A rigid net for tunnel primary support and a tunnel primary support method

By using a support mesh that combines rigidity and flexibility in the initial support of the tunnel, and combining it with anchor bolt fixing and shotcrete to form an integral support, the problems of concrete cracking and high construction risk in tunnel support under high ground stress were solved, achieving efficient and safe tunnel support.

CN117418864BActive Publication Date: 2026-11-24HOCK TECH CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202311568518.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-23
Publication Date
2026-11-24
Estimated Expiration
2043-11-23

AI Technical Summary

Technical Problem

Under high ground stress conditions, existing tunnel support technology leads to concrete cracking and spalling in the initial support, twisting and deformation of arched steel frames, low level of construction automation, high labor intensity, threat of rock bursts, and high project costs and risks.

Method used

The tunnel initial support netting, which combines rigidity and flexibility, is adopted. The base fabric of the warp-knitted directional weave structure is coated with a hydrophilic polymer coating, and then fixed with anchor bolts and sprayed with concrete to form an integral support, which improves the bonding force between the support netting and the tunnel surrounding rock and concrete, and restrains the deformation of the surrounding rock.

Benefits of technology

It effectively prevents concrete cracking during initial support, stabilizes the working surface, reduces construction risks, improves labor efficiency, and reduces project costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117418864B_ABST
    Figure CN117418864B_ABST
Patent Text Reader

Abstract

This invention relates to a rigid mesh for initial tunnel support and a method for initial tunnel support, belonging to the field of tunnel support engineering construction technology. It includes a base fabric and a hydrophilic polymer coating on the surface of the base fabric. The base fabric consists of warp and weft yarns arranged perpendicularly to each other, connected and fixed at their intersections by binding yarns. The hydrophilic polymer coating has a granular texture and a roughness of 0.1–0.4 mm. The support method involves laying the support mesh circumferentially along the tunnel, fixing it to the tunnel roof using anchor bolts, and then spraying concrete mortar to form a unified whole with the tunnel roof and the rigid mesh. This invention applies a self-made rigid mesh to the initial tunnel support, replacing the existing metal mesh, improving the bonding strength between the support mesh and the surrounding rock and concrete, forming a unified whole with the tunnel surface while bearing stress, effectively restraining surrounding rock deformation, providing support, preventing concrete cracking during initial support, and preventing rockfalls that could injure people.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel support engineering construction technology, specifically to a rigid mesh for initial tunnel support and a method for initial tunnel support. Background Technology

[0002] Southwest my country has a complex topography, mainly consisting of plateaus and mountains. With the development of railway construction in my country, the construction of railway tunnels in mountainous areas is inevitable. Long, deep-buried tunnels in the western region are characterized by high ground stress, poor lithology, well-developed joints and fissures, and fractured rock strata. These characteristics often lead to engineering accidents such as large deformation of the surrounding rock, arch collapse, and severe extrusion at the tunnel face during tunnel construction. Therefore, the tunnel construction problems caused by the high ground stress environment are becoming increasingly prominent.

[0003] However, in existing technologies, when excavating tunnels under geological conditions of high or even extremely high ground stress in soft rock strata, the same support techniques used are employed as those used under conditions of ordinary ground stress rock strata. Specifically:

[0004] 1. Construct a rigid initial support that closely fits the surface of the tunnel passage: The specific process involves using an arched steel frame with the same cross-sectional shape as the tunnel passage surface to support the tunnel passage from the inside. That is, the outer edge of the arched steel frame is closely fitted with the circumferential surface of the tunnel passage, and then concrete is sprayed onto the arched steel frame.

[0005] 2. Implement secondary lining based on the above-mentioned rigid initial support; that is, construct a cast-in-place concrete lining inside the rigid initial support to form a smooth tunnel surface that is similar in shape to the tunnel passage and extends longitudinally along the tunnel passage.

[0006] Existing support technologies employ a method of directly and tightly adhering to the surface of the tunnel to establish rigid initial support. The corresponding initial support mesh uses a metal mesh structure (such as the existing technology CN111236983A). Under the high stress of the rock strata surrounding the tunnel, this often causes concrete cracking and spalling in the initial support, as well as twisting and deformation of the arched steel frame. At the same time, the degree of automation in construction is low, the support efficiency is low, the labor intensity of construction workers is high, and they also face the personal threat of rock bursts, which greatly increases the project cost and construction risk. Summary of the Invention

[0007] This invention addresses the aforementioned problems in the prior art by providing a rigid mesh for initial tunnel support and a method for initial tunnel support. The support mesh combines rigidity and flexibility; its rigidity allows it to better conform to the tunnel surface, while its flexibility ensures it will not be damaged when the deformation is less than 14%, thus providing support for the tunnel surrounding rock. The support mesh is coated with a hydrophilic polymer, resulting in a rough coating surface that exhibits good affinity and high bonding strength with the secondary lining shotcrete material. Furthermore, the support mesh is lightweight, flexible, and can be installed mechanically, leading to high labor efficiency.

[0008] The technical solution of the present invention to solve the above-mentioned technical problems is as follows:

[0009] On one hand, the present invention provides a rigid mesh for initial support of tunnels, characterized in that it includes a base fabric and a hydrophilic polymer coating coated on the surface of the base fabric. The base fabric includes warp and weft yarns arranged perpendicularly to each other, and the warp and weft yarns are connected and fixed at their intersections by binding yarns. The surface of the hydrophilic polymer coating has a granular texture and a roughness of 0.1 to 0.4 mm.

[0010] Furthermore, the base fabric adopts a warp-knitted directional weaving structure through warp and weft yarns, and multiple adjacent warp yarns form a warp stripe, while multiple adjacent weft yarns form a weft stripe.

[0011] Furthermore, the present invention uses a full-width biaxial warp knitting machine to bind the warp and weft yarns together to weave a biaxial warp knitted mesh fabric, which is then coated with a special water-based adhesive by a coating machine and dried to form a support net with a certain rigidity.

[0012] Furthermore, the tensile strength of the base fabric is ≥200KN / m, the width of the warp and weft strips is ≤20mm, and the mesh size is ≥12*12cm.

[0013] Furthermore, the binding yarn is made of polyester, aramid, or ultra-high molecular weight polyethylene, with a knot peel force ≥5000N.

[0014] Furthermore, the warp and weft yarns are made of high-strength polyester fibers.

[0015] Furthermore, the hydrophilic polymer coating is composed of an aqueous emulsion, fillers, and additives.

[0016] Furthermore, the hydrophilic polymer coating is composed of the following components by weight fraction: 65-80% aqueous emulsion, 17-32% filler, and 3-4% additives.

[0017] Furthermore, the aqueous emulsion is at least one of aqueous epoxy emulsion, acrylic emulsion, styrene-butadiene emulsion, and styrene-acrylic emulsion; the filler is at least one of aluminum hydroxide, talc, montmorillonite, and kaolin with a particle size of 50-100 mesh; and the additives are dispersants, defoamers, and thickeners.

[0018] Furthermore, the dispersant is an alkanolamine organic compound, the defoamer is a polyether siloxane copolymer, and the thickener is an associative polyurethane organic compound.

[0019] On the other hand, the present invention provides a method for initial support of a tunnel, characterized in that a support net is laid out along the circumference of the tunnel, the support net is fixed to the top surface of the tunnel using anchor bolts, and then concrete mortar is sprayed to make it form an integral whole with the tunnel top surface and the rigid net, wherein the support net is a rigid net for initial support of a tunnel as described above.

[0020] The beneficial effects of this invention are as follows: This invention uses high-strength polyester fiber as raw material, employs warp-knitted directional weaving to create a base fabric structure, and optimizes the strip and mesh size. Simultaneously, a hydrophilic polymer coating is applied to impart a certain roughness, creating a rigid mesh for initial tunnel support that combines rigidity and flexibility. Furthermore, this invention creatively applies this rigid mesh to initial tunnel support, replacing existing metal mesh, improving the bonding strength between the support mesh and the surrounding rock and concrete. It forms a unified whole with the tunnel surface, effectively constraining surrounding rock deformation, providing support to prevent concrete cracking during initial support, and better stabilizing the working face support during rock bursts, preventing rockfalls and injuries. Attached Figure Description

[0021] Figure 1 This is a schematic diagram (partial view) of the flat structure of the rigid mesh for initial support of tunnels obtained in Embodiments 1-4 of the present invention;

[0022] Figure 2 This is a cross-sectional structural schematic diagram (partial view) of the rigid mesh for initial support of tunnels prepared according to embodiments 1-3 of the present invention;

[0023] In the diagram: 1. Warp yarn, 2. Weft yarn, 3. Binding yarn, 4. Warp strip, 5. Weft strip, 6. Hydrophilic polymer coating. Detailed Implementation

[0024] The principles and features of the present invention are described below. The embodiments given are only for explaining the present invention and are not intended to limit the scope of the present invention.

[0025] Example 1

[0026] This invention provides a rigid mesh for initial tunnel support, comprising a base fabric and a hydrophilic polymer coating 6 applied to the surface of the base fabric. The base fabric includes warp yarns 1 and weft yarns 2 arranged perpendicularly to each other, connected and fixed at their intersections by binding yarns 3. The surface of the hydrophilic polymer coating has a granular texture with a roughness of 0.28 mm. The base fabric is constructed using a warp-knitted directional weave structure with adjacent warp yarns forming warp stripes 4 and adjacent weft yarns forming weft stripes 5. The tensile strength of the base fabric is ≥200 KN / m, the width of the warp and weft stripes is 20 mm, and the mesh size is 12*12 cm. The warp and weft yarns are made of high-strength polyester fiber, and the binding yarns are made of polyester, aramid, or ultra-high molecular weight polyethylene, with a knot peel force ≥5000 N.

[0027] The hydrophilic polymer coating in this embodiment is composed of an aqueous emulsion, fillers, and additives. Specific components and weights are detailed in Table 1.

[0028] The coating process of the hydrophilic polymer coating is as follows: prepare the hydrophilic polymer adhesive according to the formula in Table 1, and inject it into the adhesive tank. Under a certain tension, unwind the base fabric into the adhesive tank, pass it through the extrusion roller into a vertical oven at 80-100℃, dry it in a flat oven at 120-140℃, and rewind it. The machine speed is controlled at 3-5m / min, and the amount of adhesive applied is controlled at 20-30%.

[0029] Example 2

[0030] This invention provides a rigid mesh for initial tunnel support, comprising a base fabric and a hydrophilic polymer coating 6 applied to the surface of the base fabric. The base fabric includes warp yarns 1 and weft yarns 2 arranged perpendicularly to each other, connected and fixed at their intersections by binding yarns 3. The surface of the hydrophilic polymer coating has a granular texture with a roughness of 0.35 mm. The base fabric is constructed using a warp-knitted directional weave structure with adjacent warp yarns forming warp stripes 4 and adjacent weft yarns forming weft stripes 5. The tensile strength of the base fabric is ≥200 KN / m, the width of the warp and weft stripes is 20 mm, and the mesh size is 12*12 cm. The warp and weft yarns are made of high-strength polyester fiber, and the binding yarns are made of polyester, aramid, or ultra-high molecular weight polyethylene, with a knot peel force ≥5000 N.

[0031] The hydrophilic polymer coating in this embodiment is composed of an aqueous emulsion, fillers, and additives. Specific components and weights are detailed in Table 1.

[0032] The coating process of the hydrophilic polymer coating is as follows: prepare the hydrophilic polymer adhesive according to the formula in Table 1, and inject it into the adhesive tank. Under a certain tension, unwind the base fabric into the adhesive tank, pass it through the extrusion roller into a vertical oven at 80-100℃, dry it in a flat oven at 120-140℃, and rewind it. The machine speed is controlled at 3-5m / min, and the amount of adhesive applied is controlled at 20-30%.

[0033] Example 3

[0034] This invention provides a rigid mesh for initial tunnel support, comprising a base fabric and a hydrophilic polymer coating 6 applied to the surface of the base fabric. The base fabric includes warp yarns 1 and weft yarns 2 arranged perpendicularly to each other, connected and fixed at their intersections by binding yarns 3. The hydrophilic polymer coating has a granular surface with a roughness of 0.26 mm. The base fabric is constructed using a warp-knitted directional weave structure with adjacent warp yarns forming warp stripes 4 and adjacent weft yarns forming weft stripes 5. The tensile strength of the base fabric is ≥200 KN / m, the width of the warp and weft stripes is 20 mm, and the mesh size is 12*12 cm. The warp and weft yarns are made of high-strength polyester fiber, and the binding yarns are made of polyester, aramid, or ultra-high molecular weight polyethylene, with a knot peel strength ≥5000 N.

[0035] The hydrophilic polymer coating in this embodiment is composed of an aqueous emulsion, fillers, and additives. Specific components and weights are detailed in Table 1.

[0036] The coating process of the hydrophilic polymer coating is as follows: prepare the hydrophilic polymer adhesive according to the formula in Table 1, and inject it into the adhesive tank. Under a certain tension, unwind the base fabric into the adhesive tank, pass it through the extrusion roller into a vertical oven at 80-100℃, dry it in a flat oven at 120-140℃, and rewind it. The machine speed is controlled at 3-5m / min, and the amount of adhesive applied is controlled at 20-30%.

[0037] Example 4

[0038] This invention provides a rigid mesh for initial tunnel support, comprising a base fabric and a hydrophilic polymer coating 6 applied to the surface of the base fabric. The base fabric includes warp yarns 1 and weft yarns 2 arranged perpendicularly to each other, and the warp yarns 1 and weft yarns 2 are connected and fixed at their intersections by binding yarns 3. The surface of the hydrophilic polymer coating has a granular texture with a roughness of 0.20 mm. The base fabric is constructed using a warp-knitted directional weave structure with adjacent warp yarns forming warp stripes 4 and adjacent weft yarns forming weft stripes 5. The tensile strength of the base fabric is ≥200 KN / m, the width of the warp and weft stripes is 20 mm, and the mesh size is 12*12 cm. The warp and weft yarns are made of high-strength polyester fiber, and the binding yarns are made of polyester, aramid, or ultra-high molecular weight polyethylene, with a knot peel force ≥5000 N.

[0039] The hydrophilic polymer coating of this embodiment is composed of an aqueous emulsion, fillers, and additives. The aqueous emulsion is at least one selected from aqueous epoxy resin, acrylic emulsion, styrene-butadiene emulsion, and styrene-acrylic emulsion. The filler is at least one selected from aluminum hydroxide with a particle size of 50-100 mesh, talc, montmorillonite, and kaolin. The additives are dispersants, defoamers, and thickeners. The dispersant is an alkanolamine organic compound, the defoamer is a polyether siloxane copolymer, and the thickener is an associative polyurethane organic compound. Specific components and weights are detailed in Table 1.

[0040] The coating process of the hydrophilic polymer coating is as follows: prepare the hydrophilic polymer adhesive according to the formula in Table 1, and inject it into the adhesive tank. Under a certain tension, unwind the base fabric into the adhesive tank, pass it through the extrusion roller into a vertical oven at 80-100℃, dry it in a flat oven at 120-140℃, and rewind it. The machine speed is controlled at 3-5m / min, and the amount of adhesive applied is controlled at 20-30%.

[0041] The components and amounts of the hydrophilic polymer coatings in the various embodiments and comparative examples of the present invention are shown in Table 1.

[0042] Table 1

[0043]

[0044] The rigid mesh prepared in the above embodiment is used for the initial tunnel support. The support method is as follows: the rigid mesh is laid out along the tunnel circumference using construction machinery, the rigid mesh is fixed to the tunnel top surface using anchor bolts, and then the sprayed concrete mortar forms a whole with the tunnel top surface and the rigid mesh.

[0045] The application performance of the rigid mesh for initial tunnel support prepared in the above embodiments and comparative examples was tested. The test method was in accordance with GB 50152-2017 "Standard Test Methods for Concrete Structures". The bond strength between the rigid mesh and the concrete was tested, and the results are shown in Table 2.

[0046] Table 2

[0047]

[0048] As shown in Table 2, the rigid mesh produced by this invention has a certain roughness, and its bond strength with concrete can reach 1.0-1.3 MPa, making it suitable for initial tunnel support. A comparison of the above embodiments and comparative examples shows that the smaller the filler particle size, the smaller the roughness of the support mesh coating, and correspondingly, the lower the bond strength with concrete, making it unsuitable for initial tunnel support.

Claims

1. A rigid mesh for initial support of a tunnel, characterized in that, The base cloth and the hydrophilic polymer coating applied on the surface of the base cloth, the base cloth comprises warp yarns and weft yarns which are arranged perpendicularly and cross each other, the warp yarns and the weft yarns are connected and fixed by binding yarns at the intersection, the surface of the hydrophilic polymer coating has a grainy feeling, and the roughness is 0.1-0.4mm; The hydrophilic polymer coating is composed of the following components by weight fraction: water-based emulsion 65-80%, filler 17-32%, and auxiliary agent 3-4%; The water-based emulsion is at least one of water-based epoxy emulsion, acrylic emulsion, styrene-butadiene emulsion, and phenylpropylene emulsion, and the filler is at least one of aluminum hydroxide, talcum powder, montmorillonite, and kaolin with a particle size of 50-100 mesh.

2. The rigid mesh for initial support of a tunnel according to claim 1, characterized in that, The base cloth is a warp-knitted oriented woven structure using warp yarns and weft yarns as raw materials, and a plurality of adjacent warp yarns form a warp strip, and a plurality of adjacent weft yarns form a weft strip.

3. The rigid mesh for initial tunnel support according to claim 2, characterized in that, The base cloth has a tensile strength of ≥200 KN / m, a warp and weft strip width of ≤20 mm, and a mesh of ≥12 12 cm.

4. The rigid mesh for initial tunnel support according to claim 1, characterized by, The binding yarns are made of polyester, aramid, or ultra-high molecular weight polyethylene, and the node peeling force is greater than or equal to 5000N.

5. The rigid mesh for initial tunnel support according to claim 1, characterized in that, The warp yarns and the weft yarns are made of high-strength polyester fibers.

6. The rigid mesh for initial tunnel support according to claim 1, characterized in that, The auxiliary agent is a dispersing agent, a defoaming agent, and a thickening agent.

7. The rigid mesh for initial tunnel support according to claim 6, characterized in that, The dispersing agent is an alcohol amine organic substance, the defoaming agent is a polyether siloxane copolymer, and the thickening agent is an associated polyurethane organic substance.

8. A method of initial support of a tunnel, characterized in that, The supporting net is spread along the tunnel in a circumferential direction, the supporting net is fixed on the top surface of the tunnel by using anchor rods, and then concrete mortar is sprayed to form an integral whole with the top surface of the tunnel and the rigid net, and the supporting net is the rigid net for tunnel primary support according to any one of claims 1-7.

Citation Information

Patent Citations

  • Primary supporting method for tunnel

    CN111236983A

  • Composition for producing waterborne coating and coating system prepared from composition

    CN108034346A

  • Rigid support net for mines, preparation method, paint composition and application

    CN110747654A

  • Waterproof engineering method for permeated water leakage in concrete structure

    JP2000272950A

  • Fabric reinforcement for improving cement board flexural strength and methods for making same

    US20230228085A1