Large-section small-clearance soft rock tunnel entry construction method

By employing a method for constructing ultra-large cross-section, small-clearance soft rock tunnels, and utilizing a separate dual-tunnel design and a multi-stage pilot tunnel conversion method, the construction challenges of ultra-large cross-section and small-clearance tunnels were solved, resulting in improvements in construction safety, quality, and efficiency.

CN117468940BActive Publication Date: 2026-11-24CHINA RAILWAY 23RD BUREAU GRP 4TH ENG CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311530958.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-16
Publication Date
2026-11-24
Estimated Expiration
2043-11-16

AI Technical Summary

Technical Problem

Existing tunnel construction technologies cannot effectively meet the construction requirements of tunnels with extra-large cross sections and small clearances, leading to increased construction difficulty, safety hazards, and uneven construction.

Method used

The construction method of using a large-section, small-clearance soft rock tunnel was adopted. Through the design of a separated twin-tunnel with small clearance, combined with the double-side-wall pilot tunnel method, single-side-wall pilot tunnel method and three-stage sectional excavation method, the construction sequence was gradually adjusted. The construction method was adjusted by monitoring and measurement to reduce stress concentration and ensure construction safety and quality.

Benefits of technology

It improves construction efficiency, reduces costs, adapts to different geological conditions and cross-sectional forms, ensures construction safety and quality, reduces disturbance to surrounding rock, and meets the construction needs of tunnels with extra-large cross sections and small clearances.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117468940B_ABST
    Figure CN117468940B_ABST
Patent Text Reader

Abstract

The present application relates to the technical field of tunnel construction, in particular to a large-section small-clearance soft rock tunnel entry construction method, which is used for construction when the tunnel enters the hole, the construction tunnel is a separated double-hole small-clearance tunnel, and the tunnel is filled with middle rock. The specific construction method is as follows: a tunnel excavation surface is arranged at the tunnel entry hole, regional excavation is carried out on the tunnel excavation surface according to a module, and synchronous support construction is carried out to obtain initial support and other supports. Then, the double-side wall pilot tunnel method is used to construct the tunnel excavation surface. Then, the tunnel excavation surface is monitored and measured, and it is determined whether to change the double-side wall pilot tunnel method into the single-side wall pilot tunnel method or the three-step sub-method according to the monitoring result. If it is the single-side wall pilot tunnel method, the tunnel excavation surface is monitored and measured again after the construction is completed, and the three-step sub-method is used for construction according to the measurement result, so that the method can adapt to different environments and improve the method and construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel construction technology, and in particular to a method for entering and constructing a soft rock tunnel with an extra-large cross-section and small clearance. Background Technology

[0002] Tunnels are passageways excavated from existing buildings or earthen structures to achieve purposes such as multi-level transportation, traversing mountains and valleys, underground passages, and crossing rivers and seas. Tunnel engineering is a complex underground engineering project. Its construction process must overcome various adverse natural conditions and human factors to ensure the tunnel's quality, safety, and progress. Tunnel construction methods refer to the technical means and technological processes used in tunnel construction. They are the core of tunnel engineering, directly affecting the tunnel's structural form, construction efficiency, cost control, and environmental protection.

[0003] my country is undertaking large-scale transportation infrastructure construction, resulting in a surge of tunnel projects with small clearances. While significant research and practical work on small clearance tunnel construction has been conducted both domestically and internationally, ensuring the successful completion of numerous complex projects and establishing relatively unified understandings and construction methods, a shortcoming remains: most construction technology achievements are still case-by-case, offering some reference value for similar projects but lacking systematic guidance. Furthermore, the engineering handling measures differ for specific small clearance tunnel projects. Currently, conventional mining methods are not suitable for small clearance tunnel construction. Conventional mining blasting significantly impacts the preceding tunnel and intermediate rock pillars. Due to the thinness of the interbedded rock, stress release during tunnel construction can disturb the interbedded rock, creating potential fracture surfaces. Improper handling could lead to instability and failure, especially during the blasting of subsequent tunnels, seriously threatening the safety of the preceding tunnel. Moreover, the construction difficulty increases dramatically for extra-large cross-sections due to their large excavation area, easily leading to uneven stress distribution during excavation. Existing construction technologies cannot adapt to construction sites that simultaneously possess both extra-large cross-sections and small clearances. Summary of the Invention

[0004] The purpose of this invention is to provide a method for constructing tunnels with large cross sections and small clearances in soft rock, addressing the problem that existing tunnel entry construction schemes cannot better adapt to different surrounding rock conditions and construction requirements of tunnels with extra-large cross sections and small clearances.

[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows:

[0006] A method for constructing an ultra-large cross-section, small-clearance soft rock tunnel for tunnel entry is disclosed. The tunnel is a separated twin-tunnel design with interbedded rock between the tunnels. This method is used for tunnel entry construction, and the specific construction method is as follows:

[0007] S1. Set up a tunnel excavation face at the tunnel entrance, and carry out regional excavation on the tunnel excavation face according to the modules and simultaneously build the support to obtain the initial support and the remaining support.

[0008] S2. After the area is divided, the double-sided wall pilot tunnel method is first used to construct the tunnel excavation face. After the construction is completed, the tunnel excavation face is monitored and measured. When the monitoring and measurement results show that the settlement is less than or equal to 2cm and the convergence is less than or equal to 5cm, the single-sided wall pilot tunnel method is used to construct the tunnel excavation face. If the monitoring and measurement results show that the settlement is less than or equal to 1cm and the convergence is less than or equal to 3cm, the three-stage sectional excavation method is directly used to construct the tunnel excavation face.

[0009] S3. After the single-side wall pilot tunnel method is completed, the tunnel excavation face is monitored and measured. When the monitoring and measurement results show that the settlement is less than or equal to 1cm and the convergence is less than or equal to 3cm, the single-side wall pilot tunnel method is converted into the three-stage sectional excavation method to construct the tunnel excavation face.

[0010] S4. Tunnel entry construction completed.

[0011] It should be noted that the initial support should also be carried out during the subsequent excavation of the tunnel face.

[0012] This invention discloses a method for constructing tunnels in soft rock with large cross-sections and small clearances. After dividing the tunnel excavation face into zones, a double-sided pilot tunnel method is used for excavation. This is then transitioned to a single-sided pilot tunnel method, with a gradual transition between the two methods. This smooth transition, compared to abrupt cross-section changes, helps reduce excessive stress concentration and improves the stability of the initial support. If, through monitoring and measurement, the settlement is less than or equal to 1 cm and the convergence is less than or equal to 3 cm after single-sided pilot tunnel construction, the method is switched to a three-stage sectional excavation method. This increases the excavation space and mechanization, accelerates construction progress, and reduces costs. The switching between various excavation methods allows for flexible adjustment of the construction sequence, adapting to different geological conditions and cross-section forms, ensuring construction safety and quality.

[0013] As a preferred embodiment of the present invention, when constructing the tunnel excavation face, the side of the interbedded rock should be excavated first to avoid disturbance to the interbedded rock during subsequent construction.

[0014] As a preferred embodiment of the present invention, in step S1, the tunnel excavation face is divided into pilot tunnel I and pilot tunnel III located on the side of the interbedded rock, pilot tunnel II and pilot tunnel IV on the opposite side, and pilot tunnel V, pilot tunnel VI and pilot tunnel VII located in the core soil position in the middle of the tunnel excavation face. Each of the pilot tunnels is supported circumferentially.

[0015] As a preferred embodiment of the present invention, the circumferential support of each of the guide tunnels is constructed as follows:

[0016] S41. The first section of the pilot tunnel is circumferentially supported by a first section of the pilot tunnel support, a second section of the pilot tunnel support, and a third section of the pilot tunnel support connected in a ring.

[0017] S42. The I-section guide tunnel is adjacent to the III-section guide tunnel. The III-section guide tunnel is circumferentially supported by a first III-section guide tunnel support, a second III-section guide tunnel support, and a second I-section guide tunnel support. The connected supports are connected to form a ring.

[0018] S43. The second guide tunnel is circumferentially supported by a first second guide tunnel support, a second second guide tunnel support, and a third second guide tunnel support, and the first second guide tunnel support is connected to the second second guide tunnel support and the third second guide tunnel support to form a ring.

[0019] S44. The II guide tunnel is adjacent to the IV guide tunnel. The IV guide tunnel is provided with a first IV guide tunnel support and a second IV guide tunnel support in the circumferential direction. The first IV guide tunnel support, the second IV guide tunnel support, and the second II guide tunnel support are connected to form a ring.

[0020] S45. The V-section guide tunnel is followed by the VI-section guide tunnel and the VII-section guide tunnel, and the V-section guide tunnel and the VII-section guide tunnel are respectively provided with V-section guide tunnel support and VII-section guide tunnel support at one end near the tunnel wall. The V-section guide tunnel support is connected to the first II-section guide tunnel support, the first IV-section guide tunnel support is connected to the VII-section guide tunnel support, and the first III-section guide tunnel support is connected to the first I-section guide tunnel support to form a ring.

[0021] S46. The third section I guide tunnel support and the second section III guide tunnel support, the VII guide tunnel support and the second section IV guide tunnel support, and the third section II guide tunnel support and the V guide tunnel support are all connected end to end to form a ring to form the initial support.

[0022] This design provides good support for tunnels with extra-large cross-sections.

[0023] As a preferred embodiment of the present invention, the steps for converting the double-sidewall guide tunnel method into the single-sidewall guide tunnel method are as follows:

[0024] S51. First, construct the pilot tunnel I located on the side of the interlocking rock. Then, move the support of the first pilot tunnel I laterally to the center of the tunnel excavation face and fix it to the centerline position of the tunnel. After excavating the pilot tunnel I, a temporary pilot tunnel ① with a single side wall is obtained. During the excavation process, the support of the single side wall I is constructed simultaneously. The support of the single side wall I is connected to the support of the second pilot tunnel I and the support of the third pilot tunnel I to form a ring.

[0025] S52. Subsequently, construct the second guide tunnel and simultaneously move the first second guide tunnel support toward the position of the fifth guide tunnel. After the lateral width of the fifth guide tunnel is reduced to 2.28m, stop the construction of the second guide tunnel and begin the construction of the fifth guide tunnel. Remove the first second guide tunnel support and merge the fifth guide tunnel and the second guide tunnel into a single-side wall temporary guide tunnel ④. The single-side wall temporary guide tunnel ④ and the single-side wall temporary guide tunnel ① share the single-side wall support I. The single-side wall support I, the second second guide tunnel support, and the third second guide tunnel support and the fifth guide tunnel support are connected to form a ring.

[0026] S53. Subsequently, the construction of the third pilot tunnel located on the side of the interlocking rock is carried out. The support of the first third pilot tunnel is moved laterally to the middle of the tunnel excavation face and fixedly excavated to obtain the second and third temporary pilot tunnels with single side walls. The second side wall support is constructed and the support of the second first pilot tunnel is removed. At this time, the support of the first and second side walls, the support of the second third pilot tunnel, and the support of the third first pilot tunnel are connected to form a ring.

[0027] S54. Subsequently, the support of the first IV section of the pilot tunnel is removed, and the IV section of the pilot tunnel and the VII section of the pilot tunnel are excavated. After the support of the second II section of the pilot tunnel is removed, a single-sided temporary pilot tunnel ⑤ section and a single-sided temporary pilot tunnel ⑥ section are obtained. At this time, the single-sided support I section, the single-sided support II section, the second IV section of the pilot tunnel support, and the third II section of the pilot tunnel support are connected to form a ring.

[0028] S55. During construction, the initial support shall be carried out in accordance with the excavation progress. After the construction is completed, monitoring and measurement shall be carried out. Once the requirements are met, the single-side wall excavation method shall be converted to the three-stage sectional excavation method.

[0029] This setup allows for a smoother transition from double-sided wall pilot tunnels to single-sided wall construction. Compared to abrupt changes in cross-section, this helps reduce excessive stress concentration and improves the stability of the initial support.

[0030] As a preferred embodiment of the present invention, after the excavation of the single-sided temporary pilot tunnel ①, the single-sided temporary pilot tunnel ②, the single-sided temporary pilot tunnel ③, the single-sided temporary pilot tunnel ④, the single-sided temporary pilot tunnel ⑤, and the single-sided temporary pilot tunnel ⑥, their respective supports need to be set in the same direction as the excavation.

[0031] As a preferred embodiment of the present invention, the specific steps for converting the single-sidewall pilot tunnel method in S55 into the three-stage sectional excavation method are as follows:

[0032] S61. Conduct monitoring and measurement, and after the requirements are met, convert the single-side wall pilot tunnel method into the three-stage sectional excavation method.

[0033] S62. Mechanical excavation, using a combination of mechanical and blasting methods, is employed to form the upper bench A section, and support is simultaneously installed at the upper bench A section.

[0034] S63. After the upper step A is completed, the temporary guide tunnel ① on the side wall of the middle rock is excavated to obtain the middle step B. Then, the temporary guide tunnel ④ on the side wall is excavated to obtain the middle step C. At the same time, the support at the middle step B and the support at the middle step C are built. The core soil of the middle step is excavated to obtain the middle step F.

[0035] S64. After completion, the lower step E is obtained by excavating the temporary guide tunnel ② along the single side wall located on the side of the middle rock. Then, the lower step D is obtained by excavating the temporary guide tunnel ⑤ along the single side wall.

[0036] S65. After completion, excavate the middle part of the lower step to obtain the lower step G part and the invert arch H part and simultaneously perform support, and make the initial support (23) closed into a ring.

[0037] This three-stage setup facilitates mechanized construction, improves construction efficiency, and allows for large-scale construction inside the tunnel.

[0038] As a preferred embodiment of the present invention, during the construction of the advanced support and initial support in the three-stage sectional excavation method, 2 to 4 Φ50 anchor pipes are added to each steel frame. This arrangement can improve the bearing capacity of the arch frame and control the settlement of the arch frame.

[0039] As a preferred embodiment of the present invention, after the tunnel excavation face area is divided in step S2, the double-side wall pilot tunnel method can be directly converted into the three-stage sectional excavation method to excavate the tunnel excavation face.

[0040] As a preferred embodiment of the present invention, the specific steps for converting the double-sidewall pilot tunnel method to the three-stage sectional excavation method are as follows:

[0041] The specific steps for converting the double-side-wall pilot tunnel method to the three-stage sectional excavation method are as follows:

[0042] S71. Remove the support of the first I section guide tunnel and the support of the first II section guide tunnel, keeping the initial support unchanged, so that the I section guide tunnel, the II section guide tunnel and the V section guide tunnel are combined into a whole;

[0043] S72. Then, from top to bottom, excavate 4m along the direction from the highest point of the V guide tunnel to the lowest point of the I guide tunnel and the II guide tunnel to obtain the upper step A.

[0044] S73. After the excavation of the upper step A section is completed, the middle step is constructed. First, the side of the interbedded rock in the middle of the tunnel excavation face is excavated, that is, the pilot tunnel of section I is excavated to obtain the middle step B section. Then, the pilot tunnel of section II is excavated to obtain the middle step C section. The core soil position of the middle step is excavated, and then the middle step F section is obtained.

[0045] S74. After the middle bench is constructed, the lower bench is constructed. First, the rock side of the tunnel excavation face is excavated, that is, the III pilot tunnel is excavated to obtain the lower bench E section. Then, the IV pilot tunnel is excavated to obtain the lower bench D section. Then, the core soil of the lower bench is excavated and the support of the first IV pilot tunnel and the support of the first III pilot tunnel are removed to obtain the lower bench G section and the invert H section.

[0046] S75. Conversion complete;

[0047] The advantage of this setup is that it transforms the double-sided pilot tunnel into a three-stage tunnel, which facilitates mechanized construction, improves construction efficiency, and allows for large-scale construction inside the tunnel.

[0048] As a preferred embodiment of the present invention, during the construction of the support for each step in the three-step sectional excavation method, each steel frame is equipped with 2 to 4 anchor pipes.

[0049] As a preferred embodiment of the present invention, after the support of the upper step A section is completed in step S72, the middle step can only be excavated after the actual strength of the shotcrete for the support reaches 70% of the design strength. The excavation distance of the upper step A section should not be too long, and should be controlled within the spacing of 5 to 8 steel arch frames (3 to 5m). The middle step should be excavated in a timely manner. The middle step B section should be excavated first, followed by the middle step C section. The vibration impact of subsequent blasting on the interbedded rock is reduced by using staggered loosening blasting excavation on both sides. At the same time, the central area of ​​the tunnel excavation face is reserved as the core soil of the middle step. The middle step is a short step, and its length should be controlled within 3 to 5m. The reserved width of the core soil of the middle step should be more than 1 / 2 of the total width of the corresponding middle step excavation to facilitate mechanized construction and serve as the working platform for all excavation and support equipment of the upper and middle steps and the transportation channel for all excavated material.

[0050] As a preferred embodiment of the present invention, in step S73, after the support of the middle bench B and middle bench C is completed, the lower bench can be excavated only after the actual strength of the initial support shotcrete reaches 70% of the design strength. The lower bench E is excavated first, followed by the lower bench D. By using alternating loosening blasting excavation on both sides, the number of vibration impacts of subsequent blasting on the interbedded rock is reduced. At the same time, the central area of ​​the tunnel excavation face is reserved as the core soil of the lower bench. The lower bench is a short bench, and its length should be controlled between 3 and 5 m. The reserved width of the core soil of the lower bench should be more than 1 / 2 of the total width of the corresponding lower bench excavation to facilitate mechanized construction and serve as the working platform for all excavation and support equipment and the transportation channel for muck removal. The core soil of the lower bench is selected by loosening blasting, and the excavation cycle advance is 1.2 to 2 m.

[0051] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0052] 1. This invention relates to a method for constructing an extra-large cross-section, small-clearance soft rock tunnel. After dividing the tunnel excavation face into zones, a double-sided wall pilot tunnel method is used for excavation. This is then transitioned to a single-sided wall pilot tunnel method, with a gradual transition between the two methods. This smoother transition, compared to abrupt cross-section changes, helps reduce excessive stress concentration and improves the stability of the initial support. After monitoring and measuring the single-sided wall pilot tunnel construction, if the settlement is less than or equal to 1 cm and the convergence is less than or equal to 3 cm, the single-sided wall pilot tunnel method is converted to a three-stage sectional excavation method. This method utilizes the single-sided wall pilot tunnel method to achieve the desired results. The initial excavation serves to reveal the surrounding rock ahead, providing a basis for subsequent construction. Simultaneously, the excavation of the pilot tunnel releases some of the surrounding rock stress, reducing stress distribution in the subsequent large sections. By closely following the pilot tunnel, the single-sidewall tunnel gradually transforms into a three-stage excavation. Under safe conditions, by closely following each stage and gradually removing the upper stage sidewall, it becomes a three-stage excavation. This facilitates mechanized construction, improves efficiency, allows for large-scale construction within the tunnel, increases excavation space and mechanization, accelerates construction progress, and reduces labor costs. The three-stage excavation method allows for flexible adjustment of construction procedures and methods to adapt to different geological conditions and cross-sectional forms, ensuring construction safety and quality.

[0053] 2. This invention relates to a method for constructing an ultra-large cross-section, small-clearance soft rock tunnel. This method can convert the double-sided wall pilot tunnel method into a three-stage sectional excavation method (when monitoring and measurement show that the settlement of the double-sided wall pilot tunnel method is less than or equal to 1 cm and the convergence is less than or equal to 3 cm, the double-sided wall pilot tunnel method is converted into the three-stage sectional excavation method). By dividing the tunnel excavation face into three stages (upper, middle, and lower) and adjusting the construction method of the double-sided wall pilot tunnel method, the double-sided wall pilot tunnel method is gradually converted into the three-stage sectional excavation method. The advanced excavation of the single-sided pilot tunnel of the double-sided wall plays a role in revealing the surrounding rock ahead, which is beneficial for subsequent excavation. The construction provides a basis for the project. After the pilot tunnel is excavated, some of the surrounding rock stress is released, which reduces the stress distribution in the subsequent large section. By following closely, the double-sided pilot tunnel is gradually transformed into a three-stage section. Under the premise of ensuring safety, by following closely in each section, the upper stage sidewall is gradually removed, and it is transformed into a three-stage section. This is conducive to mechanized construction, improves construction efficiency, and allows for large-scale construction inside the tunnel. This transformation can reduce the number of excavation face sections and simplify construction procedures, thereby improving construction efficiency. At the same time, it also avoids secondary disturbance to the surrounding rock when removing temporary supports, saving costs.

[0054] 3. This invention is a method for constructing an extra-large cross-section soft rock tunnel with a small clearance. By transforming the double-sided wall pilot tunnel method into the single-sided wall pilot tunnel method during construction, and then transforming the single-sided wall pilot tunnel method into the three-stage sectional excavation method, or directly transforming the double-sided wall pilot tunnel method into the three-stage sectional excavation method, this method can adapt to different environments, improve the flexibility of the method, and increase the construction efficiency during the construction process. Attached Figure Description

[0055] Figure 1 This is a schematic diagram of the region division structure of the double-sidewall guide pit method of the present invention;

[0056] Figure 2 This is a schematic diagram of the first step in the gradual conversion of the double-sided wall guide tunnel method to the single-sided wall guide tunnel method of the present invention;

[0057] Figure 3 This is a schematic diagram of the second part of the invention, showing the gradual conversion of the double-sided wall guide tunnel method into the single-sided wall guide tunnel method;

[0058] Figure 4 This is a schematic diagram of the third step of the present invention, in which the double-sided wall guide tunnel method is gradually converted into the single-sided wall guide tunnel method;

[0059] Figure 5 This is a schematic diagram of the fourth step of the present invention, which gradually transforms the double-sided wall guide tunnel method into the single-sided wall guide tunnel method;

[0060] Figure 6 This is a schematic diagram of the fifth step of the present invention, which gradually transforms the double-sided wall guide tunnel method into the single-sided wall guide tunnel method;

[0061] Figure 7 This is a schematic diagram of the tunnel excavation face after construction using the single-side-wall pilot tunnel method of the present invention;

[0062] Figure 8 This is a schematic diagram of the first step in converting the single-sidewall pilot tunnel method of the present invention into the three-stage sectional excavation method;

[0063] Figure 9 This is a schematic diagram of the second step in converting the single-sidewall pilot tunnel method of the present invention into the three-stage sectional excavation method;

[0064] Figure 10 This is a schematic diagram of the third step in converting the single-sidewall pilot tunnel method of the present invention into the three-stage sectional excavation method;

[0065] Figure 11 This is a schematic diagram of the fourth step in converting the single-sidewall pilot tunnel method of the present invention into the three-stage sectional excavation method;

[0066] Figure 12 This is a schematic diagram of the first step in converting the double-side-wall pilot tunnel method of the present invention into the three-stage sectional excavation method;

[0067] Figure 13 This is a schematic diagram of the second step in converting the double-side-wall pilot tunnel method of the present invention into the three-stage sectional excavation method;

[0068] Figure 14 This is a schematic diagram of the third step in converting the double-side-wall pilot tunnel method of the present invention into the three-stage sectional excavation method;

[0069] Figure 15 This is a flowchart of the construction method of the present invention.

[0070] Icons: 1-Section I pilot tunnel; 101-First Section I pilot tunnel support; 102-Second Section I pilot tunnel support; 103-Third Section I pilot tunnel support; 2-Section II pilot tunnel; 201-First Section II pilot tunnel support; 202-Second Section II pilot tunnel support; 203-Third Section II pilot tunnel support; 3-Section III pilot tunnel; 301-First Section III pilot tunnel support; 302-Second Section III pilot tunnel support; 4-Section IV pilot tunnel; 401-First Section IV pilot tunnel support; 402-Second Section IV pilot tunnel support; 5-Section V pilot tunnel; 501-Section V pilot tunnel support; 6-Section VI pilot tunnel; 7-Section VII pilot tunnel; 701-

[0071] VII. Pilot tunnel support; 8. Tunnel excavation face; 9. Temporary pilot tunnel ① with single side wall; 91. Single side wall support I

[0072] Section 10 - Temporary pilot tunnel with single-sided wall ②; Section 111 - Single-sided wall support II; Section 11 - Temporary pilot tunnel with single-sided wall ③

[0073] Section 12 - Temporary pilot tunnel with single side wall ④; Section 13 - Temporary pilot tunnel with single side wall ⑤; Section 14 - Temporary pilot tunnel with single side wall ⑥; Section 15 - Upper bench A; Section 16 - Middle bench B; Section 17 - Middle bench C; Section 18 - Lower bench D; Section 19 - Lower bench E; Section 20 - Middle bench F; Section 21 - Lower bench G; Section 22 - Invert H; Section 23 - Initial support. Detailed Implementation

[0074] The present invention will now be described in detail with reference to the accompanying drawings.

[0075] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative and not intended to limit the invention.

[0076] Example 1

[0077] like Figure 15 The diagram illustrates a method for tunnel entry construction in soft rock with a large cross-section and small clearance. The tunnel is a separated twin-tunnel design with interbedded rock between the tunnels. This method is used for tunnel entry construction and is described below:

[0078] S1. Before construction, a tunnel excavation face 8 is set up at the tunnel entrance. The tunnel excavation face 8 is divided into areas according to modules and excavated and supported. The initial support 23 and the remaining support are obtained through construction.

[0079] S2. After the area is divided, the tunnel excavation face 8 is constructed using the double-side wall pilot tunnel method. After the double-side wall pilot tunnel method is completed, the tunnel excavation face 8 is monitored and measured. When the monitoring and measurement results show that the settlement is less than or equal to 2cm and the convergence is less than or equal to 5cm, the double-side wall pilot tunnel method is converted to the single-side wall pilot tunnel method for excavation of the tunnel excavation face 8. When the monitoring and measurement results show that the settlement is less than or equal to 1cm and the convergence is less than or equal to 3cm, the double-side wall pilot tunnel method is converted to the three-step sectional method for excavation of the tunnel excavation face 8.

[0080] S3. After excavation using the single-side-wall pilot tunnel method, monitoring and measurement are carried out. When the results show that the settlement is less than or equal to 1cm and the convergence is less than or equal to 3cm, the single-side-wall pilot tunnel method is converted into the three-step sectional method for construction of the tunnel excavation face 8.

[0081] S4. Tunnel entry construction completed;

[0082] Furthermore, the aforementioned initial support 23 needs to be installed synchronously with the excavation process after the tunnel excavation face 8 is excavated.

[0083] By using the double-sided wall pilot tunnel method described above to convert the construction method based on the monitoring and measurement results, the stability and timeliness of the excavation can be effectively guaranteed in the construction of extra-large cross-section tunnels.

[0084] The surrounding rock grade for this tunnel construction is V, which is soft rock. The definition of minimum clearance for this grade of surrounding rock is shown in the table below:

[0085]

[0086] Furthermore, the clearance distance between the left and right tunnels at the tunnel entrance is 22.21m, the clearance distance between the left and right tunnels in the middle standard section is 25m, and the clearance distance between the left and right tunnels at the tunnel exit is 17.16m, classifying it as a tunnel with small clearance. The excavation end face of this tunnel is 207.7m. 2 It belongs to the category of extra-large cross sections (excavation cross section greater than 100m). 2 (It belongs to an extra-large cross section).

[0087] As mentioned above, since this is a separated twin-tunnel with a small clearance, and the two tunnels are separated by interbedded rock, when constructing the excavation face 8 of a single tunnel, the interbedded rock side of the tunnel should be constructed first. This will reduce the impact of the later tunnel construction on the interbedded rock.

[0088] As mentioned above, the tunnel excavation face 8 is divided into seven areas, namely: pilot tunnel I 1, pilot tunnel II 2, pilot tunnel III 3 and pilot tunnel IV 4 located on both sides of the tunnel excavation face 8, and pilot tunnel V 5, pilot tunnel VI 6 and pilot tunnel VII 7 located in the middle of the tunnel excavation face 8.

[0089] Furthermore, both pilot tunnel I (section 1) and pilot tunnel III (section 3) are located on the side of the interbedded rock. This means that the construction of tunnel excavation face 8 begins with pilot tunnel I (section 1) and proceeds towards the opposite side, followed by pilot tunnel III (section 3) and proceeds towards the opposite side. In other words, starting from the side of the interbedded rock, excavation proceeds from the opposite sides first, then from top to bottom, and finally excavates the middle section. This allows for the retention of core soil, which is beneficial for the stability of the surrounding rock and the connection of the support, reducing deformation and damage to the surrounding rock. Figure 1 As shown.

[0090] The aforementioned circumferential support structure for each pilot tunnel is as follows:

[0091] First, the pilot tunnel 1 is constructed circumferentially with the tunnel axis as the reference, consisting of a first pilot tunnel support 101, a second pilot tunnel support 102, and a third pilot tunnel support 103. One end of the first pilot tunnel support 101 is connected to one end of the third pilot tunnel 103, while the other ends of the first pilot tunnel support 101 and the third pilot tunnel 103 are respectively connected to the second pilot tunnel 102. This allows the first pilot tunnel support 101, the second pilot tunnel support 102, and the third pilot tunnel support 103 to be connected to each other to form a ring, which is beneficial for the support of the tunnel.

[0092] Second, the first guide tunnel 1 is adjacent to the third guide tunnel 3 and located above the third guide tunnel 3. The third guide tunnel 3 is circumferentially supported by a first third guide tunnel support 301 and a second third guide tunnel support 302. One end of the first third guide tunnel support 301 is connected to one end of the second third guide tunnel support 302, while the other ends of the first third guide tunnel support 301 and the second third guide tunnel support 302 are respectively connected to the second first guide tunnel support 102. This allows the first third guide tunnel support 301, the second third guide tunnel support 302 and the second first guide tunnel support 102 to be connected to form a ring.

[0093] Furthermore, the first section I pilot tunnel support 101, the first section III pilot tunnel support 301, the second section III pilot tunnel support 302, and the third section I pilot tunnel support 103 are all connected to form a ring, which enhances the support for the extra-large cross-section tunnel.

[0094] Third, the second guide tunnel 2 is circumferentially supported by a first second guide tunnel support 201, a second second guide tunnel support 202, and a third second guide tunnel support 203. One end of the first second guide tunnel support 201 is connected to one end of the second second guide tunnel support 202, while the other ends of the first second guide tunnel support 201 and the second second guide tunnel support 202 are respectively connected to the third second guide tunnel support. This allows the first second guide tunnel support 201, the second second guide tunnel support 202, and the third second guide tunnel support 203 to be connected to each other to form a ring.

[0095] Fourth, the second section of the pilot tunnel 2 is adjacent to the fourth section of the pilot tunnel 4 and is located above the fourth section of the pilot tunnel 4. The fourth section of the pilot tunnel 4 is provided with a first fourth section of the pilot tunnel support 401 and a second fourth section of the pilot tunnel support 402 around its perimeter. One end of the first fourth section of the pilot tunnel support 401 is connected to one end of the second fourth section of the pilot tunnel support 402, while the other ends of the first fourth section of the pilot tunnel support 401 and the second fourth section of the pilot tunnel support 402 are respectively connected to the second second section of the pilot tunnel support 202. This makes the first fourth section of the pilot tunnel support 401, the second fourth section of the pilot tunnel support 402 and the second second section of the pilot tunnel support 202 interconnected to form a ring, which is beneficial to improving the stability of the tunnel support.

[0096] Furthermore, the first II section pilot tunnel support 201, the first IV section pilot tunnel support 401, the second IV section pilot tunnel support 402, and the third II section pilot tunnel support 203 are all connected to form a ring to improve the support for the excavation of the extra-large cross-section tunnel.

[0097] Fifth, at one end of the tunnel near the tunnel wall, the V-section pilot tunnel 5 and the VII-section pilot tunnel 7 are respectively provided with V-section pilot tunnel support 501 and VII-section pilot tunnel support 701, and the V-section pilot tunnel support 501 is connected in sequence with the first II-section pilot tunnel support 201, the first IV-section pilot tunnel support 401 is connected with the VII-section pilot tunnel support 701, and the first III-section pilot tunnel support 301 is connected with the first I-section pilot tunnel support 101 to form a ring;

[0098] Sixth, the third section I pilot tunnel support 103 and the second section III pilot tunnel support 302, the VII pilot tunnel support 701 and the second section IV pilot tunnel support 402, and the third section II pilot tunnel support 203 and the V pilot tunnel support 501 are all connected end to end to form a ring to form the initial support 23.

[0099] By setting the various supports in a ring shape, the structural stability during the excavation of tunnels with extra-large cross sections can be improved.

[0100] Furthermore, it should be noted that pilot tunnel I 1 and pilot tunnel III 3 are symmetrical, while pilot tunnel II 2 and pilot tunnel IV 4 are symmetrical, and the symmetrical pilot tunnels do not contact each other. This allows for the reservation of a core soil location in the middle of the tunnel excavation face 8. This core soil location is divided from top to bottom into pilot tunnel V 5, pilot tunnel VI 6, and pilot tunnel VII 7, as follows... Figure 1 As shown.

[0101] The conversion steps from the double-sided wall pilot ditch method to the single-sided wall pilot ditch method are as follows:

[0102] The first step is to conduct advanced geological forecasting, monitoring and measurement, and to set up support structures and conduct geological analysis.

[0103] The second step is to construct the pilot tunnel 1 (Section I). The longitudinal spacing of the first pilot tunnel support 101 is 0.6m per cycle. In each cycle, it is moved 20cm laterally towards the centerline of the tunnel of pilot tunnel 5 (Section V) in the cross-sectional direction. After advancing 14 sections and 8.4m, the first pilot tunnel support 101 is moved laterally to the centerline of the tunnel and then to the position of the temporary pilot tunnel 1 (Section 9) with one side wall. The lateral movement is stopped. The construction of the temporary pilot tunnel 1 (Section 9) with one side wall is carried out in accordance with the method of pilot tunnel with one side wall.

[0104] It should be noted that when constructing the temporary pilot tunnel ① 9 on a single side wall, the support I 91 on a single side wall should be erected at the same time, and the support I 91 on a single side wall should be connected to the second pilot tunnel support 102 and the third pilot tunnel support 103 to form a ring.

[0105] Step 3: After constructing the first guide tunnel 1 of the double side walls for 3-5m, begin the construction of the second guide tunnel 2. The second guide tunnel 2 moves laterally and gradually changes from the first guide tunnel 1. The first second guide tunnel support 201 is moved laterally, advancing 8 sections and 4.8m. After the lateral width of the fifth guide tunnel 5 is reduced to 2.28m, the construction of the second guide tunnel 2 is stopped.

[0106] Step 4: After the construction of the double-sided wall II section pilot tunnel 2 is stopped, the construction of the V section pilot tunnel 5 begins. After the V section pilot tunnel 5 is constructed to the position where the II section pilot tunnel 2 stops, the first II section pilot tunnel support 201 is removed and the V section pilot tunnel 5 and the II section pilot tunnel 2 are merged into a single-sided wall temporary pilot tunnel ④ section 12. At this time, the single-sided wall temporary pilot tunnel ④ section 12 and the single-sided wall temporary pilot tunnel ① section 9 share the single-sided wall support I section 91 as support.

[0107] It should be noted that the single-sided wall support I part 91 and the second II part guide tunnel support 202, as well as the third II part guide tunnel support 203 and the V part guide tunnel support 501, are connected to form a ring;

[0108] Step 5: After merging the double-sided wall II pilot tunnel 2 and V pilot tunnel 5 into a single-sided wall temporary pilot tunnel ④ 12, proceed forward 5m and then pause construction. During construction, maintain the initial support 23 in a ring and continue its construction. Subsequently, construct the double-sided wall III pilot tunnel 3. The longitudinal spacing of the first III pilot tunnel support 301 is 0.6m per cycle. In each cycle, move 20cm laterally towards the tunnel centerline of VI pilot tunnel 6 and VII pilot tunnel 7 in the cross-sectional direction. At the same time, construct the single-sided wall temporary pilot tunnel ③ 11. Each adjacent support should form a ring in time. After the first III pilot tunnel support 301 advances 14 sections and 8.4m, the first III pilot tunnel support 301 is moved laterally to the centerline of the tunnel. The second section 10 and the third section 11 of the single side wall temporary pilot tunnel are constructed. The lateral movement is stopped, and the second section 111 of the single side wall support is constructed. The second section 111 of the single side wall support is connected to one end of the first section 91 of the single side wall support. At this time, the second section I pilot tunnel support 102 between the first section pilot tunnel 1 and the third section pilot tunnel 3 is removed.

[0109] It should be noted that the merged single-sided wall support II part 111 is connected to the single-sided wall support I part 91, the third I part pilot tunnel support 103, and the second III part pilot tunnel support 302 to form a ring;

[0110] Step 6: The temporary pilot tunnels ① 9, ② 10, and ③ 11 of the single-sided wall are constructed normally as single-sided walls. After the temporary pilot tunnel ③ 11 of the single-sided wall exceeds the position of the temporary pilot tunnel ④ 12 of the single-sided wall by 5m, the pilot tunnel 4 of the double-sided wall IV is constructed. After advancing 8 sections and 4.8m, construction is suspended. Then the pilot tunnel 7 of the double-sided wall VII is constructed. The pilot tunnel 7 of the double-sided wall is constructed until the position of the pilot tunnel 4 of the double-sided wall IV is stopped. The temporary supports of the pilot tunnel 4 of the double-sided wall IV and the pilot tunnel 7 of the double-sided wall VII are removed, and the construction is converted to the single-sided wall pilot tunnel method to obtain the temporary pilot tunnels ⑤ 13 and ⑥ 14 of the single-sided wall VI. After the construction here is completed, the support 202 of the second pilot tunnel II should be removed. The temporary pilot tunnels ⑤ 13 and ⑥ 14 of the single-sided wall VI are both supported by the support of the single-sided wall support II 111.

[0111] Step 7: Conduct monitoring and measurement. Once the requirements are met, convert the single-sidewall pilot tunnel method to the three-stage sectional excavation method, such as... Figure 2-6 As shown.

[0112] The specific steps for converting the single-sidewall pilot tunnel method into the three-stage sectional excavation method, as described above, are as follows:

[0113] The first step is to excavate using machinery and a combination of machinery and blasting to form the upper bench A section 15, and at the same time set up support for the upper bench A section;

[0114] Step 2: After the completion of the upper step A section 15, the middle step can only be excavated after the actual strength of the initial support shotcrete reaches 70% of the design strength. The excavation distance of the upper step should not be too long, controlled within 5-8 steel arches (3-5m) apart, and the middle step should be excavated in a timely manner. Considering the impact of blasting on the interbedded rock during the excavation process, the middle step B section 16 is obtained by excavating the temporary guide tunnel ① 9 on one side wall first, and then the other side, namely the temporary guide tunnel ④ 12 on one side wall, is obtained by excavating the middle step C section 17. Then, the advanced support and initial support at the middle step B section and the middle step C section are constructed to reduce the number of vibration impacts of blasting on the interbedded rock. The loosening blasting excavation is carried out alternately on both sides, and the core soil of the middle step is reserved at the same time. The middle step is a short step, and the length should be controlled within 3-5m. The reserved width of the core soil of the middle step should be more than 1 / 2 of the total excavation width of the corresponding middle step, and the length is determined according to the mechanical configuration to facilitate mechanized construction.

[0115] Step 3: After the middle bench support is completed, the lower bench can only be excavated after the actual strength of the initial support shotcrete reaches 70% of the design strength. Considering the impact of blasting on the interbedded rock during excavation, the lower bench is first excavated by excavating the temporary pilot tunnel ②10 on one side wall to obtain the lower bench E19, followed by the excavation of the temporary pilot tunnel ⑤13 on one side wall to obtain the lower bench D18, reducing the number of vibration impacts of blasting on the interbedded rock. Staggered loosening blasting excavation is used on both sides, while reserving core soil for the bench. The lower bench is a short bench, with a length preferably controlled between 3 and 5 meters. The reserved width of the core soil for the lower bench should be more than 1 / 2 of the total excavation width of the corresponding lower bench, and the length depends on the machinery configuration to facilitate mechanized construction. It serves as an operating platform for all excavation and support equipment and a transportation channel for excavated material. Loosening blasting is used for the lower bench, with an excavation cycle advance of 1.2 to 2 meters.

[0116] In the fourth step, core soil should be reserved during the excavation of the middle and lower benches, and the single-sided wall support I part 91 should be removed. The cross-section of the core soil should be more than 50% larger than the excavation cross-section. The reserved width of the core soil should preferably be more than 1 / 2 of the corresponding bench excavation width, and the length should be determined according to the machinery configuration to provide a construction passage for the machinery and facilitate mechanized construction. The core soil reserved for the middle and lower benches serves as an operating platform for all excavation and support equipment and a transportation channel for excavated material. Loosening blasting should be used for the core soil reserved for the middle and lower benches, and the excavation cycle advance should be 2-2.5m. The core soil reserved for the middle and lower benches should be excavated promptly after the other side is excavated and supported for 3-5m. In particular, the excavation of the core soil reserved for the lower bench should provide conditions for the excavation and support from the bottom and the initial support of the tunnel as a whole to close the ring, so as to avoid the suspension time on both sides for too long. After the lower bench is excavated (within 5m), the bottom excavation should be organized as soon as possible. The bottom excavation adopts loosening blasting, and the cycle advance is no more than 5 steel arches (3m) apart, to obtain the middle bench F part 20, the lower bench G part 21 and the invert arch H part 22;

[0117] Furthermore, during the support construction of each step in the three-step sectional excavation method, 2 to 4 anchor pipes are installed for each steel frame, such as... Figure 7-10 As shown.

[0118] Example 2

[0119] like Figure 11-14 After the tunnel excavation face 8 area is divided according to Embodiment 1, the double-sidewall pilot tunnel method can be directly converted into the three-stage sectional excavation method to excavate the tunnel excavation face 8. The excavation method is as follows:

[0120] Step 1: Remove the first I section guide tunnel support 101 and the first II section guide tunnel support 201, while keeping the initial support 23 unchanged, so that the I section guide tunnel 1, the II section guide tunnel 2 and the V section guide tunnel 5 are combined into a whole;

[0121] The second step is to excavate 4m from top to bottom along the direction from the highest point of the V guide tunnel 5 to the lowest point of the I guide tunnel 1 and the II guide tunnel 2 to obtain the upper step A section 15.

[0122] The third step involves excavating the upper step A section 15 after completion, and then constructing the middle step. First, the side of the interbedded rock located in the tunnel excavation face 8 is excavated, that is, the pilot tunnel I is excavated to obtain the middle step B section 16. Then, the pilot tunnel II is excavated to obtain the middle step C section 17. Finally, the core soil of the middle step is excavated to obtain the middle step F section 20.

[0123] Step 4: After the middle bench is constructed, the lower bench is constructed. First, the rock side of the tunnel excavation face 8 is excavated, that is, the III pilot tunnel 3 is excavated to obtain the lower bench E section 19. Then, the IV pilot tunnel 4 is excavated to obtain the lower bench D section 18. Then, the core soil of the lower bench is excavated and the first IV pilot tunnel support 401 and the first III pilot tunnel support 301 are removed to obtain the lower bench G section 21 and the invert H section 22.

[0124] Step 5: Conversion complete.

[0125] As mentioned above, after the support of the upper step A section 15 is completed, the middle step can only be excavated after the actual strength of the shotcrete for the support reaches 70% of the design strength. The excavation distance of the upper step A section 15 should not be too long, and should be controlled within the spacing of 5 to 8 steel arch frames (3 to 5m). The middle step should be excavated in a timely manner. The middle step B section 16 should be excavated first, followed by the middle step C section 17. The vibration impact of subsequent blasting on the interbedded rock should be reduced by using staggered loosening blasting on both sides. At the same time, the central area of ​​the tunnel excavation face 8 should be reserved as the core soil of the middle step. The middle step is a short step, and its length should be controlled within 3 to 5m. The reserved width of the core soil of the middle step should be more than 1 / 2 of the total width of the corresponding middle step excavation. The length depends on the configuration of machinery to facilitate mechanized construction and serve as the working platform for all excavation and support equipment of the upper and middle steps and the transportation channel for all excavated material.

[0126] In the aforementioned steps, after the support of the middle bench B section 16 and the middle bench C section 17 is completed, the lower bench can only be excavated after the actual strength of the initial support shotcrete reaches 70% of the design strength. The lower bench E section 19 is excavated first, followed by the lower bench D section 18. The excavation is carried out by alternating loosening blasting on both sides to reduce the vibration impact of subsequent blasting on the interbedded rock. At the same time, the central area of ​​the tunnel excavation face 8 is reserved as the core soil of the lower bench. The lower bench is a short bench, and its length should be controlled between 3 and 5 meters. The reserved width of the core soil of the lower bench should be more than 1 / 2 of the total width of the corresponding lower bench excavation. The length is determined according to the mechanical configuration to facilitate mechanized construction. It serves as the working platform for all excavation and support equipment and the transportation channel for muck removal. The core soil of the lower bench is obtained by loosening blasting, and the excavation cycle advance is 1.2 to 2 meters.

[0127] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A method for constructing an ultra-large cross-section, small-clearance soft rock tunnel, wherein the tunnel is a separated twin-tunnel with a narrow clearance, and the space between the tunnels is interbedded with rock. The method is characterized by... This method is used for construction during tunnel entry, and the specific construction method is as follows: S1. Set up a tunnel excavation face (8) at the tunnel entrance, and carry out regional excavation on the tunnel excavation face (8) according to the module and simultaneously build the support to obtain the initial support (23) and the remaining support; S2. After the area is divided, the double-sided wall pilot tunnel method is used to construct the tunnel excavation face (8). After the construction is completed, the tunnel excavation face (8) is monitored and measured. When the monitoring and measurement results show that the settlement is less than or equal to 2cm and the convergence is less than or equal to 5cm, the single-sided wall pilot tunnel method is used to construct the tunnel excavation face (8). If the monitoring and measurement results show that the settlement is less than or equal to 1cm and the convergence is less than or equal to 3cm, the three-stage sectional excavation method is directly used to construct the tunnel excavation face (8). S3. After the single-side wall pilot tunnel method is completed, the tunnel excavation face (8) is monitored and measured. When the monitoring and measurement results show that the settlement is less than or equal to 1cm and the convergence is less than or equal to 3cm, the single-side wall pilot tunnel method is converted into the three-stage sectional excavation method to construct the tunnel excavation face (8). S4. Tunnel entry construction completed; In step S1, the tunnel excavation face (8) is divided into modules: I pilot tunnel (1) and III pilot tunnel (3) located on the side of the interbedded rock, II pilot tunnel (2) and IV pilot tunnel (4) on the opposite side, V pilot tunnel (5) and VI pilot tunnel (6) and VII pilot tunnel (7) located in the core soil position in the middle of the tunnel excavation face (8), and each of the pilot tunnels is supported in the circumferential direction; The circumferential support for each pilot tunnel is constructed as follows: S41. The first section of the pilot tunnel (1) is circumferentially supported by a first section of the pilot tunnel support (101), a second section of the pilot tunnel support (102), and a third section of the pilot tunnel support (103) that are connected end to end to form a ring. S42. The I-section guide tunnel (1) is adjacent to the III-section guide tunnel (3). The III-section guide tunnel (3) is circumferentially supported by a first III-section guide tunnel support (301), a second III-section guide tunnel support (302), and a second I-section guide tunnel support (102), and the connected supports are connected to form a ring. S43. The second guide tunnel (2) is circumferentially supported by a first second guide tunnel support (201), a second second guide tunnel support (202) and a third second guide tunnel support (203), and the first second guide tunnel support (201) is connected to the second second guide tunnel support (202) and the third second guide tunnel support (203) to form a ring; S44. The II guide pit (2) is adjacent to the IV guide pit (4). The IV guide pit (4) is provided with a first IV guide pit support (401) and a second IV guide pit support (402) in the circumferential direction. The first IV guide pit support (401), the second IV guide pit support (402) and the second II guide pit support (202) are connected to form a ring. S45. The V-section guide tunnel (5) is provided with the VI-section guide tunnel (6) and the VII-section guide tunnel (7) in sequence. The V-section guide tunnel (5) and the VII-section guide tunnel (7) are respectively provided with V-section guide tunnel support (501) and VII-section guide tunnel support (701) at one end near the tunnel wall. The V-section guide tunnel support (501) is connected to the first II-section guide tunnel support (201), the first IV-section guide tunnel support (401) is connected to the VII-section guide tunnel support (701), and the first III-section guide tunnel support (301) is connected to the first I-section guide tunnel support (101) to form a ring. S46. The third section I guide tunnel support (103) and the second section III guide tunnel support (302), the VII guide tunnel support (701) and the second section IV guide tunnel support (402), and the third section II guide tunnel support (203) and the V guide tunnel support (501) are all connected end to end to form a ring to form the initial support (23).

2. The method for constructing an ultra-large cross-section, small-clearance soft rock tunnel according to claim 1, characterized in that, When constructing the tunnel excavation face (8), the side of the interbedded rock should be excavated first.

3. The method for constructing an ultra-large cross-section, small-clearance soft rock tunnel according to claim 1, characterized in that, The steps for converting the double-sided wall guide tunnel method into the single-sided wall guide tunnel method are as follows: S31. First, construct the pilot tunnel (1) located on the side of the middle interlocking rock. Then, fix the first pilot tunnel support (101) to the center of the tunnel excavation face (8) by moving it laterally to the center line position of the tunnel. After excavating the pilot tunnel (1), a temporary pilot tunnel ① (9) with a single side wall is obtained. During the excavation process, the single side wall support ① (91) is constructed simultaneously. The single side wall support ① (91) is connected to the second pilot tunnel support (102) and the third pilot tunnel support (103) to form a ring. S32. Subsequently, the construction of the second guide tunnel (2) is carried out and the first second guide tunnel support (201) is moved toward the position of the fifth guide tunnel (5) at the same time. After the transverse width of the fifth guide tunnel (5) is reduced to 2.28m, the construction of the second guide tunnel (2) is stopped and the construction of the fifth guide tunnel (5) is started. The first second guide tunnel support (201) is removed and the fifth guide tunnel (5) and the second guide tunnel (2) are merged into a single-side wall temporary guide tunnel ④ (12). The single-side wall temporary guide tunnel ④ (12) and the single-side wall temporary guide tunnel ① (9) share the single-side wall support I (91). The single-side wall support I (91) is connected to the second second guide tunnel support (202) and the third second guide tunnel support (203) is connected to the fifth guide tunnel support (501) to form a ring. S33. Subsequently, the construction of the third pilot tunnel (3) located on the side of the middle interlocking rock is carried out. The first third pilot tunnel support (301) is moved laterally to the middle of the tunnel excavation face (8) and fixed excavation is carried out to obtain the second (10) and the third (11) of the single-side wall temporary pilot tunnel. The second (111) of the single-side wall support is constructed and the second (102) of the first pilot tunnel support is removed. At this time, the first (91) of the single-side wall support and the second (111) of the single-side wall support, as well as the second (302) of the third pilot tunnel support and the third (103) of the first pilot tunnel support are connected end to end to form a ring. S34. Subsequently, the first IV section guide tunnel support (401) is removed, and the IV section guide tunnel (4) and the VII section guide tunnel (7) are excavated. After the second II section guide tunnel support (202) is removed, a single-side wall temporary guide tunnel ⑤ (13) and a single-side wall temporary guide tunnel ⑥ (14) are obtained. At this time, the single-side wall support I (91) and the single-side wall support II (111) and the second IV section guide tunnel support (402) and the third II section guide tunnel support (203) are connected end to end to form a ring. S35. The initial support (23) mentioned during construction shall be carried out in accordance with the construction progress. After the construction is completed, monitoring and measurement shall be carried out. Once the requirements are met, the single-side wall excavation method shall be converted into the three-stage sectional excavation method.

4. The method for constructing an ultra-large cross-section, small-clearance soft rock tunnel according to claim 3, characterized in that, The specific steps for converting the single-sidewall pilot tunnel method in S55 into the three-stage sectional excavation method are as follows: S41. Conduct monitoring and measurement, and after the requirements are met, convert the single-side wall pilot tunnel method into the three-stage sectional excavation method. S42. Mechanical excavation and blasting are used to form the upper bench A section (15), and support is set up at the upper bench A section at the same time. S43. After the upper step A section (15) is completed, the temporary guide tunnel ① section (9) located on the side of the middle interlocking rock is excavated to obtain the middle step B section (16). Then, the temporary guide tunnel ④ section (12) is excavated to obtain the middle step C section (17). At the same time, the support at the middle step B section and the support at the middle step C section are built. The core soil of the middle step is excavated to obtain the middle step F section (20). S44. After completion, the lower step E (19) is obtained by excavating along the temporary guide tunnel ② (10) located on the side of the middle rock. Then, the lower step D (18) is obtained by excavating the temporary guide tunnel ⑤ (13). S45. After completion, excavate the middle part of the lower step to obtain the lower step G part (21) and the invert arch H part (22) and simultaneously perform support, and make the initial support (23) closed into a ring.

5. The method for constructing an ultra-large cross-section, small-clearance soft rock tunnel according to claim 1, characterized in that, The specific steps for converting the double-side-wall pilot tunnel method to the three-stage sectional excavation method are as follows: S51. Remove the first I-section guide tunnel support (101) and the first II-section guide tunnel support (201), keep the initial support (23) unchanged, so that the I-section guide tunnel (1), the II-section guide tunnel (2) and the V-section guide tunnel (5) are combined into a whole; S52. Then, from top to bottom, excavate 4m along the direction from the highest point of the V guide tunnel (5) to the lowest point of the I guide tunnel (1) and the II guide tunnel (2) to obtain the upper step A (15). S53. After the excavation of the upper step A (15) is completed, the middle step is constructed. First, the side of the interbedded rock in the tunnel excavation face (8) is excavated, that is, the pilot tunnel (1) of part I is excavated to obtain the middle step B (16). Then, the pilot tunnel (2) of part II is excavated to obtain the middle step C (17). The core soil of the middle step is excavated, and then the middle step F (20) is obtained. S54. After the middle step is completed, the lower step is constructed. First, the rock side of the tunnel excavation face (8) is excavated, that is, the III pilot tunnel (3) is excavated to obtain the lower step E (19). Then, the IV pilot tunnel (4) is excavated to obtain the lower step D (18). Then, the core soil of the lower step is excavated and the first IV pilot tunnel support (401) and the first III pilot tunnel support (301) are removed to obtain the lower step G (21) and the invert H (22). S55, Conversion complete.

6. The method for constructing an ultra-large cross-section, small-clearance soft rock tunnel according to claim 5, characterized in that, In the three-stage sectional excavation method, during the construction of support for each stage, 2 to 4 anchor pipes are installed for each steel frame.

7. The method for constructing an ultra-large cross-section, small-clearance soft rock tunnel according to claim 5, characterized in that, After the upper step A (15) is supported in step S52, the middle step can be excavated only after the actual strength of the shotcrete for support reaches 70% of the design strength. The excavation distance of the upper step A (15) should not be too long and should be controlled within the spacing of 5 to 8 steel arch frames (3 to 5m). The middle step should be followed up in a timely manner. The middle step should be excavated first, then the middle step B (16) and then the middle step C (17). By alternating loosening blasting excavation on both sides, the vibration impact of subsequent blasting on the interbedded rock can be reduced. At the same time, the central area of ​​the tunnel excavation face (8) should be reserved as the core soil of the middle step. The middle step is a short step, and its length should be controlled within 3 to 5m. The reserved width of the core soil of the middle step should be more than 1 / 2 of the total width of the corresponding middle step excavation. The length depends on the mechanical configuration to facilitate mechanized construction and serve as the operating platform for all excavation and support equipment of the upper and middle steps and the transportation channel for all excavated material.

8. The method for constructing an ultra-large cross-section, small-clearance soft rock tunnel according to claim 5, characterized in that, In step S53, after the support of the middle bench B (16) and the middle bench C (17) is completed, the lower bench can be excavated only after the actual strength of the initial support shotcrete reaches 70% of the design strength. The lower bench E (19) is excavated first, followed by the lower bench D (18). By using alternating loosening blasting excavation on both sides, the number of vibration impacts of subsequent blasting on the interbedded rock is reduced. At the same time, the central area of ​​the tunnel excavation face (8) is reserved as the core soil of the lower bench. The lower bench is a short bench, and its length should be controlled between 3 and 5 m. The reserved width of the core soil of the lower bench should be more than 1 / 2 of the total width of the corresponding lower bench excavation. The length depends on the mechanical configuration to facilitate mechanized construction. It serves as the working platform for all excavation and support equipment and the transportation channel for muck removal. The core soil of the lower bench is selected by loosening blasting, and the excavation cycle advance is 1.2 to 2 m.

Citation Information

Patent Citations

  • Single-hole double-layer overlapping tunnel structure and construction method thereof

    CN101067374A

  • Excavating method for jump-digging of double-side wall guide pit combined arch part of tunnel

    CN102182466A