A method for processing ground of a combined structure of an operating period tunnel micro pile and an embedded beam

By using a combination structure of micropiles and embedded beams, the problems of large construction workload and low safety in tunnel foundation treatment during operation were solved, achieving good foundation reinforcement effect and construction safety.

CN117090598BActive Publication Date: 2026-11-24GUANGXI SHUANGXIANG GEOTECHNICAL ENG CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202311294756.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-08
Publication Date
2026-11-24
Estimated Expiration
2043-10-08

AI Technical Summary

Technical Problem

Existing tunnel foundation treatment methods involve large construction workloads, high risk factors, and unsatisfactory treatment effects, especially in tunnels during operation where there are problems such as insufficient foundation bearing capacity and excessive deformation.

Method used

A micropile-beam composite structure is adopted. By drilling and grouting micropiles, excavating the beams, and using prestressed force-transfer anchors, the foundation is reinforced without damaging the invert arch. The beams and the invert arch share the load and transfer it together.

Benefits of technology

It achieved good foundation reinforcement, high construction safety, reduced construction risks and workload, lowered construction difficulty, and did not damage the original structure, thus meeting the requirements for tunnel operational stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117090598B_ABST
    Figure CN117090598B_ABST
Patent Text Reader

Abstract

This invention provides a foundation treatment method for a tunnel with a micropile and embedded support beam combination structure during operation, belonging to the field of tunnel foundation treatment technology. The method involves shallow void grouting of the tunnel foundation, tunnel pavement excavation, micropile drilling, micropile grouting, embedded support beam excavation, embedded support beam casting, prestressed force-transfer anchor installation, and finally pavement installation. This invention eliminates the need to dismantle the invert arch and avoids the use of large equipment, greatly reducing construction risks and difficulties, and ensuring the safety of construction personnel. The alternating arrangement of the embedded support ribs and mutually transmitting force plates integrates the post-cast embedded support beam with the original arch ring into a unified whole.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel foundation treatment technology, and in particular to a foundation treatment method for a combination structure of micropiles and embedded beams in tunnels during operation. Background Technology

[0002] During the operational phase, tunnels often experience problems such as insufficient foundation bearing capacity and excessive deformation due to increased usage time, traffic volume exceeding design limits, and construction defects. Current technologies commonly employ methods such as replacing the initial lining invert or replacing the invert with beams for tunnel repair. Replacing the invert requires large-scale road excavation, resulting in a large workload, high risk, and generally limited effectiveness. Replacing the invert with beams damages the original arch structure, leading to subsidence at the arch foot and compromising long-term operational stability. Therefore, a simple, effective, safe, and reliable mature technical solution is needed to address the foundation treatment issues of tunnels during the operational phase. Summary of the Invention

[0003] The purpose of this invention is to provide a foundation treatment method for a tunnel micropile plus embedded beam combination structure during the operation period, which solves the technical problems of large construction workload, high risk factor and poor treatment effect of existing tunnel foundation treatment methods.

[0004] This invention differs from traditional methods of replacing the invert arch with beams, devising a method for foundation reinforcement without damaging the invert arch. This technology utilizes methods such as embedded support ribs, lateral bracing, and anchor pipes to repair the tunnel foundation's bearing capacity and address defects caused by excessive deformation without damaging the invert arch. Simultaneously, it avoids the safety risks associated with excavating the invert arch, ensuring construction safety.

[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows:

[0006] A foundation treatment method for a tunnel micropile plus embedded support beam composite structure during operation includes: shallow void grouting of the tunnel foundation, tunnel pavement excavation, micropile drilling, micropile grouting, embedded support beam excavation, embedded support beam pouring, prestressed force transmission anchor installation, and finally pavement paving.

[0007] Furthermore, the specific process of micropile drilling is as follows:

[0008] Micropile drilling employs a dry drilling method. During drilling, for sections prone to collapse, a method of advancing steel pipes during drilling or pre-drilling small holes, grouting, and then drilling is used. The length L of the embedded rib section is set. t Section length D t The rib section and the section are drilled with n rows of holes, with a drilling interval of [missing information]. Drilling shall be carried out in four sequences: first, single-row, single-numbered holes; then, double-row, double-numbered holes; then, single-row, double-numbered holes; and finally, double-row, single-numbered holes. The drilling angle at the rib shall be 0° to 45° outward. The drilling process shall be recorded. The borehole shall be embedded at least 1m into intact bedrock. Drill cuttings shall be blown out during the drilling process.

[0009] Furthermore, the specific process of micropile drilling is as follows:

[0010] First, insert the grouting pipe to the bottom of the hole, then inject fine aggregate into the outer wall of the grouting pipe and the inner wall of the hole, and then perform grouting. The grouting adopts the bottom-return grouting process. The grouting pipe is inserted to the bottom of the hole, grouting is performed, and air is vented from the hole opening. When grout emerges from the hole opening, the hole is full. M30 cement mortar is injected using steel perforated pipe. The grouting is performed first for single-row, single-numbered holes as the first sequence, then for double-row, double-numbered holes as the second sequence, then for single-row, double-numbered holes as the third sequence, and finally for double-row, single-numbered holes as the fourth sequence, for a total of four sequences. Aggregate and bottom-return grouting processes are used. After construction is completed, the uniformity of the pile, the strength of the fine stone concrete in the pile body, the strength of the mortar in the pile body, and the bearing capacity of the single pile should be tested. The diameter of the micropile is d1, and the diameter of the steel pipe pile is d2. Their ratio is k, and the value of k is between 2 and 4. The grouting pipe is a steel perforated pipe, and its length is the distance from the bottom of the hole to the design height.

[0011] Furthermore, the specific process of excavating the embedded support beam is as follows:

[0012] The embedded beam and rib are embedded in the arch ring, connecting the beam and arch ring to share the load. Simultaneously, the secondary lining is cantilevered, transferring the load of the upper arch ring to the pile foundation to prevent later settlement of the arch foot. First, load-transfer anchors are driven into the arch foot section and connected with connecting plates to strengthen the connection between the general section and the arch ring. Then, the rib sections are constructed. Construction adopts a method of constructing odd-numbered ribs first, followed by even-numbered ribs. The length of the embedded rib section is set as L. t Section length D t L t 50-100cm, D t For L t 1-4 times, the rib is driven through the arch foot to the surrounding rock. After the rib is excavated, the pre-embedded pipe is driven into the prestressed force transmission anchor design position to prepare for the subsequent prestressed anchor. The pre-embedded pipe is driven through the invert arch to the foundation. One pre-embedded pipe is set in the gap between every two pile foundations.

[0013] Furthermore, the specific process of casting the embedded support beam is as follows:

[0014] Level the site, tie the reinforcing bars, erect the formwork, and pour the embedded support beams in sections. First, pour the rib section, then remove the formwork, and then pour the general section. The interval between pouring two adjacent sections should not be less than 7 days. After the concrete has solidified, weld the steel plate with the same size as the pile foundation cross section to the exposed end of the steel flower pile. The welding adopts full circumferential welding.

[0015] Furthermore, the specific process for installing prestressed force-transfer anchor rods is as follows: the force-transfer anchor rods are placed into the pre-embedded pipes, fixed in place, and then prestressed. After the prestressing is completed, concrete is poured in.

[0016] Furthermore, the specific construction process is as follows:

[0017] Step 1: Grouting for shallow voids in the base. Drill small holes from the micropile location to the shallow base and inject cement grout for reinforcement to ensure construction safety.

[0018] Step 2: Excavate the road surface, remove the damaged road surface, and retain the invert arch;

[0019] Step 3: Drilling of micropiles. Drilling is carried out using the steel pipe following method. The drilling sequence follows the four-stage skip drilling method. Finally, drilling is carried out from the inside out at the rib support. The drilling at the rib support is inclined outward at 0°, 15° and 30° respectively, with a hole diameter of 350mm. The drilling process is recorded during construction. The hole is embedded 3m into the intact bedrock. Drill cuttings should be blown out during the drilling process. The interval between two adjacent rows of holes is 150cm. The six rows of holes are symmetrically arranged, with the distance from the central axis being 230cm, 380cm and 580cm.

[0020] Step 4: Micropile grouting. Insert a grouting pipe with a diameter of 108mm and a wall diameter of 8mm into the bottom of the hole. Pour C50 fine stone aggregate into the outer wall of the grouting pipe and into the inner wall of the hole. Then pour M30 cement mortar until grout emerges from the hole opening. The grouting sequence follows the four-stage skip-hole grouting method. Finally, grout the micropile at the support rib from the inside out. After construction is completed, the uniformity of the pile, the strength of the fine stone concrete in the pile body, the strength of the mortar in the pile body, and the bearing capacity of the single pile should be tested. The diameter of the micropile d1 is 350mm, the diameter of the steel pipe pile d2 is 108mm, and the length of the steel pipe is the distance from the bottom of the hole to the design height.

[0021] Step 5: Excavation of the embedded support beam. First, drive force-transmitting anchor bolts into the arch foot of the general section and connect them with connecting plates. Then, construct the support rib section. The construction adopts the method of constructing the odd-numbered support ribs first and then the even-numbered support ribs. The length of the embedded support rib section is L. t For 100cm, the typical segment length is D t The diameter is 200cm. The rib is driven through the arch foot to the surrounding rock. After the rib is excavated, the pre-embedded pipe is driven through the invert arch to the foundation at the design position of the prestressed force transmission anchor. The diameter is 32mm. A row of pre-embedded pipes is driven between each two adjacent rows of micro piles. The six rows of pipes are arranged symmetrically with a distance of 80cm, 300cm and 420cm from the central axis.

[0022] Step 6: Excavate the embedded support beam, level the site, tie the reinforcing bars, erect the formwork, and pour the embedded support beam in sections. It is advisable to pour the rib section first, then remove the formwork, and then pour the general section. The time interval between pouring two adjacent sections should be 7 days. After the concrete has solidified, weld a 300×300×10mm steel plate to the exposed end of the steel flower pile. The welding adopts full circumferential welding.

[0023] Step 7: Installation of prestressed force transmission anchors. Place the force transmission anchors into the pre-embedded pipes, fix them in place, and then tension the prestress. After tensioning is completed, pour in concrete.

[0024] Compared to traditional large-scale replacement of tunnel linings, this invention does not require excavation of the invert arch. The embedded support beam structure transfers most of the vertical load of the tunnel, originally borne by the invert arch, to the embedded support beam through embedded support ribs, force-transfer anchors, and prestressed force-transfer anchors. This invention results in less disturbance and lower construction safety risks.

[0025] This technology utilizes a beam-supporting structure consisting of alternating beam-supporting ribs and general sections. The beam-supporting ribs are embedded into the bottom of the sidewalls to achieve cantilever support of the tunnel secondary lining, while the general sections are connected to the sidewalls via force-transfer anchor bolts to further support the cantilever of the secondary lining. Vertical prestressed force-transfer anchor bolts are installed between the beam-supporting structure and the invert arch to connect them, enhancing the overall structural integrity and ensuring coordinated stress distribution. The tunnel's load-bearing capacity meets design requirements in the same way as methods involving large-scale replacement of the invert arch and lining.

[0026] Compared to other methods of piling foundations or replacing invert arches, this technology has a simple construction process. The main processes are drilling micropiles and excavating embedded support beams. It does not require the use of large machinery and all steps can be completed with small machinery, making construction convenient, with a short construction period and low cost.

[0027] The present invention, by adopting the above-described technical solution, has the following beneficial effects:

[0028] (1) This invention does not require the removal of the inverted arch and does not use large equipment, which greatly reduces the danger and difficulty of construction and ensures the safety of construction personnel. The interleaved setting of the embedded ribs and the mutual force transmission plates combines the later-cast embedded beam with the original arch ring into a whole.

[0029] (2) A prestressed force-transmitting anchor rod is installed between the rib and the invert arch. This anchor rod acts like a suspender rod. When the invert arch deforms downward, the force-transmitting anchor rod is under tension, preventing the invert arch from being damaged due to deformation.

[0030] (3) Application of micropiles in maintenance. Driving micropiles does not require the use of large equipment, is convenient and simple, and has low construction risk. However, the bearing capacity of a single pile is not as large as that of traditional pile foundations. But by setting up a large number of micropiles and combining them with embedded beams and prestressed force-transfer anchors for reinforcement, the bearing capacity after reinforcement can meet the requirements. Attached Figure Description

[0031] Figure 1 This is a flowchart of the method of the present invention;

[0032] Figure 2 This is a plan view of the combined structure of micropiles and embedded beams of the present invention;

[0033] Figure 3 yes Figure 2 Section I-II;

[0034] Figure 4 yes Figure 2 Section II.

[0035] In the attached diagram, 1-prestressed force-transmitting anchor rod, 2-micro steel pipe pile, 3-embedded support rib, 4-arc-shaped force-transmitting rib plate, 5-force-transmitting anchor bolt, 6-force-transmitting plate, and 7-asphalt bolt surface layer. Detailed Implementation

[0036] To make the objectives, technical solutions, and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and preferred embodiments. However, it should be noted that many details listed in the specification are merely to provide the reader with a thorough understanding of one or more aspects of the present invention, and these aspects of the invention can be implemented even without these specific details.

[0037] like Figure 1-4 As shown, a foundation treatment method for a tunnel micropile plus embedded beam composite structure during operation includes the following steps:

[0038] 1. Road excavation. The damaged road surface will be removed, leaving the invert arch intact. The invert arch serves as a construction platform, facilitating construction while ensuring the safety of construction workers.

[0039] 2. Micropile drilling. Micropile drilling can be performed using dry drilling methods. The micropile arrangement can be as follows: Figure 1 Arrangement. During drilling, for sections prone to borehole collapse, a method of advancing the steel pipe during drilling can be used, or a method of pre-drilling small holes, grouting, and then drilling can be employed. Let the length of the embedded rib section be L. t General segment length D t Drill n rows of holes in the rib section and the general section, with a drilling interval of [missing information]. Drilling can be performed in four sequences: first, drilling single-row, odd-numbered holes; then, drilling double-row, even-numbered holes; then, drilling single-row, even-numbered holes; and finally, drilling double-row, odd-numbered holes. The holes at the ribs should be inclined outwards at a certain angle (preferably 0° to 45°), determined based on the soil's internal friction angle and other properties. The drilling process should be recorded, and the borehole should be embedded at least 1 meter into intact bedrock. Drill cuttings should be blown out during drilling.

[0040] This invention does not require the removal of the invert arch and does not use large equipment, which greatly reduces the danger and difficulty of construction and ensures the safety of construction personnel. The interlocking of the embedded ribs and the mutual force transmission plates 6 combines the post-cast embedded beam with the original arch ring into a whole.

[0041] 3. Micropile Grouting. First, insert the grouting pipe to the bottom of the hole. Then, inject fine aggregate (such as C50 fine stone) from the outer wall of the grouting pipe to the inner wall of the hole, followed by grouting. The grouting uses a bottom-return grouting process: the grouting pipe is inserted to the bottom of the hole, grout is injected, air is vented from the hole opening, and grout overflows from the hole opening, indicating it is full. M30 cement mortar is preferably injected using a steel pipe. Grouting can be performed in four sequences: single-row, single-numbered holes as the first sequence, then double-row, double-numbered holes as the second sequence, then single-row, double-numbered holes as the third sequence, and finally double-row, single-numbered holes as the fourth sequence. Due to the use of a large amount of aggregate and the bottom-return grouting process, the micropile has a high compressive strength. After construction, the uniformity of the pile, the strength of the fine stone concrete in the pile body, the strength of the mortar in the pile body, and the bearing capacity of the single pile should be tested and should meet the relevant specifications. See the diagram for the grouting hole layout. Figure 1 The diameter of the micropile is d1, and the diameter of the steel pipe pile is d2. Their ratio is k, and the value of k should preferably be between 2 and 4. The grouting pipe can be a steel perforated pipe, and its length is the distance from the bottom of the hole to the design height.

[0042]

[0043] 4. Excavation and placement of embedded parts for the embedded support beam. The embedded support beam ribs are embedded into the arch ring, connecting the beam and the arch ring to share the load. Simultaneously, the secondary lining is cantilevered, transferring the load of the upper arch ring to the pile foundation and preventing later settlement of the arch foot. First, load-transfer anchors are driven into the arch foot of the general section and connected with connecting plates to strengthen the connection between the general section and the arch ring. Then, the support rib sections are constructed, using a method of excavating the support ribs by first constructing the odd-numbered ribs and then the even-numbered ribs. This skip-slot construction method speeds up the construction process and reduces the impact on the original arch ring. Let the length of the embedded support rib section be L. t General segment length D t L can be selected t 50-100cm, D t For L t 1-4 times the length of the support ribs, which penetrate the arch foot to the surrounding rock. After the support ribs are excavated, pre-embedded pipes are driven into the prestressed force transmission anchor 1 at the designed location to prepare for subsequent prestressed anchors. The pre-embedded pipes penetrate the invert arch to the foundation; the diameter and number of pipes should meet the requirements. It is recommended to set one pre-embedded pipe in the gap between every two pile foundations. The embedded support ribs 3 are designed to protrude outwards and are spaced apart. An arc-shaped force transmission rib plate 4 is set between two embedded support ribs 3.

[0044] 5. Casting of Embedded Support Beams. Level the site, tie the reinforcing bars, erect formwork, and cast the embedded support beams in sections. It is advisable to cast the rib section first, then remove the formwork, and then cast the general section, with an interval of no less than 7 days between adjacent sections. After the concrete has solidified, weld a steel plate with dimensions close to the cross-section of the pile foundation to the exposed end of the steel pile. The welding should be a full circumferential weld.

[0045] 6. Tensioning the prestressed force transmission anchor rod 1. Place the force transmission anchor rod into the pre-embedded pipe, fix it, and then tension the prestress. After tensioning is completed, pour in concrete.

[0046] The reinforcement effect of this invention mainly relies on the synergistic effect of micropiles, embedded support beams, and prestressed force-transfer anchors 1. The support ribs of the embedded support beams achieve cantilevering of the tunnel secondary lining by embedding into the bottom of the sidewalls. In general sections, the cantilevering of the secondary lining is aided by connecting the sidewalls to the force-transfer anchors 5. The prestressed force-transfer anchors 1 prevent the invert arch from deflecting under pressure, allowing the embedded support beams and the original invert arch to share the load. The embedded support beams and the invert arch are precisely positioned on the micropiles, transferring the force to the bearing layer through the micropiles. After reinforcement, the tunnel is fully stressed, with layer-by-layer reinforcement. Compared to traditional primary lining invert arch replacement, this invention only removes the damaged road surface, allowing construction workers to work directly on the invert arch, reducing construction hazards. The use of micro steel pipe piles 2 for foundation reinforcement eliminates the need for large-scale impact drilling equipment, reducing construction hazards and difficulty.

[0047] The construction process is as follows:

[0048] Grouting for shallow voids in the base. Drill small holes from the micropile location to the shallow base, and inject cement grout for reinforcement, ensuring construction safety. This part is not a key technical point of this document.

[0049] Road excavation. The damaged road surface will be removed, and the invert arch will be preserved.

[0050] Micropile drilling. Drilling was conducted using a steel pipe follow-up method, following a four-stage skip-hole drilling sequence. Drilling was carried out last at the rib supports, with the rib supports inclined outwards at 0°, 15°, and 30° respectively. The hole diameter was 350mm. The drilling process was recorded, with each hole penetrating 1m into intact bedrock. Drill cuttings were blown out during drilling. Adjacent rows of holes were spaced 150cm apart, with six rows symmetrically arranged, and distances from the central axis of 230cm, 380cm, and 580cm.

[0051] Micropile grouting. A 108mm diameter grouting pipe with an 8mm borehole diameter is inserted to the bottom of the hole. C50 fine aggregate is poured into the outer wall of the grouting pipe and then into the inner wall of the hole. M30 cement mortar is then poured until grout emerges from the hole opening. The grouting sequence follows a four-stage skip-hole grouting method, with the micropile at the support rib finally grouting from the inside out. After construction, the uniformity of the piles, the strength of the fine aggregate concrete in the pile body, the strength of the pile mortar, and the single pile bearing capacity should be tested. The grouting hole layout is shown in the diagram. Figure 1The diameter of the micropile, d1, is 350 mm, and the diameter of the steel pipe pile, d2, is 108 mm. The length of the steel pipe is the distance from the bottom of the hole to the designed height.

[0052] Excavation of the embedded support beam. First, drive force-transmitting anchor bolts into the arch foot of the general section and connect them with connecting plates. Then construct the support rib section, using the method of constructing odd-numbered support ribs first and then even-numbered support ribs. The length L of the embedded support rib section. t For 100cm, the typical segment length is D t The ribs are 200cm long, and the support ribs are driven through the arch foot to the surrounding rock. After the support ribs are excavated, the prestressed force transmission anchor rod 1 is positioned at the design location. The pre-embedded pipes are driven through the invert arch to the foundation, with a diameter of 32mm. One row of pre-embedded pipes is driven between every two adjacent rows of micropiles, with 6 rows of pipes arranged symmetrically, with distances from the central axis of 80cm, 300cm, and 420cm.

[0053] Excavation of the embedded support beams. Level the site, tie the reinforcing bars, erect formwork, and pour the embedded support beams in sections. It is advisable to pour the rib section first, then remove the formwork, and then pour the general section, with a 7-day interval between pouring adjacent sections. After the concrete has solidified, weld 300×300×10mm steel plates to the exposed ends of the steel piles. Welding should be a full circumferential weld.

[0054] Installation of prestressed force-transfer anchor 1. Place the force-transfer anchor into the pre-embedded pipe, fix it, and then tension the prestress. After tensioning, pour in concrete. Road surface paving asphalt anchor layer 7.

[0055] Compared to traditional large-scale replacement of tunnel linings, this invention does not require excavation of the invert arch. The embedded support beam structure transfers most of the vertical load of the tunnel, originally borne by the invert arch, to the embedded support beam through embedded support ribs, force-transfer anchors, and prestressed force-transfer anchors. This invention results in less disturbance and lower construction safety risks.

[0056] This technology utilizes a beam-supporting structure consisting of alternating beam-supporting ribs and general sections. The beam-supporting ribs are embedded in the bottom of the sidewalls to achieve cantilever support of the tunnel secondary lining, while the general sections are connected to the sidewalls via force-transfer anchor bolts 5 to further support the cantilever of the secondary lining. Vertical prestressed force-transfer anchor bolts are installed between the beam-supporting structure and the invert arch to connect them, enhancing the overall structural integrity and ensuring coordinated stress distribution. The tunnel's load-bearing capacity meets design requirements in the same way as methods involving large-scale replacement of the invert arch and lining.

[0057] Compared to other methods of piling foundations or replacing invert arches, this technology has a simple construction process. The main processes are drilling micropiles and excavating embedded support beams. It does not require the use of large machinery and all steps can be completed with small machinery, making construction convenient, with a short construction period and low cost.

[0058] The above description is only a preferred embodiment of the present invention. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be considered within the scope of protection of the present invention.

Claims

1. A foundation treatment method for a combined structure of micropiles and embedded beams in a tunnel during operation, characterized in that: The process includes shallow grouting of the tunnel foundation, excavation of the tunnel pavement, drilling of micropiles, grouting of micropiles, excavation of the embedded support beam, pouring of the embedded support beam, installation of prestressed force transmission anchors, and finally paving of the pavement. The specific process of drilling micropiles is as follows: Micropile drilling employs a dry drilling method. During drilling, for sections prone to collapse, a method of advancing steel pipes during drilling or pre-drilling small holes and grouting before drilling is used. The length of the embedded rib section is set. Section Chief The rib section and the section are drilled with n rows of holes, with a drilling interval of s= Drilling shall be carried out in four sequences: first, single-row single-numbered holes as the first sequence; then, double-row double-numbered holes as the second sequence; then, single-row double-numbered holes as the third sequence; and finally, double-row single-numbered holes as the fourth sequence. The drilling angle at the rib shall be 0° to 45° outward tilt. The drilling process shall be recorded during construction. The borehole shall be embedded into intact bedrock for no less than 1m. Drill cuttings shall be blown out during the drilling process. The specific process of micropile grouting is as follows: First, insert the grouting pipe to the bottom of the hole. Then, inject fine aggregate into the outer wall of the grouting pipe and into the inner wall of the hole. Next, perform grouting using a bottom-return grouting process. Insert the grouting pipe to the bottom of the hole, inject grout, and vent air from the hole opening. Grout overflowing from the hole opening indicates it is full. Use a steel pipe to inject M30 cement mortar. Grouting is performed in four sequences: first, single-row, single-numbered holes are grouted in sequence one; then, double-row, double-numbered holes are grouted in sequence two; then, single-row, double-numbered holes are grouted in sequence three; and finally, double-row, single-numbered holes are grouted in sequence four times. Aggregate and bottom-return grouting techniques are used. After construction, the uniformity of the pile, the strength of the fine aggregate concrete in the pile body, the strength of the pile mortar, and the bearing capacity of a single pile should be tested. The diameter of the micropile is [missing information]. The diameter of the steel pipe pile is The ratio is k, where k is between 2 and 4. The grouting pipe is a steel perforated pipe, and its length is the distance from the bottom of the hole to the designed height.

2. The foundation treatment method for a tunnel micropile plus embedded beam composite structure during operation, as described in claim 1, is characterized in that: The specific process of excavating the embedded support beam is as follows: The embedded beam and rib are embedded in the arch ring, connecting the beam and arch ring to share the load. Simultaneously, the secondary lining is cantilevered, transferring the load of the upper arch ring to the pile foundation to prevent later settlement of the arch foot. First, force-transfer anchors are driven into the arch foot section and connected with connecting plates to strengthen the connection between the general section and the arch ring. Then, the rib sections are constructed. Construction adopts a method of constructing odd-numbered ribs first, followed by even-numbered ribs. The length of the embedded rib section is set. Section Chief , It is 50-100cm. For 1-4 times, the rib is driven through the arch foot to the surrounding rock. After the rib is excavated, the pre-embedded pipe is driven into the prestressed force transmission anchor design position to prepare for the subsequent prestressed anchor. The pre-embedded pipe is driven through the invert arch to the foundation. One pre-embedded pipe is set in the gap between every two pile foundations.

3. The foundation treatment method for a tunnel micropile plus embedded beam composite structure during operation, as described in claim 1, is characterized in that: The specific process of casting the embedded support beam is as follows: Level the site, tie the reinforcing bars, erect the formwork, and pour the embedded support beams in sections. First, pour the rib section, then remove the formwork, and then pour the general section. The interval between pouring two adjacent sections should not be less than 7 days. After the concrete has solidified, weld the steel plate with the same size as the pile foundation cross section to the exposed end of the steel pipe. The welding adopts full circumferential welding.

4. The foundation treatment method for a tunnel micropile plus embedded support beam composite structure during operation, as described in claim 1, is characterized in that: The specific process for installing prestressed force-transfer anchors is as follows: the force-transfer anchor is placed into the pre-embedded pipe, fixed, and then prestressed. After the tensioning is completed, concrete is poured in.

5. The foundation treatment method for a tunnel micropile plus embedded beam composite structure during operation, as described in claim 1, is characterized in that: The specific construction process is as follows: Step 1: Grouting for shallow voids in the base. Drill small holes from the micropile location to the shallow base and inject cement grout for reinforcement to ensure construction safety. Step 2: Excavate the road surface, remove the damaged road surface, and retain the invert arch; Step 3: Drilling of micropiles. Drilling is carried out using the steel pipe following method. The drilling sequence follows the four-stage skip drilling method. Finally, drilling is carried out from the inside out at the rib support. The drilling at the rib support is inclined outward at 0°, 15° and 30° respectively, with a hole diameter of 350mm. The drilling process is recorded during construction. The hole is embedded 3m into the intact bedrock. Drill cuttings should be blown out during the drilling process. The interval between two adjacent rows of holes is 150cm. The six rows of holes are symmetrically arranged, with the distance from the central axis being 230cm, 380cm and 580cm. Step 4: Micropile grouting. Insert a 108mm diameter grouting pipe with an 8mm borehole diameter to the bottom of the hole. Pour C50 fine aggregate into the outer wall of the grouting pipe and then into the inner wall of the hole. Next, pour M30 cement mortar until grout oozes from the hole opening. The grouting sequence follows the four-stage skip-hole grouting method. Finally, grout the micropile at the support rib from the inside out. After construction, the uniformity of the pile, the strength of the fine aggregate concrete in the pile body, the strength of the pile mortar, and the single pile bearing capacity should be tested. The diameter of the micropile... The diameter of the steel pipe pile is 350mm. The diameter is 108mm, and the length of the steel perforated pipe is the distance from the bottom of the hole to the designed height; Step 5: Excavation of the embedded support beam. First, drive force-transmitting anchor bolts into the arch foot of the general section and connect them with connecting plates. Then, construct the support rib section. The construction adopts the method of constructing the odd-numbered support ribs first and then the even-numbered support ribs. The length of the embedded support rib section is... 100cm, typical segment length The diameter is 200cm. The rib is driven through the arch foot to the surrounding rock. After the rib is excavated, the pre-embedded pipe is driven through the invert arch to the foundation at the design position of the prestressed force transmission anchor. The diameter is 32mm. A row of pre-embedded pipes is driven between each two adjacent rows of micro piles. The six rows of pipes are arranged symmetrically with a distance of 80cm, 300cm and 420cm from the central axis. Step 6: Casting the embedded support beams. Level the site, tie the reinforcing bars, erect formwork, and cast the embedded support beams in sections. It is advisable to cast the rib section first, then remove the formwork, and then cast the general section. The time interval between casting two adjacent sections should be 7 days. After the concrete has solidified, [the following steps are taken]. A 10mm steel plate is welded to the exposed end of the steel pipe, and the welding is a full circumferential weld. Step 7: Install the prestressed force transmission anchor. Place the force transmission anchor into the pre-embedded pipe, fix it, and then tension the prestress. After tensioning, pour in concrete.