Method and system for dispatching optical storage direct flexible system based on distribution robust optimization, and medium

By clustering and optimizing the time-series light-load scenarios of the photovoltaic-storage-direct-drive-flexible system, typical scenarios are generated, and the expected values ​​of load curtailment rate and light curtailment rate are controlled. This solves the scheduling problem of the photovoltaic-storage-direct-drive-flexible system under harsh scenarios and improves the robustness and flexibility of the system.

CN117439040BActive Publication Date: 2026-11-24CHINA ELECTRIC POWER RESEARCH INSTITUTE CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311392472.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-25
Publication Date
2026-11-24
Estimated Expiration
2043-10-25

AI Technical Summary

Technical Problem

Existing technologies have failed to effectively address the uncertainties and correlations between light and load in photovoltaic-storage direct-drive flexible systems, resulting in overly conservative or insufficiently robust decisions regarding curtailment rates and load rates under the worst-case scenarios, making it difficult to achieve flexible scheduling.

Method used

By clustering the time-series light-load scenarios, multiple typical scenarios are generated. The flexible operating domain model of the optical-storage-direct-flexible system with distributed bar constraints is used to control the expected values ​​of load abandonment rate and light abandonment rate under the worst probability distribution. The main problem and sub-problems are solved iteratively to obtain the flexible operating domain and realize system scheduling.

Benefits of technology

It improves the robust optimization universality and stochastic programming robustness of the photovoltaic-storage-DC-flexible system, ensures that the curtailment rate and curtailment rate are within the expected values, and provides the upper-level power grid with flexible scheduling support for the photovoltaic-storage-DC-flexible system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117439040B_ABST
    Figure CN117439040B_ABST
Patent Text Reader

Abstract

This invention discloses a method, system, and medium for scheduling a photovoltaic-storage-DC-flexible system based on bibloc bar optimization. The method includes considering the temporal randomness and temporal correlation of the photovoltaic-load transition (PV-load) scenario. Multiple typical PV-load scenarios are obtained by applying a K-clustering algorithm to the PV-load time-series scenarios. A pre-established flexible operating domain model of the PV-storage-DC-flexible system based on bibloc bar constraints is used. The uncertainty set of typical PV-load scenarios is calculated using the 1-norm and ∞-norm, simultaneously controlling the expected values ​​of load curtailment rate and solar power curtailment rate under the worst-case probability distribution within the expected values. The CCG algorithm is used to iteratively solve the main problem and sub-problems to obtain the flexible operating domain of the model. System scheduling is then performed based on the flexible operating domain. This invention improves the universality of robust optimization and the robustness of stochastic programming by controlling the expected values ​​of solar power curtailment rate and load curtailment rate under the worst-case probability distribution to meet requirements, and makes decisions based on this premise, thus achieving flexible scheduling of the PV-storage-DC-flexible system by the upper-level power grid.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of photovoltaic-storage-direct-drive-flexible system scheduling technology, specifically relating to a photovoltaic-storage-direct-drive-flexible system scheduling method, system, and medium based on distributed blue bar optimization. Background Technology

[0002] "PV-Storage-DC-Flexible" refers to an integrated technology path that uses direct current (DC) as the core architecture of a system, connecting distributed solar photovoltaic (PV) systems, distributed energy storage systems, and adjustable energy loads. Through flexible energy user-side technology, it interacts with the power system in a "load-follows-source" manner. The advantage of "PV-Storage-DC-Flexible" technology lies in transforming the system's power load from a rigid load to a flexible load, better adapting to the high proportion of wind and solar power in future grid power sources. However, under the influence of uncertainties and correlations in the solar-load relationship, the absorption of PV and the reduction of flexible loads still face challenges. Furthermore, the flexible operating domain of the PV-Storage-DC-Flexible system is a set of operating points for all state variables under the constraints of flexible and controllable resource operation and safety constraints within the system; it is a high-dimensional and complex space that is difficult to observe directly. Existing technologies mitigate the impact of solar-load stochasticity on system operation and improve solution efficiency, but because they ignore the probability distribution of uncertainties and make decisions under the worst-case scenario, the results are either overly conservative or have poor robustness. Summary of the Invention

[0003] The purpose of this invention is to address the problems in the prior art by providing a method, system, and medium for scheduling a photovoltaic-storage-DC-flexible system based on robust optimization. By controlling the expected values ​​of curtailment rate and load curtailment rate under the worst probability distribution to meet the requirements, and making decisions based on this premise, the universality of robust optimization and the robustness of stochastic programming are improved, enabling flexible scheduling of the photovoltaic-storage-DC-flexible system by the upper-level power grid.

[0004] To achieve the above objectives, the present invention provides the following technical solution: Firstly, a scheduling method for a direct-drive-flexible optical storage system based on distributed bar optimization is provided, including: Multiple sets of typical light-charge scenarios were obtained by clustering the light-charge time-series scenarios; By utilizing a pre-established flexible operating domain model of a photovoltaic-storage-direct-flexible system based on split-blown rod constraints, the uncertainty set of typical photovoltaic-load scenarios is calculated, and the expected values ​​of load abandonment rate and light abandonment rate under the worst probability distribution are simultaneously controlled within the expected values. The flexible operating domain of the model is obtained by iteratively solving the main problem and subproblems, and the system is scheduled according to the flexible operating domain.

[0005] As a preferred embodiment, in the step of obtaining multiple sets of typical light-load scenarios by clustering the light-load time-series scenarios, the optimal number of clusters is determined by the elbow method, and the K-clustering algorithm is used to obtain multiple sets of typical light-load scenarios.

[0006] As a preferred embodiment, in the step of determining the optimal number of clusters using the elbow method, the sum of squared errors is used. SSE The core indicator is the sum of squared errors. SSE The smaller the value, the better the clustering effect; sum of squared errors. SSE The calculation expression is as follows: (B-1) In the formula: It is the first n A cluster; p yes Sample points in; yes The centroid is numerically equal to The average of all samples in the sample; K It represents the total number of clusters.

[0007] As a preferred embodiment, in the step of obtaining multiple sets of typical light-charge scenarios using the K-clustering algorithm, the typical light-charge scenarios are generated according to the following formula: (B-2) (B-3) (B-4) In the formula, Total number of scenes; For the first s Number of scenes in the class; and They are the first i Photovoltaic output and load status in each scenario; For the first s A typical photovoltaic power output scenario; For the first s A typical load scenario; For the first s The initial probability of a typical photovoltaic / load scenario; 0-1 state variables for classifying scenes, when scene i Classified by scene s When the center is in the class Otherwise, it is 0.

[0008] As a preferred approach, in the step of using a pre-established flexible operating domain model of a photovoltaic-storage-DC-flexible system based on sub-Brønsted bar constraints to calculate the uncertainty set of typical photovoltaic-load scenarios and simultaneously control the expected values ​​of load curtailment rate and solar curtailment rate under the worst probability distribution within the expected values, the flexible operating domain model of the photovoltaic-storage-DC-flexible system based on sub-Brønsted bar constraints includes expressions for equipment operation constraints and the main problem. The equipment operation constraints include constraints for the energy storage system, photovoltaic system, air conditioning operation, flexible load, AC / DC converter, distribution transformer, and energy conservation constraints. The main problem aims to obtain an observable flexible safety domain.

[0009] As a preferred embodiment, the expression for the constraints of the energy storage system includes: Upper limit constraints on energy storage charging and discharging power: (B-5) (B-6) Non-simultaneous charge / discharge energy constraints: (B-7) Energy storage balance constraints: (B-8) Energy storage upper and lower bound constraints: (B-9) In the formula: and Typical scenarios s China Energy Storage t Charging and discharging power during different time periods; The maximum output and input power of the energy storage; and Typical scenarios s middle t The energy storage charging and discharging status is displayed at all times; it is 1 when charging or discharging, and 0 otherwise. Typical scenario s middle t Energy storage capacity at all times; and These are the energy storage charging and discharging efficiencies, respectively. The self-consumption rate of energy storage; The time interval between adjacent time periods; Define the rated capacity for energy storage access; set the parameters for each scenario ( t The energy storage capacity is consistent at time -1).

[0010] As a preferred embodiment, the photovoltaic system constraints consider establishing a curtailment rate constraint for a single typical scenario and an expected curtailment rate constraint for a typical scenario under the worst-case probability distribution; the expressions for the photovoltaic system constraints include: Upper and lower limits of photovoltaic power output constraints: (B-10) Typical scenarios s Down t Amount of light discarded at any given time: (B-11) Upper limit constraints on light curtailment rate for various typical scenarios: (B-12) Upper limit constraint on the expected value of curtailment rate in a typical scenario under the worst probability distribution: (B-13) In the formula: Typical scenario s Down t The maximum output of photovoltaic power at any given time; Typical scenario s Down t The actual output of photovoltaic power at any given moment; Typical scenario s The worst probability; This represents the upper limit of light rejection rate for a single typical scenario; This represents the upper limit of the expected light rejection rate for a typical scenario under the worst probability distribution.

[0011] As a preferred embodiment, the expression for the air conditioning operation constraint includes: Load power limit constraint: (B-14) Power factor constraints of the load: (B-15) Ensure the indoor temperature remains within a certain range: (B-16) The linear relationship between the next indoor temperature and the current indoor temperature, outdoor temperature, and load power conforms to the following: (B-17) HVAC converter capacity constraints: (B-18) In the formula, , This is a typical scenario s Down t Active power and reactive power of HVAC load at any given time; This is the upper limit of active power for HVAC systems; It is a constant that defines a fixed power factor; This is a typical scenario s Down t The building's indoor temperature at any given time; , These are the highest and lowest indoor temperatures, respectively. and These are thermal parameters that specify the characteristics of buildings and their environment; It can be positive or negative; in winter, a positive value is taken as warm, and in summer, a negative value is taken as cold. This is the maximum capacity of the HVAC converter; set for each scenario ( t The indoor temperature is consistent at time -1).

[0012] As a preferred embodiment, the expression for the flexible load constraint includes: Maximum load reduction limit at any given time: (B-19) Upper limit constraints on the payload abandonment rate for each typical scenario: (B-20) Upper limit constraint on the expected value of the abandonment rate in a typical scenario under the worst-case probability distribution: (B-21) In the formula, Typical scenario s Down t The amount of load reduction at any given time; The maximum load power that can be reduced for DC flexible loads; A 0-1 variable representing the DC flexible load reduction state; This represents the upper limit of the payload abandonment rate for a single typical scenario; This represents the upper limit of the expected payload abandonment rate for a typical scenario under the worst-case probability distribution.

[0013] As a preferred embodiment, the expression for the AC / DC converter constraint includes: The efficiency conversion of power flowing through VSC conforms to: (B-22) Reactive power compensation constraint upper and lower limits: (B-23) VSC capacity constraints: (B-24) In the formula, and They are t Active power values ​​on the AC and DC sides of the converter at all times; yes tThe reactive power compensation value of the converter at any given time; and They are respectively The upper and lower limits; For the capacity of VSC; The expressions for the distribution transformer constraints include: (B-25) (B-26) (B-27) In the formula, for t The active power of the distribution transformer at all times; for t The reactive power of the distribution transformer at all times; Maximum capacity; The expression for the energy conservation constraint is: (B-28) In the formula, It refers to the efficiency of the AC / DC converter; It refers to the efficiency of the DC / DC converter; This is a typical scenario s Down t The load demand at any time, yes t The active power values ​​of the AC and DC sides of the converter at any given time.

[0014] As a preferred embodiment, the expression for the main problem includes: by W Let represent all operational state variables of the optical-storage-direct-drive-flexible system. Then, the security domain of the optical-storage-direct-drive-flexible system is: (B-29) In the formula, These are equality constraints; These are inequality constraints. To meet the flexible and controllable resource operation constraints and safety constraints within the system, the gate converter has a flexible and adjustable operating space for active or reactive power. The upper and lower boundaries of the reactive power of the switchgear in the photovoltaic-storage-DC-flexible system are obtained using the following formulas: (B-30) (B-31) In the formula, and These are the upper and lower limits of the system's reactive power, respectively. In the interval One of a series of working points obtained at equal internal distances, then ; Fixed reactive power compensation as By repeatedly solving the following two equations, a series of safety boundary points corresponding to the active power values ​​of the converter are obtained: (B-32) (B-33) For the set of boundary points of the flexible operating domain, Y The boundary points of the operating domain are solved using the following formula: (B-34) In the formula For the first l Each piecewise coefficient; For the first l One work site; The number of boundary points; z A linear combination of operating points; Based on the obtained series of runtime boundary points, the flexible runtime is generated by MATLAB's ConvexHull function.

[0015] As a preferred embodiment, in the step of using a pre-established flexible operating domain model of the optical-storage-direct-flexible system based on the constraint of the split-bulb rod to calculate the uncertainty set of typical light-load scenarios and simultaneously control the expected values ​​of the load abandonment rate and light abandonment rate under the worst probability distribution within the expected values, the uncertainty set of typical light-load scenarios is calculated by using the 1-norm and the ∞-norm. The sub-problem aims to obtain the expected value of the maximum curtailment rate of light and load; The worst-case probability distribution was obtained through the following max-min two-level optimization: (B-35) (B-36) In the formula, This represents an uncertain set of adverse probability distributions for typical scenarios; For the first s The initial probability of a typical photovoltaic / load scenario; This represents the allowed probability deviation value under the 1-norm constraint; This represents the allowed probability deviation value under the infinite norm constraint; Given a confidence level of uncertainty and In this case, and Calculate according to the following formula: (B-37) (B-38).

[0016] As a preferred embodiment, in the step of iteratively solving the main problem and subproblems to obtain the flexible operating domain of the model, and then performing system scheduling based on the flexible operating domain, the CCG algorithm is used to iteratively solve the main problem and subproblems to obtain the flexible operating domain of the model. The main problem is retained, and the subproblems are further decomposed into a first subproblem SP1 and a second subproblem SP2 for solving. The objective function expression is as follows: (MP):

[0017] (SP1):

[0018] (SP2): .

[0019] Secondly, a scheduling system for a photovoltaic-storage-direct-flexible system based on distributed bar optimization is provided, including: The light-load scene acquisition module is used to obtain multiple sets of typical light-load scenes by clustering light-load time-series scenes; The load curtailment rate and light curtailment rate control module is used to utilize a pre-established flexible operating domain model of the optical-storage-direct-flexible system based on the bibliometric rod constraint to calculate the uncertainty set of typical optical-load scenarios, and simultaneously control the expected values ​​of load curtailment rate and light curtailment rate under the worst probability distribution within the expected values. The flexible operating domain solution and scheduling module is used to iteratively solve the main problem and sub-problems to obtain the flexible operating domain of the model, and to perform system scheduling based on the flexible operating domain.

[0020] Thirdly, an electronic device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the optical storage direct current flexible system scheduling method based on distributed bar optimization.

[0021] Fourthly, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program, and the computer program, when executed by a processor, implements the optical storage direct current flexible system scheduling method based on distributed bar optimization.

[0022] Compared with the prior art, the first aspect of the present invention has at least the following beneficial effects: For photovoltaic-storage-DC-flexible systems based on biplastic bar optimization, solving for their flexible operating domain is of great significance. This invention considers the temporal randomness and temporal correlation of light-load, and obtains multiple typical light-load scenarios by clustering the light-load time-series scenarios. The uncertain set of typical light-load scenarios is calculated using a flexible operating domain model of the photovoltaic-storage-DC-flexible system based on biplastic bar constraints. This ensures that the expected values ​​of curtailment rate and light curtailment rate under the worst-case probability distribution are simultaneously controlled within expected values, guaranteeing that the expected values ​​of light curtailment rate and load curtailment rate under the worst-case probability distribution for each typical scenario meet the requirements. Decisions are made based on this premise, improving the universality of robust optimization and the robustness of stochastic programming. The flexible operating domain of the model can be obtained by repeatedly solving the main problem and sub-problems, enabling visualization of the flexible operating domain and providing support for the upper-level power grid to flexibly schedule the photovoltaic-storage-DC-flexible system.

[0023] It is understood that the beneficial effects of the second to fifth aspects mentioned above can be found in the relevant descriptions in the first aspect mentioned above, and will not be repeated here. Attached Figure Description

[0024] To more clearly illustrate the technical solutions in the embodiments of this application, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of this application. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0025] Figure 1 Flowchart of the optical-storage-direct-flexible system scheduling method based on split-blown bar optimization according to an embodiment of the present invention; Figure 2 Topology diagram of the optical-storage direct-drive flexible system according to an embodiment of the present invention; Figure 3 Clustering bias diagrams with different K values ​​in embodiments of the present invention; Figure 4 A typical light-charge scenario diagram of an embodiment of the present invention; Figure 5 Three-dimensional operating domain diagram under initial indoor temperature changes in this embodiment of the invention; Figure 6 Figure 5 A two-dimensional magnified view of a portion of the image; Figure 7 Three-dimensional flexible operating domain diagram under the initial energy storage state of charge change in an embodiment of the present invention; Figure 8 The present invention provides a comparison diagram of the robust operating domain and the robust operating domain in its embodiments. Detailed Implementation

[0026] In the following description, specific details such as particular system architectures and techniques are set forth for illustrative purposes and not for limitation, in order to provide a thorough understanding of the embodiments of this application. However, those skilled in the art will understand that this application may also be implemented in other embodiments without these specific details. In other instances, detailed descriptions of well-known systems, apparatuses, circuits, and methods have been omitted so as not to obscure the description of this application with unnecessary detail.

[0027] Furthermore, in the description of this application and the appended claims, the terms "first," "second," "third," etc., are used only to distinguish descriptions and should not be construed as indicating or implying relative importance.

[0028] Please see Figure 1 The scheduling method for a direct-drive flexible optical-storage system based on split-bar optimization according to embodiments of the present invention includes the following steps: Step 1: Introduce the "elbow method" to determine the optimal number of clusters, and use the K-clustering algorithm to obtain multiple sets of typical light-load scenarios; Step 2: Introduce equipment, state variables, and decision variables, and map the original high-dimensional operating domain to the two-dimensional state space of the active and reactive power of the switch converter at the distribution transformer outlet of the photovoltaic-storage-DC-flexible system, and construct a flexible operating domain model of the photovoltaic-storage-DC-flexible system based on the Bruker bar constraint. Step 3: Based on the flexible operating domain model constructed in Step 2, calculate the uncertain set of the time series scenario through the 1-norm and ∞-norm, and simultaneously control the expected values ​​of the load abandonment rate and light abandonment rate under the worst probability distribution within the expected values.

[0029] Step 4: Solve the main and sub-problems proposed in Steps 2 and 3, that is, use the CCG algorithm to repeatedly solve the main and sub-problems to obtain the flexible operating domain of the model.

[0030] Furthermore, in step 1, the "elbow method" is introduced to determine the optimal number of clusters, and the K-clustering algorithm is used to obtain multiple sets of typical light-charge scenarios. The specific method is as follows: The core indicator of the "elbow method" is the sum of squared errors. SSE , SSE The smaller the value, the better the clustering effect.

[0031] (B-1) In the formula: It is the first n A cluster; p yes Sample points in; yes The centroid is numerically equal to The average of all samples in the sample; K It represents the total number of clusters.

[0032] The core idea of ​​the "elbow method" has two points. First, as the number of clusters increases... K As the size increases, the sample partitioning becomes more refined, and the aggregation degree of each cluster gradually increases. SSE It will gradually become smaller. Secondly, when... K When the number is less than the actual number of clusters, K Increasing the value of will significantly increase the aggregation degree of each cluster; when K When the true number of clusters is reached, the degree of clustering tends to level off as the value of k continues to increase, meaning that... SSE and K The relationship diagram is the shape of an elbow, and the elbow corresponds to... K The value represents the actual number of clusters in the data. Based on the above, the optimal number of clusters can be determined. K .

[0033] A typical light-charge time series scenario can be generated according to the following formula: (B-2) (B-3) (B-4) In the formula: Total number of scenes; For the first s Number of scenes in the class; and These represent the photovoltaic output and load conditions for the i-th scenario, respectively. For the first s A typical photovoltaic power output scenario; This is the s-th typical load scenario; For the first s The initial probability of a typical photovoltaic / load scenario; 0-1 state variables for classifying scenes, when scene i Classified by scene s When the center is in the class Otherwise, it is 0.

[0034] Furthermore, in step 2, the equipment is introduced, and the state variables and decision variables are associated with the equipment. The original high-dimensional operating domain is mapped to the state space of the active and reactive power of the switch converter at the distribution transformer outlet of the photovoltaic-storage-DC-flexible system, thus constructing a flexible operating domain model of the photovoltaic-storage-DC-flexible system based on the Bruker bar constraint. The specific method is as follows: Equipment operation constraints: energy storage system constraints, photovoltaic system constraints, air conditioning operation constraints, flexible load constraints, AC / DC converter constraints, distribution transformer constraints, energy conservation constraints; 1) Constraints of energy storage systems (B-5) (B-6) (B-7) (B-8) (B-9) In the formula: and Typical scenarios s China Energy Storage t Charging and discharging power during different time periods; The maximum output and input power of the energy storage; and Typical scenarios s middle t The energy storage charging and discharging status is displayed at all times; it is 1 when charging or discharging, and 0 otherwise. Typical scenario s middle t Energy storage capacity at all times; and These are the energy storage charging and discharging efficiencies, respectively. The self-consumption rate of energy storage; The time interval between adjacent time periods; Define the rated capacity for energy storage access; set the parameters for each scenario ( t The energy storage capacity is consistent at time -1).

[0035] Equations (B-5) and (B-6) are the upper limit constraints of energy storage charging and discharging power, respectively; Equation (B-7) is the constraint of simultaneous charging and discharging; Equation (B-8) is the energy storage balance constraint; and Equation (B-9) is the upper and lower limit constraints of energy storage.

[0036] 2) Constraints of photovoltaic systems Consider establishing a curtailment rate constraint for a single typical scenario and an expected curtailment rate constraint for the typical scenario under the worst-case probability distribution: (B-10) (B-11) (B-12) (B-13) In the formula: Typical scenario s Down t The maximum output of photovoltaic power at any given time; Typical scenario s Down t The actual output of photovoltaic power at any given moment; Typical scenario s The worst probability; This represents the upper limit of light rejection rate for a single typical scenario; This represents the upper limit of the expected light rejection rate for a typical scenario under the worst probability distribution.

[0037] Equation (B-10) represents the upper and lower limits of photovoltaic power output; Equation (B-11) calculates typical scenarios. s Down t The amount of light wasted at any given time; Equation (B-12) is the upper limit constraint of the light wasted rate for each typical scenario; Equation (B-13) is the upper limit constraint of the expected value of the light wasted rate for a typical scenario under the worst probability distribution.

[0038] 3) Air conditioning operation constraints (B-14) (B-15) (B-16) (B-17) (B-18) In the formula: , This is a typical scenario s Down t Active power and reactive power of HVAC load at any given time; This is the upper limit of active power for HVAC systems; It is a constant, meaning that a fixed power factor is defined; This is a typical scenario s Down t The building's indoor temperature at any given time; , These are the highest and lowest indoor temperatures, respectively. and These are thermal parameters that specify the characteristics of buildings and their environment; It can be positive or negative; positive for heating (in winter) and negative for cooling (in summer). This is the maximum capacity of the HVAC converter. Set for each scenario ( t The indoor temperature is consistent at time -1).

[0039] Equation (B-14) represents an upper limit constraint on load power; Equation (B-15) represents a power factor constraint on the load; Equation (B-16) ensures that the indoor temperature is within a certain range; Equation (B-17) represents a linear relationship between the indoor temperature at the next moment and the current indoor temperature, outdoor temperature, and load power; Equation (B-18) represents a capacity constraint on the HVAC converter.

[0040] 4) Flexible load constraints A certain proportion of the electrical load is flexible load, and the implementation plan mainly considers loads that can be reduced.

[0041] (B-19) (B-20) (B-21) In the formula: Typical scenario s Down t The amount of load reduction at any given time; The maximum load power that can be reduced for DC flexible loads; A 0-1 variable representing the DC flexible load reduction state; This represents the upper limit of the payload abandonment rate for a single typical scenario; This represents the upper limit of the expected payload abandonment rate for a typical scenario under the worst-case probability distribution.

[0042] Equation (B-19) is the upper limit constraint of the load reduction amount at each moment; Equation (B-20) is the upper limit constraint of the load abandonment rate for each typical scenario; Equation (B-21) is the upper limit constraint of the expected value of the load abandonment rate for a typical scenario under the worst probability distribution.

[0043] 5) AC / DC converter constraints (B-22) (B-23) (B-24) In the formula: and They are t Active power values ​​on the AC and DC sides of the converter at all times; yes t The reactive power compensation value of the converter at any given time; and They are respectively The upper and lower limits; This refers to the capacity of the VSC.

[0044] Equation (B-22) represents the efficiency conversion of power flowing through the VSC; Equation (B-23) represents the upper and lower limits of reactive power compensation constraints; Equation (B-24) represents the VSC capacity constraint.

[0045] 6) Constraints of distribution transformers (B-25) (B-26) (B-27) In the formula: for t The active power of the distribution transformer at all times; for t The reactive power of the distribution transformer at all times; This is the maximum capacity.

[0046] Equation (B-25) indicates that losses are ignored; Equation (B-27) indicates that capacity is constrained.

[0047] 7) Energy conservation constraint (B-28) In the formula: It refers to the efficiency of the AC / DC converter; It refers to the efficiency of the DC / DC converter; This is a typical scenario s Down t The load demand at any given moment. yes t The active power values ​​of the AC and DC sides of the converter at any given time.

[0048] Main problem (MP): The objective is to obtain an observable flexible security domain; W Let the variables represent all operating state variables of the optical-storage-direct-drive-flexible system be represented. Then, the expression for the security domain of the optical-storage-direct-drive-flexible system is as follows: (B-29) In the formula: These are equality constraints; These are inequality constraints. To meet the flexible and controllable resource operation constraints and safety constraints within the system, the active / reactive power of the gateway converter is flexibly adjustable.

[0049] The upper and lower boundaries of the reactive power of the gateway converter in the photovoltaic-storage-DC-flexible system are obtained using equations (B-30) and (B-31), respectively: (B-30) (B-31) In the formula: and These are the upper and lower limits of the system's reactive power, respectively.

[0050] In the interval One of a series of working points obtained at equal internal distances, then The reactive power compensation is fixed at... By repeatedly solving the optimization model equations (B-32) and (B-33), a series of safety boundary points corresponding to the converter's active power value can be obtained: (B-32) (B-33) Based on the obtained series of operating points, a flexible operating domain based on a convex hull can be constructed. The set of boundary points of the flexible operating domain is defined as follows: Y The expression for the boundary points of the running domain is: (B-34) In the formula For the first l Each piecewise coefficient; For the first l One work site; The number of boundary points; z It is a linear combination of operating points.

[0051] The flexible operating domain is essentially a process of linearizing the nonlinear safety boundary into pieces. Based on a series of safety domain boundary points, the flexible operating domain can be generated by MATLAB's ConvexHull function.

[0052] Furthermore, step 3, based on the flexible operating domain model constructed in step 2, calculates the uncertain set of the time-series scenario using the 1-norm and ∞-norm, and simultaneously controls the expected values ​​of the load shedding rate and light curtailment rate under the worst-case probability distribution within the expected values. The specific method is as follows: Subproblem (SP): The goal is to find the expected value of the maximum curtailment rate.

[0053] The worst-case probability distributions in equations (B-13) and (B-21) are obtained through the following max-min two-layer optimization, assuming that curtailment of light and curtailment of payload are equally important.

[0054] (B-35) (B-36) In the formula: This represents an uncertain set of adverse probability distributions for typical scenarios; For the first s The initial probability of a typical photovoltaic / load scenario; This represents the allowed probability deviation value under the 1-norm constraint; This represents the allowed probability deviation value under the infinite norm constraint.

[0055] In equation (B-36), the inner layer minimizes the amount of curtailed solar power in each scenario to promote photovoltaic (PV) consumption and load reduction in the PV-storage-DC-flexible system; the outer layer maximizes the expected amount of curtailed solar power in each scenario, aiming to identify the worst-case probability distribution and improve the overall robustness of the model. (Probability uncertainty set) Equation 1 is a constraint that the sum of probabilities of each scenario is 1; Equation 2 is a constraint that the upper and lower limits of the probability of each scenario being severe are constrained; Equation 3 is a constraint that the upper limit of the sum of the probability deviations of each scenario is constrained; Equation 4 is a constraint that the upper limit of the maximum probability of each scenario is constrained.

[0056] Given a confidence level of uncertainty and In this case, and It can be calculated using the following formula: (B-37) (B-38) Where: Uncertainty confidence level and The larger the value, the greater the allowable probability deviation. and The larger the set of uncertainties, the worse the worst probability distribution that can be achieved under the constraints of uncertain sets, and the more conservative the model becomes.

[0057] Furthermore, in step 4, the main and sub-problems proposed in steps 2 and 3 are solved. That is, the CCG algorithm is used to repeatedly solve the main and sub-problems to obtain the flexible operating domain of the model. The specific method is as follows: The main problem (MP) solves for the boundary points of the feasible region under the constraint of a finite probability distribution of worst-case conditions. The subproblem (SP), given the boundary points obtained from the main problem, minimizes the expected light and payload abandonment amounts for each typical scenario under the worst-case probability distribution, thus identifying the worst-case probability distribution. Since the outer and inner decision variables of the subproblem are uncoupled in the constraints, it can be further decomposed into subproblem 1 (SP1) and subproblem 2 (SP2) for solution. MP, SP1, and SP2 are described below.

[0058] (MP):

[0059] (SP1):

[0060] (SP2):

[0061] Additionally: , .

[0062] In summary, the steps for solving the main and subproblems based on the CCG algorithm are as follows: (1) Set the number of iterations L =0, Pick ,set up r 1=1, r 2 = 1; (2) Give the loop condition: r1> Or r2> ; (3) Solve for MP: Equation (B-30) and Equation (B-31); (4) Solve SP1 to obtain the optimal amount of light and payload wastage for each typical scenario; (5) Solve for SP2 and identify the probability distribution of adverse events. ; (6) L = L +1, ; (7) Determine whether the loop condition is met. If it is met, exit the loop; otherwise, continue the loop. (8) Modify MP in step (3) to Equation (B-32) and Equation (B-33); (9) Repeat steps (B-1~B-7) to solve the problem repeatedly.

[0063] Adopting such Figure 2 The implementation effect of the method of the present invention will be explained by taking the optical-storage-direct-flexible system topology shown as an example.

[0064] The energy storage battery has a capacity of 100kWh, a charge / discharge efficiency of 0.9, and minimum and maximum SOC of 0.2 and 0.8, respectively. The upper limit for curtailment rate in a single typical scenario is 10%, and the upper limit for expected curtailment rate in a typical scenario is 5%. The upper limit for load curtailment rate in a single typical scenario is 10%, and the upper limit for expected load curtailment rate in a typical scenario is 5%. The minimum and maximum indoor temperatures are set at 20℃ and 26℃, respectively. The upper and lower limits for active power at the transformer outlet of the photovoltaic-storage-DC-flexible system are 200kWh and 0, respectively, and the upper and lower limits for reactive power are 200kVar and -200kVar, respectively. The efficiency of the AC / DC converter is set at 0.88, and the efficiency of the DC / DC converter is set at 0.93. Uncertainty confidence level. and Each is 0.95. 11:00 is selected as the research object. This invention is implemented through the GAMS optimization platform and uses the GUROBI solver to solve the MIP problem.

[0065] Depend on Figure 3 It can be seen that when K When it is less than 6, K Increasing the value of will significantly increase the aggregation degree of each cluster; when K When the value is greater than 6, the degree of polymerization increases with... K The value continues to increase and then tends to level off, thus allowing us to determine the optimal number of clusters. K It is 6.

[0066] Figure 4The study showcases six typical solar-load scenarios after clustering. These typical solar-load scenarios include high PV load, high PV load, low PV load, low PV load, and low PV load, demonstrating strong representativeness.

[0067] With an initial SOC of 0.5 for the energy storage battery and an outdoor temperature of 31.8℃, the flexible operating domains of the photovoltaic-storage-flexible system under different initial indoor temperatures are as follows: Figure 5 As shown, as the indoor temperature rises, the power required for air conditioning cooling increases, and the overall flexible operating range shifts upwards. Figure 6 It provides a more intuitive demonstration of the changes in the operating domain as the initial indoor temperature changes.

[0068] Initial indoor temperature 23℃, outdoor temperature 31.8℃, uncertainty confidence level and Each is 0.95, representing the bibloc rod flexibility operating domain of a photovoltaic-storage-DC-flexible system under different initial energy storage charge states. Figure 7 As shown, as the initial SOC of the energy storage increases, the maximum charging capacity decreases, the maximum discharging capacity increases, and the overall flexible operating domain shifts downward.

[0069] The initial SOC of the energy storage battery is 0.5, the initial indoor temperature is 23℃, and the outdoor temperature is 31.8℃. (Uncertainty level confidence level) and Each is 0.95. The robust operating domain and robust operating domain of the optical-storage-flexible system are as follows: Figure 8 As shown. Since the robust operating domain does not allow light or load abandonment in each scenario, compared with the partially robust constrained operating domain, the upper limit of active power in VSC is lowered and the lower limit is raised; the range of reactive power values ​​in VSC is narrowed.

[0070] Another embodiment of the present invention proposes a scheduling system for a photovoltaic-storage-direct-flexible system based on split-blown bar optimization, comprising: The light-load scene acquisition module is used to obtain multiple sets of typical light-load scenes by clustering light-load time-series scenes; The load curtailment rate and light curtailment rate control module is used to utilize a pre-established flexible operating domain model of the optical-storage-direct-flexible system based on the bibliometric rod constraint to calculate the uncertainty set of typical optical-load scenarios, and simultaneously control the expected values ​​of load curtailment rate and light curtailment rate under the worst probability distribution within the expected values. The flexible operating domain solution and scheduling module is used to iteratively solve the main problem and sub-problems to obtain the flexible operating domain of the model, and to perform system scheduling based on the flexible operating domain.

[0071] Another embodiment of the present invention provides an electronic device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the optical storage direct current flexible system scheduling method based on split-blown bar optimization.

[0072] Another embodiment of the present invention provides a computer-readable storage medium storing a computer program, which, when executed by a processor, implements the optical-storage-direct-flexible system scheduling method based on distributed bar optimization.

[0073] The computer program includes computer program code, which can be in the form of source code, object code, executable file, or some intermediate form. The computer-readable storage medium can include any entity or device capable of carrying the computer program code, a medium, a USB flash drive, a portable hard drive, a magnetic disk, an optical disk, a computer memory, a read-only memory, a random access memory, an electrical carrier signal, a telecommunication signal, and a software distribution medium, etc. It should be noted that the content included in the computer-readable medium can be appropriately added or removed according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, the computer-readable medium does not include electrical carrier signals and telecommunication signals. For ease of explanation, the above content only shows the parts related to the embodiments of the present invention; for specific technical details not disclosed, please refer to the method section of the embodiments of the present invention. This computer-readable storage medium is non-transitory and can be stored in storage devices formed by various electronic devices, enabling the execution process described in the method of the embodiments of the present invention.

[0074] Those skilled in the art will understand that embodiments of the present invention can be provided as methods, systems, or computer program products. Therefore, the present invention can take the form of a completely hardware embodiment, a completely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present invention can take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0075] This invention is described with reference to flowchart illustrations and / or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the invention. It should be understood that each block of the flowchart illustrations and / or block diagrams, and combinations of blocks in the flowchart illustrations and / or block diagrams, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, special-purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, generate instructions for implementing the flowchart illustrations and / or block diagrams. Figure 1 One or more processes and / or boxes Figure 1 A device that provides the functions specified in one or more boxes.

[0076] These computer program instructions may also be stored in a computer-readable storage medium that can direct a computer or other programmable data processing device to function in a particular manner, such that the instructions stored in the computer-readable storage medium produce an article of manufacture including instruction means, which are implemented in a process Figure 1 One or more processes and / or boxes Figure 1 The function specified in one or more boxes.

[0077] These computer program instructions may also be loaded onto a computer or other programmable data processing equipment to cause a series of operational steps to be performed on the computer or other programmable equipment to produce a computer-implemented process, thereby providing instructions that execute on the computer or other programmable equipment for implementing the process. Figure 1 One or more processes and / or boxes Figure 1 The steps of the function specified in one or more boxes.

[0078] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention and not to limit it. Although the present invention has been described in detail with reference to the above embodiments, those skilled in the art should understand that modifications or equivalent substitutions can still be made to the specific implementation of the present invention. Any modifications or equivalent substitutions that do not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

Claims

1. A scheduling method for a photovoltaic-storage-direct-drive-flexible system based on distributed bar optimization, characterized in that, include: Multiple sets of typical light-charge scenarios were obtained by clustering the light-charge time-series scenarios; By utilizing a pre-established flexible operating domain model of a photovoltaic-storage-direct-flexible system based on split-blown rod constraints, the uncertainty set of typical photovoltaic-load scenarios is calculated, and the expected values ​​of load abandonment rate and light abandonment rate under the worst probability distribution are simultaneously controlled within the expected values. Iteratively solve the main problem and subproblems to obtain the flexible operating domain of the model, and perform system scheduling based on the flexible operating domain; In the step of calculating the uncertainty set of typical solar-load scenarios using a pre-established flexible operating domain model of a photovoltaic-storage-DC-flexible system based on sub-Brønsted bar constraints, and simultaneously controlling the expected values ​​of the curtailment rate and the curtailment rate under the worst probability distribution within the expected values, the flexible operating domain model of the photovoltaic-storage-DC-flexible system based on sub-Brønsted bar constraints includes expressions for equipment operation constraints and the main problem. The equipment operation constraints include constraints for the energy storage system, photovoltaic system, air conditioning operation, flexible load, AC / DC converter, distribution transformer, and energy conservation. The main problem aims to obtain an observable flexible safety domain. The photovoltaic system constraints consider establishing a curtailment rate constraint for a single typical scenario and an expected curtailment rate constraint for a typical scenario under the worst-case probability distribution; the expressions for the photovoltaic system constraints include: Upper and lower limits of photovoltaic power output constraints: (B-10) Typical scenarios s Down t Amount of light discarded at any given time: (B-11) Upper limit constraints on light curtailment rate for various typical scenarios: (B-12) Upper limit constraint on the expected value of abandoned light rate in a typical scenario under the worst probability distribution: (B-13) In the formula: Typical scenario s Down t The maximum output of photovoltaic power at any given time; Typical scenario s Down t The actual output of photovoltaic power at any given moment; Typical scenario s The worst probability; This represents the upper limit of light rejection rate for a single typical scenario; This represents the upper limit of the expected light curtailment rate for a typical scenario under the worst-case probability distribution. The expression for the flexible load constraint includes: Maximum load reduction limit at any given time: (B-19) Upper limit constraints on the payload abandonment rate for each typical scenario: (B-20) Upper limit constraint on the expected value of the abandonment rate in a typical scenario under the worst-case probability distribution: (B-21) In the formula, Typical scenario s Down t The amount of load reduction at any given time; The maximum load power that can be reduced for DC flexible loads; A 0-1 variable representing the DC flexible load reduction state; This represents the upper limit of the payload abandonment rate for a single typical scenario; This represents the upper limit of the expected payload abandonment rate for a typical scenario under the worst-case probability distribution. This is a typical scenario s Down t The load demand at any given moment; The expression for the main problem includes: by W Let represent all operational state variables of the optical-storage-direct-drive-flexible system. Then, the security domain of the optical-storage-direct-drive-flexible system is: (B-29) In the formula, These are equality constraints; These are inequality constraints. To meet the flexible and controllable resource operation constraints and safety constraints within the system, the gate converter has a flexible and adjustable operating space for active or reactive power. yes t The active power value on the AC side of the converter at any given time; yes t The reactive power compensation value of the converter at any given time; The upper and lower boundaries of the reactive power of the switchgear in the photovoltaic-storage-DC-flexible system are obtained using the following formulas: (B-30) (B-31) In the formula, and These are the upper and lower limits of the system's reactive power, respectively. For in the interval One of a series of working points obtained at equal internal distances, then ; Fixed reactive power compensation as By repeatedly solving the following two equations, a series of safety boundary points corresponding to the active power values ​​of the converter are obtained: (B-32) (B-33) For the set of boundary points of the flexible operating domain, Y The boundary points of the operating domain are solved using the following formula: (B-34) In the formula For the first l Each piecewise coefficient; For the first l One work site; The number of boundary points; z A linear combination of operating points; Based on the obtained series of runtime boundary points, the flexible runtime is generated by MATLAB's ConvexHull function; In the step of using a pre-established flexible operating domain model of the optical-storage-direct-flexible system based on the constraint of the split-bulb rod to calculate the uncertainty set of typical light-load scenarios and simultaneously control the expected values ​​of the load abandonment rate and the light abandonment rate under the worst probability distribution within the expected values, the uncertainty set of typical light-load scenarios is calculated by using the 1-norm and the ∞-norm. The sub-problem aims to obtain the expected value of the maximum curtailment rate of light and load; The worst-case probability distribution was obtained through the following max-min two-level optimization: (B-35) (B-36) In the formula, This represents an uncertain set of adverse probability distributions for typical scenarios. For the first s The initial probability of a typical photovoltaic / load scenario; This represents the allowed probability deviation value under the 1-norm constraint; This represents the allowed probability deviation value under the infinite norm constraint; Typical scenario s Down t The amount of light discarded at any given moment.

2. The scheduling method for a direct-drive flexible optical storage system based on split-blob bar optimization according to claim 1, characterized in that, In the step of obtaining multiple sets of typical light-load scenarios by clustering light-load time-series scenarios, the optimal number of clusters is determined by the elbow method, and the K-clustering algorithm is used to obtain multiple sets of typical light-load scenarios.

3. The scheduling method for a direct-drive flexible optical storage system based on split-blown bar optimization according to claim 2, characterized in that, In the step of determining the optimal number of clusters using the elbow method, the sum of squared errors is used. SSE The core indicator is the sum of squared errors. SSE The smaller the value, the better the clustering effect; sum of squared errors. SSE The calculation expression is as follows: (B-1) In the formula: It is the first n A cluster; p yes Sample points in; yes The centroid is numerically equal to The average of all samples in the sample; K It represents the total number of clusters.

4. The scheduling method for a direct-drive flexible optical storage system based on split-blob bar optimization according to claim 2, characterized in that, In the step of obtaining multiple sets of typical light-charge scenarios using the K-clustering algorithm, the typical light-charge scenarios are generated by the following formula: (B-2) (B-3) (B-4) In the formula, Total number of scenes; For the first s Number of scenes in the class; and They are the first i Photovoltaic output and load status for each scenario; For the first s A typical photovoltaic power output scenario; For the first s A typical load scenario; For the first s The initial probability of a typical photovoltaic / load scenario; 0-1 state variables for classifying scenes, when scene i Classified by scene s When the center is in the class Otherwise, it is 0.

5. The scheduling method for a direct-drive flexible optical storage system based on split-blob bar optimization according to claim 1, characterized in that, The expressions for the constraints of the energy storage system include: Upper limit constraints on energy storage charging and discharging power: (B-5) (B-6) Non-simultaneous charge / discharge energy constraints: (B-7) Energy storage balance constraints: (B-8) Energy storage upper and lower bound constraints: (B-9) In the formula: and Typical scenarios s China Energy Storage t Charging and discharging power during different time periods; The maximum output and input power of the energy storage; and Typical scenarios s middle t The energy storage charging and discharging status is displayed at all times; it is 1 when charging or discharging, and 0 otherwise. Typical scenario s middle t Energy storage capacity at all times; and These are the energy storage charging and discharging efficiencies, respectively. The self-consumption rate of energy storage; The time interval between adjacent time periods; Define the rated capacity for energy storage access; set the parameters for each scenario ( t The energy storage capacity is consistent at time -1).

6. The scheduling method for a direct-drive flexible optical-storage system based on split-blob bar optimization according to claim 1, characterized in that, The expressions for the air conditioning operation constraints include: Load power limit constraint: (B-14) Power factor constraints of the load: (B-15) Indoor temperature is within a certain range: (B-16) The linear relationship between the next indoor temperature and the current indoor temperature, outdoor temperature, and load power conforms to the following: (B-17) HVAC converter capacity constraints: (B-18) In the formula, , This is a typical scenario s Down t Active power and reactive power of HVAC load at any given time; This is the upper limit of active power for HVAC systems; It is a constant that defines a fixed power factor; This is a typical scenario s Down t The building's indoor temperature at any given time; , These are the highest and lowest indoor temperatures, respectively. and These are thermal parameters that specify the characteristics of buildings and their environment; It can be positive or negative; in winter, a positive value is taken as warm, and in summer, a negative value is taken as cold. This is the maximum capacity of the HVAC converter; set for each scenario ( t The indoor temperature is consistent at time -1).

7. The scheduling method for a direct-drive flexible optical storage system based on split-blob bar optimization according to claim 1, characterized in that, The expressions for the AC / DC converter constraints include: The efficiency conversion of power flowing through VSC conforms to: (B-22) Reactive power compensation constraint upper and lower limits: (B-23) VSC capacity constraints: (B-24) In the formula, and They are t Active power values ​​on the AC and DC sides of the converter at all times; yes t The reactive power compensation value of the converter at any given time; and They are respectively The upper and lower limits; For the capacity of VSC; The expressions for the distribution transformer constraints include: (B-25) (B-26) (B-27) In the formula, for t The active power of the distribution transformer at all times; for t The reactive power of the distribution transformer at all times; Maximum capacity; The expression for the energy conservation constraint is: (B-28) In the formula, It refers to the efficiency of the AC / DC converter; It refers to the efficiency of the DC / DC converter; This is a typical scenario s Down t The load demand at any time, yes t The active power values ​​of the AC and DC sides of the converter at any given time.

8. The scheduling method for a direct-drive flexible optical storage system based on split-blob bar optimization according to claim 1, characterized in that, Given a confidence level of uncertainty and In this case, and Calculate according to the following formula: (B-37) (B-38) In the formula, K It is the total number of clusters. This represents the total number of scenes.

9. The scheduling method for a direct-drive flexible optical-storage system based on split-blob bar optimization according to claim 1, characterized in that, In the step of iteratively solving the main problem and subproblems to obtain the flexible operating domain of the model, and then performing system scheduling based on the flexible operating domain, the CCG algorithm is used to iteratively solve the main problem and subproblems to obtain the flexible operating domain of the model. The main problem is retained, and the subproblems are further decomposed into a first subproblem SP1 and a second subproblem SP2 for solving. The objective function expression is as follows: (MP): (SP1): (SP2): .

10. A scheduling system for a photovoltaic-storage-direct-drive-flexible system based on distributed blue bar optimization, characterized in that, The method for scheduling a direct-drive-flexible optical storage system based on split-bar optimization as described in any one of claims 1 to 9 includes: The light-load scene acquisition module is used to obtain multiple sets of typical light-load scenes by clustering light-load time-series scenes; The load curtailment rate and light curtailment rate control module is used to utilize a pre-established flexible operating domain model of the optical-storage-direct-flexible system based on the split-bar constraint to calculate the uncertainty set of typical optical-load scenarios, and simultaneously control the expected values ​​of load curtailment rate and light curtailment rate under the worst probability distribution within the expected values. The flexible operating domain solution and scheduling module is used to iteratively solve the main problem and sub-problems to obtain the flexible operating domain of the model, and to perform system scheduling based on the flexible operating domain.

11. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, it implements the optical storage direct current flexible system scheduling method based on split-bar optimization as described in any one of claims 1 to 9.

12. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by the processor, it implements the optical storage direct current flexible system scheduling method based on split-bar optimization as described in any one of claims 1 to 9.

Citation Information

Patent Citations

  • AC / DC hybrid power distribution network safety domain calculation method considering photovoltaic output fluctuation

    CN112994010A

  • Method for evaluating flexibility of alternating-current and direct-current hybrid power distribution network based on typical operation scene

    CN114819504A