一种钢板桩围堰改建加固为钢筋混凝土围堰的结构和施工方法
By installing internal and external support structures on the sheet pile cofferdam and pouring concrete, the sheet pile cofferdam was converted into a reinforced concrete cofferdam, which solved the structural corrosion problem caused by exceeding its service life, realized an economical and efficient conversion method, and reduced the impact on the water area.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- CHINA YANGTZE POWER
- Filing Date
- 2023-09-28
- Publication Date
- 2026-07-17
AI Technical Summary
The extended service life of the sheet pile cofferdam has led to accelerated corrosion of the structure, which has severely weakened its overall strength and stability, posing a risk of collapse. The existing demolition and reconstruction plan involves a large amount of work and has a significant impact on the water area.
By setting up internal support structures, external support structures, and circumferential support I-beams on the sheet pile cofferdam, and combining this with concrete pouring, the sheet pile cofferdam is rebuilt into a reinforced concrete cofferdam, forming a permanent structure.
This method enables the economical and efficient conversion of sheet pile cofferdams into reinforced concrete cofferdams without increasing the cofferdam area or occupying water areas, while maintaining structural stability and reducing the impact on the aquatic ecological environment.
Smart Images

Figure CN117364809B_ABST