Integrated mining method for thin ore body cutting and leaving
By constructing artificial false bottoms and chutes along the route in the mining of extremely thin ore bodies, concrete waste rock cemented pillars are formed, solving the problems of high labor intensity and low efficiency, and realizing safe and efficient mining operations.
Patent Information
- Application Number
- CN202311397795.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-26
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2043-10-26
AI Technical Summary
Existing methods for mining extremely thin ore bodies suffer from problems such as high labor intensity, low mining efficiency, poor stability of the hanging wall and footwall supports, and insufficient safety.
The integrated mining method of cutting and retaining ultra-thin ore bodies is adopted. By constructing artificial false bottoms and chutes along the road, layered mining is carried out. Concrete waste rock cemented pillars are formed in the waste rock filling area to support the upper and lower walls, reduce the amount of waste rock cut-off, and improve the stability and safety of the support.
It improves the support stability of the upper and lower plates, ensures the safety of mining operations, reduces labor intensity and production costs, and improves the overall mining efficiency of the mining area.
Smart Images

Figure CN117248909B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of mine backfilling and mining technology, and in particular to an integrated mining method for cutting and retaining extremely thin ore bodies. Background Technology
[0002] When mining extremely thin ore bodies, the commonly used mining method is the cut-and-fill method. When the stability of the ore body is relatively poor, the cut-and-fill method requires a lot of support. However, due to the limited working space, the entire mining process needs to be carried out manually, which is labor-intensive and has a poor working environment. Moreover, the cut-and-fill method uses waste rock to fill the voids, which has limited support for the hanging wall and footwall. As mining progresses, the mining risk increases further and the mining efficiency decreases further.
[0003] Patent application CN201911238237.2 discloses an intermittent cemented support wall-cutting and backfilling mining method. This method arranges the stope along the strike of the ore body, without top or bottom supports between intermediate sections or between adjacent stops. The ore body within the intermediate section is divided into layers and mined layer by layer from bottom to top. An artificial false bottom is constructed of reinforced concrete at the bottom of the stope. The upper layers are mined using a slotting method, with mining proceeding backward from the center to both sides. Collapsed ore is manually raken to the loading end of a belt conveyor and waste rock is sorted. The ore is then directly transported to the ore pass via a belt conveyor. The layers above the artificial false bottom are backfilled using an intermittent cemented method, i.e., one layer is filled with waste rock, then another with cemented backfill, and so on, alternating between the two. This method, involving partial wall cutting and partial backfilling, improves the support of the backfill for the hanging wall and footwall. However, it still requires a large amount of manual labor, resulting in high labor intensity and limited improvement in overall mining efficiency.
[0004] Patent application CN201910128261.4 discloses a mining method for thin and extremely thin ore bodies. It employs medium-deep hole drilling, pre-splitting blasting, and the installation of a false roof to isolate the upper waste rock from the goaf. Except for 5m pillars retained on both sides of the ore pass as safety pillars, no other pillars are left in the stope, and all are mined out. By introducing a pre-constructed artificial false roof and employing a small-segment caving method, the mining capacity is improved and labor intensity reduced. However, during caving mining, the safety of the artificial false roof cannot be guaranteed, leading to surrounding rock collapse and surface subsidence.
[0005] In view of this, there is an urgent need to provide a method for mining extremely thin ore bodies that can improve the support stability of the hanging wall and footwall, ensure the safety of mining operations, and improve the overall mining efficiency of the stope. Summary of the Invention
[0006] To overcome the shortcomings of existing mining backfilling and mining technologies, this invention provides an integrated mining method for ultra-thin ore body cutting and retention. This method can improve the support stability of the hanging wall and footwall, ensure the safety of mining operations, and enable continuous ore discharge from multi-layered ore bodies, reducing manual ore discharge time in the stope and improving the overall mining efficiency of the stope.
[0007] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is: to provide an integrated mining method for ultra-thin ore bodies, which includes the following steps: The ore body is extracted upward along the transport roadway, an artificial false bottom is constructed, and multiple ore passes perpendicular to the ore body strike are excavated along the ore body strike direction. The width of the ore passes along the ore body strike direction is 4-6m. The bottom of the ore pass is sealed, and the ore body is mined in layers using the upward layered mining method. Each layer is mined along the direction of the ore body, and the mined ore is collected in the ore pass. The area between adjacent road chutes is a waste rock filling area. The mined waste rock is raken to the waste rock filling area and flooded with cement slurry to form concrete waste rock cemented columns. After the ore body is mined out, the bottom of the ore pass will be opened to release the ore stored therein and transport it out of the mining area. The bottom of the chute was sealed, and tailings were used to fill the chute.
[0008] Preferably, the area between adjacent ore passes is a waste rock filling area, and the length of a single drilling and blasting operation for layered mining is the sum of the lengths of a single ore pass and a single waste rock filling area along the ore body strike.
[0009] Preferably, the upper ore body corresponding to the waste rock filling area is mined by slotting, and the upper ore body corresponding to the roadway pass is mined by wall cutting.
[0010] Preferably, after rock drilling and blasting, all ore bodies within the single rock drilling and blasting length are first mined by slotting, and then only the upper ore body corresponding to the ore pass is mined by wall cutting.
[0011] Preferably, when the vein width is less than 0.6m, the portion that is only used for slotting mining needs to be mined by wall cutting.
[0012] Preferably, after each rock drilling and blasting operation, the mined ore is collected in the ore pass and a portion of the ore is released from the bottom of the ore pass.
[0013] Preferably, after each rock drilling and blasting operation, the mined ore is collected in the ore pass and one-third of the mined ore is released from the bottom of the ore pass.
[0014] Preferably, the retaining plate of the chute in the current mining layer is installed along the chute in the previous layer, and then the mined waste rock is raken to the area between the adjacent chutes and flooded with cement grout to form a concrete waste rock cemented column.
[0015] Preferably, the width of the chute is the minimum extraction width.
[0016] Preferably, the bottom of the ore pass is a bucket-shaped outlet.
[0017] The beneficial effects of this invention are: This invention uses cement grout to flood the waste rock filling area, forming concrete waste rock cemented columns. These concrete waste rock cemented columns support the upper and lower plates, thereby improving the stability of the support and ensuring the safety of mining operations. In addition, by pouring concrete waste rock cemented columns to increase the support strength of the upper and lower plates, it is also possible to ensure that the upper and lower plates are not damaged during ore discharge, thus increasing the overall ore recovery rate.
[0018] This invention increases the length of the ore pass along the strike of the ore body, ensuring sufficient ore storage space within the ore pass. Since the area between adjacent ore passes is a waste rock filling area, while increasing the length of the ore pass along the strike of the ore body, the length of the waste rock filling area between adjacent ore passes is correspondingly reduced. This provides a suitable width for the concrete waste rock cemented column, avoiding the problem of excessively wide concrete waste rock cemented columns leading to excessively high casting costs.
[0019] This invention involves slotting and mining the upper ore body corresponding to the waste rock filling area, and cutting and mining the upper ore body corresponding to the ore pass. This ensures sufficient ore-holding space within the ore pass while reducing the amount of detonators and explosives used, thus saving mining costs. Furthermore, by only cutting and mining the upper ore body corresponding to the ore pass, the amount of waste rock produced is reduced, thereby lowering the dilution loss rate and saving some mining costs, resulting in a reduction in overall production costs.
[0020] After each rock drilling and blasting operation, the mined ore is collected into a pass ore chute, and a portion of the ore is released from the bottom of the pass ore chute. Preferably, after each rock drilling and blasting operation, the mined ore is collected into the pass ore chute, and one-third of the mined ore is released from the bottom of the pass ore chute, while the remaining ore remains in the pass ore chute. This ensures sufficient mining space for subsequent ore body mining and avoids affecting the next mining step.
[0021] After each rock drilling and blasting operation, the mined ore is collected in a pass shaft. After the ore body mining is completed, the bottom of the pass shaft is opened to release all the ore stored therein and transport it out of the mining area. This enables continuous ore release from multi-layered ore bodies, reduces the time required for manual ore release in the mining area, and improves the overall mining efficiency of the mining area. Attached Figure Description
[0022] Figure 1 This is a schematic diagram of the initial structure of the ore body in the integrated mining method for ultra-thin ore body cutting and retention described in an embodiment of the present invention.
[0023] Figure 2 This is a schematic diagram of the structure of the ore body waste rock filling area to form a concrete waste rock cemented column in the integrated mining method for cutting and retaining ultra-thin ore bodies described in the embodiments of the present invention.
[0024] Figure 3 for Figure 2 Cross-sectional view along the middle AA.
[0025] Figure 4 for Figure 2 Cross-sectional view of the middle BB.
[0026] Figure 5 This is a schematic diagram of the structure for backfilling tailings in the integrated mining method for cutting and retaining extremely thin ore bodies as described in this embodiment of the invention.
[0027] The components in the attached diagram are labeled as follows: 1. Artificial false bottom; 2. Passage along the road; 3. Supporting crossbar; 4. Waste rock cemented body; 6. Ore body; 7. Footwall surrounding rock; 9. Collapsed ore; 10. Tailings backfill; 11. Ore body transport roadway along the vein. Detailed Implementation
[0028] The preferred embodiments of the present invention will now be described in detail with reference to the accompanying drawings, so that the advantages and features of the present invention can be more easily understood by those skilled in the art, thereby providing a clearer and more explicit definition of the scope of protection of the present invention.
[0029] This invention provides an integrated mining method for ultra-thin ore bodies, comprising the following steps: S1. The ore body is extracted upward along the transport roadway 11, an artificial false bottom 1 is constructed, and multiple chutes 2 perpendicular to the ore body strike are excavated along the ore body strike direction. The width of the chutes 2 along the ore body strike direction is 4-6m. S2. Seal the bottom of the ore pass 2 and use the upward layered mining method to mine the ore body 6 in layers. Each layer is mined along the direction of the ore body, and the mined ore is collected into the ore pass 2. S3. The area between adjacent roadway chute 2 is a waste rock filling area. The mined waste rock is rake to the waste rock filling area and cement slurry is used to flood it to form a concrete waste rock cemented column. After the mining of S4 and ore body 6 is completed, the bottom of the chute 2 will be opened to release the ore stored therein and transport it out of the mining area. S5. Seal the bottom of the chute 2 and fill it with tailings.
[0030] Specifically, along the vertical direction of the ore vein, intermediate transport roadways are excavated every 30 to 60 meters inside the ore body 6, dividing the extremely thin ore vein into several intermediate sections; within each intermediate section, transport roadways are excavated along the strike of the ore body, and the preferred cross-sectional dimensions of the transport roadways are 2.5m × 2.5m.
[0031] like Figure 1 and Figure 2 As shown, the top of the ore body along the transport roadway 11 is excavated upwards by 1.2-1.5m to construct an artificial false bottom 1; then, multiple ore passes 2 perpendicular to the ore body strike are excavated upwards. The width of the ore pass 2 is the minimum mining width, and the width of the ore pass 2 along the ore body strike direction is approximately half the length of a single drilling and blasting extraction in layered mining; preferably, the width of the ore pass 2 along the ore body strike direction is 4-6m. To enable the ore to quickly flow out of the ore pass 2, such as... Figure 1 and Figure 2 As shown, the bottom of Shunlu chute 2 is a bucket-shaped ore outlet.
[0032] Since most of the ore mined later needs to be stored in the ore pass 2, the length of the ore pass 2 along the strike direction is set to be greater than that of a conventional ore pass 2. This increases the length of the ore pass 2 along the strike direction, ensuring sufficient ore storage space within it. The area between adjacent ore passes 2 is a waste rock filling area. Therefore, while increasing the length of the ore pass 2 along the strike direction, the length of the waste rock filling area between adjacent ore passes 2 is correspondingly reduced. This allows for a suitable width to be reserved for the concrete waste rock cemented column, avoiding the problem of excessively wide concrete waste rock cemented columns leading to excessively high casting costs.
[0033] Before stratified mining, the bottom opening of the ore pass 2 is sealed with wooden planks to create an ore-containing cavity inside. The upward stratified mining method is used to mine ore body 6 in stratified layers. Each layer is mined along the strike of the ore body, i.e., using the haulage roadway as the cutting roadway and mining from bottom to top. The layer height is 2.0m. Figure 2 As shown, the length of a single drilling and blasting operation in layered mining is the sum of the lengths of a single ore pass 2 and a single waste rock filling area along the ore body strike.
[0034] To reduce the amount of waste rock cut into the wall and decrease the amount of detonators and explosives used, such as Figure 3 and Figure 4As shown, the upper ore body 6 corresponding to the waste rock filling area is mined by slotting, and the upper ore body 6 corresponding to the ore pass 2 is mined by wall-cutting. Specifically, in the process of layered mining, after drilling and blasting, all ore bodies 6 within the single drilling and blasting length are first mined by slotting, and then only the upper ore body 6 corresponding to the ore pass 2 is mined by wall-cutting. This ensures sufficient ore-holding space within the ore pass 2 while reducing the amount of detonators and explosives used, thus saving mining costs. In addition, since only the upper ore body 6 corresponding to the ore pass 2 is mined by wall-cutting, it is not necessary to blast and mine the footwall 7 corresponding to the waste rock filling area. Compared with the existing technology of mining all ore bodies 6 by wall-cutting, this not only reduces the mining range but also reduces waste rock output, lowers the dilution loss rate, and saves some mining costs, resulting in a reduction in overall production costs. Preferably, a rubber mat is laid at the bottom of the stope before slotting and blasting.
[0035] Furthermore, when the width of the vein in the upper ore body 6 corresponding to the waste rock filling area is less than 0.6m, personnel cannot pass through normally. Therefore, the wall of the section to be mined by slotting must be cut to a width exceeding 0.6m. The upper ore body 6 corresponding to the chute 2 must always be mined by cutting the wall. Therefore, when the vein width is less than 0.6m, the section to be mined by slotting must be mined by cutting the wall, that is, the upper ore body 6 corresponding to the waste rock filling area must be mined by cutting the wall to make its width exceed 0.6m in order to ensure that personnel can pass through normally.
[0036] After the wall is cut and the mining is completed, the surrounding plate of the current mining chute 2 is installed along the chute 2 in the previous layer. The height of the surrounding plate of the chute 2 is the height of the mining layer. Preferably, the surrounding plate of the chute 2 is made of multiple steel plates welded together. In this way, the surrounding plate of the chute 2 separates the ore-containing area of the chute 2 from the waste rock filling area.
[0037] The collapsed ore is then raken to the feeding end of the belt conveyor and sorted for waste rock. The sorted ore is then conveyed to the feed chute 2 via the belt conveyor, separating the ore and waste rock. This allows for backfilling of feed chute 2, ensuring that feed chute 2 and the waste rock filling area are at the same level. This prevents feed chute 2 from forming large pits in the mining area, which would hinder subsequent mining operations. The mined waste rock is then raken to the waste rock filling area using an electric rake and flooded with cement slurry to form concrete waste rock cemented pillars. These concrete waste rock cemented pillars support the upper and lower plates, improving their stability and ensuring the safety of mining operations. Furthermore, by increasing the support strength of the upper and lower plates through the pouring of concrete waste rock cemented pillars, it also ensures that the upper and lower plates are not damaged during ore discharge, thereby increasing the overall ore recovery rate.
[0038] To ensure sufficient mining space for subsequent mining of ore body 6, after each drilling and blasting operation, the mined ore is collected into the pass 2, and a portion of the ore is released from the bottom of the pass 2. Preferably, after each drilling and blasting operation, the mined ore is collected into the pass 2, and one-third of the mined ore is released from the bottom of the pass 2, with the remaining ore inside the pass. This ensures sufficient mining space for subsequent mining of ore body 6 and avoids affecting the next mining step.
[0039] After the mining of ore body 6 is completed, the bottom of the ore pass 2 will be opened to release all the ore stored therein and transport it out of the stope. This allows for continuous ore discharge from the multi-layered ore body 6, reducing manual ore discharge time and improving the overall mining efficiency. Then, the bottom of the ore pass 2 will be sealed and backfilled with tailings. Figure 5 As shown.
[0040] Specifically, embodiments of the present invention provide an integrated mining method for ultra-thin ore bodies, comprising the following steps: S1. The ore body is extracted upward along the transport roadway 11, and an artificial false bottom 1 with a thickness of 1.2~1.5m is constructed. Multiple chutes 2 perpendicular to the ore body are excavated along the strike of the ore body. The width of the chutes 2 along the strike of the ore body is 4-6m. The area between adjacent chutes 2 is a waste rock filling area.
[0041] S2. Seal the bottom of the ore pass 2 and use the ore transport roadway as the cutting roadway to mine in layers from bottom to top. The layer height is 2.0m. Each layer is mined along the ore body strike. The single drilling and blasting mining length of the layered mining is the sum of the length of a single ore pass 2 and a single waste rock filling area along the ore body strike.
[0042] S3. During the layered mining process, after rock drilling and blasting, all ore bodies 6 within the single rock drilling and blasting mining length are first slotted and then mined. Then, only the upper ore body 6 corresponding to the ore pass 2 is chipped and mined. When the vein width is less than 0.6m, the part that was only slotted and mined is chipped and mined.
[0043] S4. After the wall cutting and mining, install the retaining plate of the current mining layer's retaining plate along the chute 2 in the previous layer. The height of the retaining plate of the chute 2 is the height of the mining layer.
[0044] S5. The collapsed ore is raken to the feeding end of the belt conveyor and sorted for waste rock. The sorted ore is transported to the chute 2 via the belt conveyor, and 1 / 3 of the single-time mining volume of ore is discharged from the bottom of the chute 2. The remaining ore is in the chute. The mined waste rock is raken to the waste rock filling area by electric rake and flooded with cement slurry to form concrete waste rock cemented columns.
[0045] S6. After the mining of ore body 6 is completed, the bottom of the ore pass 2 will be opened, and all the ore stored therein will be released and transported out of the mining area.
[0046] S7. Seal the bottom of the chute 2 and fill it with tailings.
[0047] The above are merely embodiments of the present invention and do not limit the scope of the patent. Any equivalent structural or procedural transformations made based on the description and drawings of the present invention, or direct or indirect applications in other related technical fields, are similarly included within the scope of patent protection of the present invention.
Claims
1. A method for integrated mining of extremely thin ore bodies, characterized in that, Includes the following steps: The ore body is extracted upward along the transport roadway, an artificial false bottom is constructed, and multiple ore passes perpendicular to the ore body strike are excavated along the ore body strike direction. The width of the ore passes along the ore body strike direction is 4-6m. The bottom of the ore pass is sealed, and the ore body is mined in layers using the upward layered mining method. Each layer is mined along the direction of the ore body, and the mined ore is collected in the ore pass. The area between adjacent road chutes is a waste rock filling area. The mined waste rock is raken to the waste rock filling area and flooded with cement slurry to form concrete waste rock cemented columns. After the ore body is mined out, the bottom of the ore pass will be opened to release the ore stored therein and transport it out of the mining area. The bottom of the roadway chute was sealed, and the chute was filled with tailings. The upper ore body corresponding to the waste rock filling area is mined by slotting, and the upper ore body corresponding to the roadway chute is mined by wall cutting. After drilling and blasting, all ore bodies within the single drilling and blasting length are first mined by slotting, and then only the upper ore body corresponding to the ore pass is mined by wall cutting. When the width of the ore vein is less than 0.6m, the portion that is only used for slotting mining needs to be cut and mined by wall cutting.
2. The integrated mining method for ultra-thin ore bodies according to claim 1, characterized in that, The length of a single drilling and blasting operation in layered mining is the sum of the lengths of a single ore pass and a single waste rock filling area along the strike of the ore body.
3. The integrated mining method for ultra-thin ore bodies according to claim 1, characterized in that, After each rock drilling and blasting operation, the mined ore is collected in the ore pass and some ore is released from the bottom of the ore pass.
4. The integrated mining method for ultra-thin ore bodies according to claim 3, characterized in that, After each rock drilling and blasting operation, the mined ore is collected in the ore pass and one-third of the mined ore is released from the bottom of the ore pass.
5. The integrated mining method for ultra-thin ore bodies according to claim 1, characterized in that, Install the retaining plate of the current mining chute along the chute in the previous layer, then rake the mined waste rock to the area between adjacent chutes and flood it with cement grout to form a concrete waste rock cemented column.
6. The integrated mining method for ultra-thin ore bodies according to claim 1, characterized in that, The width of the chute along the route is the minimum mining width.
7. The integrated mining method for ultra-thin ore bodies according to claim 1, characterized in that, The bottom of the ore pass is a bucket-shaped outlet.
Citation Information
Patent Citations
Thin and extremely thin ore body mining method
CN109653748A
Interval cemented pillar resuing and filling mining method
CN111042817A
Thin ore-body mechanized highly-layering continuous mining method
CN104747190A
Downhole movable cement waste rock cemented filling system and filling method
CN113202550A