An emergency hydrogen energy station site optimization method and system for minimizing transportation costs

By constructing a layout optimization model for hydrogen refueling and hydrogen production stations and using a genetic algorithm to optimize the location and number of these stations, the problem of transportation losses in the construction of hydrogen infrastructure for hydrogen fuel cell vehicles was solved, transportation costs were reduced, and the commercialization of hydrogen fuel cell vehicles was promoted.

CN117314279BActive Publication Date: 2026-11-24WUCHANG UNIV OF TECH
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311261210.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-27
Publication Date
2026-11-24
Estimated Expiration
2043-09-27

AI Technical Summary

Technical Problem

The commercialization of hydrogen fuel cell vehicles faces challenges such as insufficient hydrogen infrastructure, particularly transportation losses between hydrogen refueling and production stations, which lead to high transportation costs and hinder the promotion and application of hydrogen fuel cell vehicles.

Method used

A layout optimization model for hydrogen refueling stations and hydrogen production stations is constructed and solved using a genetic algorithm to minimize transportation losses of hydrogen refueling vehicles and hydrogen transport vehicles, forming a multi-objective optimization model for construction losses, and optimizing the location and number of hydrogen refueling stations and hydrogen production stations.

Benefits of technology

It reduces transportation losses between hydrogen refueling vehicles and hydrogen refueling and production stations, improves the efficiency of hydrogen energy transportation, reduces the construction cost of hydrogen infrastructure, and promotes the commercialization of hydrogen fuel cell vehicles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117314279B_ABST
    Figure CN117314279B_ABST
Patent Text Reader

Abstract

This invention provides a method and system for optimizing emergency hydrogen energy stations to minimize transportation costs. The method includes: first, obtaining the number of hydrogen refueling stations and the weight of road conditions based on the average daily hydrogen refueling volume, total daily hydrogen demand, and road condition information, and calculating the losses along the entire construction section; then, constructing a hydrogen refueling station layout optimization model with the goal of minimizing the losses of all hydrogen refueling vehicles to their nearest hydrogen refueling station; constructing a hydrogen production station layout optimization model with the goal of minimizing the transportation cost of hydrogen transport vehicles from the hydrogen production station to the hydrogen refueling station; combining the hydrogen refueling station layout optimization model to form a multi-objective optimization model for construction losses, and solving the model; finally, constructing a construction cost optimization model with the goals of minimizing the transportation costs of all hydrogen refueling vehicles to the hydrogen refueling station and the transportation costs of hydrogen transport vehicles from the hydrogen production station to the hydrogen refueling station, and solving the optimal solution of the model. This invention optimizes transportation losses and costs, contributing to the construction of hydrogen infrastructure and achieving cost reduction and efficiency improvement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of site optimization technology, and in particular to an emergency hydrogen energy site optimization method and system that minimizes transportation costs. Background Technology

[0002] my country attaches great importance to the development of the clean energy industry, and with the continuous improvement of people's environmental awareness, the new energy vehicle market continues to grow. Hydrogen fuel cell vehicles, which use hydrogen as fuel and energy, have many advantages compared to traditional gasoline-powered vehicles and electric vehicles. First, hydrogen fuel cell vehicles use fuel cell technology to react hydrogen with oxygen to generate electricity, which then drives an electric motor. This means that hydrogen fuel cell vehicles do not produce harmful exhaust emissions like traditional gasoline-powered vehicles; they only release water vapor, resulting in zero emissions and a significant improvement in air quality. Second, hydrogen fuel cell vehicles have high energy density and fast refueling. Compared to electric vehicles, the refueling time for hydrogen fuel cell vehicles is similar to that of traditional gasoline-powered vehicles, taking only a few minutes to complete the refueling process. They also provide a longer driving range to meet long-distance driving needs. Furthermore, hydrogen fuel cell vehicles have the potential to utilize renewable energy sources, being produced through water electrolysis, biomass conversion, and natural gas reforming, achieving zero emissions. Therefore, the combination of hydrogen fuel cell vehicles and renewable energy is expected to promote energy transformation and reduce dependence on fossil fuels.

[0003] However, the commercialization of hydrogen fuel cell vehicles faces a significant challenge: the lack of adequate hydrogen infrastructure, including facilities for hydrogen production, storage, transportation, and refueling. Currently, my country's hydrogen refueling stations primarily rely on external hydrogen supplies, meaning they need to be replenished through off-site hydrogen production stations. The planning and construction of hydrogen refueling stations must consider various aspects, including hydrogen sourcing, storage and transportation, and station operation. Despite these challenges, hydrogen fuel cell vehicles, as an important application of clean energy technology, have attracted attention and promotion from many countries and regions worldwide.

[0004] To address the challenges of hydrogen infrastructure development, this study comprehensively considers factors such as the spacing between hydrogen refueling stations, the location of hydrogen production stations, and geographical factors during transportation. Using transportation losses between hydrogen refueling vehicles and stations, and between refueling and production stations, as decision variables, an optimization model for the layout of hydrogen production and refueling stations is constructed. This model aims to improve the relevant infrastructure, enabling hydrogen-powered vehicles to play a vital role in the future, promoting sustainable energy development, and reducing environmental pollution. Summary of the Invention

[0005] In view of the technical problems existing in the prior art, the present invention provides an emergency hydrogen energy station optimization method and system that minimizes transportation costs, so as to solve the construction problem of hydrogen infrastructure.

[0006] According to a first aspect of the present invention, the present invention provides an optimization method for emergency hydrogen energy sites that minimizes transportation costs, comprising the following steps: Step S1: Based on the average daily hydrogen refueling volume of hydrogen refueling stations, the total daily hydrogen demand, and road condition information, obtain the number of hydrogen refueling stations and the weight of road condition, and then calculate the loss of the entire road section under construction. Step S2: With the goal of minimizing the loss of all hydrogen refueling vehicles to their nearest hydrogen refueling station, construct a hydrogen refueling station layout optimization model; Step S3: With the goal of minimizing the transportation cost of hydrogen vehicles from hydrogen production stations to hydrogen refueling stations, construct a hydrogen production station layout optimization model. Combine this with the hydrogen refueling station layout optimization model to form a multi-objective optimization model for construction losses, and solve for the optimal solution set of the model. Step S4: With the goal of minimizing the transportation costs of all hydrogen refueling vehicles to the hydrogen refueling station and the transportation costs of hydrogen transport vehicles from the hydrogen production station to the hydrogen refueling station, construct a construction cost optimization model and solve for the optimal solution of the model.

[0007] Based on the above technical solution, the present invention can also be improved as follows.

[0008] Optionally, in step 1, obtaining the number of hydrogen refueling stations includes: S111. Based on construction planning or relevant demand surveys and forecasts, the total daily hydrogen demand for the construction section is: The average daily hydrogen refueling volume at each hydrogen refueling station is ;

[0009] S112. Based on the average daily hydrogen refueling volume of the hydrogen refueling station Total daily demand for hydrogen The number of hydrogen refueling stations and the optimization target for the number of hydrogen refueling stations were derived; the formula for calculating the number of hydrogen refueling stations is as follows: The target for optimizing the number of hydrogen refueling stations is... ;

[0010] S113. Calculate the number of hydrogen refueling stations based on the optimization objective.

[0011] Optionally, in step 1, obtaining the road condition weight set includes: S121. Based on the on-site survey, the number of road condition types for the construction section is determined, and denoted as follows: kind;

[0012] S122. Based on the actual road conditions, give the road condition coefficients for each road segment to obtain the set of road condition coefficients. .

[0013] Optionally, in step 1, calculating the loss of the entire construction section includes: S131, will The hydrogen refueling station divides the entire construction section into several parts. Segment, let the length of each segment be . km, and ;

[0014] S132, Section In the middle, the road conditions are as follows: The length of the road segment is km, then the road section The formula for calculating loss is: ;

[0015] S133. Obtain the total road loss of the construction section using the following formula: .

[0016] Optionally, in step 2, constructing the hydrogen refueling station layout optimization model includes: Assuming hydrogen refueling vehicles have Vehicles, then hydrogen refueling vehicles for , Take the integer part;

[0017] When hydrogen refueling cars On the road section Above, let it be connected to the adjacent hydrogen refueling station. Inter-road conditions are The length of the road segment is ;

[0018] Hydrogen refueling vehicles Section of road Two hydrogen refueling stations and In this context, the nearest hydrogen refueling station to the hydrogen refueling vehicle is defined as the one with the least loss.

[0019] Hydrogen refueling vehicles To the section of road Up near a hydrogen refueling station The road conditions in the section are as follows: The length of the road segment is Then hydrogen refueling vehicles To the nearest hydrogen refueling station The distance is Calculate hydrogen refueling vehicles To the nearest hydrogen refueling station The loss is calculated using the following formula: ;

[0020] The calculation formula is as follows: [Formula omitted for brevity] ;

[0021] Calculate the optimization model .

[0022] Optionally, in step 3, constructing the hydrogen production station layout optimization model includes: S31, Establish a hydrogen production station Route to all hydrogen refueling stations for ;

[0023] S32, Establish a hydrogen production station to hydrogen refueling station Road conditions are The length of the road segment is km, then hydrogen production station to hydrogen refueling station The distance is km;

[0024] S331, Computational Hydrogen Production Station to hydrogen refueling station The loss is calculated using the following formula: ;

[0025] S332, Computational Hydrogen Production Station The loss to all hydrogen refueling stations is calculated using the following formula: ;

[0026] S333, Obtain the optimized model .

[0027] Optionally, the process of forming a multi-objective optimization model for construction losses and solving for the optimal solution set of the model includes: obtaining a multi-objective optimization model for construction losses based on the loss optimization model from a hydrogen refueling vehicle to its nearest hydrogen refueling station and the loss optimization model from a hydrogen production station to all hydrogen refueling stations for a hydrogen transport vehicle. The optimal solution set of the multi-objective optimization model for construction loss is obtained by using a genetic algorithm; the genetic algorithm uses chromosome encoding.

[0028] Optionally, in step 4, constructing a construction cost optimization model and solving for the optimal solution of the model includes: Assume the road conditions are as follows: The construction cost of the road section is Yuan;

[0029] Calculation of hydrogen production station The cost of visiting all hydrogen refueling stations is calculated using the following formula: ;

[0030] Calculate hydrogen refueling vehicles To the section of road The cost of refueling near a hydrogen refueling station is calculated using the following formula: ;

[0031] Calculate the distance of all hydrogen refueling vehicles to their respective road sections The cost of refueling near a hydrogen refueling station is calculated using the following formula: ;

[0032] Calculate the total cost using the following formula: ;

[0033] This yields the cost optimization model, namely the construction cost optimization model; Substitute the optimal solution set obtained in step 3 into the cost optimization model to solve for the solution with the lowest cost, which is the optimal solution of the model.

[0034] Optionally, the cost optimization model expression is: .

[0035] According to a second aspect of the present invention, an emergency hydrogen energy site optimization system for minimizing transportation costs is provided, comprising: The first calculation module is used to obtain the number of hydrogen refueling stations and the weight of road conditions based on the average daily hydrogen refueling volume of hydrogen refueling stations, the total daily hydrogen demand, and road condition information, and then calculate the loss of the entire road section under construction. The second calculation module is used to construct a hydrogen refueling station layout optimization model based on the optimization objective of minimizing the loss of all hydrogen refueling vehicles to their nearest hydrogen refueling station. The third calculation module is used to construct a hydrogen production station layout optimization model based on the optimization objective of minimizing the transportation cost of hydrogen vehicles from hydrogen production stations to hydrogen refueling stations. Combined with the hydrogen refueling station layout optimization model, a multi-objective optimization model for construction losses is formed, and the optimal solution set of the model is solved. The fourth calculation module is used to construct a construction cost optimization model based on the optimization objective of minimizing the transportation costs of all hydrogen refueling vehicles to hydrogen refueling stations and the transportation costs of hydrogen transport vehicles from hydrogen production stations to hydrogen refueling stations, and to solve the optimal solution of the model.

[0036] The present invention provides an optimization method and system for emergency hydrogen energy sites that minimizes transportation costs, which has the following technical effects and advantages: To address the transportation losses between hydrogen refueling vehicles and hydrogen refueling stations, the road conditions between hydrogen refueling vehicles and two adjacent hydrogen refueling stations were analyzed. An optimization model for the layout of hydrogen refueling stations was constructed, resulting in a hydrogen refueling station layout with minimal losses. This reduces losses during the hydrogen refueling process from hydrogen refueling vehicles to hydrogen refueling stations and improves the transportation efficiency of hydrogen refueling vehicles.

[0037] To address the transportation losses between hydrogen production stations and refueling stations, the road conditions between these stations were analyzed, and an optimization model for the layout of hydrogen production stations was constructed. This model yielded the optimal location for hydrogen production stations with minimal losses, thereby reducing transportation losses between the stations and improving the efficiency of hydrogen energy transportation.

[0038] The emergency hydrogen energy site optimization method for minimizing transportation costs provided in this application can comprehensively consider the transportation losses between hydrogen refueling vehicles and hydrogen refueling stations, as well as between hydrogen production stations and hydrogen refueling stations. It avoids the shortcomings that may be caused by only considering the impact of a single aspect, so as to optimize transportation losses and costs, help the construction of hydrogen infrastructure, and achieve cost reduction and efficiency improvement. Attached Figure Description

[0039] Figure 1 This is a flowchart of an emergency hydrogen energy station optimization method that minimizes transportation costs, provided by an embodiment of the present invention. Figure 2 This is a schematic diagram illustrating the actual situation of step S222 provided in the embodiment of the present invention; Figure 3 This is a schematic diagram illustrating the meaning of each parameter in an emergency hydrogen energy station optimization method for minimizing transportation costs provided in an embodiment of the present invention; Figure 4 This is an example diagram of chromosome encoding for step S341 provided in an embodiment of the present invention; Figure 5 This is a schematic diagram of the hardware structure of a possible electronic device provided by the present invention. Detailed Implementation

[0040] To make the objectives, technical solutions, and advantages of this invention clearer, the technical solutions of this invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some, not all, of the embodiments of this invention. All other embodiments obtained by those skilled in the art based on the embodiments of this invention without creative effort are within the scope of protection of this invention.

[0041] Understandably, given the deficiencies in the background technology, this invention proposes an optimization method for emergency hydrogen energy sites that minimizes transportation costs, specifically as follows: Figure 1 As shown, the optimization method includes the following steps: Step S1: Based on the average daily hydrogen refueling volume of hydrogen refueling stations, the total daily hydrogen demand, and road condition information, obtain the number of hydrogen refueling stations and the weight of road condition, and then calculate the loss of the entire road section under construction. The specific implementation process of this step in the above technical solution is as follows: Based on the average daily hydrogen refueling volume and total daily hydrogen demand at each hydrogen refueling station, the specific number of hydrogen refueling stations includes: S111. Based on construction planning or relevant demand surveys and forecasts, the total daily hydrogen demand for the construction section is: The average daily hydrogen refueling volume at each hydrogen refueling station is ;

[0042] S112. Based on the average daily hydrogen refueling volume of the hydrogen refueling station Total daily demand for hydrogen The formula for calculating the number of hydrogen refueling stations is as follows: The optimization target for the number of hydrogen refueling stations is: ;

[0043] S113. Based on the optimization objective, the number of hydrogen refueling stations is calculated as follows: After that, a hydrogen refueling station will be set up. for .

[0044] Based on the road condition conditions of the road segment, the specific set of road condition weights includes: S121. Based on the on-site survey, the number of road condition types for the construction section is as follows: Types, such as tunnels, ramps, and flat roads;

[0045] S122. Based on the actual road conditions, give the road condition coefficient (PQI) for each road segment to obtain the set of road condition coefficients. for The road condition coefficient is defined as the weight of road condition conditions. The road condition calculation method uses the PQI (Road Quality Index), which is calculated as follows: PQI = S1×P1 + S2×P2 + S3×P3 + S4×P4. Here, S1, S2, S3, and S4 represent the scores for road surface smoothness, damage condition, load-bearing capacity, and skid resistance, respectively, while P1, P2, P3, and P4 represent the weight values ​​for these indicators.

[0046] The calculation of losses across the entire construction section specifically includes: S131, The hydrogen refueling station divides the entire construction section into several parts. Segment, let the length of each segment be . km, and ;

[0047] Among them, when hour, From the start of the construction section to the first hydrogen refueling station The distance; when hour, For hydrogen refueling stations to hydrogen refueling station The distance between; when hour, For the last hydrogen refueling station Distance to the end of the construction section.

[0048] S132, Section In the middle, the road conditions are as follows: The length of the road segment is km, then the road section The formula for calculating loss is: ;

[0049] S133, The formula for calculating the loss of the entire construction section is as follows: .

[0050] Step S2: With the goal of minimizing the loss of all hydrogen refueling vehicles to their nearest hydrogen refueling station, construct a hydrogen refueling station layout optimization model; The above technical solution includes the following specific steps: S21, Assuming hydrogen refueling vehicles have Vehicles, then hydrogen refueling vehicles for , Take the integer part;

[0051] S22, Confirm hydrogen refueling vehicles Nearby hydrogen refueling station ;

[0052] S221, When a hydrogen refueling vehicle On the road section Above, let it be connected to the adjacent hydrogen refueling station. Inter-road conditions are The length of the road segment is ;

[0053] S222, Hydrogen refueling vehicles Section of road Two hydrogen refueling stations and In this context, the one with the smaller loss is defined as the nearest hydrogen refueling station to the hydrogen refueling vehicle. The formula for determining the value of is:

[0054]

[0055] Among them, hydrogen refueling vehicles To its nearest hydrogen refueling station The formula for calculating the loss between road sections is as follows: Therefore, according to the definition of a nearby hydrogen refueling station:

[0056] Specifically, such as Figure 2 As shown in ①, when At that time, hydrogen refueling vehicles On road segment 0 (between the start of the construction section and the first hydrogen refueling station), there are only two adjacent hydrogen refueling stations. ,but ;

[0057] like Figure 2 As shown in ②, when At that time, hydrogen refueling vehicles On the road section There are two adjacent hydrogen refueling stations. ,but ,like ,but ;

[0058] like Figure 2 As shown in ③, when At that time, hydrogen refueling vehicles On the road section (Between the last hydrogen refueling station and the end of the construction section) there are only two adjacent hydrogen refueling stations. ,but .

[0059] S23. Obtain the loss optimization model for all hydrogen refueling vehicles to their nearest hydrogen refueling station; S231, As can be seen from S22, hydrogen refueling vehicles To the section of road Up near a hydrogen refueling station The road conditions in the section are as follows: The length of the road segment is Then hydrogen refueling vehicles To the nearest hydrogen refueling station The distance is ,

[0060] Hydrogen-fueled vehicles To the nearest hydrogen refueling station The formula for calculating the loss is: ;

[0061] S232. The formula for calculating the loss of all hydrogen refueling vehicles to their nearest hydrogen refueling station is as follows: .

[0062] S233, Obtain the optimized model .

[0063] Step S3: With the goal of minimizing the transportation cost of hydrogen vehicles from hydrogen production stations to hydrogen refueling stations, construct a hydrogen production station layout optimization model. Combine this with the hydrogen refueling station layout optimization model to form a multi-objective optimization model for construction losses, and solve for the optimal solution set of the model. The above technical solution includes the following specific steps: S31, Establish a hydrogen production station Route to all hydrogen refueling stations for ;

[0064] S32, see reference as follows Figure 3 As shown, a hydrogen production station is to be set up. to hydrogen refueling station Road conditions are The length of the road segment is km, then hydrogen production station to hydrogen refueling station The distance is km;

[0065] S33, Obtain hydrogen production station Loss optimization models for all hydrogen refueling stations; specifically including:

[0066] S331, Hydrogen Production Station to hydrogen refueling station The formula for calculating loss is: ;

[0067] S332, Hydrogen Production Station The formula for calculating the loss to all hydrogen refueling stations is as follows: ;

[0068] S333, Obtain the optimized model .

[0069] S34, combined with S23 and S33, yields a multi-objective optimization model for construction loss. The optimal solution set of the multi-objective optimization model for construction loss was obtained using a genetic algorithm. The genetic algorithm employed chromosome encoding.

[0070] It should be noted that the genetic algorithm chromosomes used in this method are exemplified as follows: Figure 4 As shown. (Using...) Indicates hydrogen refueling station Is it near a hydrogen refueling station? Indicates road section conditions Does it exist; use Indicates road conditions as The length of the road segment; using Indicates the establishment of hydrogen production stations to hydrogen refueling station Between, road conditions are The length of the road segment.

[0071] Step S4: With the goal of minimizing the transportation costs of all hydrogen refueling vehicles to the hydrogen refueling station and the transportation costs of hydrogen transport vehicles from the hydrogen production station to the hydrogen refueling station, construct a construction cost optimization model and solve for the optimal solution of the model.

[0072] In the above technical solution, this step specifically includes: obtaining the destinations of all hydrogen refueling vehicles on their respective road sections. The cost of the nearest hydrogen refueling station is used to obtain the construction cost optimization objective, and the solution is calculated based on the Pareto optimal solution set obtained in step 3.

[0073] Among them, all hydrogen refueling vehicles were obtained from their respective road sections. The cost of accessing a nearby hydrogen refueling station includes the following steps:

[0074] S41, Assume the road conditions are as follows: The construction cost of the road section is Yuan;

[0075] S42, Computational Hydrogen Production Station The cost of visiting all hydrogen refueling stations is calculated using the following formula: ;

[0076] S431, Calculation of hydrogen refueling vehicles To the section of road The cost of refueling near a hydrogen refueling station is calculated using the following formula: ;

[0077] S432, Calculate the distance of all hydrogen refueling vehicles to their respective road segments. The cost of refueling near a hydrogen refueling station is calculated using the following formula: .

[0078] The process involves obtaining the construction cost optimization objective and calculating the solution based on the optimal solution set of the multi-objective optimization model for construction losses, including: S441. Calculate the total cost using the following formula: ;

[0079] S442, Obtain the cost optimization model ;

[0080] S443. Substitute the optimal solution set of the construction loss multi-objective optimization model obtained in S34 into the formula in S442 to solve for the solution with the minimum cost, which is the optimal solution of the model.

[0081] In summary, this invention provides an emergency hydrogen energy station optimization method that minimizes transportation costs. It constructs a hydrogen refueling station layout optimization model to reduce losses during the hydrogen refueling process from the vehicle to the station, and a hydrogen production station layout optimization model to reduce transportation losses between the production station and the refueling station. By combining these two models, a multi-objective optimization model for construction losses is formed, which reduces the construction cost of hydrogen infrastructure, improves the efficiency of hydrogen energy transportation, and solves the construction problem of hydrogen infrastructure.

[0082] Based on this, the emergency hydrogen energy station optimization method for minimizing transportation costs proposed in this invention can use a genetic algorithm to solve a multi-objective optimization model to obtain the optimal layout of hydrogen refueling / hydrogen production stations, thereby promoting sustainable energy development and reducing environmental pollution.

[0083] On the other hand, embodiments of the present invention also provide an emergency hydrogen energy site optimization system that minimizes transportation costs, comprising: The first calculation module is used to obtain the number of hydrogen refueling stations and the weight of road conditions based on the average daily hydrogen refueling volume of hydrogen refueling stations, the total daily hydrogen demand, and road condition information, and then calculate the loss of the entire road section under construction. The second calculation module is used to construct a hydrogen refueling station layout optimization model based on the optimization objective of minimizing the loss of all hydrogen refueling vehicles to their nearest hydrogen refueling station. The third calculation module is used to construct a hydrogen production station layout optimization model based on the optimization objective of minimizing the transportation cost of hydrogen vehicles from hydrogen production stations to hydrogen refueling stations. Combined with the hydrogen refueling station layout optimization model, a multi-objective optimization model for construction losses is formed, and the optimal solution set of the model is solved. The fourth calculation module is used to construct a construction cost optimization model based on the optimization objective of minimizing the transportation costs of all hydrogen refueling vehicles to hydrogen refueling stations and the transportation costs of hydrogen transport vehicles from hydrogen production stations to hydrogen refueling stations, and to solve the optimal solution of the model.

[0084] It is understood that the emergency hydrogen energy station optimization system for minimizing transportation costs provided by the present invention corresponds to the emergency hydrogen energy station optimization method for minimizing transportation costs provided in the foregoing embodiments. The relevant technical features of the emergency hydrogen energy station optimization system for minimizing transportation costs can be referred to the relevant technical features of the emergency hydrogen energy station optimization method for minimizing transportation costs, and will not be repeated here.

[0085] Figure 5 An example is a schematic diagram of the physical structure of an electronic device, such as... Figure 5 As shown, the electronic device may include a processor 810, a communications interface 820, a memory 830, and a communication bus 840, wherein the processor 810, communications interface 820, and memory 830 communicate with each other via the communication bus 840. The processor 810 can call logical instructions in the memory 830 to execute steps of an emergency hydrogen energy site optimization method that minimizes transportation costs.

[0086] Furthermore, the logical instructions in the aforementioned memory 830 can be implemented as software functional units and, when sold or used as independent products, can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or a part of the technical solution, can be embodied in the form of a software product. This computer software product is stored in a storage medium and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute all or part of the steps of the methods described in the various embodiments of the present invention. The aforementioned storage medium includes various media capable of storing program code, such as USB flash drives, portable hard drives, read-only memory (ROM), random access memory (RAM), magnetic disks, or optical disks.

[0087] The device embodiments described above are merely illustrative. The units described as separate components may or may not be physically separate. The components shown as units may or may not be physical units; that is, they may be located in one place or distributed across multiple network units. Some or all of the modules can be selected to achieve the purpose of this embodiment according to actual needs. Those skilled in the art can understand and implement this without any creative effort.

[0088] Through the above description of the embodiments, those skilled in the art can clearly understand that each embodiment can be implemented by means of software plus necessary general-purpose hardware platforms, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solutions, in essence or the part that contributes to the prior art, can be embodied in the form of a software product. This computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, magnetic disk, optical disk, etc., and includes several instructions to cause a computer device (which may be a personal computer, server, or network device, etc.) to execute the methods described in the various embodiments or some parts of the embodiments.

[0089] Although preferred embodiments of the invention have been described, those skilled in the art, upon learning the basic inventive concept, can make other changes and modifications to these embodiments. Therefore, the appended claims are intended to be interpreted as including both the preferred embodiments and all changes and modifications falling within the scope of the invention.

[0090] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, and not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features; and these modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. An emergency hydrogen energy station site optimization method that minimizes transportation costs, characterized by, Includes the following steps: Step S1: Based on the average daily hydrogen refueling volume of hydrogen refueling stations, the total daily hydrogen demand, and road condition information, obtain the number of hydrogen refueling stations and the weight of road condition information, and then calculate the loss of the entire construction section; among which, The number of hydrogen refueling stations obtained includes: S111、According to the construction planning or related demand investigation prediction, the total daily hydrogen demand of the construction road section is set as , and the average daily hydrogenation amount of each hydrogenation station is ; S112、according to the average daily hydrogenation amount of the hydrogenation station and the total daily hydrogen demand , the number of hydrogenation stations and the optimization target of the number of hydrogenation stations are obtained; wherein the number of hydrogenation stations is calculated by the formula , and the optimization target of the number of hydrogenation stations is ; S113. Calculate the number of hydrogen refueling stations based on the optimization objective; The resulting set of road condition weights includes: S121、According to the construction site investigation, the number of road condition types of the construction section is obtained, which is set as one; S122, according to the actual road conditions, the road conditions coefficient of each road section is given, and a road condition weight set is obtained ; The calculation of losses across the entire construction section includes: S131、 hydrogen stations divide the entire construction road section into segments, set the length of each segment as km, and ; S132, set the road section In the road condition is The length of the road section is km, the road section The loss calculation formula is ; S133. Obtain the total road loss of the construction section using the following formula: ; Step S2: With the goal of minimizing the losses of all hydrogen refueling vehicles traveling to their nearest hydrogen refueling station, construct a hydrogen refueling station layout optimization model, including: Assuming hydrogen refueling vehicles have Vehicles, then hydrogen refueling vehicles for , Take the integer part; When hydrogen refueling cars On the road section Above, let it be connected to the adjacent hydrogen refueling station. Inter-road conditions are The length of the road segment is ; Hydrogen refueling vehicles Section of road Two hydrogen refueling stations and In this context, the nearest hydrogen refueling station to the hydrogen refueling vehicle is defined as the one with the least loss. Hydrogen refueling vehicles To the section of road Up near a hydrogen refueling station The road conditions in the section are as follows: The length of the road segment is Then hydrogen refueling vehicles To the nearest hydrogen refueling station The distance is ; Calculate hydrogen refueling vehicles To the nearest hydrogen refueling station The loss is calculated using the following formula: ; The calculation formula is as follows: [Formula omitted for brevity] ; Calculate the optimization model ; Step S3: With the goal of minimizing the transportation cost of hydrogen vehicles from hydrogen production stations to hydrogen refueling stations, construct a hydrogen production station layout optimization model. Combine this with the hydrogen refueling station layout optimization model to form a multi-objective optimization model for construction losses, and solve for the optimal solution set of the model. Step S4: With the goal of minimizing the transportation costs of all hydrogen refueling vehicles to the hydrogen refueling station and the transportation costs of hydrogen transport vehicles from the hydrogen production station to the hydrogen refueling station, construct a construction cost optimization model and solve for the optimal solution of the model.

2. The method for optimizing emergency hydrogen energy stations to minimize transportation costs according to claim 1, characterized in that, In step S3, the construction of the hydrogen production station layout optimization model includes: S31, Establish a hydrogen production station Route to all hydrogen refueling stations for ; S32, Establish a hydrogen production station to hydrogen refueling station Road conditions are The length of the road segment is km, then hydrogen production station to hydrogen refueling station The distance is km; S331, Computational Hydrogen Production Station to hydrogen refueling station The loss is calculated using the following formula: ; S332, Computational Hydrogen Production Station The loss to all hydrogen refueling stations is calculated using the following formula: ; S333, Obtain the optimized model .

3. The method for optimizing emergency hydrogen energy stations to minimize transportation costs according to claim 2, characterized in that, The process of forming a multi-objective optimization model for construction losses and solving for the optimal solution set of the model includes: Based on the loss optimization models for hydrogen refueling vehicles traveling to their nearest hydrogen refueling station and for hydrogen transport vehicles traveling from hydrogen production stations to all hydrogen refueling stations, a multi-objective optimization model for construction losses is derived. The optimal solution set of the multi-objective optimization model for construction loss is obtained by using a genetic algorithm; the genetic algorithm uses chromosome encoding.

4. The method for optimizing emergency hydrogen energy stations to minimize transportation costs according to claim 1, characterized in that, In step S4, constructing a construction cost optimization model and solving for the optimal solution of the model includes: Assume the road conditions are as follows: The construction cost of the road section is Yuan; Calculation of hydrogen production station The cost of visiting all hydrogen refueling stations is calculated using the following formula: ; Calculate hydrogen refueling vehicles To the section of road The cost of refueling near a hydrogen refueling station is calculated using the following formula: ; Calculate the distance of all hydrogen refueling vehicles to their respective road sections The cost of refueling near a hydrogen refueling station is calculated using the following formula: ; Calculate the total cost using the following formula: ; Once the cost optimization model is obtained, the optimal solution set of the model obtained in step S3 is substituted into the cost optimization model for solving to obtain the solution with the minimum cost, which is the optimal solution of the model.

5. The method for optimizing emergency hydrogen energy stations to minimize transportation costs according to claim 4, characterized in that, The cost optimization model expression is: 。 6. An emergency hydrogen energy station optimization system for minimizing transportation costs, applied to the emergency hydrogen energy station optimization method for minimizing transportation costs as described in any one of claims 1 to 5, characterized in that, include: The first calculation module is used to obtain the number of hydrogen refueling stations and the weight of road conditions based on the average daily hydrogen refueling volume of hydrogen refueling stations, the total daily hydrogen demand, and road condition information, and then calculate the loss of the entire road section under construction. The second calculation module is used to construct a hydrogen refueling station layout optimization model based on the optimization objective of minimizing the loss of all hydrogen refueling vehicles to their nearest hydrogen refueling station. The third calculation module is used to construct a hydrogen production station layout optimization model based on the optimization objective of minimizing the transportation cost of hydrogen vehicles from hydrogen production stations to hydrogen refueling stations. Combined with the hydrogen refueling station layout optimization model, a multi-objective optimization model for construction losses is formed, and the optimal solution set of the model is solved. The fourth calculation module is used to construct a construction cost optimization model based on the optimization objective of minimizing the transportation costs of all hydrogen refueling vehicles to hydrogen refueling stations and the transportation costs of hydrogen transport vehicles from hydrogen production stations to hydrogen refueling stations, and to solve the optimal solution of the model.

Citation Information

Patent Citations

  • Hydrogen energy station scene intelligent operation platform

    CN113034055A

  • Site selection planning method for hydrogen refueling station of hydrogen energy highway

    CN115759568A