A TBM small-radius tunnel construction equipment deviation correction method

By establishing a three-dimensional model of the TBM and performing stress analysis, combined with passive articulated jacks and finite element software simulation, the problem of TBM equipment shifting in tunnels with extremely small radii was solved, achieving efficient and accurate correction, and ensuring the quality and safety of tunnel construction.

CN117090585BActive Publication Date: 2026-11-24SINOHYDRO BUREAU 5
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311022159.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-08-14
Publication Date
2026-11-24
Estimated Expiration
2043-08-14

AI Technical Summary

Technical Problem

In tunnel construction on sections with extremely small radius curves, it is difficult to accurately correct the deviation of TBM equipment, which affects construction quality and safety.

Method used

By establishing a 3D model of the TBM and conducting stress analysis, updating the model based on actual construction conditions, configuring passive articulated jacks, simulating the correction process using finite element analysis software, and adjusting the TBM equipment to meet stress requirements.

Benefits of technology

This improves the efficiency and accuracy of TBM equipment correction, reduces the probability of deviation, and ensures the quality and safety of tunnel construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117090585B_ABST
    Figure CN117090585B_ABST
Patent Text Reader

Abstract

This invention relates to the field of tunnel construction technology, specifically to a method for correcting the deviation of a TBM (Tunnel Boring Machine) in small-radius tunnel construction. The method includes the following steps: establishing a three-dimensional model of the TBM and its construction environment and performing stress analysis on it; adjusting the three-dimensional model to ensure the stress analysis results meet requirements; configuring passive articulated jacks between the support shield and the shield body; conducting real-time measurements and providing advanced geological forecasts during tunnel excavation, while simultaneously updating the three-dimensional model; designing motion simulation examples of the TBM excavation process, and correcting the deviation of the updated three-dimensional model until the stress analysis results meet construction requirements. This invention can achieve accurate deviation correction for TBM equipment, improve correction efficiency, and save construction time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel construction technology, and more specifically, to a method for correcting the deviation of a TBM (Tunnel Boring Machine) for small-radius tunnel construction. Background Technology

[0002] In recent years, full-face tunnel boring machines (TBMs, also commonly referred to as TBM equipment in China) have increasingly demonstrated their advanced capabilities in tunnel excavation, especially double-shield TBMs. These TBMs enable tunnel construction to achieve excavation, segment assembly, and muck removal in a single, continuous operation, ensuring high-quality, high-standard, and safe tunnel construction. Their structural design and construction characteristics have made them popular with construction companies. Tunnel construction in my country started relatively late, and excavation methods and locations are often limited by the underground structures of numerous building complexes and municipal facilities. Tunnels with extremely small turning radii offer an effective solution to spatial layout challenges. In the construction of sections with extremely small radius curves, the thrust of the tunnel boring machine (TBM) acts on the forming tunnel wall, causing the tunnel to shift outward in the direction of the turn. In soft soil foundations, the soil layer outside the turning tunnel is compressed, but its strength is extremely low, resulting in even greater outward displacement of the soil layer and the tunnel together under the thrust of the shield. Therefore, in actual construction, accurate correction of the TBM equipment to reduce the probability of TBM deviation is particularly important. Summary of the Invention

[0003] This invention provides a method for correcting the deviation of a TBM (Tunnel Boring Machine) in small-radius tunnel construction. Before construction, a three-dimensional model of the TBM is established and stress analysis is performed. Simultaneously, during excavation, the three-dimensional model of the TBM environment is updated based on the actual construction conditions. The three-dimensional model simulates the excavation movement of the actual TBM equipment, and the stress analysis results are used to correct the deviation of the TBM model. This provides an accurate reference for correcting the deviation of the actual TBM equipment, thereby achieving accurate deviation correction of the TBM equipment in small-radius tunnel construction environments.

[0004] This invention is achieved through the following technical solution:

[0005] A method for correcting the deviation of a TBM (Tunnel Boring Machine) for small-radius tunnel construction includes the following steps:

[0006] A three-dimensional model of the TBM and a three-dimensional model of the TBM environment are established. The stress analysis of the excavation process of the TBM three-dimensional model in the TBM environment three-dimensional model is performed using finite element analysis software to obtain the stress analysis results of the TBM three-dimensional model during the excavation process.

[0007] Adjust the TBM 3D model until the stress analysis results meet the construction requirements, and adjust the actual TBM equipment according to the TBM 3D model that meets the construction requirements;

[0008] A passive articulated jack is installed between the support shield and the shield body of the TBM equipment;

[0009] During tunnel excavation, the actual excavation path parameters are measured and advanced geological prediction is performed. The TBM environment three-dimensional model is updated based on the actual excavation path parameters, and the stratum hardness is constrained based on the geological prediction.

[0010] The updated TBM environment 3D model and TBM 3D model are re-imported into the finite element analysis software. The TBM 3D model is adjusted based on the deviation between the actual excavation path and the preset excavation path to correct the deviation until the stress analysis results obtained by simulating the actual excavation movement of the TBM equipment meet the preset values.

[0011] In some alternative embodiments, a traverse point is set at a spacing of 200m on the straight section of the tunnel construction and at a spacing of 15m on the 30m curved section of the tunnel construction to achieve actual excavation path measurement.

[0012] In some alternative embodiments, when the tunnel excavation radius is reduced, a traverse point is set at a spacing of 15m.

[0013] In some alternative embodiments, when the passive articulated jack is configured, the articulation angle of the TBM device satisfies the following relationship:

[0014] a = (L1 + L2) × 180 / π × R;

[0015] Where L1 and L2 are the lengths of the front and rear bodies of the articulated shield, respectively; R is the radius of curvature of the small-radius turning section of the tunnel; and a is the articulation angle of the TBM equipment on the curve of the small-radius turning section.

[0016] In some optional embodiments, during tunnel excavation, the TBM's advance speed is set to 50 mm / min, and the step-changing frequency is increased, with a step-changing operation every 30 cm of excavation. In some optional embodiments, during tunnel excavation, the elevation of the TBM's head and tail is adjusted to be within 100 mm above and below the axis.

[0017] In some optional embodiments, during the excavation of the small-radius turning section, the traverse points and elevation control points are re-measured every 200m. In some optional embodiments, during the excavation of the small-radius turning section, the head of the TBM is adjusted to be offset 30-40mm towards the turning direction, and the rear end of the TBM's support shield is adjusted to be offset 20-35mm towards the turning direction.

[0018] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0019] This invention provides a method for correcting the deviation of a TBM (Tunnel Boring Machine) in small-radius tunnel construction. By establishing a three-dimensional model and combining it with finite element analysis software, the structure of the TBM can be easily modified and corresponding stress analysis results can be obtained. First, the excavation process is simulated using a three-dimensional model and finite element analysis software. Then, the actual TBM is adjusted according to the three-dimensional model structure that meets the stress requirements. This improves the adjustment efficiency of the TBM during deviation correction, simplifies the actual verification work of the TBM, and provides a more reliable guarantee for the normal excavation of the TBM. During the excavation process, the excavation path is detected and advanced geological prediction is performed. Then, the three-dimensional model of the TBM environment is updated. When deviation occurs, the deviation can be simulated using finite element analysis software to obtain the stress analysis results during the correction process. Based on the stress analysis results, the three-dimensional model of the TBM is adjusted in reverse, providing correct guidance for the actual TBM deviation correction work, simplifying the TBM deviation correction process, ensuring the accuracy of deviation correction, and thus reducing the probability or degree of deviation during the TBM excavation process. Attached Figure Description

[0020] To more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the accompanying drawings used in the embodiments will be briefly described below. It should be understood that the following drawings only show some embodiments of the present invention and should not be regarded as a limitation of the scope. For those skilled in the art, other related drawings can be obtained based on these drawings without creative effort.

[0021] Figure 1 This is a schematic diagram of the TBM small-radius tunnel construction equipment correction method provided in an embodiment of the present invention. Detailed Implementation

[0022] To make the objectives, technical solutions, and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the embodiments and accompanying drawings. The illustrative embodiments and descriptions of the present invention are only used to explain the present invention and are not intended to limit the present invention.

[0023] In the following description, numerous specific details are set forth in order to provide a thorough understanding of the invention. However, it will be apparent to those skilled in the art that these specific details are not necessary to practice the invention. In other embodiments, well-known structures, circuits, materials, or methods have not been specifically described in order to avoid obscuring the invention.

[0024] Throughout this specification, references to "an embodiment," "an example," or "an example" mean that a particular feature, structure, or characteristic described in connection with that embodiment or example is included in at least one embodiment of the invention. Therefore, the phrases "an embodiment," "an example," "an example," or "an example" appearing in various places throughout the specification do not necessarily refer to the same embodiment or example. Furthermore, specific features, structures, or characteristics can be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. Moreover, those skilled in the art will understand that the illustrations provided herein are for illustrative purposes and are not necessarily drawn to scale. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.

[0025] In the description of this invention, the terms "front," "rear," "left," "right," "up," "down," "vertical," "horizontal," "high," "low," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limiting the scope of protection of this invention.

[0026] like Figure 1 As shown, this embodiment of the invention provides a method for correcting the deviation of a TBM (Tunnel Boring Machine) construction equipment with a small radius, comprising the following steps:

[0027] S1. Establish a 3D model of the TBM and a 3D model of the TBM environment. Use finite element analysis software to perform stress analysis on the excavation process of the TBM 3D model in the 3D model of the TBM environment to obtain the stress analysis results of the TBM 3D model during the excavation process.

[0028] When constructing a 3D model of a TBM, the physical properties of each component, such as material, density, and elastic modulus, can be accurately constrained to ensure that the mechanical properties of the TBM model are comparable to those of the actual TBM equipment. The 3D environmental model of the TBM is the geological model of the site to be excavated. In constructing the 3D environmental model, a tunnel of a certain depth can be pre-designed according to the planned excavation route. The property constraint parameters of the 3D environmental model can adopt the geological parameters initially obtained on-site. Then, the 3D TBM model and the 3D environmental model are combined, and motion calculations conforming to the pre-designed excavation path are designed for the TBM model. Finally, stress analysis results of the TBM model during motion are obtained using finite element analysis software.

[0029] S2. Adjust the TBM 3D model until the stress analysis results meet the construction requirements, and adjust the actual TBM equipment according to the TBM 3D model that meets the construction requirements.

[0030] When adjusting the TBM 3D model, the structure and operating parameters of the TBM 3D model can be adjusted based on engineering experience. For example, the specific structural construction of the TBM 3D model can be adjusted, such as removing the tail shield, auxiliary thrust cylinder, segment assembly machine, etc. The material constraint parameters of each component of the TBM 3D model can also be adjusted, as can the constraint dimensions between the components in the TBM 3D model. Furthermore, the motor speed, the output hydraulic pressure of the hydraulic system, and the fluid flow rate in the hydraulic distribution system can also be adjusted.

[0031] S3. A passive articulated jack is installed between the support shield and the shield body of the TBM equipment.

[0032] In small-radius construction environments, the alignment between the shield shell and the tunnel curve is often poor, easily leading to significant over-excavation during TBM advancement. Furthermore, the advancement axis is difficult to control. By installing passive articulated jacks between the TBM support shield and the shield body, the shield shell itself can turn, allowing the TBM to be adjusted during excavation to align with the tunnel curve. This reduces over-excavation and enables the TBM to generate a propulsion force aligned with the excavation direction, facilitating advancement axis control during curved tunnel sections. Moreover, with passive articulated jacks, the jacks automatically retract when the shield tail shell collides with the tunnel wall, preventing jamming between the tunnel wall and the shield tail.

[0033] When configuring a passive articulated jack, its articulation angle can satisfy the relationship: a=(L1+L2)×180 / π×R, where L1 and L2 are the lengths of the front and rear bodies of the tunnel boring machine, respectively, R is the radius of curvature of the small radius turning section of the tunnel, and a is the articulation angle of the TBM equipment on the curve of the small radius turning section.

[0034] S4. Excavate the tunnel. During the excavation process, measure the actual excavation path parameters and perform advanced geological prediction. Update the TBM environment three-dimensional model using the actual excavation path parameters and constrain the TBM environment three-dimensional model based on the stratum hardness obtained from the advanced geological prediction.

[0035] In specific testing, traverse points can be set at 200m intervals on straight sections of tunnel construction and at 15m intervals on curved sections. These traverse points are specific locations used to guide and control the accurate advancement of the TBM (Tunnel Boring Machine). They are typically predetermined and established on the tunnel axis, and are set at the tunnel's start and end points, as well as at important bends. The TBM is equipped with a VMT (Vehicle Measurement and Control) automatic measurement system. During TBM excavation, the VMT system uses sensors to collect various data, such as the TBM's displacement, attitude, and horizontal and vertical deviations. This data is compared with the pre-set traverse points. By comparing with the traverse points, the VMT system can provide real-time construction control and feedback information, helping operators ensure the TBM advances accurately on the track and correct any deviations. Therefore, traverse points provide a reference benchmark during construction, while the VMT system, by measuring and tracking differences from the traverse points, helps achieve accurate control and advancement of the TBM, thus ensuring the accurate location and construction quality of the tunnel.

[0036] Of course, during the correction process, if the TBM's position happens to correspond to a certain traverse point, the TBM's excavation direction can be determined by its attitude, thus determining its actual position in the tunnel environment. Based on this actual position, the TBM's 3D model is updated within the 3D model of the tunnel environment. Simultaneously, the 3D model of the TBM environment is re-constrained based on soil characteristics, groundwater conditions, and principal stress states to make the 3D model of the TBM environment more refined within a certain range, resulting in more accurate stress analysis results. If the TBM's position is between two traverse points during correction, the excavation direction at each traverse point can be determined based on the TBM's attitude measured at multiple traverse points. Integrating the excavation directions of multiple TBMs and using curve fitting yields the actual excavated tunnel axis. Based on the curve fitting results, a predicted TBM excavation direction can be obtained. Combining this with data measured by the TBM's VMT system yields a more accurate TBM excavation direction.

[0037] Of course, long-distance excavation will also lead to significant error accumulation in the automatic measurement system, especially in the small-radius turning sections where each step introduces substantial errors. To control the TBM equipment's axis from deviating, in addition to increasing the density of traverse point placement, the measurement of the suspended platform and traverse points can also be intensified to promptly verify and correct the automatic measurement system. For example, during the construction of small-radius turning sections, manual measurements are performed each time a station is changed, and the measurement results are transmitted from the traverse points to the suspended platform to ensure the timeliness of the automatic measurement system's verification or correction. At the same time, the traverse points and elevation control points in the small-radius turning sections can be remeasured every 10-15 meters. Simultaneously, if outward deviation occurs due to the tunnel boring machine's (TBM) thrust, the thrust axis can be pre-offset appropriately. For example, when the turning direction of a small-radius turning section is left, the excavation line of the TBM head can be offset to the left by 30-40mm, and the rear end of the TBM's shield tensioning device can also be offset to the left by 20-35mm. When offsetting the TBM head, the following can be included: Determining the offset target and parameters: Based on tunnel design requirements and actual conditions, determine the target direction and amount of offset required for the TBM head. This can be determined through design documents, measurement data, and engineering requirements. Determining and adjusting the cutterhead hydraulic system: Adjust the working parameters of the cutterhead hydraulic system according to the target offset direction, such as the working pressure, flow rate, and direction of the hydraulic cylinders. As needed, rotate and tilt the cutterhead accordingly to achieve the head offset. Real-time monitoring and correction control: Use a VMT system to monitor the position and attitude of the TBM in real time. Based on the monitoring data, compare it with pre-set guide points to determine whether the offset has achieved the expected effect. If further adjustments are needed, correction control can be performed based on the monitoring data, such as fine-tuning the parameters of the hydraulic system. Comprehensive Adjustment and Repeated Monitoring: Based on feedback from real-time monitoring data, comprehensively adjust parameters such as the hydraulic system, track and guidance system, as well as propulsion force and propulsion speed to ensure the offset effect is optimized and meets engineering requirements. Repeat monitoring and adjustment until design requirements are met. Verification and Testing: After the TBM head offset is completed, calibration and testing are performed to verify the accuracy of the offset. This may include measuring the cutterhead position and checking and verifying other relevant parameters of the tunnel wall.

[0038] If there is a significant discrepancy between the measurement data from the VMT system in the TBM and the traverse points, manual adjustments and corrections by operators can be made to ensure the accurate location of the tunnel and the stability of the track. In some implementations, when there is a significant discrepancy between the measurement data from the TBM and the traverse points, the following methods can be used:

[0039] S5. Re-import the updated TBM environment 3D model and TBM 3D model into the finite element analysis software. Adjust the TBM 3D model based on the deviation between the actual excavation path and the preset excavation path to correct the deviation until the stress analysis results obtained by simulating the actual excavation movement of the TBM equipment meet the preset values.

[0040] During the simulation of TBM excavation, the three-dimensional model of the TBM environment is constrained by geological parameters predicted in advance. Therefore, the stress analysis results of the TBM during the simulation are basically consistent with the actual TBM excavation process. That is, by simulating the excavation movement of the TBM and combining it with the stress analysis results, the actual excavation results of the TBM can be predicted, thereby ensuring the accuracy and effectiveness of the actual correction results.

[0041] In some alternative embodiments, when the tunnel excavation radius is reduced, the visibility conditions inside the tunnel are limited. In order to obtain accurate measurement results, a traverse point can be set at a spacing of 70m.

[0042] While excavating the tunnel, grouting is also involved in the tunnel wall to reinforce the strata, fill voids, control groundwater and soil liquefaction, etc. In some optional embodiments, the grouting volume during the tunnel excavation grouting process can be set to 120% to 200% of the theoretical building voids.

[0043] In some alternative embodiments, as the tunnel excavation radius decreases, the initial grouting volume is set to 130%–200% of the theoretical building void, and then the grouting volume is gradually reduced to 125%–180% of the theoretical building void.

[0044] During tunnel excavation, the deviation of the TBM equipment may also be caused by the advancing speed of the TBM equipment, especially in small-radius turning sections. The faster the advancing speed, the easier it is to deviate. Therefore, in some optional embodiments, during tunnel excavation, the advancing speed of the TBM equipment should be set to 50mm / min, and the step-changing frequency should be increased, with a step-changing every 30cm of excavation.

[0045] In actual construction, the small-radius turning section is located in a complex geological area, in a saturated, water-bearing soft soil foundation. Therefore, in some optional embodiments, the elevation of the head and tail of the TBM equipment can be adjusted to be lower than the elevation of the tunnel's central axis to eliminate some of the upward impact, so that the final stable tunnel axis elevation is within the design and specification requirements.

[0046] In summary, this invention, by combining a 3D model with stress analysis, enables pre-adjustment of the TBM equipment within the 3D model. The stress analysis results quickly determine whether the adjustment meets requirements. Then, the 3D model of the TBM can be adjusted back to meet construction requirements based on the stress analysis results. The adjusted 3D model provides accurate guidance for the actual adjustment of the TBM equipment, simplifying the actual adjustment process and reducing post-adjustment verification and testing. This improves the overall efficiency of the correction process and saves overall construction time. Furthermore, the pre-simulation of the TBM excavation process in the stress analysis software provides guidance for the actual TBM excavation process, reducing the probability of deviation during actual excavation.

[0047] The specific embodiments described above further illustrate the purpose, technical solution, and beneficial effects of the present invention. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A TBM small radius tunnel construction equipment deviation rectification method, characterized in that, Includes the following steps: A three-dimensional model of the TBM and a three-dimensional model of the TBM environment are established. The stress analysis of the excavation process of the TBM three-dimensional model in the TBM environment three-dimensional model is performed using finite element analysis software to obtain the stress analysis results of the TBM three-dimensional model during the excavation process. Adjust the TBM 3D model until the stress analysis results meet the construction requirements, and adjust the actual TBM equipment according to the TBM 3D model that meets the construction requirements; A passive hinge jack is installed between the support shield and the shield body of the TBM equipment. When installed, the hinge angle of the TBM equipment satisfies the following relationship: a = (L1 + L2) × 180 / π × R; Where L1 and L2 are the lengths of the front and rear bodies of the articulated shield, respectively; R is the radius of curvature of the small-radius turning section of the tunnel; and a is the articulation angle of the TBM equipment on the curve of the small-radius turning section. During tunnel excavation, actual excavation path parameters are measured and advanced geological prediction is performed. The TBM environmental 3D model is updated using the actual excavation path parameters, and the TBM environmental 3D model is constrained based on the stratum hardness obtained from the advanced geological prediction. The TBM's advance speed is set to 50 mm / min, and the step-changing frequency is increased, with a step-changing every 30 cm of excavation. The elevation of the head and tail of the TBM equipment is adjusted to be within 100 mm above and below the axis. When excavating small-radius turning sections, the guide points and elevation control points are re-measured every 200 m. The head of the TBM equipment is adjusted to be biased towards the turning direction by 30-40 mm, and the rear end of the TBM equipment's shield is adjusted to be biased towards the turning direction by 20-35 mm. The updated TBM environment 3D model and TBM 3D model are re-imported into the finite element analysis software. The TBM 3D model is adjusted based on the deviation between the actual excavation path and the preset excavation path to correct the deviation until the stress analysis results obtained by simulating the actual excavation movement of the TBM equipment meet the preset values.

2. The TBM small-radius tunnel construction equipment correction method according to claim 1, characterized in that, A traverse point is set up at a spacing of 200m on the straight section of the tunnel construction, and at a spacing of 15m on the 30m curved section of the tunnel construction to realize the measurement of the actual excavation path.

3. The TBM small-radius tunnel construction equipment correction method according to claim 2, characterized in that, When the tunnel excavation radius decreases, a traverse point is set at a spacing of 15m.

Citation Information

Patent Citations

  • A shield tunneling machine (VMT) based on a BIM platform and a deviation rectification scheme three-dimensional display method

    CN109446716A

  • Three-dimensional continuous-discontinuous coupling numerical simulation method for shield type TBM (Tunnel Boring Machine) excavation jamming machine

    CN115292975A