Prefabricated tunnel wall

By using prefabricated tunnel grout stop wall structures and prefabricated slabs and anchor bolts, the problems of long construction cycles and poor safety of traditional formwork and pouring construction have been solved, achieving efficient and safe grout stop wall construction in tunnel construction.

CN117328900BActive Publication Date: 2026-11-24CHONGQING JIAOTONG UNIV
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202311378044.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-24
Publication Date
2026-11-24
Estimated Expiration
2043-10-24

AI Technical Summary

Technical Problem

In tunnel construction, especially when water and mud inrush disasters occur in fault fracture zones, the traditional on-site formwork and concrete grout-stopping wall construction has a long construction cycle, poor safety, difficulty in meeting the tunnel construction progress requirements, and is prone to settlement and collapse.

Method used

The prefabricated tunnel grout stop wall structure includes a base, grout stop wall body, and limiting components. It utilizes prefabricated slabs, front fixed anchor bolts, lateral fixed anchor bolts, and reinforcing beams to form a stable grout stop wall structure through prefabricated construction, thereby improving construction efficiency and safety.

Benefits of technology

It improves the efficiency and safety of tunnel construction, ensures the structural stability and construction progress of the grout-stopping wall, and is suitable for construction in fault fracture zones after water and mud inrush disasters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117328900B_ABST
    Figure CN117328900B_ABST
Patent Text Reader

Abstract

This invention discloses a prefabricated tunnel grout-stopping wall, comprising a base, a grout-stopping wall body, and a limiting component for fixing and positioning the grout-stopping wall body. The base is fixed in the soil and rock layer at the bottom of the tunnel. The grout-stopping wall body is formed by sealing and connecting multiple prefabricated slabs and supported on the base. The limiting component includes an arched guard plate supported on the base, a front limiting plate and a rear limiting plate respectively parallel and conformally arranged on the front and rear sides of the arched guard plate, an arch protection layer formed between the front and rear limiting plates corresponding to the upper side of the arched guard plate, and a limiting groove formed between the front and rear limiting plates corresponding to the lower side of the arched guard plate for fixing and limiting the multiple prefabricated slabs. It also includes multiple sets of front fixed anchor rods and multiple sets of lateral fixed anchor rods. This prefabricated tunnel grout-stopping wall has good structural stability and high safety, and can be applied to the construction of fault fracture zones after water inrush and mud inrush disasters. It is also easy to construct, which can effectively improve the construction efficiency of the grout-stopping wall and ensure the overall construction progress of the tunnel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of tunnel construction technology, and specifically relates to a prefabricated tunnel grout-stopping wall. Background Technology

[0002] When tunnel excavation reaches weak zones such as fault fracture zones and intrusion contact zones, sudden water and mud inrush disasters are likely to occur. After a disaster, grouting reinforcement of the affected section's soil and rock is necessary. The grout stop wall plays a crucial role in withstanding the grouting pressure and the pressure of the soil and rock at the tunnel face. Currently, a concrete grout stop wall is typically formed by on-site formwork casting, followed by full-section grouting behind the grout stop wall to reinforce the weak soil and rock behind it. After the soil and rock are reinforced, the grout stop wall is gradually removed for excavation. However, on-site formwork casting has a long construction cycle, especially in high-pressure, water-rich fault fracture zones, requiring extensive preliminary support construction to ensure the stability of the wall formwork installation. Furthermore, the removal of the integrally cast grout stop wall is relatively slow, which cannot meet the schedule requirements of tunnel construction. In addition, since the grout stop wall is constructed on a weak foundation after a disaster, the presence of mudslide deposits and mud-water erosion can easily cause the traditionally formwork-cast concrete grout stop wall to settle and collapse, threatening the safety of construction workers.

[0003] Therefore, there is an urgent need to provide a new tunnel grout stop structure that can improve the construction efficiency of the tunnel grout stop and thus ensure the overall construction progress of the tunnel; at the same time, it should have good structural stability and high safety, and be suitable for construction in fault fracture zones after water inrush and mud inrush disasters. Summary of the Invention

[0004] In view of this, the purpose of the present invention is to provide a prefabricated tunnel grout stop wall, which has good structural stability, high safety and convenient construction, and can effectively improve the construction efficiency of the grout stop wall and ensure the overall construction progress of the tunnel.

[0005] To achieve the above objectives, the present invention provides the following technical solution: a prefabricated tunnel grout-stopping wall, comprising a base, a grout-stopping wall body, and a limiting component for fixing and limiting the grout-stopping wall body. The base is fixed in the soil and rock layer at the bottom of the tunnel. The grout-stopping wall body is formed by sealing and connecting multiple prefabricated plates and supported on the base. The limiting component includes an arched guard plate supported on the base, a front limiting plate and a rear limiting plate respectively parallel to and conformally arranged on the front and rear sides of the arched guard plate. The front limiting plate is connected to the arched guard plate. The plate is fixedly connected, and the rear limiting plate is detachably connected to the front limiting plate. An arch protection layer is formed on the upper side of the arched guard plate between the front limiting plate and the rear limiting plate, and a limiting groove for fixing and limiting multiple precast plates is formed on the lower side of the arched guard plate between the front limiting plate and the rear limiting plate. It also includes multiple sets of front fixed anchors and multiple sets of lateral fixed anchors. The front fixed anchors fix the front limiting plate in the rock and soil layer in front of the tunnel excavation face, and the lateral fixed anchors fix the arched guard plate in the rock and soil layer on the side of the tunnel.

[0006] Furthermore, all of the multiple sets of front fixed anchor rods are hollow grouting anchor rods, and are evenly distributed along the upper edge of the front limiting plate.

[0007] Furthermore, the multiple sets of lateral fixing anchors are hollow grouting anchors, and are evenly distributed along the circumference of the arched protective plate.

[0008] Furthermore, the top of the rear limiting plate is pre-set with multiple first grouting holes for grouting into the arch protection layer.

[0009] Furthermore, the multiple precast slabs are seamlessly spliced ​​sequentially along the width of the tunnel, and matching splicing staggers are provided at the splicing points of two adjacent precast slabs.

[0010] Furthermore, the lower edge of the front limiting plate extends inward to form multiple protrusions that abut against the rear limiting plate, and each of the multiple protrusions has a threaded hole; the lower edge of the rear limiting plate has multiple bolt holes corresponding to the multiple protrusions, and the rear limiting plate is fixed to the front limiting plate by bolts; the top of the multiple prefabricated plates has avoidance holes for avoiding the protrusions at the positions corresponding to the multiple protrusions.

[0011] Furthermore, each of the precast slabs is pre-set with a second grouting hole for grouting the soil and rock layer in front of the tunnel excavation face.

[0012] Furthermore, it also includes a reinforcement component, which comprises multiple sets of reinforcement beams fixed to the lateral sides of the rear limiting plate along the tunnel width direction.

[0013] Furthermore, the reinforcing beam is an I-beam, and the I-beam extends protruding towards the side of the precast slab to form a limiting part that abuts against the precast slab.

[0014] Furthermore, the top of the base is provided with multiple pre-set guide platforms spaced at intervals along the tunnel width direction, and the bottom of the multiple precast slabs is provided with guide protrusions that match the guide platforms.

[0015] Compared with the prior art, the beneficial effects of the present invention are as follows:

[0016] The prefabricated tunnel grout stop wall structure provided by this invention has good stability and high safety. It can be applied to the construction of fault fracture zones after water and mud inrush disasters. It is also easy to construct and can effectively improve the construction efficiency of the grout stop wall and ensure the overall construction progress of the tunnel.

[0017] Specifically: Setting a base at the bottom of the wall helps prevent settlement, making it suitable for construction on weak foundations softened by sudden water or mudflows, ensuring the stability and safety of the wall base; multiple sets of front and lateral anchor bolts effectively guarantee the stable connection between the front limiting plate and the arched protective plate and the surrounding soil and rock layers. The resulting arched protective layer can be further reinforced by grouting to ensure this stable connection; the limiting groove formed between the rear and front limiting plates effectively fixes and limits each precast slab, resulting in good structural stability and high safety; the overall structure can be assembled... With good compatibility, compared to walls formed by traditional formwork and casting, the precast slabs here can be prefabricated in advance, thereby reducing the time for formwork erection, wall casting, solidification, and curing, and improving the construction efficiency of the main wall. At the same time, the front limiting plate and the arched guard plate can be prefabricated as a whole, and then the front fixing anchor rod and the lateral fixing anchor rod are applied and installed respectively, followed by the installation of the precast slab, and finally the rear limiting plate is closed. The installation is convenient and the structure is reliable. Moreover, since the rear limiting plate is detachable, it is convenient to quickly dismantle the wall formed by the precast slabs later, thereby improving the construction efficiency of the tunnel and ensuring the overall construction progress of the tunnel.

[0018] Other advantages, objectives, and features of the invention will be set forth in part in the description which follows, and in part will be apparent to those skilled in the art from the following examination, or may be learned from practice of the invention. The objectives and other advantages of the invention can be realized and obtained through the following description. Attached Figure Description

[0019] Figure 1 This is a schematic diagram of the transverse cross-section of the tunnel according to the present invention.

[0020] Figure 2 This is a schematic diagram of the longitudinal section of the tunnel according to the present invention.

[0021] Figure 3 This is an axonometric schematic diagram of the overall structure of the present invention.

[0022] Figure 4 This is a schematic diagram of the exploded structure of the present invention.

[0023] Reference numerals: 1-Base; 101-Guide platform; 2-Grouting wall body; 201-Precast slab; 201a-Splicing staggered platform; 201b-Avoidance hole; 201c-Second grouting hole; 201d-Guide boss; 3-Limiting component; 301-Arch-shaped protective plate; 302-Front limiting plate; 302a-Protrusion platform; 303-Rear limiting plate; 303a-First grouting hole; 303b-Bolt through hole; 304-Arch protection layer; 305-Limiting groove; 4-Soil layer; 5-Front fixed anchor; 6-Lateral fixed anchor; 7-Reinforcing beam; 701-Limiting part. Detailed Implementation

[0024] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.

[0025] Please see Figure 1-4 A prefabricated tunnel grout-stopping wall includes a base 1, a grout-stopping wall body 2, and a limiting component 3 for fixing the grout-stopping wall body 2. The base 1 is fixed in the soil and rock layer 4 at the bottom of the tunnel. Here, the base 1 is generally a concrete base, which can be formed by excavating a foundation pit of a certain depth in the stratum and then pouring it. By setting the base 1 at the bottom of the wall, it can play a role in preventing settlement. It is suitable for construction on weak foundations softened by sudden water or mud inrush, ensuring the stability and safety of the bottom of the wall. The grout-stopping wall body 2 is composed of multiple pieces The precast slab 201 is sealed and connected and supported on the base 1. The sealed connection here is like a seamless splice, which can be achieved by applying sealant or mortar to the splice. The precast slab 201 is generally a precast concrete slab. To ensure the strength of the precast slab 201, steel bars can be added inside the concrete slab. Compared with the traditional formwork and casting to form the wall, the precast slab 201 can be precast in advance, thereby reducing the formwork support and the time for wall casting, solidification and curing of the main wall 2, and improving the construction efficiency of the main wall.

[0026] The limiting component 3 includes an arched guard plate 301 supported on the base 1. The arched guard plate 301 is generally a steel plate of a certain thickness (15-25mm), which can be a single piece or welded from multiple plates. The arched guard plate 301 provides initial support for the upper part of the tunnel excavation face. A front limiting plate 302 and a rear limiting plate 303 are respectively and conformally arranged parallel to and on the front and rear sides of the arched guard plate 301. "Conformally arranged" here means conforming to the transverse cross-section of the arched guard plate 301. Typically, the front limiting plate 302 and the rear limiting plate 303 are arc-shaped plates. "Front" refers to the direction of tunnel excavation, and "rear" refers to the already excavated side. The front limiting plate 302 is fixedly connected to the arched guard plate 301, such as by welding, while the rear limiting plate 303 is detachably connected to the front limiting plate 302, such as by bolts. The arched guard plate 301 is positioned between the front limiting plate 302 and the rear limiting plate 303. An arch support layer 304 is formed on the upper side. This arch support layer 304 is generally formed by pressure grouting. The formed arch support layer 304 can effectively fill the gap between the upper part of the arch support layer 304 and the soil layer, enhance the connection reliability between the front limiting plate 302 and the arched guard plate 301 and the surrounding soil layer 4, and improve the structural stability. A limiting groove 305 is formed on the lower side of the arched guard plate 301 between the front limiting plate 302 and the rear limiting plate 303 for fixing and limiting multiple precast slabs 201. It can be understood that the limiting groove 305 is an arc groove. The top of the precast slab 201 can be stably locked in the limiting groove 305, which is structurally reliable. Since the rear limiting plate 303 is detachable, it is convenient to install the precast slabs 201 in the early stage and to quickly dismantle the wall formed by the precast slabs 201 in the later stage, thereby improving the tunnel construction efficiency and ensuring the overall construction progress of the tunnel.

[0027] It also includes multiple sets of front fixed anchor bolts 5 and multiple sets of lateral fixed anchor bolts 6. The front fixed anchor bolts 5 fix the front limiting plate 302 in the soil and rock layer 4 in front of the tunnel excavation face. Preferably, the front fixed anchor bolts 5 extend horizontally forward. The lateral fixed anchor bolts 6 fix the arched guard plate 301 in the soil and rock layer 4 on the side of the tunnel. Preferably, the lateral fixed anchor bolts 6 extend radially outward along the arc plate. By setting the front fixed anchor bolts 5 and the lateral fixed anchor bolts 6, the stable connection between the front limiting plate 302 and the arched guard plate 301 and the surrounding soil and rock layer can be ensured, the reliability of the precast plate 201 during installation can be ensured, the stable installation of the limiting component 3 can be ensured, the horizontal bearing capacity of the limiting component 3 can be improved, the overall structure is stable and reliable, and the safety is high.

[0028] In this embodiment, the multiple sets of front fixed anchor rods 5 are all hollow grouting anchor rods, and are evenly distributed along the upper edge of the front limiting plate 302. For high-pressure, water-rich fractured fault zones with loose rock strata, the emergence of self-advancing hollow grouting anchor rods allows the use of hollow grouting anchor rods in loose rock and soil conditions. Hollow grouting anchor rods provide better anchoring quality and are easier to install than ordinary anchor rods, ensuring timely application of prestress. At the same time, by evenly distributing multiple sets of front fixed anchor rods 5 along the upper edge of the front limiting plate 302, the structure is compact and reliable, and will not affect the installation of the lower precast slab 201.

[0029] In this embodiment, the multiple sets of lateral fixing anchors 6 are hollow grouting anchors, and are evenly distributed along the circumference of the arched protective plate 301. Here, the transverse cross section of the arched protective plate 301 is generally arc-shaped. The lateral fixing anchors 6 are preferably arranged to extend outward along the radial direction of the arched protective plate 301. The structure is compact and easy to construct. The hollow grouting anchors have better anchoring quality than ordinary anchors, are easy to install, and can ensure that prestress can be applied in a timely manner.

[0030] In this embodiment, the top of the rear limiting plate 303 is pre-set with multiple first grouting holes 303a for grouting into the arch protection layer 304. Specifically, there are two such holes. Setting multiple holes can improve grouting efficiency. The first grouting holes 303a are through holes that run from front to back. In use, grout can be injected into the arch protection layer 304 through the first grouting holes 303a by installing pipes, grout pumps, etc. Since the first grouting holes 303a are set at the top of the rear limiting plate 303, the injected grout can be well dispersed to various parts under the action of gravity, forming a dense arch protection layer 304. The pre-set position of the first grouting holes 303a is reasonable.

[0031] In this embodiment, the multiple precast slabs 201 are seamlessly spliced ​​sequentially along the width of the tunnel, and matching splicing staggered platforms 201a are provided at the splicing points of two adjacent precast slabs 201. Seamless splicing sequentially along the width of the tunnel facilitates splicing construction, reduces hoisting construction, and further ensures construction efficiency. Here, the matching splicing staggered platforms 201a refer to the staggered platforms designed on two adjacent precast slabs. Preferably, the staggered platforms are set vertically along the height direction. The splicing staggered platforms 201a improve the sealing contact surface at the splicing point to reduce leakage at the splicing point.

[0032] In this embodiment, the lower edge of the front limiting plate 302 extends inward to form multiple protrusions 302a that abut against the rear limiting plate 303. These protrusions 302a can be sleeves fixed to the front limiting plate 302 by welding. Each of the protrusions 302a has a threaded hole. To prevent external soil or rock from flowing in and causing blockage, the front ends of the threaded holes are generally not through-holes. The abutment of the protrusions 302a against the rear limiting plate 303 improves connection reliability, increases the overall structural rigidity, and reduces [damage / loss]. Deformation, thereby ensuring structural reliability; the lower edge of the rear limiting plate 303 is provided with multiple bolt holes 303b corresponding to multiple protrusions 302a, and the rear limiting plate 303 and the front limiting plate 302 are fixed by bolts, which is convenient to connect and simple to install; the top of the multiple prefabricated plates 201 are respectively provided with avoidance holes 201b for avoiding the protrusions 302a at the positions corresponding to the multiple protrusions 302a. Usually, the edge of the avoidance hole 201b is notched to reduce interference and improve assemblability.

[0033] In this embodiment, each of the precast slabs 201 is pre-set with a second grouting hole 201c for grouting the soil and rock layer in front of the tunnel excavation face. Preferably, it is generally set at the upper part, and usually multiple holes are set. By pre-setting the second grouting hole 201c, it is convenient to drill holes and install grouting pipes to grout into the soil layer to be excavated in the later stage, thereby further improving the construction efficiency.

[0034] In this embodiment, a reinforcing component is also included. The reinforcing component includes multiple sets of reinforcing beams 7 fixed to the lateral sides of the rear limiting plate 303 along the tunnel width direction. The reinforcing beams 7 can be fixedly connected to the lateral sides of the rear limiting plate 303 by welding, bolting, or other means. The lateral direction refers to the width direction of the tunnel. By setting the reinforcing beams 7, the stability of the overall structure can be further improved, the horizontal bearing capacity of the wall can be improved, and the reverse pressure of the grouting process can be resisted. In practice, vertical reinforcing beams can also be set as needed.

[0035] In this embodiment, the reinforcing beam 7 is an I-beam, and the I-beam extends protruding towards the side of the precast slab 201 to form a limiting part 701 that abuts against the precast slab 201. The limiting part 701 is a steel plate that extends along the length of the I-beam, such as being welded and fixed to the I-beam. The I-beam has good structural strength and bending strength. By setting the limiting part 701 that abuts against the precast slab 201, the stable limiting of each precast slab 201 is ensured.

[0036] In this embodiment, the top of the base 1 is provided with a plurality of pre-set guide platforms 101 spaced apart along the tunnel width direction. The guide platforms 101 can be integrally formed during the base construction. The bottom of the multiple precast slabs 201 is provided with guide protrusions 201d that match the guide platforms 101. During construction, the guide protrusions 201d can be placed on the guide platforms 101 first, and then the precast slab can be pushed to the position where it abuts against the front limiting plate 302. By setting the guide platforms 101, the assembly efficiency of the precast slabs can be improved, while ensuring the accurate positioning of the precast slabs.

[0037] The above-mentioned prefabricated tunnel grout-stopping wall can be constructed according to the following steps: First, pour and construct the base 1. Then, weld and fix the front limiting plate 302 and the arched protective plate 301 together and place them on the base 1. Next, fix the front limiting plate 302 and the arched protective plate 301 to the surrounding soil and rock layers using hollow grouting anchor rods. Then, install the precast plate 201 from left to right. Next, install the limiting plate 303 with bolts. Then, grout through the first grouting hole 303a on the rear limiting plate 303 to form the arch protection layer 304. Next, fix the reinforcing beam. Finally, grout into the soil and rock layer in front of the excavation face through the second grouting hole 201c on the precast plate 201. The entire construction process is convenient and efficient.

[0038] Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solutions of the present invention without departing from the spirit and scope of the present invention, and all such modifications or substitutions should be covered within the scope of the claims of the present invention.

Claims

1. A prefabricated tunnel grout-stopping wall, characterized in that: It includes a base (1), a grout-stopping wall body (2), and a limiting component (3) for limiting and fixing the grout-stopping wall body (2). The base (1) is fixed in the rock and soil layer (4) at the bottom of the tunnel. The grout-stopping wall body (2) is formed by sealing and connecting multiple precast plates (201) and supported on the base (1). The limiting component (3) includes an arched guard plate (301) supported on a base (1), a front limiting plate (302) and a rear limiting plate (303) respectively parallel and conformally arranged on the front and rear sides of the arched guard plate (301), the front limiting plate (302) being fixedly connected to the arched guard plate (301), and the rear limiting plate (303) being detachably connected to the front limiting plate (302). An arch protection layer (304) is formed between the front limiting plate (302) and the rear limiting plate (303) on the upper side of the arched guard plate (301), and a limiting groove (305) for fixing and limiting multiple precast slabs (201) is formed between the front limiting plate (302) and the rear limiting plate (303) on the lower side of the arched guard plate (301). It also includes multiple sets of front fixed anchor bolts (5) and multiple sets of lateral fixed anchor bolts (6). The front fixed anchor bolts (5) fix the front limiting plate (302) in the soil and rock layer (4) in front of the tunnel excavation face, and the lateral fixed anchor bolts (6) fix the arched protective plate (301) in the soil and rock layer (4) on the side of the tunnel. The multiple precast slabs (201) are seamlessly spliced ​​sequentially along the width of the tunnel, and matching splicing staggers (201a) are provided at the splicing points of two adjacent precast slabs (201). The lower edge of the front limiting plate (302) extends inward to form a plurality of protrusions (302a) that abut against the rear limiting plate (303), and each of the plurality of protrusions (302a) is provided with a threaded hole. The lower edge of the rear limiting plate (303) is provided with multiple bolt holes (303b) corresponding to multiple protrusions (302a), and the rear limiting plate (303) and the front limiting plate (302) are fixed by bolts; The top of each of the multiple precast slabs (201) has a clearance hole (201b) for avoiding the protrusions (302a) at a position corresponding to the multiple protrusions (302a); Each of the precast slabs (201) is pre-set with a second grouting hole (201c) for grouting the soil and rock layer in front of the tunnel excavation face.

2. The prefabricated tunnel grout-stopping wall according to claim 1, characterized in that: The multiple sets of front fixed anchor rods (5) are all hollow grouting anchor rods, and are evenly distributed along the upper edge of the front limiting plate (302).

3. The prefabricated tunnel grout-stopping wall according to claim 2, characterized in that: The multiple sets of lateral fixed anchors (6) are hollow grouting anchors and are evenly distributed along the circumference of the arched protective plate (301).

4. The prefabricated tunnel grout-stopping wall according to claim 1, characterized in that: The top of the rear limiting plate (303) is pre-set with a plurality of first grouting holes (303a) for grouting into the arch protection layer (304).

5. The prefabricated tunnel grout-stopping wall according to claim 1, characterized in that: It also includes a reinforcement component, which includes multiple sets of reinforcement beams (7) fixed to both sides of the rear limiting plate (303) along the tunnel width direction.

6. The prefabricated tunnel grout-stopping wall according to claim 5, characterized in that: The reinforcing beam (7) is an I-beam, and the I-beam extends protruding towards the side of the precast slab (201) to form a limiting part (701) that abuts against the precast slab (201).

7. The prefabricated tunnel grout-stopping wall according to claim 1, characterized in that: The base (1) has multiple pre-set guide platforms (101) spaced apart along the tunnel width direction at its top, and the bottom of the multiple precast slabs (201) is provided with guide bosses (201d) that match the guide platforms (101) respectively.

Citation Information

Patent Citations

  • Fabricated green ecological retaining wall and construction method thereof

    CN112726644A

  • Construction method for mud and water burst of tunnel

    CN113404517A

  • Novel tunnel curtain grouting structure

    CN215057463U

  • Precast panel for tunnel lining and installation method thereof

    KR1019990003296A