Construction method for rapid construction of air pushing of full-negative ring pipe segment shield through air shaft by combination of permanent and temporary guide platforms
By employing a method of using a permanent and temporary combined guide platform with full negative ring segments to push the shield tunneling machine through the ventilation shaft in water-rich sandy areas, the problems of receiving and launching the shield machine in the construction of the ventilation shaft in the section were solved, achieving rapid and safe construction results.
Patent Information
- Application Number
- CN202311384345.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-24
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-10-24
AI Technical Summary
Existing technologies pose risks when tunnel boring machines (TBMs) pass through ventilation shafts in water-rich sandy areas, especially in terms of difficulties in receiving and launching the TBM, and there is a lack of systematic and rapid construction methods.
The method of using a combination of permanent and temporary guide platforms and full negative ring segments for shield tunneling through ventilation shafts involves the construction of retaining piles for the ventilation shafts, sand jet grouting reinforcement, and dewatering well construction. By assembling the entire negative ring segments to provide reaction force, the advancement is gradually controlled, enhancing the integrity and frictional resistance of the segments and reducing compression deformation.
It adapts to the geological conditions of water-rich sandy layers, improves the safety and efficiency of construction, reduces the need for reaction facilities, and enables rapid construction.
Smart Images

Figure CN117365503B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of subway construction technology, specifically relating to a rapid construction method for a shield tunneling machine with a permanent and temporary combined guide platform and full negative ring segments, which is pushed through a ventilation shaft. Background Technology
[0002] The tunnel sections are often quite long, and an intermediate ventilation shaft is usually installed. Due to structural and other limitations, pushing the tunnel boring machine (TBM) to the ventilation shaft may not allow for normal receiving and launching operations. It is necessary to receive the TBM, then push it empty through the ventilation shaft before launching it a second time. In water-rich sandy areas, the receiving and launching of the TBM poses significant risks and is a major challenge in construction management.
[0003] Currently, hydraulic jacks or semi-ring segments are commonly used for air-pushing construction in China. Although there is some research on air-pushing shield tunneling using concrete guide platforms, a systematic method has not yet been developed for rapid construction in water-rich sandy areas and for shield tunneling through ventilation shafts.
[0004] For example, Chinese invention patent application CN201910949266.3 discloses a construction method for a tunnel boring machine (TBM) to pass through a curved ventilation shaft: the tunnel axis section where the ventilation shaft is located is curved, and the method includes the following steps:
[0005] Step 1: Construction of Concrete Guide Platform
[0006] The construction of the concrete guide platform is completed before the tunnel boring machine reaches the curved ventilation shaft. The concrete guide platform includes a "︺" shaped groove, and the symmetrical center line of the "︺" shaped groove is consistent with the tunnel axis.
[0007] The first stage involves surveying and setting out, using online measurement to accurately locate the concrete guide platform and strictly control the alignment of its axis with the tunnel axis.
[0008] The second stage involves tying the reinforcing steel structure. The outline of the reinforcing steel structure is consistent with the design outline of the concrete guide platform. The reinforcing steel is tied according to the position of the measurement and layout, and stirrups are welded between the upper and lower layers of reinforcing steel.
[0009] In the third stage, the guide rail embedded parts are installed. Several guide rail embedded parts are welded on the two inclined surfaces of the "︺" shaped groove of the steel structure. The welding position of the guide rail embedded parts is located by a total station.
[0010] The fourth stage is template installation;
[0011] The fifth stage involves pouring concrete, with the concrete cover thickness for reinforced structures not less than 5cm.
[0012] In the sixth stage, the guide rails are installed. The guide rails are welded to the embedded parts of the guide rails by small pressure plates. The guide rails are connected by fishplates. The height of the guide rails at the receiving end is lower than the height of the guide rails at the launching end. The height of the guide rails at the launching end is the design elevation.
[0013] Step Two: The first stage of tunnel boring machine (TBM) advancement into the curved ventilation shaft. When the TBM is about to enter the curved ventilation shaft, adjust the cutterhead to avoid contact with the concrete guide platform, adjust the jacks of the TBM, and adjust the attitude of the TBM. When installing the tunnel segments, set the pressure of the advancing jacks to the assembly pressure. After each tunnel segment is installed, first use manual labor to pre-tighten the connecting bolts of the tunnel segments, and then use a high-speed pneumatic wrench to tighten the bolts.
[0014] The second stage involves the concrete guide platform on the tunnel boring machine.
[0015] Step 3: Tunnel boring machine passes through curved ventilation shaft
[0016] In the first stage, a steel ring is installed at each of the two portals of the curved ventilation shaft, and the starting negative ring segment penetrates the side wall of the starting end by 400-800mm.
[0017] In the second stage, after the front body of the tunnel boring machine (TBM) detaches from the portal steel ring and enters the curved ventilation shaft, a 30mm thick steel plate is welded to the bottom of the front body, a 35mm thick steel plate is welded to the bottom of the middle body, and a 40mm thick steel plate is welded to the bottom of the tail section. The reverse thrust provided by the negative ring segments assembled at the tail section is used to allow the TBM to pass through the curved ventilation shaft as a whole. After the negative ring segments detach from the tail section, the waist of the negative ring segments is fixed to the side wall or column of the curved ventilation shaft by H-beams to prevent lateral displacement of the negative ring segments.
[0018] Although the aforementioned existing technology is also a construction method for the tunnel boring machine to pass through the ventilation shaft as a whole, the following technical problems exist in the actual construction process:
[0019] Without addressing the geological conditions of the curved ventilation shaft, it is not suitable for construction in water-rich sandy layers.
[0020] Based on the aforementioned technical problems existing in the prior art, this invention proposes a rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling machine to pass through the ventilation shaft. Summary of the Invention
[0021] The purpose of this invention is to address the shortcomings of existing technologies by providing a rapid construction method for a shield tunneling machine with a permanent and temporary combined guide platform and full negative ring segments to pass through the ventilation shaft.
[0022] This invention provides a rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling machine to pass through a ventilation shaft using air thrust, employing the following technical solution:
[0023] A rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling machine to pass through a ventilation shaft via air thrust, comprising:
[0024] Step 1: Construction of retaining piles for the ventilation shaft in the section;
[0025] Step 2: Shield tunneling reception and secondary launching construction at both ends of the ventilation shaft; sand layer jet grouting reinforcement in the ventilation shaft area; and dewatering wells constructed in the ventilation shaft area.
[0026] Step 3: Excavate the foundation pit of the ventilation shaft in the section, and construct the bottom slab, side walls and top slab of the main structure of the ventilation shaft in the section;
[0027] Step 4: Determine the elevation and structure of the guide platform;
[0028] Step 5: Construction of the guide platform. Obtain data on the bottom slab structure of the ventilation shaft, the center position of the guide platform, the location of the rebar, and the top surface position of the guide platform; plant two rows of rebar on each side of the guide platform and weld the rebar firmly; embed the pre-embedded rebar for tensioning and anchoring the segment steel wire rope; embed the pre-embedded steel plate for positioning the rail and weld the pre-embedded rebar to the pre-embedded steel plate; install the guide platform formwork and reinforce it; pour, cure, and remove the formwork for concrete; fix the rail to the pre-embedded steel plate.
[0029] Step 6: Construction of the receiving end portal;
[0030] Step 7: The tunnel boring machine is pushed onto the guide platform without air.
[0031] Step 8: The tunnel boring machine (TBM) receiving and ventilation shaft are both excavated using assembled full-ring negative ring segments; when the shield tail detaches from the segments, wooden wedges are used to fill the gaps between the segments and the concrete guide platform; after the segments are assembled, the connecting bolts are tightened again, and steel wire ropes are used to tighten the segments in the middle of the outer ring surface to enhance the integrity of the segments; sandbags are filled between the concrete guide platform and the shield body to increase frictional resistance and reduce the squeezing deformation between segments at the start of the tunneling.
[0032] Step 9: Reinforce the segments by supporting the bottom, sides, and top of the segments, fixing adjacent ring segments, and fixing the entire ring segment.
[0033] Step 10, Construction of the initial tunnel portal;
[0034] Step 11, empty thrust assembly of tunnel segments, secondary launch. The reaction force used by the tunnel boring machine for secondary launch from the ventilation shaft is provided by the complete ring negative ring tunnel segments assembled in the ventilation shaft. The total thrust during the initial propulsion stage is controlled at 800T, and the thrust gradually increases as the shield enters the soil.
[0035] Step 12: The tunnel boring machine (TBM) starts and breaks through the tunnel for the second time. The negative ring segments and the steel rails on the concrete guide platform are removed. The concrete guide platform and the bottom slab are backfilled with concrete and poured into one piece, which is then used as a permanent structure.
[0036] Furthermore, in step 4, the elevation of the guide platform is determined by taking into account the weight of the tunnel boring machine and the forces generated during the empty thrust and tunneling process, and by combining the design elevations of the receiving end and the launching end.
[0037] Furthermore, in step 4, the concrete strength of the guide platform is C40, the guide platform section is inclined, and the steel rails are installed vertically on the trapezoidal inclined surface, with the two steel rails forming a 50° angle to facilitate the movement of the tunnel boring machine.
[0038] Furthermore, in step 4, the guide platform has an internal steel reinforcement frame: vertical steel bars Φ20@200mm are embedded in the structural base plate, longitudinal steel bars Φ18 are arranged along the entire length, and the stirrups are Φ10 plain round steel bars.
[0039] Furthermore, step 6 includes:
[0040] Step 6.1: Receive the scaffolding erection and erect a double-row platform using φ48 steel pipes;
[0041] Step 6.2: Install the curtain and flap of the receiving hole. The assembly sequence is as follows: first install the curtain rubber sheet, then install the circular plate, and finally install the fan-shaped plate, proceeding from top to bottom. Flip the fan-shaped plate into the hole.
[0042] Step 6.3: Remove the receiving tunnel entrance by manual wet operation. The removal sequence is as follows: vertical segmentation and horizontal staggered pile method. First, remove the concrete and steel bars on the side closest to the main structure. Then, remove the concrete until the steel bars of the retaining structure on the soil-facing side are exposed. Cut the steel bars when the tunnel boring machine arrives.
[0043] Step 6.4: When the shield machine cut is 500mm away from the sealing gate, stop the shield advance, empty the soil in the balance chamber to reduce the balance pressure on the front of the cut, and resume the advance after the remaining steel bars have been cut.
[0044] Furthermore, in step 7, when the tunnel boring machine enters the station, the cutterhead is stopped from rotating, a layer of grease is applied to the rubber curtain, and the portal fan-shaped pressure plate is adjusted to facilitate the exit of the cutterhead from the tunnel.
[0045] Furthermore, in step 7, during the 5th to 6th ring before the tunnel boring machine (TBM) breaks through, the thrust, speed, and cutterhead rotation speed of the TBM are reduced, with the thrust maintained at 700 to 800t and the tunneling speed controlled at 5mm to 10mm / min.
[0046] Furthermore, step 8 includes: re-measuring the plane position and elevation of the concrete guide platform before the shield passes through the station, testing the concrete strength, and arranging monitoring points on the circumferential and longitudinal horizontal sections of the tunnel segments to monitor the attitude of the shield machine.
[0047] Furthermore, in step 11, when each ring segment protrudes beyond half the width of the shield tail, wedge-shaped square timber is inserted at the bottom of the segment to fill the gap between the ring and the guide platform.
[0048] Furthermore, in step 11, I-beam anti-torsion devices are welded onto the shield machine shell on both sides of the starting guide rail. One is welded on each side of the shield machine every 2.0m. When the anti-torsion device is close to the tunnel entrance seal, the I-beam anti-torsion device is cut off.
[0049] The beneficial effects of this invention are:
[0050] 1. The method for rapid construction of a permanent and temporary combined guide platform full negative ring segment shield tunneling through a ventilation shaft, as described in this invention, including the construction of retaining piles for the ventilation shaft, the sand layer jet grouting reinforcement construction, and the dewatering well construction, can adapt to the geological conditions of water-rich sand layers.
[0051] 2. The method for rapid construction of shield tunneling through ventilation shafts using permanent and temporary combined guide platforms and full negative ring segments, as described in this invention, provides the reaction force used for secondary launch by the complete negative ring segments assembled in the ventilation shaft, eliminating the need to construct reaction force facilities again and thus accelerating construction efficiency. Attached Figure Description
[0052] Figure 1 This is a flowchart illustrating the rapid construction method of the shield tunneling machine with permanent and temporary combined guide platform and full negative ring segment through the ventilation shaft in an embodiment of the present invention.
[0053] Figure 2 This is a schematic diagram of the cross-sectional arrangement of the guide platform in an embodiment of the present invention. Detailed Implementation
[0054] To better understand the above-mentioned objectives, features and advantages of the present invention, the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be noted that, unless otherwise specified, the embodiments and features in the embodiments of this application can be combined with each other.
[0055] Example
[0056] This embodiment proposes a rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling machine to pass through a ventilation shaft, such as... Figure 1 As shown, the rapid construction method for the full negative ring segment shield tunneling of the permanent and temporary combined guide platform through the ventilation shaft includes:
[0057] Step 1: Construction of retaining piles for the ventilation shaft in the section;
[0058] Step 2: Shield tunneling reception and secondary launching construction at both ends of the ventilation shaft; sand layer jet grouting reinforcement in the ventilation shaft area; and dewatering wells constructed in the ventilation shaft area.
[0059] Step 3: Excavate the foundation pit of the ventilation shaft in the section, and construct the bottom slab, side walls and top slab of the main structure of the ventilation shaft in the section;
[0060] Step 4: Determine the elevation and structure of the guide platform;
[0061] Step 5: Construction of the guide platform. Obtain data on the bottom slab structure of the ventilation shaft, the center position of the guide platform, the location of the rebar, and the top surface position of the guide platform; plant two rows of rebar on each side of the guide platform and weld the rebar firmly; embed the pre-embedded rebar for tensioning and anchoring the segment steel wire rope; embed the pre-embedded steel plate for positioning the rail and weld the pre-embedded rebar to the pre-embedded steel plate; install the guide platform formwork and reinforce it; pour, cure, and remove the formwork for concrete; fix the rail to the pre-embedded steel plate.
[0062] Step 6: Construction of the receiving end portal;
[0063] Step 7: The tunnel boring machine is pushed onto the guide platform without air.
[0064] Step 8: The tunnel boring machine (TBM) receiving and ventilation shaft are both excavated using assembled full-ring negative ring segments; when the shield tail detaches from the segments, wooden wedges are used to fill the gaps between the segments and the concrete guide platform; after the segments are assembled, the connecting bolts are tightened again, and steel wire ropes are used to tighten the segments in the middle of the outer ring surface to enhance the integrity of the segments; sandbags are filled between the concrete guide platform and the shield body to increase frictional resistance and reduce the squeezing deformation between segments at the start of the tunneling.
[0065] Step 9: Reinforce the segments by supporting the bottom, sides, and top of the segments, fixing adjacent ring segments, and fixing the entire ring segment.
[0066] Step 10, Construction of the initial tunnel portal;
[0067] Step 11, Empty thrust assembly of tunnel segments, secondary launch. The reaction force used by the tunnel boring machine for secondary launch from the ventilation shaft is provided by the complete ring negative ring tunnel segments assembled in the ventilation shaft. The total thrust during the initial propulsion stage is controlled at 800T, and the thrust gradually increases as the shield enters the soil.
[0068] Step 12: The tunnel boring machine (TBM) starts and breaks through the tunnel for the second time. The negative ring segments and the steel rails on the concrete guide platform are removed. The concrete guide platform and the bottom slab are backfilled with concrete and poured into one piece, which is then used as a permanent structure.
[0069] As a specific implementation method, in step 4:
[0070] The elevation of the guide platform should take into account factors including at least the weight of the tunnel boring machine and the forces generated during the empty thrust and tunneling process, and should be determined in conjunction with the design elevations of the receiving end and the launching end.
[0071] For example, the guide platform is made of C40 concrete, and the cross-section of the guide platform is trapezoidal. The steel rails are installed vertically on the trapezoidal inclined surface, and the two steel rails form a 50° angle to facilitate the movement of the tunnel boring machine.
[0072] The guide platform has an internal steel reinforcement cage, for example, vertical steel bars Φ20@200mm, anchored to the structural base slab, longitudinal steel bars Φ18 arranged along the entire length, and stirrups using Φ10 plain round steel bars, such as... Figure 2 As shown.
[0073] As a specific implementation method, in step 5:
[0074] The purpose of the pre-embedded steel bars is to tighten and anchor the steel wire ropes of the tunnel segment. For example, the pre-embedded steel bars are Φ18, which are inserted 10cm into the steel bar skeleton of the guide platform and extend 10cm out of the steel bar skeleton. The extended length is bent into the form of a hook after the overall construction of the guide platform is completed, so as to facilitate the connection of the steel wire ropes.
[0075] For example, the size of the embedded steel plate is 2mm*50cm*30cm, and the longitudinal spacing of the embedded steel plate is 50cm. When welding, it should be welded together with the embedded steel bar and the vertical Φ18 continuous steel bar. In specific implementation, positioning welding is performed first, the elevation is checked and then welded firmly. After all the embedded steel plates are welded, the elevation is measured again.
[0076] For example, the guide platform is poured in one go using C40 cement. The formwork is removed after 3 days, and the strength is tested after 14 days of curing.
[0077] The rails are installed vertically on the trapezoidal inclined surface of the guide platform. First, clean the surface of the embedded steel plate, then measure the center of the rail. The rails and the embedded steel plate are welded firmly without any gaps, and the joints between the rails are smooth.
[0078] After the guide rails are installed, the rail surface elevation is re-measured, and calculations are performed to compare the linearity of the tunnel boring machine during reception and launch to determine whether the requirements are met.
[0079] As a specific implementation method, in step 6:
[0080] When receiving scaffolding erection, for example, using φ48 steel pipes to erect a double-row platform with an area exceeding the opening area;
[0081] When installing the curtain and flap at the receiving tunnel entrance, the assembly sequence is curtain rubber sheet, circular sheet, and fan-shaped sheet, proceeding from top to bottom, with the fan-shaped sheet being flipped into the tunnel.
[0082] The receiving tunnel entrance was removed by manual wet operation. The removal sequence was as follows: vertical segmentation and horizontal staggered pile method. First, the concrete and steel bars on the side close to the main structure were removed. Then, the concrete was removed until the steel bars of the retaining structure on the soil-facing side were exposed. The steel bars were cut off when the tunnel boring machine arrived.
[0083] When the tunnel boring machine cut is 500mm from the sealing gate, stop the tunnel boring machine and empty the soil in the balance chamber as much as possible to reduce the balance pressure on the front of the cut to the lowest value. Continue the tunnel boring machine after the remaining steel bars have been cut.
[0084] As a specific implementation method, in step 7:
[0085] When the cutterhead is 10 rings away from the inner wall of the ventilation shaft structure, increase the number of measurements and adjust the vertical posture.
[0086] For the 5th to 6th rings before the tunnel is completed, reduce the thrust, speed and cutterhead speed of the tunnel boring machine, keep the thrust below 800t, and control the tunneling speed at 5mm to 10mm / min to avoid large disturbances.
[0087] The rail surface elevation of the receiving base shall be reduced by 20-30mm while still meeting the requirements of the track alignment.
[0088] When the tunnel boring machine enters the station, stop rotating the cutterhead, apply grease to the rubber curtain and adjust the portal fan-shaped pressure plate in time to allow the cutterhead to exit the tunnel smoothly.
[0089] As a specific implementation method, in step 8:
[0090] Both the tunnel boring machine receiving and ventilation shafts are excavated using assembled whole-ring negative ring segments;
[0091] When the shield tail detaches from the segment, promptly fill the gap between the segment and the concrete guide platform with wooden wedges.
[0092] After the tunnel segments are assembled, the connecting bolts are tightened in time, and the tunnel segments are pulled taut with steel wire rope in the middle of the outer ring surface to enhance the integrity of the tunnel segments.
[0093] Sandbags were filled between the concrete guide platform and the shield to increase frictional resistance and reduce the squeezing deformation between the segments at the start of launch.
[0094] Before the tunnel boring machine passes through the station, the plane position and elevation of the concrete guide platform are re-measured, and the concrete strength is tested.
[0095] Monitoring points are set up on the circumferential and longitudinal horizontal sections of the tunnel segments to monitor the attitude of the tunnel boring machine.
[0096] As a specific implementation method, in step 9:
[0097] Segment reinforcement includes bottom support, side support, top support, fixing between two ring segments, and whole-ring fixing. The support uses [18a channel steel. For example, the negative ring segment is reinforced with a total of 12 rings.
[0098] Install bottom support. After the segment detaches from the shield tail, for example, there is a 15cm gap between the guide rail and the segment. Place 4-6 wooden wedges in each ring to prevent the segment from sinking.
[0099] Construct side supports and set up diagonal supports in the ventilation shaft section. After the tunnel segment comes out of the shield tail, use steel sections and wooden wedges to fix the tunnel segment. Diagonal supports are set in each ring to prevent the tunnel segment from shifting to the sides.
[0100] To prevent the tunnel segments from floating, a [18a channel steel support is installed on the top of the tunnel segments. The channel steel supports the top of the ventilation shaft structure, so that when the tunnel boring machine moves forward in the ventilation shaft section, the lower reaction force is provided by the bottom three tunnel segments and the upper reaction force is provided by the top three tunnel segments.
[0101] For securing the two ring segments, tighten the bolts between the segments in a timely manner.
[0102] When the tunnel segment is halfway out of the shield tail, use steel wire rope to pull the segment circumferentially to prevent it from shifting upwards.
[0103] In a specific implementation method, step 11:
[0104] The advance speed is controlled at 10-20 mm / min, the horizontal attitude of the tunnel boring machine is controlled at ±20 mm, and the vertical attitude is controlled at +30 mm. The tunnel boring machine is launched by assembling the entire ring.
[0105] When each segment protrudes beyond half the width of the shield tail, wedge-shaped square timber should be promptly inserted into the bottom of the segment to fill the gap between the segment ring and the guide platform.
[0106] When the cutterhead enters the tunnel, adjust the distance between the fan-shaped plate and the shield shell to about 10mm. When the shield tail wire brush just enters the tunnel and exposes the tunnel segment, adjust the fan-shaped plate again so that it falls on the tunnel segment.
[0107] Weld I-beam anti-torsion devices onto the shield machine shell on both sides of the starting guide rail. Weld one on each side of the shield machine every 2.0m. When the anti-torsion device is close to the tunnel portal seal, cut off the anti-torsion device.
[0108] After the shield tail enters the soil, grouting is carried out to prevent the first few rings of segments at the tunnel entrance from sinking.
[0109] This invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of the invention. Various changes and modifications can be made to the invention without departing from its spirit and scope, and all such changes and modifications fall within the scope of the invention as claimed. The scope of protection of this invention is defined by the appended claims.
Claims
1. A rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling machine to pass through a ventilation shaft, characterized in that, include: Step 1: Construction of retaining piles for the ventilation shaft in the section; Step 2: Shield tunneling reception and secondary launching construction at both ends of the ventilation shaft; sand layer jet grouting reinforcement in the ventilation shaft area; and dewatering wells constructed in the ventilation shaft area. Step 3: Excavate the foundation pit of the ventilation shaft in the section, and construct the bottom slab, side walls and top slab of the main structure of the ventilation shaft in the section; Step 4: Determine the elevation and structure of the guide platform. The elevation of the guide platform is determined by taking into account the weight of the tunnel boring machine and the forces generated during the empty thrust and tunneling process, and by combining the design elevations of the receiving end and the launching end. The concrete strength of the guide platform is C40. The guide platform has an inclined cross section, and the steel rails are installed vertically on the trapezoidal inclined surface. The two steel rails form a 50° angle to facilitate the movement of the tunnel boring machine. The guide platform has an internal steel reinforcement skeleton: vertical steel bars Φ20@200mm, which are embedded in the structural base plate, longitudinal steel bars Φ18 are arranged along the entire length, and the stirrups are Φ10 plain round steel bars. Step 5: Construction of the guide platform. Obtain data on the bottom slab structure of the ventilation shaft, the center position of the guide platform, the location of the rebar, and the top surface position of the guide platform; plant two rows of rebar on each side of the guide platform and weld the rebar firmly; embed the pre-embedded rebar for tensioning and anchoring the segment steel wire rope; embed the pre-embedded steel plate for positioning the rail and weld the pre-embedded rebar to the pre-embedded steel plate; install the guide platform formwork and reinforce it; pour, cure, and remove the formwork for concrete; fix the rail to the pre-embedded steel plate. Step 6: Construction of the receiving end portal; Step 7: The tunnel boring machine is pushed onto the guide platform without air. Step 8: The tunnel boring machine (TBM) receiving and ventilation shaft are both excavated using assembled full-ring negative ring segments; when the shield tail detaches from the segments, wooden wedges are used to fill the gaps between the segments and the concrete guide platform; after the segments are assembled, the connecting bolts are tightened again, and steel wire ropes are used to tighten the segments in the middle of the outer ring surface; sandbags are filled between the concrete guide platform and the shield body to increase frictional resistance and reduce the squeezing deformation between segments at the start of the tunnel. Step 9: Reinforce the segments by supporting the bottom, sides, and top of the segments, fixing adjacent ring segments, and fixing the entire ring segment. Install bottom support. After the segment detaches from the shield tail, there is a 15cm gap between the guide rail and the segment. Place 4-6 wooden wedges in each ring to prevent the segment from sinking. Construct side supports and set up diagonal supports in the ventilation shaft section. After the tunnel segment comes out of the shield tail, use steel sections and wooden wedges to fix the tunnel segment. Diagonal supports are set in each ring to prevent the tunnel segment from shifting to the sides. To prevent the tunnel segments from floating, a [18a channel steel support is installed on the top of the tunnel segments. The channel steel supports the top of the ventilation shaft structure, so that when the tunnel boring machine moves forward in the ventilation shaft section, the lower reaction force is provided by the bottom three tunnel segments and the upper reaction force is provided by the top three tunnel segments. For securing the two ring segments, tighten the bolts between the segments in a timely manner. When the tunnel segment is halfway out of the shield tail, use steel wire rope to pull the tunnel segment circumferentially to prevent the tunnel segment from shifting upwards; Step 10, Construction of the initial tunnel portal; Step 11, Empty thrust assembly of tunnel segments, secondary launch, wherein the reaction force used by the tunnel boring machine for secondary launch from the ventilation shaft is provided by the complete ring negative ring tunnel segments assembled in the ventilation shaft; Step 12: The tunnel boring machine (TBM) starts and breaks through the tunnel for the second time. The negative ring segment and the steel rail on the concrete guide platform are removed. The concrete guide platform and the bottom slab are backfilled with concrete and poured into one piece, which is used as a permanent structure.
2. The rapid construction method for shield tunneling through ventilation shafts using a permanent and temporary combined guide platform with full negative ring segments as described in claim 1, characterized in that... Step 6 includes: Step 6.1: Receive the scaffolding erection and erect a double-row platform using φ48 steel pipes; Step 6.2: Install the curtain and flap of the receiving hole. The assembly sequence is as follows: first install the curtain rubber sheet, then install the circular plate, and finally install the fan-shaped plate, proceeding from top to bottom. Flip the fan-shaped plate into the hole. Step 6.3: Remove the receiving tunnel entrance by manual wet operation. The removal sequence is as follows: vertical segmentation and horizontal staggered pile method. First, remove the concrete and steel bars on the side closest to the main structure. Then, remove the concrete until the steel bars of the retaining structure on the soil-facing side are exposed. Cut the steel bars when the tunnel boring machine arrives. Step 6.4: When the shield machine cut is 500mm away from the sealing gate, stop the shield advance, empty the soil in the balance chamber to reduce the balance pressure on the front of the cut, and resume the advance after the remaining steel bars have been cut.
3. The rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling through a ventilation shaft according to claim 1, characterized in that, In step 7, when the tunnel boring machine enters the station, stop rotating the cutterhead, apply a layer of grease to the rubber curtain and adjust the portal fan-shaped pressure plate so that the cutterhead can exit the tunnel.
4. The rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling through a ventilation shaft according to claim 1 or 3, characterized in that, In step 7, during the 5th to 6th ring before the tunnel boring machine (TBM) breaks through, the thrust, speed, and cutterhead rotation speed of the TBM are reduced. The thrust is maintained at 700 to 800 t, and the tunneling speed is controlled at 5 mm to 10 mm / min.
5. The rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling through a ventilation shaft according to claim 1, characterized in that, Step 8 includes: re-measuring the plane position and elevation of the concrete guide platform before the shield passes through the station, testing the concrete strength, and arranging monitoring points on the circumferential and longitudinal horizontal sections of the tunnel segments to monitor the attitude of the shield machine.
6. The rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling through a ventilation shaft according to claim 1, characterized in that, In step 11, when each ring segment protrudes beyond half the width of the shield tail, wedge-shaped square timber is inserted at the bottom of the segment to fill the gap between the ring and the guide platform.
7. The rapid construction method for a permanent and temporary combined guide platform full negative ring segment shield tunneling through a ventilation shaft according to claim 1 or 6, characterized in that, In step 11, I-beam anti-torsion devices are welded onto the shield machine shell on both sides of the starting guide rail. One is welded on each side of the shield machine every 2.0m. When the anti-torsion device is close to the tunnel portal seal, the I-beam anti-torsion device is cut off.
Citation Information
Patent Citations
Construction method of integrally pushing empty shield machine to pass through curved air shaft
CN110617073A
Safety construction method for digging shield shaft and vertical shaft deep foundation pit
CN110820756A