A method for monitoring stress state of steel structure of power plant dust collector

By combining ANSYS software with on-site stress testing, the stress state of the steel structure of the power plant dust collector can be accurately monitored, solving the problem of insufficient calculation accuracy in existing technologies and achieving safety early warning and cost savings.

CN117367635BActive Publication Date: 2026-11-20SHANGHAI MINGHUA ELECTRIC POWER TECH & ENG
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202311414942.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-29
Publication Date
2026-11-20
Estimated Expiration
2043-10-29

AI Technical Summary

Technical Problem

Existing technologies are insufficient to accurately monitor the stress state of the steel structure of a power plant dust collector during actual operation, making it difficult to predict potential safety hazards. Furthermore, traditional strength verification analysis cannot take into account the influence of thermal stress, resulting in insufficient calculation accuracy.

Method used

A steel structure model of the power plant dust collector was established using ANSYS software. Combined with on-site stress testing, the actual stress values ​​were obtained by superimposing finite element simulation calculations and on-site stress monitoring. Factors such as self-weight, dust accumulation, wind load, and seismic load were considered, and the safety status was assessed with reference to GB50017-2017 "Code for Design of Steel Structures".

Benefits of technology

It enables accurate monitoring of the stress on the steel structure of the power plant dust collector, provides safety early warnings, reduces safety accidents, lowers maintenance costs, and improves the operational safety of the power plant.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117367635B_ABST
    Figure CN117367635B_ABST
Patent Text Reader

Abstract

The application provides a kind of power station dust collector steel structure stress state monitoring method, for the safety monitoring of power station dust collector steel structure, since the last calculated steel structure stress value includes the stress value of the dust collector steel structure under self weight and the stress change value measured in the operation process, the result calculated is more accurate to reflect the actual stress state, so as to better be used to guide the operation, overhaul and maintenance of power station, reduce the cost of overhaul and maintenance;At the same time, the safety of steel structure can be warned, to avoid the occurrence of safety accidents, reduce the personnel casualties and economic losses caused by safety accidents.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of power plant dust collectors, and more particularly to stress state monitoring of the steel structure of power plant dust collectors. Background Technology

[0002] Dust collectors are essential equipment in thermal power plants. In recent years, several dust collector collapse accidents have occurred in China, causing serious casualties and property losses. The safety of dust collector steel structures cannot be ignored. Power plant personnel primarily focus on the dust removal efficiency of dust collectors, often neglecting the safety of their steel structures. Conventional power plant metal monitoring also fails to include dust collector steel structures. With long-term operation of the unit, dust collector steel structures are prone to corrosion. Combined with the development of original defects in the steel structure and untimely dust removal, this can lead to localized instability or even collapse of the dust collector steel structure. To monitor the safety status of dust collector steel structures and prevent collapse accidents, long-term monitoring of their safety is urgently needed.

[0003] The main indicators characterizing the safety status of a dust collector's steel structure are its stress and deformation. The stress sources in a dust collector's steel structure primarily consist of three parts: 1. the weight of accumulated ash in the main structure, equipment, and ash hopper; 2. thermal stress generated in the steel structure due to the temperature field of various components of the dust collector; and 3. live loads such as wind load, snow load, and seismic load. Among these, the ash weight is related to the unit's operating mode and is a variable, making it difficult to calculate accurately; live loads such as wind load are also uncertain; thermal stress can be simulated using finite element simulation software, but the accuracy of the calculation is difficult to verify.

[0004] This invention provides a method for monitoring the stress state of steel structures in power plant dust collectors, which can reflect the safety status of the steel structures in real time and accurately.

[0005] Currently, publicly available literature includes finite element simulation analyses of the stress state of steel structures in dust collectors, as well as research on construction monitoring and instability control of other steel structures such as stadiums. However, direct research on safety monitoring methods for steel structures in power plant dust collectors is limited. Currently, the assessment of the safety status of dust collector steel structures mainly relies on comprehensive metal inspection of the steel structure and strength verification analysis based on software such as the finite element method.

[0006] Patent CN116090304A provides an intelligent detection method for the stability of steel frames in power plant electrostatic precipitators. By establishing the stiffness equation of the steel frame structure, the stress ratio and stability of the steel frame are obtained to track the safety status of the steel structure.

[0007] Simple strength verification analyses are based on assumed loads and cannot accurately reflect the safety status of the dust collector steel structure during actual operation, nor can they provide early warnings of dangerous conditions. The ash load during actual operation may exceed the loads used in the strength verification. Furthermore, most strength verifications do not consider the influence of thermal stress, and even if the influence of thermal stress is considered, accurately calculating the temperature field remains a significant challenge.

[0008] The stiffness equation described in patent CN116090304A uses loads on the frame derived from design data and strain gauge test results, which can only reflect the stability state of components equipped with measuring points. Furthermore, it calculates the dynamic pressure load of a component by back-calculating the strain value of the component, which is only applicable to components with simple tension and compression, and not applicable to rigidly connected components (with bending moment loads). Summary of the Invention

[0009] The purpose of this invention is to provide a method for monitoring the stress state of steel structures in power plant dust collectors, so as to more accurately monitor the actual stress of the steel structures in power plant dust collectors and better assess the safety status of the steel structures in power plant dust collectors.

[0010] To achieve the above-mentioned objective, a method for monitoring the stress state of steel structures in power plant dust collectors is provided, comprising the following steps:

[0011] 1. A method for monitoring the stress state of a steel structure in a power plant dust collector, characterized by comprising the following steps:

[0012] Step 1: Provide the corresponding design and installation data of the dust collector steel structure for the generator set to be monitored. The data of the steel structure shall include at least the data information, structural dimension information and connection method information.

[0013] Step 2. Determine whether the generator set to be tested is a newly built unit. If so, take the following steps:

[0014] Step 3a: Based on the information described in Step 1 above, model using ANSYS software;

[0015] Step 4a: Use ANSYS software to perform finite element simulation calculations to determine the stress value of the dust collector steel structure under its own weight. ;

[0016] Step 5a: Based on the simulation results of Step 4a, select the areas with high stress and deformation in the finite element calculation results as monitoring points. Set up the on-site stress testing device before the unit starts up, and test the real-time stress change value of the dust collector steel structure during the unit operation after the unit starts up. ;

[0017] Step 6: Take the stress value obtained in step 4a above. Compared with the in-situ stress change value obtained in step 5a above Add them together to get the actual stress value. ;

[0018] Step 7: Set the standard value of safety stress according to GB50017-2017 "Code for Design of Steel Structures" ;

[0019] Step 8: Determine the stress safety status of the dust collector steel structure: where, There are no stress safety hazards; otherwise, there are safety hazards and further safety control measures need to be taken.

[0020] Following step 2 above, if the generator set to be monitored is not a newly built unit, then the following steps should be taken:

[0021] Step 3b: After the unit is shut down, empty the ash hopper or drain the ash to a measurable height;

[0022] Step 4b: Conduct on-site inspection of the dust collector steel structure and record the on-site inspection results. The inspection items include macroscopic inspection of the steel structure surface, measurement of steel structure dimensions, detection of steel structure wall thickness, measurement of column verticality, and weld flaw detection.

[0023] Step 5b: Determine and compare whether the above on-site inspection results are consistent with the information in Step 1, and whether there are any factors that affect structural safety, such as welding defects, corrosion thinning, or column tilting.

[0024] Step 6b: If the comparison results of Step 5b are inconsistent, then model the data using ANSYS software based on the information described in Step 1 and the above-mentioned field test results; otherwise, model the data based on the information described in Step 1.

[0025] Step 7b: Use finite element simulation software to calculate the stress values ​​of the steel structure of the dust collector, equipment, and the steel structure under the self-weight of the accumulated ash. ;

[0026] Step 8b: Based on the simulation results of Step 7b, select the areas with high stress and deformation in the finite element calculation results as monitoring points. Set up the on-site stress testing device after the ash hopper discharges and before the unit starts. After the unit starts, test the real-time stress change value of the dust collector steel structure during the unit's operation. ;

[0027] Step 9: Calculate the stress change value obtained by the method in step 8b above. The stress value calculated in step 7b above Adding them together, we obtain the actual stress value of the dust collector's steel structure. ;

[0028] Step 10: Determine the stress safety status of the dust collector steel structure: where, There are no potential safety hazards due to stress; otherwise, there are potential safety hazards and further safety control measures need to be taken.

[0029] Furthermore, the finite element simulation software can be any one of ANSYS, ABAQUS, STAAD.Pro, or SAP2000.

[0030] Furthermore, the on-site stress test of the dust collector steel structure can be performed using the resistance strain gauge method and the fiber optic grating method.

[0031] Furthermore, the ash accumulation quality in step 7b Calculate using the following method:

[0032] ) / 3, where For the quality of dust accumulation, The density of the ash accumulation. This refers to the height of the accumulated dust. The area of ​​the bottom surface of the ash hopper. This refers to the area of ​​the top of the ash hopper.

[0033] Furthermore, the method for applying boundary conditions in the finite element ANSYS software calculations used in step 4a or step 7b employs the following steps:

[0034] 1) Based on the actual support method of the dust collector's steel structure foundation, reasonably set displacement constraint boundary conditions;

[0035] 2) Based on the actual connection method of the beam-column bracing and other connection nodes, set the node constraints reasonably. For example, if the beam and column are connected by welding, set them as rigid nodes. If the bracing and the beam are connected by bolts, set them as hinged nodes or semi-rigid nodes according to the specific situation.

[0036] 3) Apply the weight of the ash hopper and its accumulated ash evenly onto the ash hopper beam. ;

[0037] in, For the uniformly distributed load applied to the ash hopper beam, The ash accumulation in the ash hopper is zero, and the ash accumulation in newly built power plants is zero. For the quality of the ash hopper, It is the acceleration due to gravity. The length of the ash bucket beam;

[0038] 4) Apply the insulation weight evenly to the outer cladding. ;

[0039] in, For a uniformly distributed load applied to the outer shroud, For the weight of the insulation layer, The area of ​​the outer cladding panel;

[0040] 5) Distribute the weights of other structures and equipment outside the steel structure calculation model evenly onto the nearby beams according to their locations;

[0041] 6) Apply self-weight load to the entire steel structure calculation model of the dust collector, which is achieved by increasing the gravitational acceleration g in ANSYS software.

[0042] This invention provides a method for monitoring the stress state of a power plant dust collector steel structure, used for safety monitoring of the power plant dust collector steel structure. The final calculated stress value includes the stress value of the dust collector steel structure under its own weight (a defined load) obtained from the finite element method. The stress change value of the dust collector steel structure measured on site during unit operation Therefore, the calculated results can more accurately reflect the actual stress state, thus better guiding the operation and maintenance of power plants and reducing maintenance costs; at the same time, it can provide safety warnings for steel structures, prevent safety accidents, and reduce casualties and economic losses caused by safety accidents. Attached Figure Description

[0043] Figure 1 This is a flowchart of a method for monitoring the stress state of a power plant dust collector steel structure provided by the present invention.

[0044] Figure 2 This is a schematic diagram of the on-site measurement points of the steel structure of the power plant dust collector of the present invention. Detailed Implementation

[0045] The present invention will now be described in detail with reference to the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are for illustrative and explanatory purposes only and are not intended to limit the scope of the invention.

[0046] This invention provides different methods for monitoring the safety status of dust collector steel structures for newly built generator sets and generator sets already in operation.

[0047] See Figure 1The essential feature of the stress state monitoring method for the steel structure of a power plant dust collector provided by this invention is the use of finite element numerical simulation software to establish a model of the dust collector steel structure. This model calculates the stress state and deformation of the dust collector steel structure under defined loads (the self-weight of the steel structure and its equipment, and fixed ash loads), avoiding the influence of uncertain loads on the accuracy of the calculation results. Simultaneously, on-site stress testing is used to monitor in real time the changes in stress state and deformation of the dust collector steel structure caused by loads such as ash load, wind load, seismic load, and temperature load during operation. Then, the stress results of the steel structure obtained from the finite element software simulation and the stress results obtained from the stress monitoring are superimposed to obtain the actual stress value of the dust collector steel structure during operation. ,in, Indicates steel structure The actual stress value in the direction, Indicates steel structure The stress value obtained from stress testing in the direction of stress. Indicates steel structure The stress value obtained from the finite element simulation in the direction.

[0048] For newly built generator sets, considering that the steel structure of the dust collector has not suffered corrosion thinning or column tilting due to long-term operation, the above modeling is based only on the design and installation data of the dust collector steel structure, and only the stress results under the self-weight of the structure and equipment are simulated and calculated.

[0049] For generator sets that are already in operation, after the unit is shut down, empty the ash hopper or drain the ash to a level that can be observed and measured to ensure that the height of the ash can be measured and the weight of the ash in the ash hopper can be calculated, thereby ensuring that the calculated actual stress is more accurate.

[0050] For generator sets already in operation, considering the changes in the condition of the dust collector steel structure after long-term operation, on-site inspections are conducted to assess the actual condition of the dust collector steel structure. These inspections include: macroscopic surface inspection, structural wall thickness measurement, flaw detection of connecting welds, and measurement of column verticality. The main purpose is to check whether the actual condition of the steel structure matches the design specifications and to identify any welding defects, corrosion thinning, column tilting, or other factors affecting structural safety. Among these:

[0051] The macroscopic inspection of the steel structure surface mainly examines the corrosion thinning, mechanical damage, abnormal deformation, and discrepancies with the design data of steel structures such as columns, beams, and braces.

[0052] The wall thickness of the steel structure is measured using a thickness gauge to measure the thickness of steel structures such as columns, beams and braces. For tubular structures, the wall thickness is measured. For components such as H-beams, I-beams and channel steel, the thickness of their webs and flanges is measured.

[0053] For the flaw detection of welded joints in steel structures, surface magnetic particle testing should be performed on the main welds of columns, beams and diagonal braces, and ultrasonic testing should be performed when necessary; this is used to detect whether there are surface and internal defects exceeding the standard in the welds.

[0054] For generator sets that have already been put into operation, if the above-mentioned on-site inspection results are consistent with the design and installation data, then finite element software should be used for modeling based on the design and installation data. If the above-mentioned on-site inspection results are inconsistent with the design and installation data, and there are problems such as thinning of wall thickness or tilting of columns, then finite element software should be used for modeling based on the design and installation data and the inspection results.

[0055] For generator sets already in operation, finite element simulation calculations were performed to determine the stress results under the influence of the structure, equipment, and the self-weight of the remaining ash after ash removal.

[0056] For generator sets that are already in operation, if the ash hopper has not been completely emptied, the density and volume of the ash should be measured to calculate its true weight.

[0057] The stress measurement points on site are determined based on the finite element calculation results. The areas with large stress and deformation in the finite element calculation results are selected as measurement points. The measurement points should also cover the frame columns, ash hopper beams and diagonal braces to ensure that the measurement points can reflect the stress state of the overall steel structure of the dust collector.

[0058] For newly built units, the above-mentioned strain measurement points should be set up before the unit is put into operation and monitoring should begin when the unit is put into operation.

[0059] For units already in operation, the aforementioned strain measurement points should be set up after the unit is shut down and the ash hopper is drained, and monitoring should begin when the unit is running.

[0060] The on-site stress monitoring system needs to have long-term monitoring capabilities.

[0061] The structural dimensions and constraint forms in the finite element numerical simulation calculation model should be consistent with the actual steel structure of the dust collector, and the weight of the dust collector-related equipment and accessories should be reasonably distributed in the calculation model according to their actual positions.

[0062] When conducting metal inspections on the steel structure of a dust collector, if problems affecting structural safety are found, such as severe local deformation or defects exceeding structural standards, a separate and detailed model of this part of the steel structure should be created and analyzed using a finite element numerical model.

[0063] In the following embodiment of the present invention, a subcritical power plant unit already in operation is used as an example for description. Its dust collector is an electrostatic precipitator converted to a bag filter, and it adopts the following steps:

[0064] Step 1: During the shutdown and maintenance period, conduct metal inspection on the steel structure of the dust collector to determine whether the condition of the steel structure has changed after long-term operation. The inspection includes the macroscopic appearance of the outer surface of the steel structure, wall thickness, dimensions, column verticality, weld flaw detection, etc. If it is a newly built unit, the above steps are not required.

[0065] Step 2: Empty the dust collector hoppers or drain the dust to a measurable height, measure the dust accumulation height in the hoppers, and take samples to measure the dust density. Calculate the dust mass in each hopper. This step is not required if the unit is newly built.

[0066] ) / 3, where For the quality of dust accumulation, The density of the ash accumulation. This refers to the height of the accumulated dust. The area of ​​the bottom surface of the ash hopper. This refers to the area of ​​the top of the ash hopper.

[0067] Step 3: Obtain information on at least the following dust collectors for design, installation, and modification:

[0068] 1) Original design and overall plan and elevation drawings of the steel structure of the dust collector after modification;

[0069] 2) Material grade, cross-sectional dimensions, length, and connection method of all steel structures such as columns, beams, and diagonal braces of the dust collector;

[0070] 3) The location and weight of the dust collector steel structure and related equipment and accessories, such as the weight of the insulation layer, the location and weight of the pulse jet cleaning device, and the location and weight of the filter bags.

[0071] Step 4: Based on the dust collector data, establish the finite element geometric model of the dust collector's steel structure using ANSYS software following these steps; if metal inspection reveals wall thinning and column tilting in the steel structure, the steel structure thickness in the model will be based on the wall thickness inspection results. The columns of the steel structure will be modeled based on the measured verticality. The model mainly includes the bottom frame and the middle box. The procedure for establishing the dust collector's steel structure model using ANSYS software is as follows:

[0072] Step 4.1 Based on the material grades of each component in the above information, establish a material database and set the elastic modulus and Poisson's ratio of the materials;

[0073] Step 4.2 Select the appropriate unit type according to the structural form of each component in the information. Use beam189 unit to simulate rod-shaped components such as columns, beams and diagonal braces, and use plane82 unit to simulate plate-shaped components. The unit cross-sectional dimensions are determined according to the actual dimensions of each component of the steel structure.

[0074] Step 4.3 Based on the plan and elevation drawings in the design and installation documents and the verticality of the columns measured on site, establish a three-dimensional geometric model of the dust collector steel structure, including the bottom frame and the middle box of the dust collector;

[0075] Step 4.4 Mesh the three-dimensional geometric model of the dust collector steel structure, apply the corresponding boundary conditions (see Step 5 below), and then solve the problem.

[0076] Step 5: Using the following boundary condition settings, calculate the stress and deformation of the dust collector steel structure under its own weight and the weight of accumulated ash using the finite element numerical simulation software ANSYS, and determine the locations with larger stress and deformation:

[0077] Step 5.1: Based on the actual support method of the dust collector's steel structure foundation, reasonably set the displacement constraint boundary conditions;

[0078] Step 5.2: Based on the actual connection method of the beam-column bracing and other connection nodes, set the node constraints reasonably. For example, if the beam and column are welded, set them as rigid nodes. If the bracing and beam are bolted, set them as hinged nodes or semi-rigid nodes depending on the specific situation.

[0079] Step 5.3: Apply the weight of the ash hopper and its accumulated ash evenly onto the ash hopper beam. ;

[0080] in, For the uniformly distributed load applied to the ash hopper beam, This refers to the weight of ash accumulated in the ash hopper. This refers to the weight of the ash hopper. It is the acceleration due to gravity. The length of the ash bucket beam.

[0081] Step 5.4: Apply the insulation weight evenly to the outer cladding. ;

[0082] in, For a uniformly distributed load applied to the outer shroud, For the weight of the insulation layer, This refers to the area of ​​the outer cladding.

[0083] Step 5.5: Apply the weights of other structures and equipment outside the steel structure calculation model to the nearby beams according to their locations;

[0084] Step 5.6: Apply self-weight load to the entire steel structure calculation model of the dust collector by increasing the gravitational acceleration in ANSYS software. accomplish.

[0085] Step 6: Use the finite element software ANSYS to calculate the stress and deformation under given wind load, seismic load and flue gas temperature, and identify the areas with larger stress and deformation.

[0086] Step 7: The wind load and seismic load in Step 6 are added based on local statistical information and data, and the flue gas temperature is applied based on the actual operating information of the unit. The purpose of Step 6 is to identify the weak points of the steel structure for monitoring. The calculation results do not represent the actual stress of the steel structure.

[0087] Step 8: After ash discharge from the ash hopper and before unit operation, use the areas with significant stress and deformation in the steel structure columns, beams, and diagonal braces of the dust collector, as determined by the finite element calculations in Steps 4 and 5, as measuring points (see...). Figure 2 According to the deployment of the on-site strain monitoring system, the stress in the dust collector steel structure is mainly axial stress. Strain gauges are arranged along the axial direction of the steel structure to detect the change in axial stress at the measuring points after the unit starts operating. .

[0088] Step 9: Extract the measurement points obtained from the simulation calculation in Step 5 (see...) Figure 2 stress value Compare this with the axial stress change values ​​at the measuring points after the aforementioned testing unit has been in operation. By superimposing the values, the actual stress values ​​at the measuring points of the steel structure during operation can be obtained:

[0089] In particular, because the main steel structure of the dust collector is a frame system composed of beams, columns, and diagonal braces, the principal stress direction is the axial direction. The direction is selected as the axial direction.

[0090] Step 10: Determine the safe strength stress value The Calculated and determined according to GB50017-2017 "Code for Design of Steel Structures": a. Strength requirements are based on ,in, This is the design strength value of the steel, i.e., the allowable stress; For safety reasons, a factor of 1 is generally used, because this unit has been in operation for nearly 20 years. The value is set to 1.2; and b. Stability requirements are based on... ,in The stability coefficient of the component is selected according to Appendix C and Appendix D of GB50017-2017 "Code for Design of Steel Structures".

[0091] Step 11: Based on the comparison results in Step 10, perform strength and stability analysis on the steel structure of the dust collector to assess its safety status.

[0092] In the above embodiments, those skilled in the art can make the following changes to achieve the same objective of the present invention:

[0093] 1. In this field, in addition to ANSYS software, professional finite element analysis software such as ABAQUS, or professional steel structure analysis software such as STAAD.Pro and SAP2000, can also be used for finite element simulation of dust collector steel structures. The usage methods of these software programs are known.

[0094] 2. On-site stress monitoring of the steel structure of dust collectors typically employs the resistance strain gauge method, but the fiber optic grating method can also be used.

[0095] As can be seen from the above description, the stress state monitoring method for the steel structure of a power plant dust collector provided by this invention, for newly built generator units, considers that the dust collector steel structure has not suffered corrosion thinning or column tilting due to long-term operation. In the above modeling, only the design and installation data of the dust collector steel structure are used for modeling, and only the stress results under the self-weight of the structure and equipment are simulated and calculated. For generator units already in operation, after the unit is shut down, the ash in the ash hopper is emptied or the ash height is reduced to an observable and measurable range to ensure that the ash height can be measured and the weight of the ash in the ash hopper can be calculated. The stress results under the self-weight of the structure, equipment, and ash in the ash hopper are simulated and calculated. At the same time, on-site stress testing is used to obtain the stress change values ​​of the steel structure caused by changes in ash accumulation in the ash hopper, changes in the internal temperature field of the dust collector, wind load, etc. during operation. Finally, the calculated steel structure stress value includes the stress value of the dust collector steel structure under its own weight (a defined load). and the stress change values ​​measured on-site during unit operation Therefore, the calculated results more accurately reflect the actual stress state of the dust collector steel structure, which can be better used to guide the operation and maintenance of the power plant and reduce maintenance costs; at the same time, it can provide safety warnings for the steel structure to avoid safety accidents and reduce casualties and economic losses caused by safety accidents.

[0096] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and are not intended to limit it. Although the present invention has been described in detail with reference to the embodiments, those skilled in the art should understand that modifications or equivalent substitutions to the technical solutions of the present invention do not depart from the spirit and scope of the technical solutions of the present invention, and all such modifications or substitutions should be covered within the scope of the claims of the present invention.

Claims

1. A method for monitoring the stress state of steel structures in power plant dust collectors, characterized in that, It includes the following steps: Step 1: Provide the design and installation data of the corresponding dust collector steel structure for the generator set to be monitored. The data of the steel structure shall include at least the data information, structural dimension information and connection method information. Step 2. Determine whether the generator set to be tested is a newly built unit. If so, take the following steps: Step 3a: Based on the information described in Step 1 above, model using ANSYS software; Step 4a: Use ANSYS software to perform finite element simulation calculations to determine the stress value of the dust collector steel structure under its own weight. ; Step 5a: Based on the simulation results of Step 4a, select the areas with high stress and deformation in the finite element calculation results as monitoring points. Set up the on-site stress testing device before the unit starts up, and test the real-time stress change value of the dust collector steel structure during the unit operation after the unit starts up. ; Step 6: Take the stress value obtained in step 4a above. Compared with the in-situ stress change value obtained in step 5a above Add them together to get the actual stress value. ; Step 7: Set the standard value of safety stress according to GB50017-2017 "Code for Design of Steel Structures" ; Step 8: Determine the stress safety status of the dust collector steel structure: where, There are no stress-related safety hazards; conversely, if there are safety hazards, further safety control measures need to be taken. Following step 2 above, if the generator set to be monitored is not a newly built unit, then the following steps should be taken: Step 3b: After the unit is shut down, empty the ash hopper or drain the ash to a measurable height; Step 4b: Conduct on-site inspection of the dust collector steel structure and record the on-site inspection results. The inspection items include macroscopic inspection of the steel structure surface, measurement of steel structure dimensions, detection of steel structure wall thickness, measurement of column verticality, and weld flaw detection. Step 5b: Determine and compare whether the above on-site inspection results are consistent with the information in Step 1, and whether there are any factors that affect structural safety, such as welding defects, corrosion thinning, or column tilting. Step 6b: If the comparison results of Step 5b are inconsistent, then model the data using ANSYS software based on the information described in Step 1 and the above-mentioned field test results; otherwise, model the data based on the information described in Step 1. Step 7b: Use finite element simulation software to calculate the stress values ​​of the steel structure of the dust collector, equipment, and the steel structure under the self-weight of the accumulated ash. ; Step 8b: Based on the simulation results of Step 7b, select the areas with high stress and deformation in the finite element calculation results as monitoring points. Set up the on-site stress testing device after the ash hopper discharges and before the unit starts. After the unit starts, test the real-time stress change value of the dust collector steel structure during the unit's operation. ; Step 9: Calculate the stress change value obtained by the method in step 8b above. The stress value calculated in step 7b above Adding them together, we obtain the actual stress value of the dust collector's steel structure. ; Step 10: Determine the stress safety status of the dust collector steel structure: where, There are no potential safety hazards due to stress; otherwise, there are potential safety hazards and further safety control measures need to be taken.

2. The method for monitoring the stress state of a power plant dust collector steel structure as described in claim 1, characterized in that, The finite element simulation software can be any one of ANSYS, ABAQUS, STAAD.Pro, or SAP2000.

3. The method for monitoring the stress state of a power plant dust collector steel structure as described in claim 1, characterized in that, The on-site stress test of the steel structure of the dust collector can be performed using the resistance strain gauge method and the fiber optic grating method.

4. The method for monitoring the stress state of a power plant dust collector steel structure as described in claim 1, characterized in that, The ash accumulation quality in step 7b Calculate using the following method: ) / 3, where For the quality of dust accumulation, The density of the ash accumulation. This refers to the height of the accumulated dust. The area of ​​the bottom surface of the ash hopper. This refers to the area of ​​the top of the ash hopper.

5. The method for monitoring the stress state of a power plant dust collector steel structure as described in claim 1, characterized in that, The method for applying boundary conditions in the finite element simulation software used in step 4a or step 7b adopts the following steps: 1) Based on the actual support method of the dust collector's steel structure foundation, reasonably set displacement constraint boundary conditions; 2) Based on the actual connection method of the beam-column brace connection node, set the node constraints reasonably. For example, if the beam and column are welded, set it as a rigid node. If the brace and beam are bolted, set it as a hinged node or a semi-rigid node according to the specific situation. 3) Apply the weight of the ash hopper and its accumulated ash evenly onto the ash hopper beam. ; in, For the uniformly distributed load applied to the ash hopper beam, The ash accumulation in the ash hopper is zero, and the ash accumulation in newly built power plants is zero. For the quality of the ash hopper, It is the acceleration due to gravity. The length of the ash bucket beam; 4) Apply the insulation weight evenly to the outer cladding. ; in, For a uniformly distributed load applied to the outer shroud, For the weight of the insulation layer, The area of ​​the outer cladding panel; 5) Distribute the weights of other structures and equipment outside the steel structure calculation model evenly onto the nearby beams according to their locations; 6) Apply self-weight load to the entire steel structure calculation model of the dust collector, which is achieved by increasing the gravitational acceleration g in ANSYS software.

Citation Information

Patent Citations

  • Intelligent detection method for stability of electric precipitation steel frame of power station

    CN116090304A

  • Transmission tower online safety monitoring system and method for stress measuring

    CN104092308A

  • Hydro-generator rotating shaft stress state analysis method

    CN113656901A