number) are selected from these multiple similarities as the basis for screening the installation and maintenance group.
[0095] Step 202: Determine the installation and maintenance group corresponding to the first preset number of first historical installation and maintenance work orders.
[0096] Specifically, since each historical installation and maintenance work order corresponds to an installation and maintenance group, this application embodiment first filters out a number of historical installation and maintenance work orders with the highest similarity (a first preset number), and then determines the installation and maintenance group corresponding to each historical installation and maintenance work order from these historical installation and maintenance work orders with the highest similarity.
[0097] Step 203: The maintenance group that appears most frequently is identified as the target maintenance group.
[0098] Specifically, although each installation and maintenance work order corresponds to an installation and maintenance group, each installation and maintenance group corresponds to several installation and maintenance work orders. If an installation and maintenance group is frequently assigned installation and maintenance work orders, it indicates that the group has high installation and maintenance efficiency, good installation and maintenance quality, and high customer satisfaction. Therefore, in this embodiment, after selecting several installation and maintenance groups with the highest similarity ranking (a first preset number), the installation and maintenance group that appears most frequently is determined as the target installation and maintenance group. For example: the installation and maintenance work order S0 to be scheduled and historical installation and maintenance work orders S1, S2, S3...S M The similarity is highest, with S0 to S10 being the most similar. M The maintenance group that appears most frequently is selected as the target maintenance group for the maintenance work order S0 to be scheduled.
[0099] The installation and maintenance work order scheduling method provided in this application embodiment filters out the top-ranked installation and maintenance groups from multiple groups based on similarity, and then selects the installation and maintenance group with the most occurrences from the top-ranked groups as the target installation and maintenance group. This filtering method can identify the construction areas where installation and maintenance personnel most frequently perform installation and maintenance. The more times an installation and maintenance personnel perform installation and maintenance in a certain area, the more familiar they are with the specific conditions of that area, and the higher their installation and maintenance efficiency. In other words, the number of devices that can be installed and maintained in the same amount of time is also higher. Therefore, by using the installation and maintenance group with the highest occurrence frequency as the target installation and maintenance group for the installation and maintenance work orders to be scheduled, this application embodiment can further improve the rationality of work order scheduling, and at the same time improve the installation and maintenance personnel's installation and maintenance capability value. The installation and maintenance capability value of an installation and maintenance personnel refers to the number of devices that an installation and maintenance personnel can install and maintain in a fixed period of time. For example, if the number of devices that installation and maintenance personnel A can install and maintain from 9:00 am to 12:00 pm is 5, then the installation and maintenance capability value of installation and maintenance personnel A is 5.
[0100] Furthermore, Figure 3 This is the third flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application. Based on the foregoing embodiments, this embodiment provides a detailed explanation of the specific implementation process for determining target installation and maintenance personnel from the target installation and maintenance group. Figure 3 As shown, the method includes the following steps:
[0101] Step 301: Determine the recommendation index for each installation and maintenance personnel based on their first evaluation information in the target installation and maintenance group.
[0102] Specifically, this application embodiment not only selects the target installation and maintenance group, but also selects the optimal target installation and maintenance personnel from the target installation and maintenance group. Since each installation and maintenance work order will have a first evaluation information for the installation and maintenance personnel corresponding to that work order after completion, the higher the evaluation of the installation and maintenance personnel, the higher the recommendation index.
[0103] The first evaluation information includes customer satisfaction and installation / maintenance efficiency. Key factors for customer satisfaction include: on-site installation time, service fulfillment rate, and measured optical power value. Installation / maintenance efficiency is a label describing the work efficiency indicators and habits of each installation / maintenance personnel. Key factors included are selected based on expert experience and include: basic installation / maintenance information (such as gender, age, and education), historical installation habits (such as installation address, installation time period, and installation duration), and installation / maintenance star rating.
[0104] Step 302: Sort the recommendation index of each installation and maintenance personnel in descending order, and determine the installation and maintenance personnel corresponding to the first second preset number of recommendation indices.
[0105] Specifically, since each installation and maintenance personnel has different customer satisfaction and installation and maintenance efficiency, and the recommendation index varies depending on the different customer satisfaction and installation and maintenance efficiency, this application embodiment selects a number of top-ranked installation and maintenance personnel (a second preset number) based on the recommendation index, and selects the final target installation and maintenance personnel from these top-ranked installation and maintenance personnel (a second preset number).
[0106] Step 303: Determine the target installation and maintenance personnel based on the installation and maintenance capability value and available installation and maintenance time of each of the first two preset number of recommendation indices.
[0107] Specifically, the available installation and maintenance time refers to the time when installation and maintenance personnel can install and maintain equipment, i.e., the work schedule. Although the installation and maintenance personnel with the highest recommendation index can be selected from step 302, it is possible that the installation and maintenance capability value or available installation and maintenance time of the personnel with the highest recommendation index does not meet the requirements. For example, the installation and maintenance personnel B with the highest recommendation index has an installation and maintenance capability value of 5 and rests on Wednesdays and Sundays. If the on-site repair time required in the pending installation and maintenance work order is Tuesday morning from 10:00 to 11:00, although installation and maintenance personnel B can meet the requirement in terms of available installation and maintenance time, installation and maintenance personnel B has already scheduled 5 installation and maintenance work orders from 9:00 to 12:00 on Tuesday morning. Therefore, even if installation and maintenance personnel B has the highest recommendation index, other installation and maintenance personnel in the same installation and maintenance group can be reassigned to perform the work. Similarly, if the on-site repair time required in the pending installation and maintenance work order is Wednesday morning from 10:00 to 11:00, although installation and maintenance personnel B's installation and maintenance capability value meets the requirement, the available installation and maintenance time does not meet the requirement. Therefore, in this embodiment of the application, it is necessary to combine the installation and maintenance capability value, installation and maintenance time and recommendation index of each installation and maintenance personnel to jointly determine the final target installation and maintenance personnel. At this time, there may be more than one target installation and maintenance personnel who can simultaneously meet the installation and maintenance capability value, installation and maintenance time and recommendation index. The target installation and maintenance personnel who meet these three conditions are the candidate target installation and maintenance personnel.
[0108] The installation and maintenance work order scheduling method provided in this application uses the recommendation index corresponding to each installation and maintenance personnel to select a second preset number of candidate installation and maintenance personnel with the highest ranking. The final target installation and maintenance personnel are determined based on the installation and maintenance capability value and available installation and maintenance time of each candidate installation and maintenance personnel. This method not only considers the installation and maintenance situation of installation and maintenance personnel in historical installation and maintenance work orders, but also considers the current situation of the candidate target installation and maintenance personnel. By combining historical installation and maintenance situation with the current situation, the final target installation and maintenance personnel are determined, thereby further improving the rationality of work order allocation.
[0109] Furthermore, based on the initial evaluation information of each installation and maintenance personnel in the target installation and maintenance group, the recommendation index for each installation and maintenance personnel is determined according to the following installation and maintenance scoring model:
[0110] f(P,T)=C1·g(X(P,T))+C2·h(Y(P,T))
[0111] Where T is the installation and maintenance work order, P is the installation and maintenance personnel corresponding to the installation and maintenance work order; g is the indicator function affecting customer satisfaction, h is the installation and maintenance efficiency indicator function, C1 is the customer satisfaction indicator weight coefficient, C2 is the installation and maintenance efficiency indicator weight coefficient; f(P,T) is the recommendation index of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; X(P,T) is the satisfaction indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; Y(P,T) is the installation and maintenance efficiency indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T.
[0112] This application embodiment uses the above formula to formulate an installation and maintenance scoring model, which determines the recommendation index for each installation and maintenance personnel. This scoring model is based on an indicative index of customer satisfaction and an installation and maintenance efficiency index. The model assigns the most suitable installation and maintenance personnel to the pending installation and maintenance work orders by calculating the recommendation index for each candidate personnel. The scoring model includes an indicative index of factors influencing customer satisfaction and an installation and maintenance efficiency index. Installation and maintenance scores are calculated for the candidate personnel; a higher score indicates a higher recommendation index, meaning the personnel are more likely to meet the customer's needs for the new work order among the candidates. This, combined with the personnel's capabilities, determines the personnel assigned to the new installation and maintenance work orders.
[0113] Among the factors influencing customer satisfaction, it's crucial to first identify which factors affect customer satisfaction, and the scope and extent of each factor's impact. Finally, the analysis results are comprehensively ranked. The higher the ranking, the greater the impact and the closer the relationship to customer satisfaction. Calculating the satisfaction index can filter out installation and maintenance personnel who contribute to decreased customer satisfaction. For example, the scoring model focuses on on-site installation time and service fulfillment rate. The calculation results can remove installation and maintenance personnel with poor on-site installation time and service fulfillment rate from the candidate list, recommending more suitable personnel for new work orders.
[0114] The installation and maintenance efficiency index is used to comprehensively describe the efficiency and service quality of installation and maintenance personnel. Indicators are selected based on expert experience and include basic installation and maintenance information (such as gender, age, and education), installation and maintenance capability values (such as total capability value and available capability value), historical installation habits (such as installation address, installation time period, and installation duration), and work efficiency and habit tags such as installation and maintenance star rating. For example, if a new installation and maintenance work order T is located in the same frequently installed area as both installation and maintenance personnel P1 and P2, but P1 has a shorter historical installation duration at that address, then P1 will receive a higher efficiency recommendation index for work order T.
[0115] In summary, the installation and maintenance rating model needs to clarify which factors influence customer satisfaction, the degree of influence of each factor on satisfaction, and the effects of different combinations of influencing factors. By using multi-factor ANOVA to analyze historical work data, the degree of influence of each relevant factor on customer satisfaction is determined, and the factors are ranked according to their degree of influence. Finally, weights are assigned to each factor based on its degree of influence on customer satisfaction. Multi-factor ANOVA can not only analyze the independent impact of each key factor on customer satisfaction, but also analyze whether the interaction of multiple influencing factors can have a significant impact on customer satisfaction, ultimately determining the degree of influence of each factor and identifying the optimal combination for influencing customer satisfaction.
[0116] Existing solutions use fixed scheduling strategies for work order scheduling. However, different cities and regions have different concerns based on their own circumstances. Using a fixed scheduling strategy fails to consider the differences in various scenarios and cannot comprehensively meet the individual requirements of work order scheduling in different regions. Therefore, this application's embodiments define appropriate g and h forms based on the specific circumstances of each city and region. For example, g and h can be defined as a weighted sum of each component.
[0117]
[0118]
[0119] Where, x i These are all the metrics that affect customer satisfaction; y i It is all installation and maintenance efficiency indicators; α i The sum is the weight of all indicators affecting customer satisfaction, β. i It is the weight corresponding to all installation and maintenance efficiency indicators.
[0120] Specifically, an installation and maintenance personnel recommendation index is obtained by weighting the aforementioned customer satisfaction index and installation and maintenance personnel efficiency recommendation index. Based on this recommendation index, suitable installation and maintenance personnel are selected to assign tasks for pending installation and maintenance work orders. The customer satisfaction index is obtained by weighted summation of key factors affecting customer satisfaction. For example, if the key factors affecting customer satisfaction in a certain city are on-site construction time, service fulfillment rate, and test optical power value, then the customer satisfaction index is the weighted sum of these three indicators.
[0121] Given the diversity of installation and maintenance tasks and the different realities and concerns of different cities and regions, using the same scheduling rules cannot fully meet the personalized needs of each region. Therefore, regional administrators in each city can customize different scheduling strategies according to their own actual situation, making work order scheduling more suitable for the specific circumstances of each region, and achieving the goal of flexible and efficient work order scheduling. For example, if the factors affecting customer satisfaction in a certain city are: on-site construction time, total installation processing time, and service fulfillment rate, and if region A focuses on the on-site construction time indicator, the weight of this indicator in the scoring strategy can be increased.
[0122] Furthermore, the first attribute information also includes installation and maintenance time information, which includes: the floor where the installation and maintenance is performed, the access method information, and the on-site visit time information.
[0123] The floor information refers to whether the address where the installation and maintenance personnel will come for repairs is a high-rise or low-rise building, as higher-rise buildings require higher installation and maintenance skills; the access method information refers to whether the broadband service requested by the customer is fiber optic to the home or fiber optic only to the customer's building or community, as the required skills of the installation and maintenance personnel vary depending on the location of the fiber optic access; and the on-site time information refers to the scheduled time slot for the installation and maintenance personnel to come for work in the work order to be dispatched. Figure 4 This is the fourth flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application embodiment. This embodiment, based on the foregoing embodiments, provides a detailed explanation of the specific implementation process for determining the final target installation and maintenance personnel based on installation and maintenance time information; for example... Figure 4 As shown, the target installation and maintenance personnel are determined based on their respective installation and maintenance capability values and available installation and maintenance time, according to the first second preset number of recommendation indices. This process specifically includes the following steps:
[0124] Step 401: Based on the installation and maintenance capability values of the installation and maintenance personnel corresponding to the first two preset number of recommendation indices, determine the installation and maintenance personnel whose installation and maintenance capability values are greater than the preset values.
[0125] Specifically, in order to determine the final target installation and maintenance personnel from the candidate target installation and maintenance personnel who simultaneously meet the installation and maintenance capability value, the available installation and maintenance time, and the recommendation index, it is necessary to further screen these candidate target installation and maintenance personnel who simultaneously meet the set conditions. The primary condition for screening is to start with the installation and maintenance capability value, that is, to screen out a number of installation and maintenance personnel (with a certain preset value) whose installation and maintenance capability value ranks first.
[0126] Step 402: Match the available installation and maintenance time of installation and maintenance personnel whose installation and maintenance capability value is greater than the preset value with the installation and maintenance time information.
[0127] Specifically, the available installation and maintenance time for installation and maintenance personnel refers to their remaining capacity, which is the time during which they have not yet been assigned a work order. Only when the appointment time in the pending installation and maintenance work order matches the installation and maintenance time information of the installation and maintenance personnel can the optimal target installation and maintenance personnel be determined. If there is still more than one optimal target installation and maintenance personnel, the system will randomly select one as the final target installation and maintenance personnel.
[0128] Step 403: The successfully matched installation and maintenance personnel are identified as the target installation and maintenance personnel.
[0129] The installation and maintenance work order scheduling method provided in this application first filters out a number of top-ranked installation and maintenance personnel based on their installation and maintenance capability values. Then, it matches the appointment time in the work order to be scheduled with the installation and maintenance time information of the personnel to lock in the final target installation and maintenance personnel. This method locks in the target installation and maintenance personnel by using installation and maintenance capability values and installation and maintenance time information, which further improves the rationality and efficiency of work order assignment.
[0130] Furthermore, Figure 5 This is the fifth flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application. This embodiment is a detailed description of the specific implementation process of knowledge graph construction based on the foregoing embodiments. Figure 5 As shown, before retrieving the knowledge graphs corresponding to multiple historical installation and maintenance work orders from the knowledge graph database, the method further includes:
[0131] Step 501: Extract information from multiple historical installation and maintenance work orders and the corresponding installation and maintenance information for each historical installation and maintenance work order, and obtain the installation and maintenance location information, installation and maintenance personnel information, installation and maintenance group to which the installation and maintenance personnel belong, and customer information corresponding to each historical installation and maintenance work order.
[0132] Specifically, the installation and maintenance information corresponding to each of the multiple historical installation and maintenance work orders includes: basic information of the installation and maintenance personnel and basic information of the customer. The basic information of the installation and maintenance personnel includes: basic personnel information and statistical information. Basic personnel information is the basic information entered by the operator when recruiting installation and maintenance personnel; statistical information is the statistical information calculated by the system backend based on the actual work performance of the installation and maintenance personnel. Basic customer information includes: basic customer information and statistical information. Basic customer information is the basic information included in the service contract signed between the customer and the operator for each installation and maintenance work order. This basic information includes the customer's name, ID number, VIP level, gender, address, contact information, broadband requirements, etc.; statistical information includes: customer feedback, location, and installation and maintenance geographical environment. The location refers to the area where the customer's application address belongs. For example, if the customer's application address is Xingfu Community in Guangzhou, and Xingfu Community belongs to Huadu District of Guangzhou, then the area corresponding to this application address is Huadu District. The installation and maintenance geographical environment refers to the description of the environment of the application address, specifically: urban area, rural area, urban-rural fringe area, or urban village within an urban area.
[0133] Furthermore, the key information needed to construct the knowledge graph also includes key information extracted from multiple historical installation and maintenance work orders. This key information includes: customer satisfaction feedback and installation and maintenance efficiency. Customer satisfaction feedback is based on customer feedback obtained after the completion of a specific installation and maintenance work order. Installation and maintenance efficiency includes: installation duration and fulfillment rate. Installation duration is also information obtained from the completion of a specific installation and maintenance work order, i.e., when the installation and maintenance started and ended. The fulfillment rate is the ratio of the number of times installation and maintenance personnel actually performed on-site installation and maintenance within a certain period to the number of times they should have performed. Both installation duration and fulfillment rate are derived from the basic information of installation and maintenance personnel, i.e., statistical information calculated by the system backend based on the actual work performance of the installation and maintenance personnel. Therefore, it is evident that the installation and maintenance information already exists before the installation and maintenance work order is generated.
[0134] In other words, only by extracting information from three parts—basic information of installation and maintenance personnel, basic information of customers, and information corresponding to multiple historical installation and maintenance work orders—can we obtain the complete information needed to build a knowledge graph.
[0135] The equipment maintenance location information includes: the location and the geographical environment of the equipment maintenance. The location and geographical environment are obtained indirectly from the original information.
[0136] The installation and maintenance personnel information includes: age, star rating, capability score, education level, account information, and efficiency. The age, education level, and account information are obtained from the basic information of the installation and maintenance personnel. The star rating, capability score, and efficiency are obtained from the statistical information of the installation and maintenance personnel.
[0137] The installation and maintenance team to which the installation and maintenance personnel belong refers to which installation and maintenance team the personnel belong to.
[0138] Each historical installation and maintenance work order corresponds to the following customer information: customer type, broadband account, loan requirements, and customer satisfaction. The customer type, broadband account, and loan requirements are obtained from the customer's basic information. Customer satisfaction is obtained from customer statistics.
[0139] Step 502: Based on the installation and maintenance location information, installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order, construct a knowledge graph corresponding to each of the historical installation and maintenance work orders.
[0140] Specifically, each historical installation and maintenance work order corresponds to a knowledge graph. The information included in constructing each knowledge graph includes: installation and maintenance location information, installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and customer information corresponding to each historical installation and maintenance work order.
[0141] Building a knowledge graph requires extracting key information from historical data through knowledge extraction. Knowledge extraction includes three parts: entity extraction, relation extraction, and attribute extraction. The historical data here refers to: installation and maintenance location information, installation and maintenance personnel information, the installation and maintenance groups to which the personnel belong, and customer information corresponding to each historical installation and maintenance work order.
[0142] Knowledge extraction comprises three parts: entity extraction, relation extraction, and attribute extraction. Entity extraction identifies entities from historical data and is the most fundamental and crucial step in knowledge extraction, directly impacting the quality of the knowledge graph. Relationship extraction addresses the semantic links between entities, reflecting their relationships within the knowledge graph. Attribute extraction focuses on entities, providing a more comprehensive and complete picture. Attribute extraction takes two forms: one is directly obtained from historical data, such as the gender, age, installation / maintenance team, customer installation address, and customer type of installation / maintenance personnel; the other is obtained through algorithmic calculations, such as the installation / maintenance personnel's installation time and installation / maintenance capability value.
[0143] The process of constructing a knowledge graph is as follows:
[0144] First, we collect historical installation and maintenance work order data and customer satisfaction survey results, including historical work data such as customer installation information, installation geographical environment, installation equipment information, and installation and maintenance personnel data.
[0145] Then, information is extracted from the collected historical data, and the work order data and installation and maintenance information are abstracted into various tags, including application area, area type, application geographical environment, installation equipment information, installation and maintenance construction process data, customer type, rate test results, installation and maintenance personnel star rating, etc., and stored in the form of triples ("entity-attribute-entity" or "entity-attribute-attribute value"), which are used to represent the information content of each knowledge in the knowledge base. Figure 6 This is a schematic diagram of a knowledge graph triple provided in an embodiment of this application. For example, the triple representation of the address reported by customer A is as follows: Figure 6 As shown. The entity represents the customer applying for installation, and its attributes include, but are not limited to: customer type, type of installed equipment, model of installed equipment, area under the jurisdiction of the installation and maintenance personnel, the installation and maintenance team to which they belong, and star rating. Some tags can be obtained from the basic information of the installation and maintenance personnel and the customer, such as the application area, information on the installed equipment, gender, and age; other tags are obtained through algorithmic calculation, such as installation duration and installation and maintenance capability value.
[0146] By extracting information from the data, key information such as customer type, installation address, and installation / maintenance personnel is selected. This key information is then used to link customers and their installation-related information with the installation / maintenance personnel information, forming a one-to-one mapping relationship, i.e., a triple. These triples are then used to construct a knowledge graph. A knowledge graph is composed of triples; essentially, it is a semantic network where nodes represent entities and edges consist of attributes or relationships. Figure 7 A diagram illustrating the installation of a knowledge graph for home broadband, such as... Figure 7 As shown, a knowledge graph for home broadband installation is constructed by integrating the simple triplet structure data extracted in the early stage. This knowledge graph can visually present the relationships between customer application information, installation and maintenance personnel information, and other relevant data.
[0147] The knowledge graph stores the relationships between customer installation requests and installation / maintenance personnel. Based on the extracted key information, different relationships can be integrated into a knowledge graph associated with customer entities. Different key attributes are compared by calculating the similarity between them, and candidate installation / maintenance personnel are recommended for the installation / maintenance work order to be scheduled based on the similarity results. For example, if the installation / maintenance work order S0 to be scheduled has a similarity to a historical installation / maintenance work order S... i (i = 1, 2, 3, ...) The overall similarity of key attributes is high, and it can be used to determine the similarity based on historical installation and maintenance work orders S. i (i = 1, 2, 3, ...) The installation and maintenance team to which the installation and maintenance personnel who will ultimately come to the site will be determined as the candidate installation and maintenance team.
[0148] Existing work order scheduling solutions primarily focus on the perspective of installation and maintenance personnel, neglecting factors influencing customer satisfaction. Work order scheduling rules are based on the remaining capacity of installation and maintenance personnel and newly added installation and maintenance locations. Assigning work orders without considering customer satisfaction-related factors is unlikely to improve customer satisfaction. Therefore, the work order scheduling method provided in this application constructs a knowledge graph using the installation and maintenance location information corresponding to each historical work order, the installation and maintenance personnel information, the installation and maintenance group to which the personnel belong, and the customer information corresponding to each historical work order. Based on the knowledge graph, key attributes can be extracted to filter the list of recommended installation and maintenance personnel for the work orders to be scheduled. A recommendation index for candidate installation and maintenance personnel is calculated using an installation and maintenance scoring model. The installation and maintenance personnel with the highest score (i.e., the optimal personnel) are recommended. This ensures that work order scheduling respects historical experience and fully considers factors affecting customer satisfaction, thereby achieving the goal of improving customer satisfaction.
[0149] Furthermore, Figure 8 This is the sixth flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application. This embodiment is a detailed description of the specific implementation process for updating the knowledge graph database, based on the foregoing embodiments. Figure 8 As shown, after determining candidate target equipment maintenance personnel from the target equipment maintenance group, the method further includes:
[0150] Step 801: Construct a knowledge graph corresponding to the installation and maintenance work order to be scheduled, based on the installation and maintenance location information, target installation and maintenance personnel and target installation and maintenance group, and corresponding customer information of the work order to be scheduled.
[0151] Specifically, after each pending installation and maintenance work order is archived, information for each work order is collected. This collected information includes: the installation and maintenance location information, the target installation and maintenance personnel and group, and the corresponding customer information. This collected information is then used to construct a knowledge graph corresponding to each pending installation and maintenance work order. Simultaneously, this information forms the basis for updating the knowledge graph database.
[0152] The information collected specifically includes: customer installation application information, geographical location of the application, information on the installed equipment, information on the installation and maintenance personnel, and the results of satisfaction surveys.
[0153] Step 802: Add the knowledge graph corresponding to the installation and maintenance work order to be scheduled to the knowledge graph library.
[0154] Specifically, whenever a work order to be scheduled for installation and maintenance is archived, the knowledge graph corresponding to that work order will be added to the knowledge graph library to update the knowledge graph library.
[0155] The installation and maintenance work order scheduling method provided in this application adds the knowledge graph corresponding to the installation and maintenance work order to the knowledge graph library. By using incremental work order data to introduce more knowledge relationships, the knowledge graph library can continuously adjust and optimize the scoring model and the knowledge graph library. This allows for deeper mining and recommendation of suitable installation and maintenance personnel, making the work order assignment results more accurate and reliable. As a result, it achieves reasonable and balanced scheduling of installation and maintenance personnel and improves the efficiency of work order scheduling.
[0156] Furthermore, Figure 9 This is the seventh flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application. This embodiment is a detailed description of the specific implementation process for updating the recommendation index of installation and maintenance personnel, based on the foregoing embodiments. Figure 9 As shown, after sending the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel, the method also includes the following steps:
[0157] Step 901: Receive the second evaluation information sent by the terminal for the target installation and maintenance personnel.
[0158] Specifically, the second evaluation information includes customer satisfaction feedback and installation and maintenance efficiency information. Each time a pending installation and maintenance work order is completed, second evaluation information is collected for the installation and maintenance personnel corresponding to that work order, and this second evaluation information is used to update the basis for the personnel recommendation index.
[0159] Step 902: Update the first evaluation information of the target maintenance personnel based on the second evaluation information.
[0160] Specifically, the first evaluation information for the target installation and maintenance personnel refers to the evaluation information of each installation and maintenance personnel in the target installation and maintenance group. The second evaluation information is the evaluation information of the installation and maintenance personnel corresponding to the installation and maintenance work order to be dispatched. The first and second evaluation information include the same content, which refers to satisfaction feedback information and installation and maintenance efficiency information.
[0161] The installation and maintenance work order scheduling method provided in this application update the first evaluation information with the second evaluation information, which can flexibly adjust and optimize the installation and maintenance scoring model, thereby making the installation and maintenance work order scheduling more reasonable, the scheduling accuracy higher, and the customer satisfaction higher.
[0162] Figure 10 This is the eighth flowchart illustrating the scheduling method for installation and maintenance work orders provided in this application. This embodiment is a detailed description of the specific implementation process of the scheduling method for installation and maintenance work orders, based on the foregoing embodiments. Figure 10 As shown, the method includes the following steps:
[0163] Step 1001: Based on historical installation and maintenance work order data, extract the installation and maintenance location information, installation and maintenance personnel information, installation and maintenance group to which the installation and maintenance personnel belong, and customer information corresponding to each historical installation and maintenance work order to construct a knowledge graph database corresponding to each historical installation and maintenance work order.
[0164] Step 1002: Obtain the first attribute information from the installation and maintenance work order to be scheduled; obtain the second attribute information corresponding to each historical installation and maintenance work order in the knowledge graph database;
[0165] Step 1003: Determine the similarity between the first attribute information and each of the second attribute information;
[0166] Step 1004: Based on the similarity of each second attribute information, determine the target installation and maintenance group from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders;
[0167] Step 1005: Use the installation and maintenance scoring model to determine candidate target installation and maintenance personnel from the target installation and maintenance group;
[0168] Step 1006: Based on the installation and maintenance capabilities, installation and maintenance time, and work order information of the candidate installation and maintenance personnel, implement intelligent scheduling and assign target installation and maintenance personnel to the work orders to be scheduled.
[0169] Step 1007: Once the scheduled installation and maintenance work order is completed and archived, collect the installation and maintenance location information, target installation and maintenance personnel and target installation and maintenance groups, corresponding customer information, customer satisfaction information, and installation and maintenance efficiency of the personnel for the scheduled installation and maintenance work order; and feed the collected information back to the knowledge graph base and installation and maintenance scoring model to update the knowledge graph base and installation and maintenance scoring model.
[0170] Specifically, when a customer has installation and maintenance needs, a pending installation and maintenance work order is generated. This work order includes information such as the installation and maintenance address, scheduled installation time, and required products. This pending work order is then transferred to the dispatch center for centralized scheduling. When a new work order appears in the work order database, the dispatch center, based on intelligent dispatch strategies and considering the installation and maintenance personnel's skill levels and work schedules, recommends the optimal installation and maintenance personnel for the scheduled time slot, maximizing installation and maintenance efficiency and striving to improve overall customer satisfaction. After a new installation and maintenance work order is assigned, the installation and maintenance personnel's skill levels are updated in real time to prevent unreasonable work order scheduling due to outdated skill levels, ensuring accurate scheduling for the next new work order. Simultaneously, after receiving a new installation and maintenance task, installation and maintenance personnel can proactively plan their routes based on the work order's geographical distribution, urgency, and scheduled on-site arrival time, making installation and maintenance more timely and efficient.
[0171] The method provided in this application first extracts historical work data such as customer installation application information, installation geographical environment, and on-site installation and maintenance personnel information, as well as customer satisfaction survey data. A knowledge graph is then constructed based on the extracted "tag" information. This knowledge graph is used to search for a list of candidate installation and maintenance personnel with similar key attribute semantics for new work orders, providing diversity and interpretability for recommended personnel. Next, customer satisfaction survey data is analyzed to identify key factors influencing customer satisfaction, and an installation and maintenance scoring strategy is customized based on these key factors. Simultaneously, incremental archived work order data has a positive feedback effect. By analyzing and processing the newly archived data, the semantic relationships of the knowledge graph can be enriched, and factors influencing customer satisfaction can be dynamically updated, achieving the effect of continuously optimizing the scoring strategy and improving the reliability of the knowledge graph.
[0172] The method provided in this application is based on a knowledge graph database and combined with an installation and maintenance scoring model, which improves the accuracy of installation and maintenance recommendation results and reduces the workload of manual work order transfer. Based on key factors affecting customer satisfaction, the installation and maintenance scoring strategy is flexibly customized for each city and region, which improves the flexibility of work order scheduling and achieves the goal of improving both work order scheduling efficiency and customer satisfaction.
[0173] The work order scheduling method provided in this application fully considers customer satisfaction. By analyzing and mining historical work data and customer satisfaction survey data and constructing a knowledge graph, and combining it with a maintenance scoring strategy based on factors affecting customer satisfaction and customized by region, the method recommends the most suitable maintenance personnel for on-site construction for each work order, thereby improving customer satisfaction and maintenance work efficiency.
[0174] Once installation and maintenance work orders are archived, the work data is organized, including work order data, customer satisfaction survey information, and installation and maintenance efficiency indicators. This data is then used as incremental samples to supplement the knowledge graph and installation and maintenance scoring model dataset. The newly archived data is used to expand and update the knowledge graph, updating factors influencing customer satisfaction. The installation and maintenance scoring model is then adjusted based on these new factors, achieving continuous adjustment and optimization of the knowledge graph and scoring model, resulting in increasingly accurate and reliable recommendation results. Through continuous feedback from archived data to the scheduling strategy, cities and regions can adjust their intelligent work order scheduling strategies at any time based on the latest key factors influencing customer satisfaction and the knowledge graph, achieving a reasonable and balanced allocation of installation and maintenance personnel and improving scheduling efficiency.
[0175] The method described in this application can achieve accurate and reliable scheduling of installation and maintenance work orders, and improve both the rationality of work order scheduling and customer satisfaction.
[0176] The method provided in this application addresses the problems of work order backlog and low customer satisfaction caused by unreasonable work order scheduling and untimely work order transfer. It proposes a knowledge graph-based intelligent work order scheduling method. This method mines and analyzes historical work data and customer satisfaction survey data to construct a knowledge graph and installation / maintenance scoring strategy. By calculating the scores of the list of recommended installation / maintenance personnel, it recommends the most suitable personnel for each work order. The method provided in this application has the advantages of improving customer satisfaction and the rationality of work order scheduling, and reducing the need for manual work order transfer by installation / maintenance personnel.
[0177] In addition, local city and grid administrators can adjust and customize the installation and maintenance scoring model according to their own regional conditions, find the most suitable scheduling strategy for their own situation, and improve the efficiency of work order scheduling. By mining and analyzing archived data, the semantic relationship of knowledge graph and installation and maintenance scoring strategy can be continuously adjusted and optimized to make the work order scheduling results more accurate and reliable.
[0178] The scheduling device for installation and maintenance work orders provided in the embodiments of this application will be described below. The scheduling device for installation and maintenance work orders described below can be referred to in correspondence with the scheduling method for installation and maintenance work orders described above.
[0179] This application provides a scheduling device for installation and maintenance work orders, including:
[0180] The acquisition unit is used to acquire the first attribute information in the installation and maintenance work order to be scheduled, the first attribute information including the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0181] The acquisition unit is also used to acquire the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library;
[0182] The determining unit is used to determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graph corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0183] The determining unit is further configured to determine the similarity between the first attribute information and each of the second attribute information;
[0184] The determining unit is further configured to determine a target installation and maintenance group from the installation and maintenance groups corresponding to the plurality of historical installation and maintenance work orders based on the similarity of each of the second attribute information, wherein the target installation and maintenance group includes at least one installation and maintenance personnel.
[0185] The determining unit is further configured to determine the target maintenance personnel from the target maintenance group;
[0186] The sending unit is used to send the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel.
[0187] In one embodiment, the determining unit is specifically used for:
[0188] The similarity of each of the second attribute information is sorted in descending order to determine the first historical installation and maintenance work order corresponding to the first preset number of second attribute information.
[0189] Determine the installation and maintenance group corresponding to each of the first preset number of first historical installation and maintenance work orders;
[0190] The maintenance group that appears most frequently is identified as the target maintenance group.
[0191] In one embodiment, the determining unit is specifically used for:
[0192] Based on the first evaluation information of each installation and maintenance personnel in the target installation and maintenance group, determine the recommendation index of each installation and maintenance personnel;
[0193] The recommendation index of each installation and maintenance personnel is sorted in descending order to determine the installation and maintenance personnel corresponding to the first second preset number of recommendation indices;
[0194] The target installation and maintenance personnel are determined based on the installation and maintenance capability value and available installation and maintenance time of each of the first two preset number of recommendation indices.
[0195] In one embodiment, the determining unit is specifically used for:
[0196] The recommendation index for each installation and maintenance personnel is determined according to the following formula:
[0197] f(P,T)=C1·g(X(P,T))+C2·h(Y(P,T))
[0198] Where T is the installation and maintenance work order, P is the installation and maintenance personnel corresponding to the installation and maintenance work order; g is the indicator function affecting customer satisfaction, h is the installation and maintenance efficiency indicator function, C1 is the customer satisfaction indicator weight coefficient, C2 is the installation and maintenance efficiency indicator weight coefficient; f(P,T) is the recommendation index of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; X(P,T) is the satisfaction indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; Y(P,T) is the installation and maintenance efficiency indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T.
[0199] In one embodiment, the first attribute information also includes installation and maintenance time information;
[0200] The determining unit is specifically used for:
[0201] Based on the installation and maintenance capability values of the installation and maintenance personnel corresponding to the first second preset number of recommendation indices, determine the installation and maintenance personnel whose installation and maintenance capability values are greater than the preset values;
[0202] Match the available installation and maintenance time of installation and maintenance personnel whose installation and maintenance capability value is greater than the preset value with the installation and maintenance time information;
[0203] The successfully matched installation and maintenance personnel are identified as the target installation and maintenance personnel.
[0204] In one embodiment, the apparatus further includes: a building unit; wherein:
[0205] The acquisition unit is used to extract information from multiple historical installation and maintenance work orders and the installation and maintenance information corresponding to each of the multiple historical installation and maintenance work orders, and to obtain the installation and maintenance location information, installation and maintenance personnel information, installation and maintenance group to which the installation and maintenance personnel belong, and customer information corresponding to each historical installation and maintenance work order.
[0206] The construction unit is used to construct a knowledge graph corresponding to each historical installation and maintenance work order based on the installation and maintenance location information, the installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order.
[0207] In one embodiment, the apparatus further includes: an updating unit, wherein:
[0208] The construction unit is used to construct a knowledge graph corresponding to the installation and maintenance work order to be scheduled based on the installation and maintenance location information of the work order to be scheduled, the target installation and maintenance personnel and the target installation and maintenance group, and the corresponding customer information.
[0209] The update unit is used to add the knowledge graph corresponding to the installation and maintenance work order to be scheduled to the knowledge graph library.
[0210] In one embodiment, the updating unit is further configured to: receive second evaluation information for the target installation and maintenance personnel sent by the terminal; and update the first evaluation information of the target installation and maintenance personnel according to the second evaluation information.
[0211] The apparatus of this embodiment can be used to execute the method of any of the aforementioned terminal-side method embodiments. Its specific implementation process and technical effects are similar to those of the terminal-side method embodiments. For details, please refer to the detailed description in the terminal-side method embodiments, which will not be repeated here.
[0212] The terminal involved in the embodiments of this application may be a device that provides voice and / or data connectivity to a user, a handheld device with wireless connectivity, or other processing devices connected to a wireless modem. The name of the terminal device may differ in different systems; for example, in a 5G system, the terminal device may be called a User Equipment (UE).
[0213] Figure 11 This is a schematic diagram of the terminal structure provided in the embodiments of this application, with reference to... Figure 11 This application provides a terminal that may include: a memory 1110, a transceiver 1120, and a processor 1130;
[0214] Memory 1110 is used to store computer programs; transceiver 1120 is used to send and receive data under the control of processor 1130; processor 1130 is used to read the computer program in memory 1110 and perform the following operations:
[0215] Includes memory, transceiver, and processor;
[0216] Obtain the first attribute information from the installation and maintenance work order to be scheduled, wherein the first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0217] Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0218] Determine the similarity between the first attribute information and each of the second attribute information;
[0219] Based on the similarity of each of the second attribute information, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel.
[0220] The target installation and maintenance personnel are identified from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
[0221] Among them, Figure 11 In this application, the bus architecture can include any number of interconnected buses and bridges, specifically linking various circuits of one or more processors represented by processor 1130 and memory represented by memory 1110 together. The bus architecture can also link various other circuits such as peripheral devices, voltage regulators, and power management circuits, which are well known in the art and therefore will not be further described herein. The bus interface provides an interface. Transceiver 1120 can be multiple elements, including transmitters and receivers, providing a unit for communicating with various other devices over a transmission medium. For different user equipment, user interface 1140 can also be an interface capable of connecting external or internal devices as needed.
[0222] Processor 1130 is responsible for managing the bus architecture and general processing, while memory 1110 can store data used by processor 1130 when performing operations.
[0223] The processor 1130 executes any of the methods described in the embodiments of this application by calling a computer program stored in the memory 1110, according to the obtained executable instructions. The processor and the memory may also be physically separated.
[0224] Optionally, the processor 1130 is also used to perform the following operations:
[0225] The target installation and maintenance group is determined from the installation and maintenance groups corresponding to the multiple historical installation and maintenance work orders, and the target installation and maintenance group includes at least one installation and maintenance personnel;
[0226] The target installation and maintenance personnel are identified from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
[0227] The step of determining the target installation and maintenance group from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders based on the similarity of each of the second attribute information includes:
[0228] The similarity of each of the second attribute information is sorted in descending order to determine the first historical installation and maintenance work order corresponding to the first preset number of second attribute information.
[0229] Determine the installation and maintenance group corresponding to each of the first preset number of first historical installation and maintenance work orders;
[0230] The maintenance group that appears most frequently is identified as the target maintenance group.
[0231] The step of determining the target equipment maintenance personnel from the target equipment maintenance group includes:
[0232] Based on the first evaluation information of each installation and maintenance personnel in the target installation and maintenance group, determine the recommendation index of each installation and maintenance personnel;
[0233] The recommendation index of each installation and maintenance personnel is sorted in descending order to determine the installation and maintenance personnel corresponding to the first second preset number of recommendation indices;
[0234] The target installation and maintenance personnel are determined based on the installation and maintenance capability value and available installation and maintenance time of each of the first two preset number of recommendation indices.
[0235] The step of determining the recommendation index for each installation and maintenance personnel based on the first evaluation information of each personnel in the target installation and maintenance group includes:
[0236] The recommendation index for each installation and maintenance personnel is determined according to the following formula (1):
[0237] f(P,T)=C1·g(X(P,T))+C2·h(Y(P,T)) (1)
[0238] Where T is the installation and maintenance work order, P is the installation and maintenance personnel corresponding to the installation and maintenance work order; g is the indicator function affecting customer satisfaction, h is the installation and maintenance efficiency indicator function, C1 is the customer satisfaction indicator weight coefficient, C2 is the installation and maintenance efficiency indicator weight coefficient; f(P,T) is the recommendation index of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; X(P,T) is the satisfaction indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; Y(P,T) is the installation and maintenance efficiency indicator of the installation and maintenance personnel P corresponding to the installation and maintenance work order T.
[0239] The first attribute information also includes installation and maintenance time information;
[0240] The step of determining the target installation and maintenance personnel based on the installation and maintenance capability value and available installation and maintenance time of each of the first second preset number of recommendation indices includes:
[0241] Based on the installation and maintenance capability values of the installation and maintenance personnel corresponding to the first second preset number of recommendation indices, determine the installation and maintenance personnel whose installation and maintenance capability values are greater than the preset values;
[0242] Match the available installation and maintenance time of installation and maintenance personnel whose installation and maintenance capability value is greater than the preset value with the installation and maintenance time information;
[0243] The successfully matched installation and maintenance personnel are identified as the target installation and maintenance personnel. In one embodiment, before retrieving the knowledge graphs corresponding to multiple historical installation and maintenance work orders from the knowledge graph library, the method further includes:
[0244] Information is extracted from multiple historical installation and maintenance work orders and the corresponding installation and maintenance information for each of the multiple historical installation and maintenance work orders, to obtain the installation and maintenance location information, installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order;
[0245] Based on the installation and maintenance location information, the installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order, a knowledge graph corresponding to each historical installation and maintenance work order is constructed.
[0246] After determining the target equipment maintenance personnel from the target equipment maintenance group, the method further includes:
[0247] Based on the installation and maintenance location information of the installation and maintenance work order to be scheduled, the target installation and maintenance personnel and the target installation and maintenance group, and the corresponding customer information, a knowledge graph corresponding to the installation and maintenance work order to be scheduled is constructed.
[0248] Add the knowledge graph corresponding to the installation and maintenance work order to be scheduled to the knowledge graph library.
[0249] After sending the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel, the method further includes:
[0250] Receive the second evaluation information sent by the terminal for the target installation and maintenance personnel;
[0251] The first evaluation information of the target maintenance personnel is updated based on the second evaluation information.
[0252] Figure 12 An example is a schematic diagram of the physical structure of an electronic device, such as... Figure 12As shown, the electronic device may include: a processor 1210, a communication interface 1220, a memory 1230, and a communication bus 1240. The processor 1210, communication interface 1220, and memory 1230 communicate with each other via the communication bus 1240. The processor 1210 can call a computer program in the memory 1230 to execute the steps of the installation and maintenance work order scheduling method, such as including:
[0253] Obtain the first attribute information from the installation and maintenance work order to be scheduled, wherein the first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0254] Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0255] Determine the similarity between the first attribute information and each of the second attribute information;
[0256] Based on the similarity of each of the second attribute information, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel.
[0257] The target installation and maintenance personnel are identified from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
[0258] Furthermore, the logical instructions in the aforementioned memory 1230 can be implemented as software functional units and, when sold or used as independent products, can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, or a part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of this application. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical disks.
[0259] On the other hand, this application also provides a computer program product, which includes a computer program that can be stored on a non-transitory computer-readable storage medium. When the computer program is executed by a processor, the computer can perform the steps of the installation and maintenance work order scheduling method provided in the above embodiments, such as including:
[0260] Obtain the first attribute information from the installation and maintenance work order to be scheduled, wherein the first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0261] Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0262] Determine the similarity between the first attribute information and each of the second attribute information;
[0263] Based on the similarity of each of the second attribute information, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel.
[0264] The target installation and maintenance personnel are identified from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
[0265] On the other hand, embodiments of this application also provide a processor-readable storage medium storing a computer program for causing a processor to perform the steps of the methods provided in the above embodiments, such as including:
[0266] Obtain the first attribute information from the installation and maintenance work order to be scheduled, wherein the first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled.
[0267] Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order.
[0268] Determine the similarity between the first attribute information and each of the second attribute information;
[0269] Based on the similarity of each of the second attribute information, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel.
[0270] The target installation and maintenance personnel are identified from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
[0271] The processor-readable storage medium can be any available medium or data storage device that the processor can access, including but not limited to magnetic memory (e.g., floppy disk, hard disk, magnetic tape, magneto-optical disk (MO)), optical memory (e.g., CD, DVD, BD, HVD), and semiconductor memory (e.g., ROM, EPROM, EEPROM, non-volatile memory (NAND FLASH), solid-state drive (SSD)).
[0272] The device embodiments described above are merely illustrative. The units described as separate components may or may not be physically separate. The components shown as units may or may not be physical units; that is, they may be located in one place or distributed across multiple network units. Some or all of the modules can be selected to achieve the purpose of this embodiment according to actual needs. Those skilled in the art can understand and implement this without any creative effort.
[0273] Through the above description of the embodiments, those skilled in the art can clearly understand that each embodiment can be implemented by means of software plus necessary general-purpose hardware platforms, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solutions, in essence or the part that contributes to the prior art, can be embodied in the form of a software product. This computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, magnetic disk, optical disk, etc., and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute the methods described in the various embodiments or some parts of the embodiments.
[0274] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of this application, and are not intended to limit them. Although this application has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of this application.
Claims
1. A scheduling method for installation and maintenance work orders, characterized in that, include: Obtain the first attribute information from the installation and maintenance work order to be scheduled. The first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled. The installation and maintenance location information includes the location area and the geographical environment of the installation and maintenance. Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order. Determine the similarity between the first attribute information and each of the second attribute information; Based on the similarity of each of the second attribute information, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel. Based on the first evaluation information of each installation and maintenance personnel in the target installation and maintenance group, a recommendation index for each installation and maintenance personnel is determined through an installation and maintenance scoring model, which is based on indicators affecting customer satisfaction and installation and maintenance efficiency. Based on the recommendation index of each installation and maintenance personnel, target installation and maintenance personnel are determined from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
2. The scheduling method for installation and maintenance work orders according to claim 1, characterized in that, The step of determining the target installation and maintenance group from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders based on the similarity of each of the second attribute information includes: The similarity of each of the second attribute information is sorted in descending order to determine the first historical installation and maintenance work order corresponding to the first preset number of second attribute information. Determine the installation and maintenance group corresponding to each of the first preset number of first historical installation and maintenance work orders; The maintenance group that appears most frequently is identified as the target maintenance group.
3. The method according to claim 1, characterized in that, The step of determining the target equipment maintenance personnel from the target equipment maintenance group includes: Based on the first evaluation information of each installation and maintenance personnel in the target installation and maintenance group, determine the recommendation index of each installation and maintenance personnel; The recommendation index of each installation and maintenance personnel is sorted in descending order to determine the installation and maintenance personnel corresponding to the first second preset number of recommendation indices; The target installation and maintenance personnel are determined based on the installation and maintenance capability value and available installation and maintenance time of each of the first two preset number of recommendation indices.
4. The method according to claim 3, characterized in that, The step of determining the recommendation index for each installation and maintenance personnel based on the first evaluation information of each personnel in the target installation and maintenance group includes: The recommendation index for each installation and maintenance personnel is determined according to the following formula: ; in, Installation and maintenance work order, where P is the installation and maintenance personnel corresponding to the installation and maintenance work order; It is a function that influences customer satisfaction. It is a function of installation and maintenance efficiency index. It is the weighting coefficient of the customer satisfaction index. It is the weighting coefficient of the installation and maintenance efficiency index; It is the recommendation index of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; It is the satisfaction index of the installation and maintenance personnel P corresponding to the installation and maintenance work order T; It is the installation and maintenance efficiency index of the installation and maintenance personnel P corresponding to the installation and maintenance work order T.
5. The method according to claim 3 or 4, characterized in that, The first attribute information also includes installation and maintenance time information; The step of determining the target installation and maintenance personnel based on the installation and maintenance capability value and available installation and maintenance time of each of the first second preset number of recommendation indices includes: Based on the installation and maintenance capability values of the installation and maintenance personnel corresponding to the first second preset number of recommendation indices, determine the installation and maintenance personnel whose installation and maintenance capability values are greater than the preset values; Match the available installation and maintenance time of installation and maintenance personnel whose installation and maintenance capability value is greater than the preset value with the installation and maintenance time information; The successfully matched installation and maintenance personnel are identified as the target installation and maintenance personnel.
6. The method according to any one of claims 1-4, characterized in that, Before retrieving the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph database, the method further includes: Information is extracted from multiple historical installation and maintenance work orders and the corresponding installation and maintenance information for each of the multiple historical installation and maintenance work orders, to obtain the installation and maintenance location information, installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order; Based on the installation and maintenance location information, the installation and maintenance personnel information, the installation and maintenance group to which the installation and maintenance personnel belong, and the customer information corresponding to each historical installation and maintenance work order, a knowledge graph corresponding to each historical installation and maintenance work order is constructed.
7. The method according to any one of claims 1-4, characterized in that, After determining the target equipment maintenance personnel from the target equipment maintenance group, the method further includes: Based on the installation and maintenance location information of the installation and maintenance work order to be scheduled, the target installation and maintenance personnel and the target installation and maintenance group, and the corresponding customer information, a knowledge graph corresponding to the installation and maintenance work order to be scheduled is constructed. Add the knowledge graph corresponding to the installation and maintenance work order to be scheduled to the knowledge graph library.
8. The method according to claim 3 or 4, characterized in that, After sending the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel, the method further includes: Receive the second evaluation information sent by the terminal for the target installation and maintenance personnel; The first evaluation information of the target maintenance personnel is updated based on the second evaluation information.
9. A scheduling device for installation and maintenance work orders, characterized in that, include: The acquisition unit is used to acquire the first attribute information in the installation and maintenance work order to be scheduled. The first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled. The installation and maintenance location information includes the location area and the installation and maintenance geographical environment. The acquisition unit is also used to acquire the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library; The determining unit is used to determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graph corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order. The determining unit is further configured to determine the similarity between the first attribute information and each of the second attribute information; The determining unit is further configured to determine a target installation and maintenance group from the installation and maintenance groups corresponding to each of the plurality of historical installation and maintenance work orders based on the similarity of each of the second attribute information, wherein the target installation and maintenance group includes at least one installation and maintenance personnel. The determining unit is further configured to determine the recommendation index of each installation and maintenance personnel in the target installation and maintenance group based on the first evaluation information of each installation and maintenance personnel in the target installation and maintenance group, through an installation and maintenance scoring model, wherein the installation and maintenance scoring model is based on indicators affecting customer satisfaction and installation and maintenance efficiency; and to determine target installation and maintenance personnel from the target installation and maintenance group based on the recommendation index of each installation and maintenance personnel. The sending unit is used to send the installation and maintenance work order to be scheduled to the terminal corresponding to the target installation and maintenance personnel.
10. A terminal, characterized in that, Includes memory, transceiver, and processor; A memory for storing computer programs; a transceiver for sending and receiving data under the control of the processor; and a processor for reading the computer programs from the memory and performing the following operations: Obtain the first attribute information from the installation and maintenance work order to be scheduled. The first attribute information includes the installation and maintenance location information corresponding to the installation and maintenance work order to be scheduled. The installation and maintenance location information includes the location area and the geographical environment of the installation and maintenance. Obtain the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders from the knowledge graph library, and determine the second attribute information corresponding to each historical installation and maintenance work order based on the knowledge graphs corresponding to each of the multiple historical installation and maintenance work orders. The second attribute information includes the installation and maintenance location information corresponding to each historical installation and maintenance work order. Determine the similarity between the first attribute information and each of the second attribute information; Based on the similarity of each of the second attribute information, a target installation and maintenance group is determined from the installation and maintenance groups corresponding to each of the multiple historical installation and maintenance work orders. The target installation and maintenance group includes at least one installation and maintenance personnel. Based on the first evaluation information of each installation and maintenance personnel in the target installation and maintenance group, a recommendation index for each installation and maintenance personnel is determined through an installation and maintenance scoring model, which is based on indicators affecting customer satisfaction and installation and maintenance efficiency. Based on the recommendation index of each installation and maintenance personnel, target installation and maintenance personnel are determined from the target installation and maintenance group, and the installation and maintenance work order to be scheduled is sent to the terminal corresponding to the target installation and maintenance personnel.
11. An electronic device comprising a processor and a memory storing a computer program, characterized in that, When the processor executes the computer program, it implements the steps of the scheduling method for installation and maintenance work orders as described in any one of claims 1 to 8.
12. A computer program product, comprising a computer program, characterized in that, When the computer program is executed by the processor, it implements the steps of the scheduling method for installation and maintenance work orders as described in any one of claims 1 to 8.
Citation Information
Patent Citations
A method and system for work order assignment
CN112686584A
Recommendation method and device
CN114186024A
Work order allocation method and device, and storage medium
CN114331198A