Air bag sealing structure and sealing installation process for large transformer room
By designing the weighting material and the airbag sealing assembly, the problems of unstable air pressure and cumbersome operation caused by temperature changes in the annular airbag sealing structure were solved, enabling simple and stable sealing installation in large substations.
Patent Information
- Application Number
- CN202311144289.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-06
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-09-06
AI Technical Summary
The existing ring-shaped airbag sealing structure of large substations cannot actively maintain stable air pressure due to temperature fluctuations, and the inflation or deflation operation is cumbersome.
The system employs a weight-adding device and an airbag sealing assembly. The weight-adding device causes the airbag to inflate and seal against the inner wall of the cable well. The air pressure is regulated by a limiting column and a compression cylinder, and automatic adjustment is achieved by combining a telescopic hose and an elastic element.
This technology enables sealing to be completed during the hoisting process, avoiding pressure instability and explosion of the airbag due to thermal expansion and contraction, simplifying the operation process, and improving the stability and safety of the seal.
Smart Images

Figure CN117293737B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of power building technology, and in particular to an airbag sealing structure and sealing installation process for large substations. Background Technology
[0002] In some temporary construction sites, detachable mobile large substations are installed to transmit power and control signals; in some construction sites, cables are pre-buried underground to form cable wells, and the large substations will have openings that are compatible with the cable wells to allow the cables to pass through.
[0003] To ensure the airtightness of the connection between the outgoing pipe and the cable well opening at the bottom of existing large substations, our company generally adopts a method of sealing an annular airbag on the outgoing pipe and using an external air pump and a crane to install the large substation. After the outgoing pipe is connected to the cable well opening, the external air pump is used to inflate the annular airbag, thereby achieving a seal between the outgoing pipe and the cable well opening.
[0004] However, the above-mentioned sealing method has some problems:
[0005] First, since the annular airbag seal requires gas to be filled, and the gas will expand and contract with temperature, if the temperature is too low, the sealing effect between the annular airbag and the inner wall of the cable well will decrease, and if the temperature is too high, the gas pressure inside the annular airbag will increase and it will easily explode, that is, it is impossible to actively maintain the stability of the gas pressure inside the annular airbag.
[0006] Second, manually inflating or deflating the air after hoisting or dismantling is quite troublesome.
[0007] Therefore, this application provides an airbag sealing structure and sealing installation process for large substations to meet the requirements. Summary of the Invention
[0008] The purpose of this application is to provide an airbag sealing structure and sealing installation process for large substations, which solves the technical problems in the prior art where the annular airbag cannot actively maintain the stability of the air pressure inside the annular airbag due to temperature influence and requires manual inflation or deflation operations.
[0009] To achieve the above objectives, this application provides the following technical solution: an airbag sealing structure for a large substation, comprising a large substation, with a cable outlet pipe at the bottom of the large substation, and also including a weight and an airbag sealing assembly. After the large substation and cable well are installed, the weight causes the airbag in the airbag sealing assembly to expand and abut against the inner wall of the cable well to form a seal.
[0010] Preferably, the weight-adding material includes a weight-adding ring, which is located around the outlet tube;
[0011] The airbag sealing assembly includes a telescopic flexible hose sealed and installed on the outlet pipe and multiple limiting posts arranged circumferentially around the outlet pipe. A tapered guide head is provided at the lower end of the outlet pipe. The upper ends of the multiple limiting posts are fixedly connected to the lower end of the large substation. The lower end of the weight-increasing ring is provided with multiple extrusion cylinders, the number of which matches the number of limiting posts. Each extrusion cylinder is hollow, with an open upper end and a closed lower end. The weight-increasing ring has multiple through holes corresponding to the hollow cavities of the extrusion cylinders and having the same inner diameter. The lower ends of the multiple limiting posts extend through the through holes into the corresponding hollow cavities. The lower ends of the extrusion cylinders are slidably disposed within the corresponding support cylinders. The support cylinders are hollow with an open upper end and a closed lower end. Each support cylinder has an extrusion airbag at the bottom of its inner cavity, and each extrusion airbag is connected to an annular airbag sealed on the outer wall of the outlet pipe via a connecting pipe. Multiple support cylinders are connected to the outlet pipe via corresponding connectors, and the lower end face of the outlet pipe is located below the lower end face of the support cylinder. The limiting column and the outer wall of the extrusion cylinder are each provided with a slider. The through hole, the extrusion cylinder, and the inner cavity of the support cylinder are provided with a first sliding groove and a second sliding groove adapted to the slider.
[0012] The large substation is equipped with support columns at its base;
[0013] The connector is used to connect the plurality of support cylinders to the outlet pipe without affecting the movement of the outlet pipe.
[0014] Preferably, the connector includes a lower mounting plate and an upper mounting plate that are respectively fixed to the support cylinder and the outlet pipe, and an elastic element is installed between the lower mounting plate and the upper mounting plate.
[0015] Preferably, the upper and lower ends of one of the elastic elements are fixedly connected to the corresponding upper mounting plate and the lower mounting plate, respectively. The upper and lower ends of the remaining elastic elements are fixed with movable discs. The two movable discs are respectively movably installed in the receiving cavities provided in the inner cavities of the corresponding lower mounting plate and the upper mounting plate. The receiving cavities are circular and their diameter is larger than the diameter of the movable discs. The lower mounting plate and the upper mounting plate are each provided with a circular opening communicating with the inner cavity of the receiving cavity. The diameter of the circular opening is larger than the diameter of the elastic element. The axis of the circular opening and the axis of the receiving cavity are on the same straight line.
[0016] Preferably, the bottom of the movable disc is provided with ball bearings.
[0017] Preferably, the outer wall of the outlet pipe is provided with an annular mounting groove, the annular airbag is installed in the annular mounting groove, the connecting pipe is located above the annular airbag, and the outer wall of the outlet pipe is provided with a vertical groove that communicates with and is perpendicular to the annular mounting groove, the vertical groove being located at the connection between the connecting pipe and the annular airbag.
[0018] A sealing installation process for an airbag sealing structure used in large substations includes the following steps:
[0019] S1: Align the metal ring with the constructed cable well opening and seal the lower end with the cable well opening. Pour a waterproof concrete layer around the metal ring and level the upper end of the waterproof concrete layer.
[0020] S2: After the waterproof concrete layer has fully cured, the large substation is lifted and installed using a crane. During the sealing installation, the outgoing conduit is first inserted into the cable well opening, and then the lower end of the support cylinder will contact the upper surface of the waterproof concrete layer. As the large substation continues to descend, the weight of the weight-adding block will act on the compression airbag. At this time, the annular airbag expands outward and contacts the inner ring surface of the metal ring. After the annular airbag and the metal ring form a complete seal, the lower end of the support column will contact the waterproof concrete layer to support the large substation. At this time, the sealing installation is completed.
[0021] Preferably, the metal ring is made of aluminum, and the inner surface of the metal ring is a smooth surface.
[0022] In summary, the technical effects and advantages of this invention are as follows:
[0023] 1. The present invention has a reasonable structure. The large substation can be hoisted and the annular airbag and cable well can be sealed at the same time. The installation and operation are convenient and simple. At the same time, since the weight of the weights acting on the compression airbag and the compression cylinder remains constant, when the gas inside the compression airbag and the annular airbag expands and contracts due to heat, the weights can be moved up or down along the limiting column to automatically adjust and maintain the constant air pressure inside the compression airbag and the annular airbag. This can effectively avoid the problem of the airbag exceeding the rated air pressure due to thermal expansion and contraction, resulting in explosion or reduced sealing effect.
[0024] 2. In this invention, a connector is provided to work with a telescopic hose. When the guide slope comes into contact with the edge of the cable well opening, the outlet pipe can move laterally in all directions due to the squeezing force. This allows the outlet pipe to be connected to the cable well opening by moving laterally while keeping the vertical position of the large substation unchanged.
[0025] 3. In this invention, one of the elastic elements is fixedly connected, while the remaining elastic elements are movably connected, which can reduce the resistance encountered when the outlet tube moves laterally, and at the same time expand the range of the outlet tube's lateral movement distance. Attached Figure Description
[0026] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0027] Figure 1 This is a three-dimensional structural diagram of the present invention;
[0028] Figure 2 for Figure 1 Enlarged view of the structure at point A in the middle;
[0029] Figure 3 for Figure 1 A partial structural diagram of the bottom of a medium-to-large substation, viewed from below.
[0030] Figure 4 Here is an enlarged schematic diagram of the sealing components of the three airbags;
[0031] Figure 5 for Figure 4 Schematic diagram of the cross-sectional structure of the central support cylinder, extrusion cylinder, and weighting material;
[0032] Figure 6 for Figure 4 Schematic diagram of the middle connector structure;
[0033] Figure 7 This is a schematic diagram of the airbag sealing assembly and the cable wellhead installation structure.
[0034] In the diagram: 1. Large substation; 2. Support column; 3. Waterproof concrete layer; 4. Metal ring; 5. Airbag sealing assembly; 51. Outlet pipe; 52. Telescopic hose; 53. Support cylinder; 54. Limiting column; 55. Annular airbag; 56. Extrusion cylinder; 57. Conical guide head; 58. First slide groove; 59. Second slide groove; 510. Extrusion airbag; 511. Connecting pipe; 512. Sliding block; 6. Connector; 61. Upper mounting plate; 62. Lower mounting plate; 63. Elastic element; 64. Movable disc; 65. Receiving cavity; 66. Circular opening; 7. Weight. Detailed Implementation
[0035] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0036] Example: Reference Figure 1-3 The large substation airbag sealing structure shown includes a large substation 1, with a cable outlet pipe 51 at the bottom of the large substation 1, as well as a weight 7 and an airbag sealing assembly 5. After the large substation 1 and the cable well are installed, the weight 7 causes the airbag in the airbag sealing assembly 5 to expand and come into contact with the inner wall of the cable well to form a seal.
[0037] As a preferred embodiment of this example, Figure 1-5 As shown, the weight-adding component 7 includes a weight-adding ring located around the outlet pipe 51; the airbag sealing assembly 5 includes a telescopic hose 52 sealed and installed on the outlet pipe 51 and multiple limiting posts 54 arranged circumferentially around the outlet pipe 51. A conical guide head 57 is provided at the lower end of the outlet pipe 51. The upper ends of the multiple limiting posts 54 are fixedly connected to the lower end of the large substation 1. The lower end of the weight-adding ring is provided with multiple extrusion cylinders 56, the same number as the number of limiting posts 54. The extrusion cylinders 56 are hollow, with an open upper end and a closed lower end. The weight-adding ring is provided with multiple through holes corresponding to the hollow cavities of the multiple extrusion cylinders 56 and having the same inner diameter. The lower ends of the multiple limiting posts 54 extend into the corresponding hollow cavities through the through holes. The lower ends of the multiple extrusion cylinders 56 are slidably mounted on the corresponding support cylinders 53. Inside, the support cylinder 53 is hollow with an open top and a closed bottom. Each support cylinder 53 has a compression airbag 510 at the bottom of its inner cavity, and each compression airbag 510 is connected to an annular airbag 55 sealed on the outer wall of the outlet pipe 51 via a connecting pipe 511. Multiple support cylinders 53 are connected to the outlet pipe 51 via corresponding connectors 6, and the lower end face of the outlet pipe 51 is located below the lower end face of the support cylinder 53. The limiting column 54 and the outer wall of the compression cylinder 56 are both equipped with sliders 512. The inner cavity of the through hole, the compression cylinder 56 and the support cylinder 53 are equipped with a first sliding groove 58 and a second sliding groove 59 that are adapted to the sliders 512. The bottom of the large substation 1 is equipped with a support column 2. The connectors 6 are used to connect multiple support cylinders 53 to the outlet pipe 51 without affecting the movement of the outlet pipe 51.
[0038] During the installation and sealing of the large substation 1 using a crane (the large substation 1 is lifted by the crane to the top of the cable well opening, and the large transformer box 1 is vertically lowered to complete the sealing installation), the outgoing pipe 51 is first inserted into the cable well opening, and then the lower end of the support cylinder 53 contacts the upper surface of the waterproof concrete layer 3. As the large substation 1 continues to descend, the weight of the weight block 7 will act on the compression airbag 510. Since the compression airbag 510 is connected to the annular airbag 55 through the connecting pipe 511, the annular airbag 55 will expand outward and contact the inner ring surface of the metal ring 4. After the weight of the weight block 7 and the compression cylinder 56 is fully applied, the annular airbag 55 and the metal ring 4 form a good and complete seal. The air pressure inside the annular airbag 55 and the compression airbag 510 is the same. Finally, the lower end of the support column 2 will contact the waterproof concrete layer 3 to support the large substation 1. At this time, the sealing installation is completed, forming a... Figure 1 As shown, after the large substation 1 is lowered to the cable well opening, the sealing of the outlet pipe 51 and the cable well is completed simultaneously. This enables rapid sealing of the outlet pipe 51 and the cable well opening, and the installation and operation are convenient and simple. Furthermore, since the weights of the weights 7 and 56 acting on the compression airbag 510 remain constant, when the gas inside the compression airbag 510 and the annular airbag 55 undergoes thermal expansion and contraction, the weights 7 can automatically adjust and maintain a constant internal air pressure by moving upwards or downwards along the limiting column 54. This effectively prevents the airbag from exceeding its rated pressure and exploding due to thermal expansion and contraction (the weights 7 act on the compression airbag 510, compressing it, which has a large expansion capacity). To address the issue of reduced sealing performance, before sealing installation, the lower ends of the support column 2 and the outlet pipe 51 are in contact with the ground, while the support cylinder 53 is suspended. The support column 2 bears the weight of the large substation 1, and the outlet pipe 51 bears the weight of the added weight 7 and the compression cylinder 56. This prevents the outlet pipe 51 from deforming or being damaged due to the weight of the large substation 1. During disassembly and cleaning, the large substation 1 is lifted, and the added weight 7 is lifted first. The gravity acting on the compression airbag 510 disappears, and the annular air chamber contracts. Finally, the outlet pipe 51 moves upward and is removed from the cable well, facilitating the disassembly of the large substation 1.
[0039] It should be noted that: First, due to the heavy weight of the large substation 1, it is impossible to expand and seal the annular airbag 55 by applying the weight of the large substation 1 to the compression airbag 510. This would easily cause excessive air pressure inside the airbag, leading to an explosion and rupture. Therefore, a load-bearing object 7 is added to compress the compression airbag 510, causing the annular airbag 55 to expand and complete the seal. The weight of the load-bearing object 7 can be selected according to the sealing strength and the air pressure that the airbag can withstand. Second, the cable wellhead is set as a circular structure.
[0040] As a preferred embodiment of this example, Figure 6 As shown, the connector 6 includes a lower mounting plate 62 and an upper mounting plate 61 that are fixed to the support cylinder 53 and the outlet pipe 51 respectively, and an elastic member 63 is installed between the lower mounting plate 62 and the upper mounting plate 61.
[0041] When the tapered guide head 57 is inserted into the metal ring 4, if there is a certain positional deviation and the guide slope on the tapered guide head 57 comes into contact with the edge of the cable well opening, the contact force generated between the tapered guide head 57 and the edge of the cable well opening is insufficient to allow the suspended large substation 1 to move adaptively due to the heavy weight of the large substation 1. This can easily cause the annular airbag 55 on the subsequent outgoing pipe 51 to move into the inner cavity of the cable well opening, thus failing to seal the cable well opening. Furthermore, if the suspended large substation 1 tilts... Or, if there is shaking, it can easily lead to uneven stress on the substation structure, increasing the risk of structural damage and causing safety accidents. Therefore, an elastic element 63 is set so that when the guide slope comes into contact with the edge of the cable well, the outlet pipe 51 can move laterally in all directions due to the squeezing force. This allows the outlet pipe 51 to be connected to the cable well by moving laterally while keeping the vertical position of the large substation 1 unchanged. Ultimately, the annular airbag 55 moves into the cable well.
[0042] It should be noted that the elastic element can be set as a spring. The spring can be extended or compressed in the longitudinal direction and bent in various lateral directions when subjected to force. The telescopic hose 52 can also move in the longitudinal and lateral directions, which is conducive to guiding the tapered guide head 57 into the inner cavity of the cable well.
[0043] As a preferred embodiment of this example, Figure 4 and Figure 6 As shown, the upper and lower ends of an elastic element 63 are fixedly connected to the corresponding upper mounting plate 61 and lower mounting plate 62, respectively. The upper and lower ends of the remaining elastic elements 63 are all fixed with movable discs 64. The two movable discs 64 are respectively movably installed in the receiving cavities 65 provided in the inner cavities of the corresponding lower mounting plate 62 and upper mounting plate 61. The receiving cavity 65 is circular and its diameter is larger than the diameter of the movable disc 64. The lower mounting plate 62 and the upper mounting plate 61 are both provided with circular openings 66 that communicate with the inner cavity of the receiving cavity 65. The diameter of the circular opening 66 is larger than the diameter of the elastic element 63. The axis of the circular opening 66 and the axis of the receiving cavity 65 are on the same straight line.
[0044] One of the elastic elements 63 is fixedly connected to the upper and lower mounting plates 61 and 62 respectively. The purpose is to allow the outlet pipe 51 to automatically return to its original position when it moves out of the cable well. The upper and lower ends of the other elastic elements 63 are movably connected to the upper and lower mounting plates 61 and 62 to reduce the resistance encountered by the outlet pipe 51 when it moves laterally, and at the same time expand the range of lateral movement of the outlet pipe 51 (when the outlet pipe 51 is squeezed by the edge of the metal ring 4, the reaction force generated is entirely applied to the single fixed elastic element 63 and the telescopic hose 52, thereby expanding the range of movement of the outlet pipe 51).
[0045] As a preferred embodiment of this example, Figure 6 As shown, the bottom of the movable disc 64 is provided with ball bearings, which can reduce the friction between the movable disc 64 and the upper mounting plate 61 or the lower mounting plate 62. This allows the outlet tube 51 to move laterally when the conical guide head 57 and the edge of the metal ring 4 are subjected to a small amount of pressure, thus preventing the outlet tube 51 from being deformed and damaged due to excessive pressure.
[0046] As a preferred embodiment of this example, Figure 4 As shown, an annular mounting groove is provided on the outer wall of the outlet pipe 51, and an annular airbag 55 is installed in the annular mounting groove. The connecting pipe 511 is located above the annular airbag 55. A vertical groove is provided on the outer wall of the outlet pipe 51, which is connected to and perpendicular to the annular mounting groove. The vertical groove is located at the connection between the connecting pipe 511 and the annular airbag 55. The purpose of placing the annular airbag 55 in the inner cavity of the annular mounting groove is to prevent the protruding annular airbag 55 from contacting and rubbing against the edge of the cable well opening, which would cause wear and reduce its service life.
[0047] A sealing installation process for an airbag sealing structure used in large substations includes the following steps:
[0048] S1: Align the metal ring 4 with the constructed cable well opening and seal the lower end with the cable well opening. Pour a waterproof concrete layer 3 around the metal ring 4 and level the upper end of the waterproof concrete layer 3.
[0049] S2: After the waterproof concrete layer 3 has completely cured, the large substation 1 is lifted and installed by a crane. During the sealing installation, the outgoing pipe 51 is first inserted into the wellhead of the cable well, and then the lower end of the support cylinder 53 will contact the upper surface of the waterproof concrete layer 3. As the large substation 1 continues to descend, the weight of the weight block 7 will act on the compression airbag 510. At this time, the annular airbag 55 expands outward and contacts the inner ring surface of the metal ring 4. After the annular airbag 55 and the metal ring 4 form a complete seal, the lower end of the support column 2 will contact the waterproof concrete layer 3 to support the large substation 1. At this time, the sealing installation is completed.
[0050] As a preferred embodiment of this example, Figure 2 As shown, the metal ring 4 is made of aluminum, and the inner ring surface of the metal ring 4 is set as a smooth surface.
[0051] The outer wall of the annular airbag 55 is pressed into contact with the inner wall of the metal ring 4 to achieve a seal on the cable wellhead. Its inner ring surface is smooth, which can reduce the friction between it and the annular airbag 55. Since there is no uneven surface with grooves, the expanded annular airbag 55 and the metal ring 4 form a good seal. The aluminum metal has good oxidation resistance, which prevents it from corroding and rusting.
[0052] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. An airbag sealing structure for a large substation, comprising a large substation (1), wherein a cable outlet pipe (51) is provided at the bottom of the large substation (1), characterized in that: It also includes a weighting device (7) and an airbag sealing assembly (5). After the large substation (1) and the cable well are installed, the weighting device (7) will cause the airbag in the airbag sealing assembly (5) to expand and come into contact with the inner wall of the cable well to form a seal. The weight-adding material (7) includes a weight-adding ring, which is located around the outlet tube (51); The airbag sealing assembly (5) includes a telescopic hose (52) sealed on the outlet pipe (51) and a plurality of limiting posts (54) arranged in a circle around the outlet pipe (51). The lower end of the outlet pipe (51) is provided with a conical guide head (57). The upper ends of the plurality of limiting posts (54) are fixedly connected to the lower end of the large substation (1). The lower end of the weight-increasing ring is provided with a plurality of extrusion cylinders (56) with the same number as the limiting posts (54). The extrusion cylinders (56) are hollow and open at the upper end and closed at the lower end. The weight-increasing ring is provided with a plurality of through holes that communicate with the hollow cavities of the plurality of extrusion cylinders (56) and have the same inner diameter. The lower ends of the plurality of limiting posts (54) extend into the corresponding hollow cavities through the through holes. The lower ends of the plurality of extrusion cylinders (56) are slidably arranged in a corresponding manner. Inside the corresponding support cylinder (53), the support cylinder (53) is hollow and has an open top and a closed bottom. Each support cylinder (53) has a compression airbag (510) at the bottom of its inner cavity. Each compression airbag (510) is connected to an annular airbag (55) sealed on the outer wall of the outlet pipe (51) through a connecting pipe (511). Multiple support cylinders (53) are connected to the outlet pipe (51) through corresponding connecting parts (6). The lower end face of the outlet pipe (51) is located below the lower end face of the support cylinder (53). The limiting column (54) and the outer wall of the compression cylinder (56) are both provided with sliders (512). The through hole, the compression cylinder (56) and the inner cavity of the support cylinder (53) are provided with a first groove (58) and a second groove (59) that are adapted to the slider (512). The large substation (1) is equipped with a support column (2) at its bottom. The connector (6) is used to connect the plurality of support cylinders (53) to the outlet pipe (51) without affecting the movement of the outlet pipe (51).
2. The airbag sealing structure for a large substation according to claim 1, characterized in that: The connector (6) includes a lower mounting plate (62) and an upper mounting plate (61) that are fixed to the support cylinder (53) and the outlet pipe (51) respectively, and an elastic element (63) is installed between the lower mounting plate (62) and the upper mounting plate (61).
3. The airbag sealing structure for a large substation according to claim 2, characterized in that: The upper and lower ends of one of the elastic elements (63) are fixedly connected to the corresponding upper mounting plate (61) and lower mounting plate (62), respectively. The upper and lower ends of the remaining elastic elements (63) are fixed with movable discs (64). The two movable discs (64) are respectively movably installed in the receiving cavities (65) provided in the inner cavities of the corresponding lower mounting plate (62) and upper mounting plate (61). The receiving cavity (65) is circular and its diameter is larger than that of the movable disc (64). The lower mounting plate (62) and the upper mounting plate (61) are each provided with a circular opening (66) communicating with the inner cavity of the receiving cavity (65). The diameter of the circular opening (66) is larger than that of the elastic element (63). The axis of the circular opening (66) and the axis of the receiving cavity (65) are on the same straight line.
4. The airbag sealing structure for a large substation according to claim 3, characterized in that: The bottom of the movable disc (64) is provided with ball bearings.
5. The airbag sealing structure for a large substation according to claim 1, characterized in that: The outer wall of the outlet pipe (51) is provided with an annular mounting groove, the annular airbag (55) is installed in the annular mounting groove, the connecting pipe (511) is located above the annular airbag (55), the outer wall of the outlet pipe (51) is provided with a vertical groove that communicates with and is perpendicular to the annular mounting groove, and the vertical groove is located at the connection between the connecting pipe (511) and the annular airbag (55).
6. A sealing installation process adapted to the airbag sealing structure for large substations as described in any one of claims 1-5, characterized in that: The following processes are included: S1: Align the metal ring (4) with the constructed cable well opening and seal the lower end with the cable well opening. Pour a waterproof concrete layer (3) around the metal ring (4) and level the upper end of the waterproof concrete layer (3). S2: After the waterproof concrete layer (3) has completely cured, the large substation (1) is lifted and installed by a crane. When the sealing installation is carried out, the outlet pipe (51) is first inserted into the wellhead of the cable well, and then the lower end of the support cylinder (53) will contact the upper end of the waterproof concrete layer (3). As the large substation (1) continues to descend, the weight of the weight block (7) will act on the compression airbag (510). At this time, the annular airbag (55) expands outward and contacts the inner ring surface of the metal ring (4). After the annular airbag (55) and the metal ring (4) form a complete seal, the lower end of the support column (2) will contact the waterproof concrete layer (3) to support the large substation (1). At this time, the sealing installation is completed.
7. The sealing installation process of the airbag sealing structure for a large substation according to claim 6, characterized in that: The metal ring (4) is made of aluminum, and the inner ring surface of the metal ring (4) is set as a smooth surface.
Citation Information
Patent Citations
Constant-pressure type air bag energy storage system
CN107559054A
Mobile power transformation room and use method thereof
CN116446701A