Accelerator control system for spray application and method of controlling the same
By designing a accelerator control system for spraying operations, and utilizing interlocking control and pressure gauge monitoring, the problems of accelerator blockage and insufficient pressure in wet spraying were solved, achieving continuous, reliable, and efficient operation of the spraying process. This system is suitable for spraying unshaped refractory materials.
Patent Information
- Application Number
- CN202311174357.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-13
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-09-13
AI Technical Summary
During wet spraying, the coagulant is prone to crystallization, which can lead to a smaller pipe diameter and blockage. Furthermore, when the air pressure is high, the coagulant pressure is insufficient, affecting the continuity and quality of the spraying.
A control system for accelerators used in spraying applications was designed, comprising a mixer, a pump, a spray gun, an air compressor, and an accelerator tank. The system monitors the pressure and flow rate of the accelerator through an interlocking control device and a pressure gauge to ensure stable operation of the spraying system. A booster pump and a check valve are used to prevent blockage, and an audible and visual alarm is used for real-time adjustments.
It effectively solves the problems of clogging and pressure drop in the accelerator system during wet spraying, improves the continuous reliability of spraying operations and the material's workability, and is suitable for special operating conditions such as blast furnace bases, ensuring spraying quality and efficiency.
Smart Images

Figure CN117225612B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of wet spraying construction technology for unshaped refractory materials, specifically relating to a settling accelerator control system and its control method for spraying construction. Background Technology
[0002] Unshaped refractory spray coatings are a common construction material in the refractory materials field. Because this material must achieve certain mechanical strength and density, it is generally applied by spraying. In wet spraying, a small amount of setting accelerator needs to be added to the coating to ensure that it can solidify and gain strength in a short time. However, because setting accelerators are prone to crystallization and used in small quantities, they can easily cause the pipe diameter to decrease, leading to blockages. Furthermore, due to the high air pressure inside the spray coating, if the setting accelerator pressure falls below the air pressure, the accelerator application will stop, affecting the smooth progress of the spraying process.
[0003] In view of this, and based on years of practical construction experience, we designed and improved the accelerator control system for spraying applications in order to solve the aforementioned technical problems. Summary of the Invention
[0004] One object of the present invention is to provide a accelerator control system for spraying construction, and another object of the present invention is to provide a control method thereof, which can solve the problem of accelerator interruption caused by accelerator system blockage and pressure drop in wet spraying, effectively improve the continuous reliability of spraying operations, and further improve the material workability.
[0005] The technical solution adopted is: A accelerator control system for spray coating includes a mixer, a pump, a spray gun, an air compressor, and an accelerator tank. Its features include: The mixer's outlet pipe is connected to the pump inlet.
[0006] The outlet pipe of the injection pump is connected to the inlet of the spray gun.
[0007] The outlet pipe of the coagulant tank is connected to the inlet of the booster pump.
[0008] The outlet of the pressure pump is divided into two paths, which are connected to the inlet of the main needle valve and the inlet of the bypass needle valve, respectively.
[0009] The outlet of the main needle valve and the outlet of the bypass needle valve are connected to the inlet of the check valve via a common pipeline.
[0010] The inlet pipe of the check valve is equipped with a first pressure gauge.
[0011] The outlet pipe of the one-way valve is connected to the inlet of the spray gun.
[0012] The air compressor's outlet pipe is connected to the spray gun's inlet.
[0013] The first pressure gauge is electrically connected to the interlocking control device, which is electrically connected to the injection pump and the pressurizing pump.
[0014] When the first pressure gauge detects that the pipeline pressure of the coagulant has reached the set lower limit, the pressurization pump is started through the interlock control device.
[0015] When the first pressure gauge detects that the pipeline pressure of the coagulant has reached the set upper limit, the pump injection machine is stopped through the interlock control device.
[0016] A second pressure gauge is installed on the outlet pipeline of the booster pump.
[0017] The second pressure gauge is electrically connected to the audible and visual alarm.
[0018] The inlet pipe of the check valve is also equipped with a flow meter.
[0019] A control method for a accelerator control system in spray coating application, characterized by comprising the following steps: Prepare the paint and deliver it to the spray gun using a pump.
[0020] The spray gun is connected to a high-pressure air hose and a accelerator hose. The high-pressure air carries the paint and accelerator from the spray gun and sprays them onto the area that needs repair.
[0021] When the pressure in the accelerator pipeline drops to the set value, start the booster pump.
[0022] When the pressure in the accelerator pipeline rises to the set value, the pump injection machine is interlocked and stopped.
[0023] Its advantages are: This invention effectively solves the problem of accelerator interruption caused by blockage, pressure drop, or insufficient flow in the accelerator system during wet spraying. This system can perform spraying operations under special conditions, such as when the spraying equipment is on the blast furnace base but the work site is located on the upper part of the furnace body (large height difference, large pipeline pressure loss). In this case, simply adding the above system to the existing spraying system can effectively avoid high rebound rates and spraying quality problems caused by accelerator malfunctions. It is easy to install, highly reliable, and suitable for widespread adoption in the industry. It can effectively improve the continuous reliability of spraying operations and further enhance the workability of materials.
[0024] Through the use of audible and visual alarms, monitoring by pressure gauges and flow meters, real-time manual adjustments, and interlocking control of the booster pump, this system can always ensure that the accelerator outlet pressure is more than 20% higher than the compressed air pressure at the spray nozzle, thus ensuring the reliable and stable operation of the entire spraying system. Attached Figure Description
[0025] Figure 1 This is a schematic diagram of the structure of the present invention.
[0026] Figure 2 This is a schematic diagram of the logic control of the present invention.
[0027] Figure 3 This is a schematic diagram of the voice-activated alarm of the present invention.
[0028] Figure 4 This is a schematic diagram of the pressurization pump and interlock control of the present invention.
[0029] Figure 5 This is a schematic diagram of the pressurization pump, injection machine, and interlock control system.
[0030] Figure 6 This is a schematic diagram of a check valve.
[0031] 1. Coating, water or binder, 2. Mixer, 3. Pump, 4. Air compressor, 5. Accelerator tank, 6. Second pressure gauge, 7. Main needle valve, 8. Check valve, 9. Spray gun, 10. Pressurizing pump, 11. Valve port, 12. Interlocking control device, 13. Audible and visual alarm, 14. First pressure gauge, 15. Flow meter, 16. Bypass needle valve, 17. Valve body, 18. Ball stop, 19. Spring, 20.
[0032] First lower limit switch 21, first upper limit switch 22, second lower limit switch 23, second upper limit switch 24. Detailed Implementation
[0033] The accelerator control system for spray coating includes a mixer 3, a pump 4, a spray gun 10, an air compressor 5, and an accelerator tank 6.
[0034] The outlet pipe of mixer 3 is connected to the inlet of pump 4.
[0035] The outlet pipe of the pump 4 is connected to the inlet of the spray gun 10.
[0036] The outlet pipe of the coagulant tank 6 is connected to the inlet of the pressure pump 11.
[0037] The outlet of the pressure pump 11 is divided into two paths, which are connected to the inlet of the main needle valve 8 and the inlet of the bypass needle valve 17, respectively.
[0038] The outlet of the main needle valve 8 and the outlet of the bypass needle valve 17 are connected to the inlet of the check valve 9 via a common pipeline.
[0039] The inlet pipe of the one-way valve 9 is equipped with a flow meter 16 and a first pressure gauge 15.
[0040] The outlet pipe of the one-way valve 9 is connected to the inlet of the spray gun 10.
[0041] The outlet pipe of the air compressor 5 is connected to the inlet of the spray gun 10.
[0042] A second pressure gauge 7 is installed on the outlet pipe of the booster pump 11.
[0043] The second pressure gauge 7 is electrically connected to the audible and visual alarm 14.
[0044] The first output terminal of the first pressure gauge 15 is electrically connected to the first input terminal of the interlocking control device 13, and the first output terminal of the interlocking control device 13 is electrically connected to the input terminal of the injection pump 4.
[0045] The second output terminal of the first pressure gauge 15 is electrically connected to the second input terminal of the interlocking control device 13, and the second output terminal of the interlocking control device 13 is electrically connected to the input terminal of the pressurizing pump 11.
[0046] Both the second pressure gauge 7 and the first pressure gauge 15 are electric contact pressure gauges.
[0047] The one-way valve 9 includes a valve body 18, a retaining ball 19 and a spring 20 inside the valve hole 12, with the two ends of the spring 20 abutting against the retaining ball 19 and one side of the valve hole, respectively.
[0048] Flow meter 16 is located near main needle valve 8 and bypass needle valve 17, and first pressure gauge 15 is located near check valve 9.
[0049] The second pressure gauge 7 is located between the pressure pump 11 and the two needle valves (main needle valve 8 and bypass needle valve 17).
[0050] This system adds a pressure pump 11, a bypass needle valve 17, a check valve 9, an interlock control device 13, and two pressure gauges compared to the previous spraying device.
[0051] Figure 3 This is a schematic diagram of the upper and lower limit alarm control circuit of the second pressure gauge 7. When the pressure at the first output terminal of the second pressure gauge 7 reaches the lower limit, the first lower limit switch 21 (KL1) is closed, and the audible and visual alarm 14 sounds. When the pressure at the second output terminal of the second pressure gauge 7 reaches the upper limit, the first upper limit switch 22 (KH1) is closed, and the audible and visual alarm 14 sounds. The alarm is automatically cleared after the pressure returns to normal.
[0052] Figure 4 The diagram shows the low-limit alarm connection of the first pressure gauge 15 to the pressurization pump 11. The second lower limit switch 23 (KL2) is the lower limit switch of the first pressure gauge 15 and is connected in the power supply circuit of the pressurization pump 11. When the first pressure gauge 15 detects that the pressure has reached the lower limit, the pressurization pump 11 is started.
[0053] Figure 5 A first pressure gauge 15 is added to the control circuit of the Zhongyuan pump injection machine and connected to a second upper limit switch 24 (KH2). When the pressure in the coagulant pipeline reaches the upper limit setting value, the pump injection machine 4 is interlocked and stopped.
[0054] The two pressure gauges are electrically interlocked. When the pressure at the inlet of the two needle valves or the front end of the one-way valve 9 rises to the set range, the pump injector 4 automatically cuts off power. After the pressurizing pump 11 starts or the bypass needle valve 17 is switched and adjusted, the pressurizing pump 11 starts working normally, the pressure gauge pressure returns to the normal range, and the pump injector 4 automatically starts working again.
[0055] A one-way valve 9 is installed on the accelerator pipeline to prevent compressed air or spray paint from backflowing into the accelerator pipeline and to protect the two needle valves from operating normally. Once the one-way valve 9 activates, the system pressure increases, sending a signal to stop the pump injector 4. This is because without accelerator, the sprayed material cannot solidify quickly and will fall off, necessitating the shutdown of the pump injector 4.
[0056] Add pressure gauges to the coagulant pipeline (the upper and lower limits can be set as needed), one of which is used for alarm (second pressure gauge 7), and the other is used for interlock (first pressure gauge 15).
[0057] A flow meter 16 was added to the main pipeline of the coagulant to calibrate the normal flow value during actual operation, which facilitates manual adjustment of the needle valve by the spraying personnel.
[0058] The flow rate of the coagulant is regulated by a needle valve, which is particularly prone to clogging. To prevent clogging, a parallel circuit is used. If the pressure difference across the needle valve is too large, the needle valve is adjusted immediately to ensure a normal supply of coagulant.
[0059] A booster pump 11 is added to the coagulant pipeline. Once the pressure difference between the coagulant pressure and the air pressure is detected to be less than a certain value, the booster pump 11 is immediately started.
[0060] For example, when the pressure is set to be higher than 1.2 MPa or lower than 0.8 MPa, the second pressure gauge 7 outputs a switch signal to close, and the audible and visual alarm 14 sounds an alarm.
[0061] When the pressure is greater than 1.5 MPa, the upper limit output switch signal of the first pressure gauge 15 is closed, and the pump injection machine 4 is interlocked to stop the pump; when the pressure is less than 0.8 MPa, the lower limit output switch signal of the first pressure gauge 15 is closed, and the booster pump 11 is interlocked to start.
[0062] Based on the normal dosage of pump injection machine 4 and coagulant, the pipeline pressure is set to 1.0 MPa, the flow rate to 1.8 kg / min, and the air pressure to 0.8 MPa when the coagulant is working normally.
[0063] After the pump is stopped by the four-lock interlock, it must be manually restarted after the blockage is cleared and the pressure is restored.
[0064] The booster pump can be started by either interlocking or manually, but must be stopped manually.
[0065] Based on the flow rate measured on-site, the spraying personnel should make the following adjustments to the normal manual mixing procedure: The same procedure should be followed when the audible and visual alarm device is activated (logic control diagram attached): (1) When the flow rate decreases and the pressure remains unchanged, the system adjustment sequence is as follows: open the main needle valve 8, then open the bypass needle valve 17, and then open the booster pump 11 to maintain a stable flow rate.
[0066] (2) When the flow rate decreases and the pressure decreases, the system adjustment sequence is as follows: turn on the booster pump 11, then turn on the main needle valve 8, and then turn on the bypass needle valve 17 to maintain a stable flow rate.
[0067] (3) When the flow rate decreases and the pressure increases, the system adjustment sequence is as follows: turn off the booster pump 11, then reduce the bypass needle valve 17, and then reduce the main needle valve 8 to maintain a stable flow rate.
[0068] (4) When the flow rate increases while the pressure remains constant, the system adjustment sequence is as follows: reduce the bypass needle valve 17, and then reduce the main needle valve 8 to maintain a stable flow rate.
[0069] (5) When the flow rate increases and the pressure decreases, the system adjustment sequence is: pipeline leakage warning, stop operation and repair the leak.
[0070] (6) When the flow rate and pressure increase, the system adjustment sequence is as follows: open the return valve of the booster pump 11, then close the booster pump 11, then reduce the bypass needle valve 17, and then reduce the main needle valve 8 to maintain a stable flow rate.
[0071] A control method for a accelerator control system in spray coating application, characterized by comprising the following steps: 1. Prepare the spray coating material, and add the spray coating material 1 (refractory cement) to the mixer 3, along with an appropriate amount of water or additives (silicone or resin, etc.); mix until it reaches a suitable state, and then pump the mixed coating material to the spray gun 10 through the pumping machine 4.
[0072] 2. The spray gun 10 is connected to a high-pressure air pipe and a coagulant pipe. The high-pressure air carries the paint and coagulant (sodium aluminate) from the spray gun 10 and sprays them onto the area that needs to be repaired. In a short time, a semi-solidified whole is formed and firmly adheres to the repair surface.
[0073] 3. As the spraying position increases, the pressure difference within the accelerator pipeline will rise, and the outlet pressure will be lower than that of the compressed air. Compressed air or spray paint may backflow into the accelerator pipeline, causing the needle valve to malfunction. At this time, the first pressure gauge 15 at the inlet of the one-way valve 9 in the system sends a lower limit pressure signal, which controls the pump injector 4 to stop via the interlock control device 13. Then, the pressurization pump 11 on the accelerator pipeline immediately starts, which can quickly increase the pressure at the outlet section of the accelerator pipeline to meet normal spraying requirements. Upon receiving the start signal from the pressurization pump 11 in the accelerator pipeline and confirming that the accelerator can be sprayed normally, the pump injector 4 immediately starts and resumes normal pumping operation.
[0074] When the pressure detected by the first pressure gauge 15 reaches the upper limit pressure signal, the pump 4 is stopped.
[0075] Those skilled in the art may also use other circuits with similar functions as interlocking control devices 13.
Claims
1. A settling agent control system for spray coating, comprising a mixer (3), a pump (4), a spray gun (10), an air compressor (5), and a settling agent tank (6); characterized in that: The outlet pipe of the mixer (3) is connected to the inlet of the injection pump (4); The outlet pipe of the pump injection machine (4) is connected to the inlet of the spray gun (10); The outlet pipe of the coagulant tank (6) is connected to the inlet of the pressure pump (11); The outlet of the pressure pump (11) is divided into two paths, which are connected to the inlet of the main needle valve (8) and the inlet of the bypass needle valve (17), respectively. The outlet of the main needle valve (8) and the outlet of the bypass needle valve (17) are connected to the inlet of the check valve (9) via a common pipeline; The inlet pipe of the check valve (9) is equipped with a first pressure gauge (15); The outlet pipe of the check valve (9) is connected to the inlet of the spray gun (10); The outlet pipe of the air compressor (5) is connected to the inlet of the spray gun (10); The first pressure gauge (15) is electrically connected to the interlock control device (13), and the interlock control device (13) is electrically connected to the pump (4) and the pressurizing pump (11). The lower limit switch of the first pressure gauge (15) is connected to the power supply circuit of the booster pump (11), and the upper limit switch of the first pressure gauge (15) is connected to the control circuit of the pump injection machine (4). When the first pressure gauge (15) detects that the pipeline pressure of the coagulant has reached the set lower limit, the pressurization pump (11) is started through the interlock control device (13). When the first pressure gauge (15) detects that the pipeline pressure of the coagulant has reached the set upper limit, the pump injection machine (4) is stopped through the interlock control device (13). A second pressure gauge (7) is installed on the outlet pipe of the booster pump (11); The second pressure gauge (7) is electrically connected to the audible and visual alarm (14); Both the first pressure gauge (15) and the second pressure gauge (7) are electric contact pressure gauges; The inlet pipe of the check valve (9) is also equipped with a flow meter (16).
2. The control method for the accelerator control system in spray coating construction according to claim 1, characterized in that, Includes the following steps: Prepare the paint and send it to the spray gun (10) through the pump (4); The spray gun (10) is connected to a high-pressure air pipe and a coagulant pipe. The high-pressure air carries the paint and coagulant from the spray gun (10) and sprays them onto the part that needs to be repaired. When the pressure in the accelerator pipeline drops to the set value, start the booster pump (11). When the pressure in the pipeline of the coagulant rises to the set value, stop the pump injection machine (4). After the pumping machine (4) is stopped, once the pressurizing pump (11) is started and it is confirmed that the coagulant can be sprayed out normally, the pumping machine (4) will then be started to resume normal pumping operation.
Citation Information
Patent Citations
Hardener feeder
JP1998288470A