Sealing control method and system of compressor unit, computer device and storage medium

By acquiring the outlet pressure and calculating the pressure rise rate at preset time intervals in the compressor unit, and controlling the opening of the sealing gas inlet valve, the problem of low control reliability in the prior art is solved, and stable gas injection and safe output of salt cavern compressed air energy storage are realized.

CN117450097BActive Publication Date: 2026-11-20SHENYANG BLOWER WORKS GRP AUTOMATIC CONTROL SYST ENG
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311445948.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-31
Publication Date
2026-11-20
Estimated Expiration
2043-10-31

AI Technical Summary

Technical Problem

Existing compressor control methods cannot meet the requirements of compressed air energy storage in salt caverns, resulting in low control reliability.

Method used

By acquiring the outlet pressure of the gas output terminal of the compressor unit at preset time intervals, calculating the current pressure rise rate, and controlling the valve opening of the sealing gas inlet valve to maintain the sealing gas intake volume to meet the gas requirements inside the compressor unit, a stable pressure change in the compressor unit cavity is achieved.

Benefits of technology

This improved the control reliability of the compressor unit injecting gas into the salt cavern, achieving stable gas injection from the compressor unit into the salt cavern and ensuring the stability and safety of gas output.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117450097B_ABST
    Figure CN117450097B_ABST
Patent Text Reader

Abstract

The application discloses a sealing control method and system of a compressor unit, computer equipment and a storage medium, relates to the technical field of air energy storage, and solves the problem that the original control method cannot meet the requirements of air energy storage and the control reliability is low. The method comprises the following steps: acquiring the outlet pressure of the gas output end of the compressor unit at every preset time interval; when it is detected that the current outlet pressure acquired at the current acquisition time is greater than the previous outlet pressure acquired at the previous acquisition time, it is determined that the outlet pressure of the gas output end is increased, and the current pressure increase rate is calculated based on the current outlet pressure and the previous outlet pressure; the target valve opening degree of the sealing gas inlet valve of the compressor unit is calculated according to the current pressure increase rate; and the valve opening degree of the sealing gas inlet valve is controlled to reach the target valve opening degree.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application belongs to the field of air energy storage technology, and more specifically, relates to a sealing control method, system, computer equipment, and storage medium for a compressor unit. Background Technology

[0002] In salt cavern compressed air energy storage (CAES) projects, compressors are typically used to control the sealing system. Axial sealing gas effectively reduces axial gas leakage, while also reducing bearing vibration and bearing temperature rise.

[0003] In existing technologies, compressor control primarily ensures stable compressor outlet pressure. Therefore, the sealing gas inlet pressure also needs to remain relatively stable. This means that the actual outlet pressure collected at the compressor outlet, the inlet pressure at the sealing gas inlet, and the valve opening at the sealing gas inlet valve are all controlled at a constant level. However, the applicant recognizes that in actual air energy storage processes, the compressor outlet pressure continuously increases, or the unit needs to continue pressurizing after a brief pressure holding period. The existing control methods cannot meet the requirements of air energy storage, resulting in low control reliability. Summary of the Invention

[0004] In view of this, the present invention provides a sealing control method, system, computer equipment and storage medium for compressor units, the main purpose of which is to solve the problem that the existing control methods cannot meet the requirements of air energy storage and have low control reliability.

[0005] According to a first aspect of this application, a sealing control method for a compressor unit is provided, applied to salt cavern air energy storage, comprising:

[0006] The outlet pressure of the gas output terminal of the compressor unit is obtained at preset time intervals;

[0007] When it is detected that the current outlet pressure acquired at the current acquisition time is greater than the previous outlet pressure acquired at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has increased, and the current pressure increase rate is calculated based on the current outlet pressure and the previous outlet pressure, wherein the difference between the current acquisition time and the previous acquisition time is the preset time interval.

[0008] The target valve opening of the sealing gas inlet valve of the compressor unit is calculated based on the current pressure rise rate, and the valve opening of the sealing gas inlet valve is controlled to reach the target valve opening so that the amount of sealing gas entering the compressor unit meets the requirements of the gas inside the compressor unit.

[0009] Optionally, after calculating the current pressure rise rate based on the current outlet pressure and the previous outlet pressure, the method further includes:

[0010] If the current pressure rise rate exceeds the rate threshold, the compressor unit is controlled to stop injecting gas into the salt cavern. The shaft temperature data and vibration data of the compressor unit are acquired. When it is determined that the shaft temperature data is less than the temperature threshold and the vibration data is less than the vibration threshold, the compressor unit is controlled to continue injecting gas into the salt cavern.

[0011] Optionally, the method further includes:

[0012] When the detected outlet pressure reaches the preset pressure, the compressor unit is controlled to stop injecting gas into the salt cavern.

[0013] Optionally, the method further includes:

[0014] Obtain the target outlet pressure at the gas output end of the compressor unit, and obtain the target sealing gas inlet pressure at the sealing gas inlet end of the compressor unit;

[0015] The difference between the target sealing gas inlet pressure and the target outlet pressure is calculated to obtain the pressure difference. When the pressure difference exceeds the pressure difference threshold, a fault message indicating excessive sealing gas intake is generated. The fault message is pushed to the terminal held by the maintenance personnel so that the maintenance personnel can troubleshoot the compressor unit based on the fault message received by the terminal.

[0016] Optionally, calculating the current pressure rise rate based on the current outlet pressure and the previous outlet pressure includes:

[0017] Calculate the difference between the current outlet pressure and the previous outlet pressure;

[0018] The current pressure rise rate is obtained by calculating the ratio of the difference to the previous outlet pressure.

[0019] Optionally, calculating the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure rise rate includes:

[0020] Obtain the current valve opening of the sealing gas inlet valve of the compressor unit, and determine the preset control time;

[0021] The product of the preset control time and the current pressure rise rate is calculated to obtain the opening increase value;

[0022] The target valve opening is obtained by calculating the sum of the current valve opening and the increase in the opening value.

[0023] Optionally, the method further includes:

[0024] The outlet pressure of the gas output terminal of the compressor unit is obtained at preset time intervals;

[0025] When it is detected that the current outlet pressure obtained at the current acquisition time is less than the previous target outlet pressure obtained at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has decreased, and the current pressure decrease rate is calculated based on the current outlet pressure and the previous outlet pressure.

[0026] Calculate the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure drop rate, and control the valve opening of the sealing gas inlet valve to decrease to the target valve opening.

[0027] According to a second aspect of this application, a sealing control system for a compressor unit is provided, comprising: a control unit, a compressor unit, and a pressure sensor;

[0028] The control unit is configured to execute the sealing control method of the compressor unit according to any one of the first aspects above;

[0029] The gas output end of the compressor unit is used to inject gas into the salt cavern and is equipped with a pressure sensor. The pressure sensor is connected to the control unit and is used to collect the outlet pressure of the gas output end based on the first control command when it receives the first control command issued by the control unit.

[0030] The sealing gas inlet of the compressor unit is connected to the salt cavern via a sealing gas inlet valve to receive high-pressure gas output from the salt cavern. The sealing gas inlet valve is also connected to the control unit to adjust the valve opening based on the second control command issued by the control unit.

[0031] According to a third aspect of this application, a computer device is provided, including a memory and a processor, wherein the memory stores a computer program, and the processor executes the computer program to implement the steps of the method described in any of the first aspects above.

[0032] According to a fourth aspect of this application, a readable storage medium is provided having a computer program stored thereon, which, when executed by a processor, implements the steps of the method described in any one of the first aspects above.

[0033] By employing the above technical solution, this application provides a sealing control method, system, computer equipment, and storage medium for a compressor unit. This application first acquires the outlet pressure of the gas output terminal of the compressor unit at preset time intervals. Then, when it detects that the current outlet pressure acquired at the current acquisition time is greater than the previous outlet pressure acquired at the previous acquisition time, it determines that the outlet pressure of the gas output terminal has increased. Based on the current outlet pressure and the previous outlet pressure, it calculates the current pressure increase rate. Finally, it calculates the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure increase rate, and controls the valve opening of the sealing gas inlet valve to reach the target valve opening. When it is determined that the outlet pressure of the gas output terminal has increased, the target valve opening of the sealing gas inlet valve can be calculated using the calculated current pressure increase rate. By controlling the valve opening of the sealing gas inlet valve to reach the target valve opening, the pressure at the sealing gas inlet terminal remains greater than the outlet pressure, achieving stable pressure changes within the compressor unit cavity. This further enables the compressor unit to smoothly inject gas into the salt cavern, improving control reliability.

[0034] The above description is merely an overview of the technical solution of the present invention. In order to better understand the technical means of the present invention and to implement it in accordance with the contents of the specification, and in order to make the above and other objects, features and advantages of the present invention more apparent and understandable, specific embodiments of the present invention are described below. Attached Figure Description

[0035] Various other advantages and benefits will become apparent to those skilled in the art upon reading the following detailed description of preferred embodiments. The accompanying drawings are for illustrative purposes only and are not intended to limit the invention. Furthermore, the same reference numerals denote the same parts throughout the drawings. In the drawings:

[0036] Figure 1 A flowchart of a sealing control method for a compressor unit provided in an embodiment of this application is shown;

[0037] Figure 2 A flowchart of another sealing control method for a compressor unit provided in an embodiment of this application is shown;

[0038] Figure 3 A schematic diagram of the compressor unit structure is shown, illustrating another method for sealing control of a compressor unit provided in an embodiment of this application.

[0039] Figure 4 This paper shows a schematic diagram of the structure of a sealing control system for a compressor unit according to an embodiment of this application;

[0040] Figure 5 A schematic diagram of the device structure of a computer device provided in an embodiment of this application is shown. Detailed Implementation

[0041] Various embodiments and features of this application are described herein with reference to the accompanying drawings.

[0042] It should be understood that various modifications can be made to the embodiments described herein. Therefore, the above description should not be considered as limiting, but merely as an example of embodiments. Other modifications within the scope and spirit of this application will be apparent to those skilled in the art.

[0043] The accompanying drawings, which are included in and form part of this specification, illustrate embodiments of the present application and, together with the general description of the present application given above and the detailed description of the embodiments given below, serve to explain the principles of the present application.

[0044] These and other features of this application will become apparent from the following description of preferred forms of embodiments given as non-limiting examples, with reference to the accompanying drawings.

[0045] It should also be understood that although this application has been described with reference to some specific examples, those skilled in the art can certainly implement many other equivalent forms of this application.

[0046] The above and other aspects, features and advantages of this application will become more apparent when taken in conjunction with the accompanying drawings and in view of the following detailed description.

[0047] Specific embodiments of this application are described thereafter with reference to the accompanying drawings; however, it should be understood that the claimed embodiments are merely examples of this application, which can be implemented in various ways. Well-known and / or repeated functions and structures are not described in detail to avoid unnecessary or redundant details that could obscure the application. Therefore, the specific structural and functional details claimed herein are not intended to be limiting, but merely serve as the basis and representative basis for the claims to teach those skilled in the art to use this application in a variety of substantially any suitable detailed structures.

[0048] This specification may use the phrases “in one embodiment,” “in another embodiment,” “in yet another embodiment,” or “in other embodiments,” all of which may refer to one or more of the same or different embodiments according to this application.

[0049] This application provides a sealing control method for a compressor unit, applied to salt cavern air energy storage, such as... Figure 1 As shown, it includes:

[0050] 101. Obtain the outlet pressure of the gas output terminal of the compressor unit at preset time intervals.

[0051] In this embodiment of the application, the execution subject is a control unit. The control unit can control the pressure sensor to collect the outlet pressure of the gas output end of the compressor unit at preset time intervals. In other words, many outlet pressures will be obtained.

[0052] 102. When it is detected that the current outlet pressure obtained at the current acquisition time is greater than the previous outlet pressure obtained at the previous acquisition time, it is determined that the outlet pressure at the gas output end has increased, and the current pressure increase rate is calculated based on the current outlet pressure and the previous outlet pressure.

[0053] In this embodiment, the control unit continuously monitors these outlet pressures. When an outlet pressure is acquired, it is compared with the previously acquired outlet pressure. Once it is found that the current outlet pressure is greater than the previously acquired outlet pressure, it will be determined that the outlet pressure at the gas output end is showing an upward trend. At this time, it is necessary to calculate the current pressure increase rate based on the current outlet pressure and the previous outlet pressure. It should be noted that the current outlet pressure can be understood as the latest acquired outlet pressure, that is, the current outlet pressure acquired at the current acquisition time. The previous acquisition time is the time of the last acquisition. In other words, the difference between the current acquisition time and the previous acquisition time is a preset time interval.

[0054] 103. Calculate the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure rise rate, and control the valve opening of the sealing gas inlet valve to reach the target valve opening.

[0055] In this embodiment, during the air storage loading and injection process in the salt cavern, the pressure inside the compressor unit cavity continuously increases. Therefore, injecting air into the salt cavern can be understood as a pressurization process. Since the salt cavern itself has a certain pressure, gas will only be injected into the salt cavern when the outlet pressure at the gas output end is greater than the pressure of the salt cavern. This is when the injection is truly successful. Subsequently, as more and more gas accumulates in the salt cavern with nowhere to release, the overall pressure continues to rise. The resulting sealing gas control also requires the pressure inside the compressor unit cavity to increase accordingly. However, the pressure change is somewhat delayed, so it is necessary to anticipate and activate the valves in advance to achieve the desired effect. The target valve opening is calculated based on the current pressure rise rate, thereby increasing the pressure within the compressor unit cavity. This means the target valve opening of the sealing gas inlet valve is controlled based on the target valve opening, allowing for control of the amount of sealing gas entering the compressor. By controlling the valve opening to reach the target opening, a stable gas pressure output can be achieved. Different sealing gas intake volumes result in different sealing gas inlet pressures. In this case, the sealing gas inlet pressure remains slightly higher than the outlet pressure, ensuring that the amount of sealing gas entering the compressor unit meets the internal gas requirements. This application's embodiment changes the previous stable pressure regulation function by developing a dynamic pressure boosting function that maintains a relatively stable dynamic balance regulation between the compressor outlet pressure and the sealing gas inlet pressure.

[0056] It should be noted that sealing control can be understood as controlling the leakage of gas from the compressor unit. It holds the compressed air inside the compressor unit back to prevent it from leaking out. This process is similar to inflating a bicycle tire; the more you inflate, the greater the internal gas pressure becomes, so you have to pump harder. Therefore, it is a continuous process of increasing pressure.

[0057] The method provided in this application first acquires the outlet pressure of the gas output terminal of the compressor unit at preset time intervals. Then, when it is detected that the current outlet pressure acquired at the current acquisition time is greater than the previous outlet pressure acquired at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has increased. Based on the current outlet pressure and the previous outlet pressure, the current pressure increase rate is calculated. Finally, the target valve opening of the sealing gas inlet valve of the compressor unit is calculated based on the current pressure increase rate, and the valve opening of the sealing gas inlet valve is controlled to reach the target valve opening. When it is determined that the outlet pressure of the gas output terminal has increased, the target valve opening of the sealing gas inlet valve can be calculated by calculating the current pressure increase rate. By controlling the valve opening of the sealing gas inlet valve to reach the target valve opening, the pressure at the sealing gas inlet terminal is kept greater than the outlet pressure, thereby achieving stable pressure changes in the compressor unit cavity and further realizing smooth gas injection into the salt cavern by the compressor unit, improving control reliability.

[0058] Furthermore, as a refinement and extension of the specific implementation methods of the above embodiments, and in order to fully illustrate the specific implementation process of this embodiment, this application provides another method for sealing control of a compressor unit, such as... Figure 2 As shown, it includes:

[0059] 201. Obtain the outlet pressure of the gas output terminal of the compressor unit at preset time intervals.

[0060] 202. When it is detected that the current outlet pressure obtained at the current acquisition time is greater than the previous outlet pressure obtained at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has increased, and the current pressure increase rate is calculated based on the current outlet pressure and the previous outlet pressure.

[0061] In this embodiment of the application, the difference between the current outlet pressure and the previous outlet pressure is first calculated, and then the ratio of the difference to the previous outlet pressure is calculated to obtain the current pressure rise rate.

[0062] In one optional embodiment of this application, the timing for stopping gas injection can be determined by the outlet pressure. That is, when the detected outlet pressure reaches the preset pressure, the compressor unit is controlled to stop injecting gas into the salt cavern. At this time, the control unit adjusts the sealing gas inlet valve to immediately take action. The gas pressure needs to maintain a relatively stable output because the outlet pressure drops when the unloading and shutdown are completed. Therefore, the valve must be closed. Otherwise, the gas from the salt cavern will be under high pressure and will not drop. If the valve is not closed, the sealing gas pressure will be too high. It is not allowed and is dangerous for a large amount of gas to enter the compressor through the sealing valve.

[0063] It should be noted that, in order to ensure stable gas pressure output, the process of stopping gas injection also needs to be carried out slowly. That is, the outlet pressure of the gas output terminal of the compressor unit is acquired at preset time intervals. When it is detected that the current outlet pressure acquired at the current acquisition time is less than the previous target outlet pressure acquired at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has dropped. Based on the current outlet pressure and the previous outlet pressure, the current pressure drop rate is calculated. Based on the current pressure drop rate, the target valve opening of the sealing gas inlet valve of the compressor unit is calculated, and the valve opening of the sealing gas inlet valve is controlled to be reduced to the target valve opening.

[0064] 203. Determine whether the compressor unit is in the buffer phase based on the rate threshold.

[0065] In this embodiment, if the gas injection enters the buffer phase, the compressor outlet pressure will remain relatively stable and will no longer rise continuously or the rise rate will be slow. At this time, the sealing control can promptly reduce the opening of the sealing inlet valve to ensure the pressure balance between the sealing gas and the gas inside and outside the compressor cavity. This is why, if problems are encountered during the start-up loading process, such as high vibration or high shaft temperature, the compressor unit needs to stop increasing the load and pressure to keep the outlet pressure stable. Specifically, a rate threshold is obtained. If the current pressure rise rate exceeds the rate threshold, the compressor unit is controlled to stop injecting gas into the salt cavern, and the shaft temperature data and vibration data of the compressor unit are obtained. When it is determined that the shaft temperature data is less than the temperature threshold and the vibration data is less than the vibration threshold, the compressor unit is controlled to continue injecting gas into the salt cavern.

[0066] 204. Calculate the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure rise rate, and control the valve opening of the sealing gas inlet valve to reach the target valve opening.

[0067] In this embodiment, the current valve opening of the sealing gas inlet valve of the compressor unit is obtained, and a preset control time is determined. The product of the preset control time and the current pressure rise rate is calculated to obtain the opening increase value. The sum of the current valve opening and the opening increase value is calculated to obtain the target valve opening. After obtaining the target valve opening, the valve opening of the sealing gas inlet valve can be controlled to reach the target valve opening.

[0068] 205. Generate fault information based on the target outlet pressure at the gas output end and the target sealing gas inlet pressure at the sealing gas inlet end.

[0069] In this embodiment, a large deviation between the sealing gas inlet pressure and the outlet pressure indicates that the sealing gas intake is too large, which can cause shaft vibration in the compressor. In this case, the fault can be adjusted and an alarm can be triggered. Specifically, the target outlet pressure at the gas output end of the compressor unit and the target sealing gas inlet pressure at the sealing gas inlet end of the compressor unit are obtained. The difference between the target sealing gas inlet pressure and the target outlet pressure is calculated to obtain the pressure difference. When the pressure difference exceeds the pressure difference threshold, fault information indicating excessive sealing gas intake is generated and pushed to the terminal held by the maintenance personnel. This allows the maintenance personnel to troubleshoot the compressor unit based on the fault information received by the terminal.

[0070] The above process can be summarized as follows: As the compressor's outlet pressure continuously increases during the loading process, the control unit (which can be understood as the control unit's PID function) initiates synchronous adjustment output, controlling the sealing gas inlet valve to open wider, increasing the sealing gas intake volume, i.e., increasing the sealing gas inlet pressure. This tracking and adjustment process requires comprehensive analysis of the rate trend of the compressor outlet pressure increase. The key is to control the trend accurately, ensuring that the change in outlet pressure is tracked, which corresponds to the change in the adjustment rate. Based on this rate, the target valve opening that needs adjustment can be determined, allowing for a timely response to meet sealing requirements. If the valve opening is too large, it will lead to excessive sealing gas pressure, resulting in too much sealing gas entering the compressor cavity, affecting the vibration and relative stability of the compressor bearings, causing fluctuations. If the valve opening is too small, it will lead to excessively low sealing gas pressure, insufficient sealing gas, increased leakage within the compressor cavity, resulting in incomplete sealing, gas leakage, and affecting the flow of process gas in the compressor, also causing fluctuations.

[0071] In one optional embodiment of this application, such as Figure 3As shown, the compressor unit includes a low-pressure LP compressor, a medium-pressure MP compressor, and a high-pressure HP compressor connected in series. The LP compressor's inlet is open to the atmosphere, its low-pressure output is connected to the MP compressor's inlet, the MP compressor's medium-pressure output is connected to the HP compressor's inlet, and the MP compressor's gas output is connected to a salt cavern. Essentially, the LP compressor draws in air, pressurizes it, and then the gas enters the MP compressor. The MP compressor further pressurizes the gas, which then enters the HP compressor. Finally, the gas is pressurized by the HP compressor and sent to the underground salt cavern, essentially functioning as a large tank. The compressor unit can increase the gas pressure from 1 MPa to 13 MPa. Since the compressor unit consists of three compressors connected in series, the control unit acquires the low-pressure outlet pressure of the low-pressure LP compressor, the medium-pressure outlet pressure of the MP compressor, and the outlet pressure of the high-pressure HP compressor at preset time intervals. For the LP compressor, the current low-pressure outlet pressure is compared with the previous low-pressure outlet pressure. For the MP compressor, the current medium-pressure outlet pressure is compared with the previous medium-pressure outlet pressure. For the HP compressor, the current outlet pressure is compared with the previous outlet pressure. When it is determined that the current low-pressure outlet pressure is greater than the previous low-pressure outlet pressure, the current medium-pressure outlet pressure is greater than the previous medium-pressure outlet pressure, and the current outlet pressure is greater than the previous outlet pressure, it is determined that the low-pressure outlet pressure, medium-pressure outlet pressure, and outlet pressure have increased. Under normal circumstances, the outlet pressure change trends of the three compressors are consistent. Once the outlet pressure change trend of one compressor is inconsistent, it can be determined that the compressor unit has failed, and professional personnel need to troubleshoot the fault in time. In this way, the pressure rise rate corresponding to the LP compressor, the pressure rise rate corresponding to the MP compressor, and the pressure rise rate corresponding to the HP compressor can be calculated. Based on the calculated pressure rise rates corresponding to the LP compressor, MP compressor, and HP compressor, the control unit can calculate the target valve opening of the sealing gas inlet valve for the LP compressor, MP compressor, and HP compressor. It then controls the valve opening of each sealing gas inlet valve to increase to the corresponding target valve opening. This ensures that the amount of sealing gas entering each compressor meets the gas requirements of the respective compressor unit, thereby achieving stable gas pressure output.

[0072] The method provided in this application first acquires the outlet pressure of the gas output terminal of the compressor unit at preset time intervals. Then, when it is detected that the current outlet pressure acquired at the current acquisition time is greater than the previous outlet pressure acquired at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has increased. Based on the current outlet pressure and the previous outlet pressure, the current pressure increase rate is calculated. Finally, the target valve opening of the sealing gas inlet valve of the compressor unit is calculated based on the current pressure increase rate, and the valve opening of the sealing gas inlet valve is controlled to reach the target valve opening. When it is determined that the outlet pressure of the gas output terminal has increased, the target valve opening of the sealing gas inlet valve can be calculated based on the calculated current pressure increase rate. By controlling the valve opening of the sealing gas inlet valve to reach the target valve opening, the pressure at the sealing gas inlet terminal is kept greater than the outlet pressure, thereby achieving stable pressure changes within the compressor unit cavity and further enabling the compressor unit to smoothly inject gas into the salt cavern.

[0073] Furthermore, as Figure 1 In a specific implementation of the method, this embodiment of the invention provides a sealing control system for a compressor unit, such as... Figure 4 As shown, it includes: a control unit, a compressor unit, and a pressure sensor;

[0074] A control unit for executing the sealing control method according to the compressor unit described above;

[0075] The gas output end of the compressor unit is used to inject gas into the salt cavern and is equipped with a pressure sensor. The pressure sensor is connected to the control unit and is used to collect the outlet pressure of the gas output end based on the first control command issued by the control unit. The sealing gas inlet end of the compressor unit is connected to the salt cavern through a sealing gas inlet valve and is used to receive the high-pressure gas output from the salt cavern. The sealing gas inlet valve is connected to the control unit and is used to adjust the valve opening based on the second control command issued by the control unit.

[0076] Furthermore, such as Figure 4 As shown, the system also includes: a first pressure sensor; the first pressure sensor is installed at the sealing gas inlet end of the compressor unit, and is connected to the control unit. When the control unit receives a third control command, the first pressure sensor collects the sealing gas inlet pressure based on the third control command. Furthermore, the control unit can generate relevant fault information and provide fault warnings based on the sealing gas inlet pressure and outlet pressure.

[0077] The sealing control system provided in this application includes a control unit, a compressor unit, and a pressure sensor. The control unit can control the pressure sensor to collect the outlet pressure and the sealing gas inlet pressure. At the same time, the control unit issues relevant control commands based on the outlet pressure, so that the compressor unit performs sealing control based on the relevant control commands.

[0078] In an exemplary embodiment, see Figure 5 The invention also provides a computer device including a communication bus, a processor, a memory, and a communication interface. It may also include an input / output interface and a display device, wherein the various functional units can communicate with each other via the bus. The memory stores a computer program, and the processor executes the program stored in the memory to perform the sealing control method of the compressor unit in the above embodiments.

[0079] A computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the sealing control method for the compressor unit.

[0080] Through the above description of the embodiments, those skilled in the art can clearly understand that this application can be implemented in hardware or by using software plus necessary general-purpose hardware platforms. Based on this understanding, the technical solution of this application can be embodied in the form of a software product, which can be stored in a non-volatile storage medium (such as a CD-ROM, USB flash drive, external hard drive, etc.) and includes several instructions to cause a computer device (such as a personal computer, server, or network device, etc.) to execute the methods described in the various embodiments of this application.

[0081] Those skilled in the art will understand that the accompanying drawings are merely schematic diagrams of a preferred embodiment, and the modules or processes shown in the drawings are not necessarily essential for implementing this application. Those skilled in the art will understand that the modules in the apparatus of the embodiment can be distributed within the apparatus of the embodiment as described, or can be modified to be located in one or more apparatuses different from this embodiment. The modules of the above-described embodiment can be combined into one module, or further divided into multiple sub-modules.

[0082] The above embodiments are merely exemplary embodiments of this application and are not intended to limit this application. The scope of protection of this application is defined by the claims. Those skilled in the art can make various modifications or equivalent substitutions to this application within its substance and scope of protection, and such modifications or equivalent substitutions should also be considered to fall within the scope of protection of this application.

Claims

1. A sealing control method for a compressor unit, applied to salt cavern air energy storage, characterized in that, include: The outlet pressure of the gas output terminal of the compressor unit is obtained at preset time intervals; When it is detected that the current outlet pressure acquired at the current acquisition time is greater than the previous outlet pressure acquired at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has increased, and the current pressure increase rate is calculated based on the current outlet pressure and the previous outlet pressure, wherein the difference between the current acquisition time and the previous acquisition time is the preset time interval. Calculate the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure rise rate, and control the valve opening of the sealing gas inlet valve to reach the target valve opening, so that the amount of sealing gas entering the compressor unit meets the gas requirements inside the compressor unit. The step of calculating the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure rise rate includes: obtaining the current valve opening of the sealing gas inlet valve of the compressor unit and determining a preset control time; calculating the product of the preset control time and the current pressure rise rate to obtain the opening increase value; and calculating the sum of the current valve opening and the opening increase value to obtain the target valve opening. When it is detected that the current outlet pressure obtained at the current acquisition time is less than the previous outlet pressure obtained at the previous acquisition time, it is determined that the outlet pressure of the gas output terminal has decreased, and the current pressure decrease rate is calculated based on the current outlet pressure and the previous outlet pressure. Calculate the target valve opening of the sealing gas inlet valve of the compressor unit based on the current pressure drop rate, and control the valve opening of the sealing gas inlet valve to decrease to the target valve opening.

2. The sealing control method for the compressor unit according to claim 1, characterized in that, After calculating the current pressure rise rate based on the current outlet pressure and the previous outlet pressure, the method further includes: If the current pressure rise rate exceeds the rate threshold, the compressor unit is controlled to stop injecting gas into the salt cavern. The shaft temperature data and vibration data of the compressor unit are acquired. When it is determined that the shaft temperature data is less than the temperature threshold and the vibration data is less than the vibration threshold, the compressor unit is controlled to continue injecting gas into the salt cavern.

3. The sealing control method for the compressor unit according to claim 1, characterized in that, The method further includes: When the detected outlet pressure reaches the preset pressure, the compressor unit is controlled to stop injecting gas into the salt cavern.

4. The sealing control method for the compressor unit according to claim 1, characterized in that, The method further includes: Obtain the target outlet pressure at the gas output end of the compressor unit, and obtain the target sealing gas inlet pressure at the sealing gas inlet end of the compressor unit; The difference between the target sealing gas inlet pressure and the target outlet pressure is calculated to obtain the pressure difference. When the pressure difference exceeds the pressure difference threshold, a fault message indicating excessive sealing gas intake is generated. The fault message is pushed to the terminal held by the maintenance personnel so that the maintenance personnel can troubleshoot the compressor unit based on the fault message received by the terminal.

5. The sealing control method for the compressor unit according to claim 1, characterized in that, The calculation of the current pressure rise rate based on the current outlet pressure and the previous outlet pressure includes: Calculate the difference between the current outlet pressure and the previous outlet pressure; The current pressure rise rate is obtained by calculating the ratio of the difference to the previous outlet pressure.

6. A sealing control system for a compressor unit, characterized in that, include: Control unit, compressor unit, pressure sensor; The control unit is used to execute the sealing control method of the compressor unit according to any one of claims 1 to 5; The gas output end of the compressor unit is used to inject gas into the salt cavern and is equipped with a pressure sensor. The pressure sensor is connected to the control unit and is used to collect the outlet pressure of the gas output end based on the first control command when it receives the first control command issued by the control unit. The sealing gas inlet of the compressor unit is connected to the salt cavern via a sealing gas inlet valve to receive high-pressure gas output from the salt cavern. The sealing gas inlet valve is also connected to the control unit to adjust the valve opening based on the second control command issued by the control unit.

7. A computer device comprising a memory and a processor, wherein the memory stores a computer program, characterized in that, When the processor executes the computer program, it implements the steps of the method according to any one of claims 1 to 5.

8. A readable storage medium having a computer program stored thereon, characterized in that, When the computer program is executed by a processor, it implements the steps of the method according to any one of claims 1 to 5.

Citation Information

Patent Citations

  • Gas compressor aerodynamic stability diagnosis and control device and method

    CN106640722A

  • Shutdown method and device of salt cavern energy storage system series unit, medium and equipment