An interactive link mining method

The interactive link mining method solves the problems of large mining and cutting workload and low economic efficiency caused by the large variation in thickness along the dip of gently dipping ore bodies, and achieves efficient ore recovery and increased production capacity.

CN117266853BActive Publication Date: 2026-11-24CHINA MINMETALS CHANGSHA MINING RES INST +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202311432628.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-31
Publication Date
2026-11-24
Estimated Expiration
2043-10-31

AI Technical Summary

Technical Problem

Existing technologies for mining gently dipping ore bodies with large variations in thickness along the dip have problems such as large mining and cutting workload, low economic efficiency, and the inability to effectively mine using a single layered or staged method.

Method used

The interactive link mining method is adopted. By delineating the ore body a second time, dividing it into upper and lower mining areas, and dividing the stope and panel along the strike, the ore body is alternately mined and backfilled using the stope connecting roadway and the cutting incline, forming a trackless ore extraction channel, and realizing efficient link mining of the ore body.

Benefits of technology

It reduced the loss rate in the mining area, decreased the mining-to-extraction ratio, improved the ore recovery rate and production capacity, and solved the mining problem caused by the large variation in thickness along the dip of the gently dipping ore body.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117266853B_ABST
    Figure CN117266853B_ABST
Patent Text Reader

Abstract

This application discloses an interactive link mining method; relating to the field of mining technology, it includes the following steps: S1: secondary delineation of the ore body; S2: dividing the ore body into a middle section, and further dividing the middle section into an upper mining area and a lower mining area; S3: dividing the upper and lower mining areas according to the stope panel; S4: excavating a stope connecting roadway in the lower mining area to enter the ore body, and then excavating and filling a return air shaft along the footwall of the ore body to connect it with the cross-cut roadway in the upper middle section; S5: dividing the ore body in the lower mining area into stopes, mining and filling it until mining to the height of the ore body in the upper mining area; S6: applying a roof clamp to the stope connecting roadway; S7: dividing the ore body panel in the upper mining area into stopes, mining based on the platform and reserved space formed in the lower mining area, and using the stope connecting roadway formed by the roof clamp for trackless ore extraction; this method solves the problem that the thickness of the ore body varies greatly along the dip direction, making it impossible to mine in existing mining methods, reduces the stope loss and dilution rate, reduces the mining-to-extraction ratio, and increases the mining height in the middle section.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of mining technology, and in particular to an interactive linking mining method. Background Technology

[0002] In the early stages, mining methods for gently dipping ore bodies mainly consisted of the full-area method and the shallow-hole room-and-pillar method, while the open-hole method had a high loss rate. With the application and promotion of backfilling mining methods, layered backfilling methods (mainly including horizontal layered backfilling mining method and access backfilling mining method) and staged backfilling methods (mainly referring to the two-step shallow-hole subsequent backfilling mining method) have become the main mining methods for gently dipping ore bodies.

[0003] The layered method is highly adaptable, allowing for flexible adjustment of segmented roadways, but it involves a large amount of excavation work and high mining costs, making it suitable for mining medium-thick to thick, high-value ore bodies. The staged method has relatively lower mining costs, but its stage recovery height is affected by the scraper distance, with an effective scraper distance of 40–60 m. The staged method typically results in a recovery height of less than 30 m in the middle section of gently dipping ore bodies and is not suitable for mining thick ore bodies. For gently dipping ore bodies with significant thickness variations along the dip, using a single layered method results in a large amount of cutting work and low economic efficiency. The staged method is also unsuitable for mining areas with thick ore bodies. Therefore, a new mining method is urgently needed for gently dipping ore bodies with significant thickness variations along the dip. Summary of the Invention

[0004] To enable economical and efficient mining of gently dipping ore bodies with significant variations in thickness along their dip direction, this application provides an interactive linking mining method.

[0005] This application provides an interactive link mining method, which adopts the following technical solution:

[0006] An interactive link mining method includes the following steps:

[0007] S1: Secondary delineation of the changes in the dip and attitude of the ore body;

[0008] S2: Divide the secondary delineated ore body into a middle section, and then divide the middle section into an upper mining area and a lower mining area;

[0009] S3: Divide the ore body in the lower mining area into mining areas along the strike, and divide the ore body in the upper mining area into panels along the strike.

[0010] S4: The lower mining area is excavated along the middle section of the external transport roadway to enter the ore body, and then the upper and middle sections of the ore body are excavated and cut uphill to connect with the upper and middle section cross-vein roadway.

[0011] S5: The lower mining area ore body is divided into mining areas, mined and backfilled until it is mined to the height of the upper mining area ore body, with mining and backfilling carried out alternately.

[0012] S6: Apply roof support to the connecting roadway in the mining area;

[0013] S7: Divide the upper mining area into mining areas, and mine the upper mining area ore body based on the platform and reserved space formed by the lower mining area. Then, use the mining area connecting roadway formed by the top pressure to extract ore without tracks.

[0014] Preferably, in S2, when dividing the middle section, the ore bodies of medium thickness or above are arranged in the lower part of the middle section. When the middle section is divided into upper and lower mining areas, the upper mining area is a thin ore body and the lower mining area is a medium thickness or above ore body.

[0015] Preferably, if the grade of the ore body in the lower mining area is high and the mining height is not high, and the slope of the connecting roadway after the top is pressed does not exceed the maximum allowable slope of 15%, then the ore body in S5 is divided into layers in the height direction, and the layers are divided into access roads along the thickness direction of the ore body. The access road is mined at intervals, and mining is carried out in one or two steps, and backfilling is performed.

[0016] Preferably, the access route in the first-step mining is filled with a high-strength backfill material, and the access route in the second-step mining is filled with a low-strength backfill material, with the mining and backfilling cycle being repeated.

[0017] Preferably, the upper surfaces of the higher-strength filling body and the lower-strength filling body in the same layer are provided with a rubber surface layer for loading and unloading ore by the loader and the ore truck.

[0018] Preferably, in S4, if the mining height of the lower mining area is high, causing the slope of the mining area connecting roadway to exceed the maximum allowable slope of 15% after being topped, it is necessary to excavate the mining area ramp from the middle section external transport roadway and lead the mining area connecting roadway to the ramp for topping.

[0019] Preferably, if the grade of the ore body in the lower mining area is low and the economic benefits of shallow hole mining are low, then in S5, the lower mining area is divided into sections, and the cutting riser (14) is used as a compensation space for retreat mining; backfilling is carried out after mining is completed.

[0020] Preferably, when a certain distance is maintained between the filling material and the roof of the upper mining area, filling is stopped after a high-strength filling material is filled to form a rubber surface layer.

[0021] Preferably, the connecting roadway in the mining area is constructed to the height of the rubber surface layer by top pressing.

[0022] Preferably, in S7, the space left by the mining in the lower mining area is used as the cutting bottom roadway and electric scraper chamber, and the mining of the upper mining area ore body is carried out with the cutting uphill as the compensation space. The mined ore is scraped into the cutting bottom roadway by electric scraper.

[0023] In summary, this application includes the following beneficial technical effects:

[0024] Based on an interactive design concept, the thick ore body in the lower mining area and the thin ore body in the upper mining area are linked for mining. The backfilling air shaft of the thick ore body in the lower mining area can also serve as the cutting ramp for the upper mining area. The open area of ​​the uppermost mining layer is used as the working space for mining in the upper mining area. The connecting roadway of the mining area can also serve as the trackless ore extraction channel for the upper mining area. This solves the problem that the thickness of the ore body varies greatly along the dip direction, making it impossible to mine with a single mining method. It reduces the dilution rate of the mining area, reduces the mining-to-extraction ratio, and increases the intermediate level of the stage method. Attached Figure Description

[0025] Figure 1 This is a typical schematic diagram of an embodiment of an interactive link mining method according to this application;

[0026] Figure 2 yes Figure 1 Cross-sectional view of BB in the middle;

[0027] Figure 3 This is a typical schematic diagram of a second embodiment of an interactive link mining method according to this application;

[0028] Figure 4 yes Figure 3 Cross-sectional view of BB in the middle;

[0029] Figure 5 yes Figure 3 Cross-sectional view of CC.

[0030] Explanation of reference numerals in the attached figures:

[0031] 1. Intermediate-level external transport roadway; 2. Stope connecting roadway; 3. High-strength backfill; 4. Gum-faced layer; 5. Low-strength backfill; 6. Electric scraper chamber; 7. Cutting roadway; 8. Ventilation and pedestrian connecting roadway; 9. Cutting uphill; 10. Upper-middle-level external transport roadway; 11. Blasting hole; 12. Accumulated ore; 13. Upper-middle-level cross-vein roadway; 14. Cutting shaft; 15. Rock drilling roadway. Detailed Implementation

[0032] The following is in conjunction with the appendix Figure 1-5 This application will be described in further detail.

[0033] This application discloses an interactive link mining method. Example 1 is provided below. Figure 1 and Figure 2 It includes the following steps;

[0034] Step 1: Due to the complex occurrence of the ore body, production exploration of the ore body is strengthened based on the existing geological data, and geological drilling is used to delineate the changes in the dip and occurrence of the ore body for the second time.

[0035] Step 2: Divide the secondary delineated ore body into middle sections. Arrange medium-thick or thicker ore bodies in the lower part of the middle section as much as possible. Divide the middle section into upper and lower mining areas. The upper mining area is for thin ore bodies, and the lower mining area is for medium-thick or thicker ore bodies.

[0036] Step 3: Divide the thick ore body in the middle section of the lower mining area into a stope along the strike. The length of the stope is determined based on the stability of the ore and rock, and is generally 40 to 60 meters. Similarly, divide the thin ore body in the upper mining area into a panel along the strike. The length of the panel corresponds to the length of the stope in the lower mining area.

[0037] Step 4: The middle section lower mining area enters the ore body through the external transport roadway 1 and the connecting roadway 2 of the mining area. Then, it is excavated along the footwall of the ore body and cuts the upper incline 9. The upper incline 9 (which also serves as a backfilling air shaft) is exposed to the upper and middle section through-vein roadway 13.

[0038] Step 5: Divide the ore body thickness into multiple access routes. The width of each access route is generally 3-7m, and the height of the access route is determined by the stability of the roof, generally 2-5m. Each access route is mined at one interval, and the mining is carried out in two steps. The access route mined in the first step is filled with a high-strength backfill body 3, with a 7-day strength of generally not less than 1.0 MPa. The access route mined in the second step is filled with a low-strength backfill body 5, with a lime-sand ratio of generally less than 1:10. A 0.5m-1m thick rubber surface layer 4 is arranged on the backfill body for loading and unloading ore by the loader and ore truck, with a 7-day strength of generally not less than 1.5 MPa. The mining and backfilling are carried out in layers according to the above sequence until the ore body height in the upper mining area is reached.

[0039] Step Six: After mining down to the top layer of the lower mining area, no backfilling is carried out. This layer provides working space for the mining of the upper thin ore body. The connecting roadway 2 in the stope is also topped up to become the top layer of the lower mining area, providing an ore outlet channel for the link mining of the thin ore body in the upper mining area. The lower rubber layer 4 serves as the working platform for the link mining of the upper thin ore body.

[0040] Step 7: The thin ore body panel in the upper mining area is divided into a stope, which is mined in one or two steps. The uppermost space of the lower mining area is used as the cutting bottom roadway 7 and the electric scraper chamber 6. Then, the cutting incline 9 of the stope is constructed along the dip of the ore body to be used as a filling return air shaft. The filling return air shaft is used as a compensation space for the mining of the ore body. The blasted ore is scraped into the cutting bottom roadway 7 by an electric scraper. Then, the ore is extracted without tracks using the stope connecting roadway 2 formed by the top pressure.

[0041] If the lower part of the thick ore body has a high mining height, causing the slope of the connecting roadway 2 to exceed the maximum allowable slope of 15%, it is necessary to excavate a new inclined roadway and introduce a sub-roadway to the connecting roadway 2 to mine the thick ore body.

[0042] Example 2, reference Figure 3 and Figure 5The difference between this embodiment and Embodiment 1 is that the lower, thick ore body has a lower grade and is divided into layers. Shallow-hole mining is costly and has low production capacity, so medium-deep-hole mining can be used. The resin layer and the remaining open space after medium-deep-hole mining are also used for linking mining of the upper thin ore body.

[0043] The specific steps include the following:

[0044] Step 1: Due to the complex occurrence of the ore body, production exploration of the ore body is strengthened based on the existing geological data, and geological drilling is used to delineate the changes in the dip and occurrence of the ore body for the second time.

[0045] Step 2: Divide the secondary delineated ore body into middle sections. Arrange medium-thick or thicker ore bodies in the lower part of the middle section as much as possible. Divide the middle section into upper and lower mining areas. The upper mining area is for thin ore bodies, and the lower mining area is for medium-thick or thicker ore bodies.

[0046] Step 3: Divide the thick ore body in the middle section of the lower mining area into panels along the strike. The panels are divided into first and second-stage stopes arranged perpendicular to the strike. The length of each panel is generally 40-60m. Similarly, the thin ore body in the upper mining area is divided into panels along the strike. The lengths of the panels in the upper and lower mining areas correspond.

[0047] Step 4: Enter the ore body from the middle section transport roadway 1 and the connecting roadway 2 of the mining area. At the same time, excavate and fill the return air shaft along the footwall of the ore body and expose the upper and middle section cross-vein roadway 11.

[0048] Step 5: Construct cutting riser 14 near the hanging wall of the ore body. Using cutting riser 14 as a compensation void, conduct retreating medium-deep hole caving from the hanging wall to the footwall of the ore body. Utilize trench-type bottom structure for ore extraction, or arrange a flat-bottom structure and use a remote-controlled loader for retreating ore extraction. After mining is completed, the higher-strength backfill 3 fills the mined void through the cutting uphill 9 (which also serves as a backfill return air shaft). When the distance from the roof is 3m to 4m, the higher-strength backfill forms a 0.5-1m thick rubber layer 4, and then backfilling is stopped. The second step of the lower mining area is mined again in the above sequence, replacing the higher-strength backfill 3 with lower-strength backfill 4.

[0049] Step Six: The connecting roadway 5 in the stope is constructed to the height of the top layer 4, providing working space and platform for the joint mining of thin ore bodies.

[0050] Step 7: The thin ore body panel in the upper mining area is divided into a stope and mined in one or two steps. The space left by the lower mining area is used as the cutting bottom roadway 7 and the electric scraper chamber 6. The blasted ore is scraped into the cutting bottom roadway 7 by an electric scraper, and then the ore is extracted without tracks using the stope connecting roadway 2 formed by the top pressure.

[0051] The interactive link mining method is described in detail below with a specific embodiment:

[0052] A copper mine in Sichuan Province has an ore body with a dip angle of 20°–30° and a thickness of 2m–15m, exhibiting significant variations in thickness along the dip direction. The average Cu grade is 2.21%. It is a difficult-to-mine, gently dipping, thin-to-thick, high-grade ore body with relatively good ore-rock stability.

[0053] (1) Due to the complex occurrence of the ore body, production exploration of the ore body was strengthened based on the existing geological data, and geological drilling was used to delineate the changes in the dip and occurrence of the ore body for the second time. The ore body delineated in the second time was divided into middle sections. The thick ore body area was located in the lower part of the middle section. The height of the middle section was 42m. The middle section was divided into upper and lower mining areas. The dividing line was the position where the horizontal thickness of the ore body was 8m. The thin ore body in the upper mining area had a horizontal thickness of 5-8m and a height of 30m. The thick ore body in the lower part had a horizontal thickness of 8-20m and a height of 9m. A 3m top pillar was left in the middle section.

[0054] (2) The thick ore body in the middle section of the lower mining area is divided into mining areas along the strike. The length of the mining area is 50m and the width is the thickness of the ore body. The thin ore body in the upper mining area is also divided into panels along the strike. The length of the panels corresponds to the mining area of ​​the thick ore body in the lower part, which is 50m.

[0055] (3) In the middle section of the lower mining area, the connecting roadway 2 is led into the ore body through the external transport roadway. Then, a 2×2m cross-section backfilling air shaft is excavated along the footwall of the ore body and exposed to the upper and middle section connecting roadway 13, dividing the ore body thickness into multiple access routes. The width of the access route is generally 6m and the height of the access route is 3m. The access routes are mined one at a time, and 2 to 4 access routes are mined. The access route of the first step is filled with a high-strength backfill body 3 with a lime-sand ratio of 1:6 and a 7-day strength of not less than 1.0Mpa. The access route of the second step is filled with a low-strength backfill body 5 with a lime-sand ratio of 1:12. A 0.5m layer of mortar 4 with a lime-sand ratio of 1:4 is arranged on the high-strength backfill body 3 and the low-strength backfill body 5, and its 7-day strength is not less than 1.5Mpa. The layered mining and filling are carried out in a cycle according to the above sequence until the ore body height of the upper mining area is reached. At the same time, after mining down to the top layer of the lower mining area, no backfilling is carried out. This layer provides working space for the mining of the upper thin ore body. The connecting roadway 2 in the mining area is also topped to provide an ore outlet channel for the uppermost layer of the lower mining area to link the mining of the thin ore body in the upper mining area. The lower layer of the rubber surface 4 serves as the working platform for the link mining of the upper thin ore body.

[0056] (4) The thin ore body panel in the upper mining area is divided into a mining area with a mining area structure parameter of 5×5m. It is divided into one or two steps of mining. The space left by the mining in the lower mining area is used as a cutting bottom roadway 7 and an electric scraper chamber 6. Then, a mining area cutting uphill with a cross section of 2×2m is constructed along the dipping direction of the ore body. The cutting uphill is used as a filling return air shaft 9. The filling return air shaft is used as a compensation space for mining the ore body. The blasted ore is scraped into the cutting bottom roadway by an electric scraper. Then, the mining area connecting roadway 2 formed by the top pressure is used for trackless ore extraction.

[0057] Results achieved: The height of the middle section in the original design was increased from 30m to 42m, and the ore extraction ratio was reduced from 11.76m / kt to 8.6m / kt, providing a foundation for refined zonal mining within the middle section; the ore recovery rate was increased from 87% to 92%, and the stope production capacity was increased from 160t / d to 180t / d, achieving the goal of fully utilizing the high-grade and valuable ore body; this method innovatively solved the problem of large variations in the thickness of the gently dipping ore body along the dip direction and the difficulty of mining.

[0058] The above are all preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made in accordance with the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. An interactive link mining method, characterized in that: Includes the following steps: S1: Secondary delineation of the changes in the dip and attitude of the ore body; S2: Divide the secondary delineated ore body into a middle section, and then divide the middle section into an upper mining area and a lower mining area; S3: Divide the ore body in the lower mining area into mining areas along the strike, and divide the ore body in the upper mining area into panels along the strike. S4: The lower mining area excavates the mining area connecting roadway (2) along the middle section of the external transport roadway (1) to enter the ore body, and then excavates and cuts the upper mountain (9) along the footwall of the ore body to connect it with the upper middle section through roadway (13); S5: The lower mining area ore body is divided into mining areas, mined and backfilled until it is mined to the height of the upper mining area ore body, with mining and backfilling carried out alternately. S6: Apply roof support to the connecting roadway (2) in the mining area; S7: Divide the upper mining area into mining areas, and mine the upper mining area ore body according to the platform and reserved space formed by the lower mining area. Then, use the mining area connecting roadway (2) formed by the top pressure to mine without track. In S7, the space left by the mining of the lower mining area is used as the cutting bottom roadway (7) and the electric scraper chamber (6). The mining of the upper mining area ore body is carried out with the cutting uphill (9) as the compensation space. The mined ore is scraped into the cutting bottom roadway (7) by the electric scraper.

2. The interactive link mining method according to claim 1, characterized in that: In S2, when dividing the middle section, the medium-thick or thicker ore bodies are arranged in the lower part of the middle section. When the middle section is divided into upper and lower mining areas, the upper mining area is a thin ore body, and the lower mining area is a medium-thick or thicker ore body.

3. The interactive link mining method according to claim 1, characterized in that: If the grade of the ore body in the lower mining area is high and the mining height is not high, and the slope of the connecting roadway (2) after the top is pressed does not exceed the maximum allowable slope of 15%, then the ore body in S5 is divided into layers in the height direction, and the layers are divided into access roads along the thickness direction of the ore body. The access road is mined at intervals of one step and mined in one or two steps, and then filled.

4. The interactive link mining method according to claim 3, characterized in that: The access route for the first-step mining is filled with a higher-strength backfill (3), and the access route for the second-step mining is filled with a lower-strength backfill (5). The mining and backfilling cycle is carried out.

5. The interactive link mining method according to claim 4, characterized in that: The upper surfaces of the higher strength filling body (3) and the lower strength filling body (5) in the same layer are provided with a rubber surface layer (4) for loading and unloading ore by the loader and the ore truck.

6. The interactive link mining method according to claim 3, characterized in that: In S4, if the mining height of the lower mining area is high, causing the slope of the mining area connecting roadway (2) to exceed the maximum allowable slope of 15% after being topped, it is necessary to excavate the mining area ramp from the middle section external transport roadway and lead the mining area connecting roadway (2) to the ramp for topping.

7. The interactive link mining method according to claim 1, characterized in that: If the grade of the ore body in the lower mining area is low and the economic benefits of shallow hole mining are low, then in S5, the lower mining area is divided into sections, and the cutting riser (14) is used as the compensation space for retreat mining; backfilling is carried out after mining is completed.

8. An interactive link mining method according to claim 7, characterized in that: When a certain distance is maintained between the filling body and the roof of the upper mining area, filling with a higher strength filling body (3) to form a rubber surface layer (4) is stopped.

9. An interactive link mining method according to claim 8, characterized in that: The mining connecting roadway (2) is constructed to the height of the rubber surface layer (4) by the top pressing.

Citation Information

Patent Citations

  • Upward horizontal along-vein drift step-by-step stoping cemented filling mining method

    CN113356923A