A shield tunneling machine stuck construction method suitable for soft upper and hard lower bedrock strata
By employing steps such as shield stabilizers supporting the rock face, water injection and pressurization within the soil chamber, shield shell cutting, and hydraulic rock splitters breaking through the rock strata, the problem of the tunnel boring machine (TBM) getting stuck in bedrock strata with soft upper layers and hard lower layers was solved, enabling the TBM to quickly and safely get out of trouble and resume tunneling.
Patent Information
- Application Number
- CN202311550624.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-20
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2043-11-20
AI Technical Summary
Existing technologies lack effective methods for extricating tunnel boring machines (TBMs) from difficult terrain, especially in soft-topped, hard-bottomed bedrock formations. TBMs are prone to getting stuck due to the complexity of the geological structure and the wear and tear on the cutting tools caused by the bedrock.
Through the steps of initial escape attempt, preparation work, secondary escape attempt, excavation expansion and restoration of normal operation, including shield stabilizer supporting the rock surface, water injection and pressurization in the soil chamber, shield shell cutting, water drill and hydraulic splitter breaking the rock layer, active articulation pullback and pressurization of cutterhead, etc., the gap between the shield machine shell and the rock layer is ensured to be ≥5mm.
This enabled the tunnel boring machine to extricate itself from difficult situations quickly and efficiently, reducing construction risks and costs, shortening the extrication cycle, and improving construction safety and efficiency.
Smart Images

Figure CN117365508B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel boring machine (TBM) construction technology, and in particular to a method for TBMs to escape from difficult conditions in bedrock strata with soft upper layers and hard lower layers. Background Technology
[0002] With the acceleration of urbanization and the continuous increase in urban population in my country, urban traffic pressure is becoming increasingly apparent. To alleviate urban traffic pressure, underground transportation is becoming increasingly popular. Subway transportation, a green project, has been gradually promoted in major cities.
[0003] As the most advanced construction method in underground engineering, the shield tunneling method boasts advantages such as fast tunneling speed, high quality, minimal impact on the surrounding environment, and relatively high construction safety. However, due to the complexity of geological conditions during shield tunneling and factors such as shield machine malfunctions and improper operation, shield machines often become trapped underground during subway construction. This is especially true when encountering soft-overhead, hard-underlying bedrock strata. The complex geological structure causes uneven stress on the shield, and bedrock can easily lead to tool wear and other problems, making it even more prone to becoming trapped. Currently, however, there is no systematic and effective method for extricating shield machines from trapped conditions in soft-overhead, hard-underlying bedrock strata.
[0004] Therefore, there is an urgent need to develop a method for tunnel boring machines to escape from difficult terrain in soft-topped, hard-bottomed bedrock formations. Summary of the Invention
[0005] The technical problem to be solved by the present invention is to provide a method for shield tunneling machine extrication construction applicable to bedrock strata with soft upper layers and hard lower layers.
[0006] The present invention solves the above-mentioned technical problems by adopting the following technical solutions: A method for extricating tunnel boring machines (TBMs) from difficult terrain, suitable for soft upper layers and hard lower layers in bedrock strata, includes the following steps: S1, Initial attempt to escape The shield stabilizer supports the rock face and retracts the active articulation cylinder, causing the front shield and cutterhead to retreat; at the same time, water is pumped into the soil chamber to increase the back-pushing force. If this step fails to extricate you, continue with the following steps; S2. Preparations Preparations for the secondary extrication of the tunnel boring machine from its predicament; S3, Second attempt to escape First, the shield shell inside the earth chamber is partially cut off; then, water drills and hydraulic splitters are used to break up the rock layers that were not excavated, ensuring that the gap between the shield machine shell and the rock layers is ≥5mm; after the rock layers were broken up, the shield body was pulled back by actively hinged pullback and pressing the cutterhead. S4, Expansion Excavation After the tunnel boring machine retracts into position, the widening excavation work will commence; S5, Resume normal operation The tunnel boring machine has resumed normal tunneling operations.
[0007] As one of the preferred embodiments of the present invention, in step S1, the specific operation of the shield stabilizer supporting the rock surface and the retractable active articulation cylinder is as follows: a. Extend the stabilizer support plates on both sides of the front shield to the rock surface to fix the front shield stationary; b. Extend the active articulation stroke to 90~100mm to make the shield tail retract; c. Retract the stabilizer support plates on both sides of the front shield and extend the stabilizer support plates on both sides of the middle shield to the rock surface; d. Use the retractable articulation cylinder to make the front shield and cutterhead retract to pull back the shield body.
[0008] As one of the preferred embodiments of the present invention, the specific operation of water injection and pressurization in the soil chamber in step S1 is as follows: secondary grouting and sealing is performed at the ten rings behind the shield tail, and the pores behind the pipe segment wall are filled with grout to achieve the purpose of water injection and pressurization.
[0009] As one of the preferred embodiments of the present invention, the preparatory work in step S2 includes: setting up a working platform, preparing the tools used for construction, and detecting the gas inside the chamber.
[0010] The construction of the working platform involves using Φ28 steel bars as the load-bearing frame, which are welded and fixed to the soil silo wall and cutter head. The specific installation height of the platform is determined on-site based on the specific working conditions inside the silo. Walkway slabs are laid and welded and fixed, and the platform must be firmly welded.
[0011] The tools used in the construction include: 2 sets of gas cutting equipment, 2 sets of carbon arc gouging machines, 2 sets of MIG welding machines, 2 water drills, 1 electric hydraulic splitting gun, 2 pneumatic picks, and 4 3t hand-operated chains.
[0012] Gas detection inside the chamber: The gas detection inside the chamber is qualified to ensure safe operation of personnel in a confined space. Continuous monitoring is carried out during the construction process.
[0013] As one of the preferred embodiments of the present invention, in step S3, the specific cutting scheme is as follows: cut off 6 sections of the upper half of the shield shell of the shield tunnel cutting ring, with a cutting area of 1m (circumferential). 0.5m (longitudinal), with 1m intervals between cutting positions, evenly distributed along the upper half ring, and the top 12 o'clock position reserved for not being cut; before cutting, after determining the location of the first cutting area on site, weld two lifting lugs on the selected cutting area to suspend the upper and lower guide chains. The two guide chains are respectively suspended above the cutting position and on one side of the earthen silo wall for hoisting after the steel plate is cut.
[0014] As one of the preferred methods of the present invention, regarding the hoisting of the steel plate after it is cut off: due to the small operating space, which conflicts with the subsequent chiseling work, two lifting lugs and a horizontal steel pipe support are welded on site to the inner wall of the cut ring after the steel plate is cut off; after the demolition is completed, a lifting lug is added above the steel plate, and a hoist is used to move it in conjunction with the steel section. After it is in place, four pieces of seven-shaped steel are welded and fixed.
[0015] As one of the preferred embodiments of the present invention, after the shield shell is cut off, check the shield jamming situation at the edge of the cut area; if the shield body is still closely attached to the rock layer, continue to cut the shield shell to both sides in the circumferential direction until there is a gap of ≥5mm between the shield shell and the rock layer; after the shield shell is cut off in place in the soil chamber, use a water drill to drill radial holes in the rock layer of the area where the shield shell has been cut off at a hole spacing of 200×200mm, with a hole diameter of Φ42mm and a drilling depth of ≥20cm.
[0016] As one of the preferred embodiments of the present invention, in step S3, the under-excavation and breaking of the rock strata adopts frontal breaking: first, a water drill is used to take 1-2 rows of core samples from the bottom, with a core depth ≥20cm, and then a pneumatic pick is used to chisel away layer by layer along the core sampling gap. If a hard area is encountered, the core sampling step is repeated; at the same time, horizontal and vertical breaking are carried out: after the frontal breaking is completed, the unopened hole wall is broken by extension; horizontal breaking is mainly done by pneumatic pick chisel, supplemented by oblique core sampling; vertical breaking is mainly done by dense vertical core sampling, supplemented by electric drill chisel.
[0017] As one of the preferred embodiments of the present invention, the specific operation of the active hinge pull-back in step S3 is as follows: a. Extend the stabilizer support plates on both sides of the front shield; b. Extend the active hinge to 100mm; c. Retract the front shield stabilizer and extend the middle shield stabilizer; d. Retract the hinge cylinder to pull back the shield body. The specific operation of pressurizing and retracting the cutter head is as follows: a. Retract the front and middle shield stabilizers; b. Push the propulsion cylinder to the tube segment; c. Close the chamber door and pressurize to 4.5 bar; d. Control the retraction of the propulsion cylinder; e. Use air pressure to retract the cutter head.
[0018] As one of the preferred embodiments of the present invention, in step S4, after the shield of the tunnel boring machine retreats 60 cm, it was originally planned to chisel away the under-excavated rock mass in the cut gap and carry out enlargement excavation. However, due to the limited cut position and high rock strength, the efficiency was low and the tunnel boring machine eventually retreated a total of 126 cm.
[0019] As one of the preferred embodiments of the present invention, in step S4, height-increasing pads are added to the side roller cutter to expand the excavation gradient with different cutter heights, and the expansion amount is 10mm; gradual expansion: a. After the cutter is installed, the operator manually operates the cutter head, rotates it to observe the operation of the cutter head, records the cutter head torque value at this time as the expansion control value; b. After confirming that the cutter is working normally, expansion is carried out at a low speed of 0.5~1.0r / min and a low speed of 5mm / min. During the expansion process, the focus is on the torque, speed, cutter, and changes in the current ring segment; c. Every 5~10 cm of expansion, personnel enter the chamber to check the working condition of the cutter, observe whether the cutter is split, whether the rotation is normal, the amount of cutter wear, and the expansion condition of the rock surface.
[0020] As one of the preferred embodiments of the present invention, in step S5, after the tunnel boring machine successfully escapes its predicament, the damage to the tail brush is checked, the cutting tools are replaced, and the tunnel boring machine is organized to push the shield again to resume normal tunneling work.
[0021] The advantages of this invention compared to existing technologies are as follows: After initial attempts to extricate the shield failed, this invention removed the stuck shield shell and used a water drill and hydraulic rock splitter to break up the longitudinally under-excavated portion of the surrounding rock, ensuring a gap of ≥5mm between the shield machine shell and the rock strata; then, it attempted to pull back the shield body using an active articulated pullback and a pressurized cutterhead, thus freeing the shield machine from its predicament. Specific advantages are as follows: (1) By cutting off the cut ring shield shell and breaking the under-excavated rock layer, and then using the retractable articulated cylinder to make the shield machine retract, the shield machine can be effectively and quickly organized to get out of trouble. (2) By using a water drill in conjunction with a hydraulic splitter to break through the under-excavated rock layer, the shield shell of the tunnel boring machine can be quickly separated from the rock layer, shortening the escape cycle and saving a lot of costs; (3) Select local removal of the shield shell, and continuously try to retract and pull back the shield body using articulated hydraulic cylinders during the process to reduce damage to the tunnel boring machine and reduce construction risks; (4) When carrying out welding operations in a confined space, assign a dedicated person to monitor the concentration of harmful gases in the chamber at any time to reduce the risk of harmful gas poisoning to workers and improve construction safety. In summary, the method of this invention can effectively and quickly complete the shield tunneling machine extrication construction, reduce the risks of manual operation in confined spaces, resume shield tunneling as soon as possible, shorten the extrication period, save a lot of costs, and has good practical guiding significance. Attached Figure Description
[0022] Figure 1 This is a flowchart of the steps in the shield tunneling machine extrication method in Example 1; Figure 2 This is a schematic diagram of the shield jamming position of the tunnel boring machine in Example 1; Figure 3 This is a schematic diagram of shield removal in Example 1. Detailed Implementation
[0023] The embodiments of the present invention are described in detail below. These embodiments are implemented based on the technical solution of the present invention, and provide detailed implementation methods and specific operation processes. However, the scope of protection of the present invention is not limited to the following embodiments.
[0024] Example 1 This embodiment presents a method for shield tunneling machine extrication from difficult terrain in bedrock strata with a soft upper layer and a hard lower layer. Figure 1 As shown, it includes the following steps: I. Initial assessment of the trapped situation An initial assessment of the tunnel boring machine's (TBM) entrapment revealed that the shield was stuck to the rock face within a 180° radius of the upper cut ring. Figure 2 As shown.
[0025] II. Initial Escape Attempt Based on the structural inspection upon opening the tunnel, a preliminary escape plan for the tunnel boring machine (TBM) is formulated, and an initial escape attempt is made. The shield stabilizer supports the rock face, and the active articulation cylinders are retracted to allow the front shield and cutterhead to retract; simultaneously, water is pumped into the soil chamber to increase the back-pushing force. If this step fails, a second escape attempt is made.
[0026] The specific operation of the shield stabilizer supporting the rock face and the retractable active articulation cylinder is as follows: a. Extend the stabilizer support plates on both sides of the front shield to the rock face, fixing the front shield stationary; b. Extend the active articulation stroke to 90~100mm, causing the shield tail to retract; c. Retract the stabilizer support plates on both sides of the front shield, and extend the stabilizer support plates on both sides of the middle shield to the rock face; d. Use the retractable articulation cylinder to retract the front shield and cutterhead to pull back the shield body.
[0027] The specific operation of water injection and pressurization in the soil chamber is as follows: secondary grouting and sealing are carried out at the tenth ring behind the shield tail, and the pores behind the segment wall are filled with grout to achieve the purpose of water injection and pressurization.
[0028] III. Preparations for Secondary Escape Preparations for the second extrication include: setting up a work platform, preparing the tools needed for construction, and conducting gas detection inside the chamber.
[0029] The construction of the working platform involves using Φ28 steel bars as the load-bearing frame, which are welded and fixed to the soil silo wall and cutter head. The specific installation height of the platform is determined on-site based on the specific working conditions inside the silo. Walkway slabs are laid and welded and fixed, and the platform must be firmly welded.
[0030] The tools used in the construction include: 2 sets of gas cutting equipment, 2 sets of carbon arc gouging machines, 2 sets of MIG welding machines, 2 water drills, 1 electric hydraulic splitting gun, 2 pneumatic picks, and 4 3t hand-operated chains.
[0031] Gas detection inside the chamber: The gas detection inside the chamber is qualified to ensure safe operation of personnel in a confined space. Continuous monitoring is carried out during the construction process.
[0032] IV. Second attempt to escape First, the shield shell inside the earth chamber is partially cut off; then, water drills and hydraulic splitters are used to break up the under-excavated rock layer to ensure that the gap between the shield machine shell and the rock layer is ≥5mm; after the under-excavated rock layer is broken up, an active articulated pullback and pressurized cutterhead method is used to pull back the shield body so that the shield machine can get out of trouble.
[0033] The removal plan is as follows: (Reference) Figure 3 The upper half of the shield shell was cut at 6 locations, with a cut area of 1m (circumferential). The cutting interval is 0.5m (longitudinal), with 1m intervals between cutting positions, evenly distributed along the upper half of the ring, with the top 12 o'clock position reserved for not being cut. Before cutting, after determining the location of the first cutting area on site, two lifting lugs are welded to the selected cutting area to suspend the upper and lower guide chains. The two guide chains are respectively suspended above the cutting position and on one side of the earthen wall for hoisting after the steel plate is cut. Due to the limited operating space after the steel plate is cut, which conflicts with the subsequent chiseling work, two lifting lugs and a horizontal steel pipe support are welded on site to the inner wall of the cutting ring after the steel plate is cut. After the breaking is completed, a lifting lug is added above the steel plate, and a hoist is used with the help of steel sections to move it. After it is in place, four pieces of seven-shaped steel are welded and fixed. After the shield shell is removed, check the edge of the removed area for shield jamming. If the shield is still in close contact with the rock strata, continue to remove the shield shell in both circumferential directions until there is a gap of ≥5mm between the shield shell and the rock strata. After the shield shell is removed in the soil chamber, use a water drill to drill radial holes in the rock strata of the area where the shield shell has been removed, with a hole diameter of Φ42mm and a drilling depth of ≥20cm, at a hole spacing of 200×200mm.
[0034] For under-excavated rock strata, frontal breaking is adopted: first, use a water drill to take 1-2 rows of core samples from the bottom, with a core depth of ≥20cm. Then, use a pneumatic pick to chisel away the rock layer by layer along the core sample gap. If hard areas are encountered, repeat the core sampling steps. At the same time, horizontal and vertical breaking is carried out: after the frontal breaking is completed, the ductile breaking of the un-drilled hole wall is carried out. Horizontal breaking is mainly done by pneumatic pick chiseling, supplemented by oblique core sampling. Vertical breaking is mainly done by dense vertical core sampling, supplemented by electric drill chiseling.
[0035] The specific operation of the active articulated pull-back is as follows: a. Extend the stabilizer support plates on both sides of the front shield; b. Extend the active articulation to 100mm; c. Retract the front shield stabilizer and extend the middle shield stabilizer; d. Retract the articulated cylinder to pull back the shield body. Specific operation of pressurizing and retracting the cutter head: a. Retrieve the front and middle shield stabilizers; b. Push the propulsion cylinder to the tube segment; c. Close the chamber door and pressurize to 4.5 bar; d. Control the retraction of the propulsion cylinder; e. Use air pressure to retract the cutter head.
[0036] V. Excavation After the tunnel boring machine retracts into position, the widening excavation work will commence.
[0037] Among them, after the shield of the tunnel boring machine retreated 60 cm, the original plan was to chisel away the under-excavated rock in the cut gap and carry out wide excavation. However, due to the limited cut position and high rock strength, the efficiency was low and the tunnel boring machine eventually retreated a total of 126 cm.
[0038] Elevation pads are added to the side roller cutter to allow for gradient excavation with different cutter heights, with an excavation depth of 10mm. Gradual excavation is carried out as follows: a. After the cutter is installed, the operator manually operates the cutter head, observes its operation, and records the cutter head torque value as the control value for excavation; b. After confirming that the cutter is working normally, excavation is carried out at a low speed of 0.5~1.0r / min and a low speed of 5mm / min. During the excavation process, the operator pays close attention to the torque, speed, cutter, and changes in the current ring segment; c. Every 5~10cm of excavation, personnel enter the chamber to check the cutter's working condition, observe whether the cutter is cracked, whether the rotation is normal, the amount of cutter wear, and the excavation status of the rock surface.
[0039] VI. Summarize the implementation of the tunnel boring machine's escape from difficulties and optimize the shortcomings in the construction process. a. During the shield's retreat, damage to the tail brush needs to be considered, and the retreat amount should be minimized to protect the tail brush. Before retreating, the bolts of the tail section should be retightened to prevent increased segment misalignment from further damaging the tail brush. Before the tunnel boring machine exits the full-section hard rock strata, the machine should be stopped for inspection and replacement of the tail brush.
[0040] b. After the shield body is freed from its predicament, it is advisable to replace it with a larger side roller cutter, which can enable the shield to tunnel over long distances and reduce the risk of the shield getting stuck.
[0041] c. Replace the cutter when the wear of the gauge protection cutter is 5mm, the wear of the edge cutter is 10mm, the wear of the front area hob is 15~20mm, and the wear of the center area hob reaches 20mm.
[0042] d. Shield extrication work requires prolonged operation within the confined space, posing significant safety risks. The following measures will be taken to ensure the safety and stability of confined space operations. e. Confined space operations: Place fans inside the warehouse to ensure smooth ventilation during operations; assign dedicated personnel to conduct regular hazardous gas detection; set up work platforms as required and ensure workers wear safety belts.
[0043] VII. Resumption of normal work After the tunnel boring machine successfully escaped its predicament, the damage to the tail brush was inspected, the cutters were replaced, and the machine was re-pushed to resume normal tunneling operations.
[0044] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A method for shield tunneling machine extrication from difficult terrain in bedrock strata with soft upper layers and hard lower layers, characterized in that, Includes the following steps: S1, Initial attempt to escape The shield stabilizer supports the rock face and retracts the active articulation cylinder, causing the front shield and cutterhead to retreat; at the same time, water is pumped into the soil chamber to increase the back-pushing force. If this step fails to extricate you, continue with the following steps; S2. Preparations Preparations for the secondary extrication of the tunnel boring machine from its predicament; S3, Second attempt to escape First, the shield shell inside the earth chamber is partially cut away. Then, water drills and hydraulic splitters are used to break up the under-excavated rock layers, ensuring that the gap between the shield machine shell and the rock layers is ≥5mm. After the under-excavated rock layers are broken up, an active articulated pullback and pressurized cutterhead method is used to pull back the shield body. The specific cutting plan is as follows: cut 6 points on the upper half of the shield shell of the shield cutting ring, with a cutting area of 1m×0.5m and a cutting position interval of 1m, evenly distributed along the upper half of the ring, with the top 12 o'clock position reserved for not cutting. Before cutting, after determining the location of the first cutting area on site, two lifting lugs are welded to the selected cutting area to suspend the upper and lower guide chains. The two guide chains are respectively suspended above the cutting position and on one side of the earth chamber wall for hoisting after the steel plate is cut. S4, Expansion Excavation After the tunnel boring machine retracts into position, the widening excavation work will commence; S5, Resume normal operation The tunnel boring machine has resumed normal tunneling operations.
2. The method for shield tunneling machine extrication from difficult terrain in soft-topped, hard-bottomed bedrock strata according to claim 1, characterized in that, In step S1, the specific operations of the shield stabilizer supporting the rock surface and the retractable active articulation cylinder are as follows: a. Extend the stabilizer support plates on both sides of the front shield to the rock surface to fix the front shield in place; b. Extend the active articulation stroke to 90~100mm to make the shield tail retract; c. Retract the stabilizer support plates on both sides of the front shield and extend the stabilizer support plates on both sides of the middle shield to the rock surface; d. Use the retractable articulation cylinder to make the front shield and cutterhead retract to pull back the shield body.
3. The method for shield tunneling machine extrication from difficult terrain in soft-topped, hard-bottomed bedrock strata according to claim 1, characterized in that, In step S1, the specific operation of water injection and pressurization in the soil chamber is as follows: secondary grouting and sealing are performed at the tenth ring behind the shield tail, and the pores behind the pipe segment wall are filled with grout to achieve water injection and pressurization.
4. The method for shield tunneling machine extrication from difficult terrain in soft-topped, hard-bottomed bedrock strata according to claim 1, characterized in that, In step S2, the preparatory work includes: setting up the work platform, preparing the tools for construction, and detecting the gas inside the chamber.
5. The method for shield tunneling machine extrication from difficult terrain in soft-topped, hard-bottomed bedrock strata according to claim 1, characterized in that, In step S3, after the shield shell is cut off, check the shield jamming situation at the edge of the cut area; if the shield body is still closely attached to the rock stratum, continue to cut the shield shell to both sides in the circumferential direction until there is a gap of ≥5mm between the shield shell and the rock stratum; after the shield shell is cut off in place in the soil chamber, use a water drill to drill radial holes in the rock stratum of the area where the shield shell has been cut off at a hole spacing of 200×200mm, with a hole diameter of Φ42mm and a drilling depth of ≥20cm.
6. The method for shield tunneling machine extrication from difficult terrain in soft-topped, hard-bottomed bedrock strata according to claim 1, characterized in that, In step S3, the rock strata are under-excavated and broken using a frontal breaking method: first, use a water drill to take 1-2 rows of core samples from the bottom, with a core depth ≥20cm. Then, use a pneumatic pick to chisel away the rock layer by layer along the core sample gap. If hard areas are encountered, repeat the core sampling step. At the same time, horizontal and vertical breaking is carried out: after the frontal breaking is completed, the unopened hole wall is broken by extension. Horizontal breaking is mainly done by pneumatic pick chiseling, supplemented by oblique core sampling. Vertical breaking is mainly done by dense vertical core sampling, supplemented by electric drill chiseling.
7. The method for shield tunneling machine extrication from difficult terrain in soft-topped, hard-bottomed bedrock strata according to claim 1, characterized in that, In step S3, the specific operation of the active articulation pull-back is as follows: a. Extend the stabilizer support plates on both sides of the front shield; b. Extend the active articulation to 100mm; c. Retract the front shield stabilizer and extend the middle shield stabilizer; d. Retract the articulation cylinder to pull back the shield body. The specific operation of pressurizing and retracting the cutter head is as follows: a. Retract the front and middle shield stabilizers; b. Push the propulsion cylinder to the tube segment; c. Close the chamber door and pressurize to 4.5 bar; d. Control the retraction of the propulsion cylinder; e. Use air pressure to retract the cutter head.
8. The method for shield tunneling machine extrication construction applicable to soft upper and hard lower bedrock strata according to claim 1, characterized in that, In step S4, the tunnel boring machine eventually retracts 126cm.
9. The method for shield tunneling machine extrication from difficult terrain in soft-topped, hard-bottomed bedrock strata according to claim 1, characterized in that, In step S4, height-increasing pads are added to the side roller cutter to expand the excavation gradient with different cutter heights, with an expansion amount of 10mm; gradual expansion: a. After the cutter is installed, the operator manually operates the cutter head, rotates it to observe the operation of the cutter head, and records the cutter head torque value at this time as the expansion control value; b. After confirming that there are no abnormalities in the operation of the cutter, expansion is carried out at a low speed of 0.5~1.0r / min and a low speed of 5mm / min. During the expansion process, the focus is on the torque, speed, cutter, and changes in the current ring segment; c. Every 5~10 cm of expansion, personnel enter the chamber to check the operation of the cutter, observe whether the cutter is split, whether the rotation is normal, the amount of cutter wear, and the expansion of the rock surface.
Citation Information
Patent Citations
Method for relieving and cutterhead repairing of shield machine in weathering groove
CN102305082A
Jamming reason analysis and trouble removal construction method for TBM (tunnel boring machine)