A method of delineating ore bodies
By combining fan-shaped boreholes with guiding instruments, the projections of the ore-bearing and ore-exit points in the boreholes were adjusted, solving the mining difficulties caused by borehole deviation. This enabled accurate delineation of the ore body and an economically reasonable mining layout, improving the recovery rate and reducing costs.
Patent Information
- Application Number
- CN202311529775.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-16
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-11-16
AI Technical Summary
When the existing technology results in a large deviation in the borehole location, the ore-bearing point and the ore-extraction point deviate from the actual ore body location, leading to difficulties in mining engineering, difficulty in economically and rationally recovering the ore body, and poor management of ore loss and dilution.
By adopting a fan-shaped borehole layout, combined with guiding instruments and unidirectional mining equipment, the projection of the ore-bearing point and the ore-exit point of the borehole are adjusted by measuring the vertical distance. The data is processed and corrected using a reference distance (such as 1/2 of the width of the mining area) to form an accurate borehole columnar section and profile.
It improved the accuracy of ore body delineation, reduced the workload of mining and cutting operations, increased the recovery rate, reduced the dilution rate, lowered mining costs, and enhanced economic benefits.
Smart Images

Figure CN117474995B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of ore body delineation technology, and more particularly to a method for delineating ore bodies. Background Technology
[0002] The mine conducts general and detailed surveys, using boreholes to delineate the ore body: 1. Lay out exploration lines perpendicular to the overall strike of the ore body; 2. Arrange boreholes on each exploration line; 3. After drilling, compile borehole columnar sections; 4. Based on the measured results of the boreholes (three-dimensional coordinates, azimuth, dip angle, and borehole depth), reflect the boreholes on cross-sectional and plan views; 5. Then reflect the ore-bearing conditions from the borehole columnar sections on the cross-sectional and plan views; 6. Delineate the ore body based on the entry and exit points of each borehole on the cross-sectional view; 7. Submit the mining plan design.
[0003] The drawbacks of this method of delineating ore bodies are as follows: Taking a 12m wide stope with vertical ore body layout as an example, when the borehole location is basically on the exploration line or the deviation is small (<6m), the ore-bearing points and ore-producing points of the borehole are basically accurate, and the ore body delineated based on the ore-bearing points and ore-producing points is also relatively objective. However, when the borehole is deep and the ore-bearing points and ore-producing points deviate significantly from the line (>6m), then the ore body on the profile delineated based on the ore-bearing points and ore-producing points (whether directly used or vertically projected) will have a large displacement from the actual location of the ore body. This brings considerable difficulties to mining technicians in planning mining operations, is not conducive to the economical and rational recovery of the ore body, and is also not conducive to the management of ore loss and dilution. Summary of the Invention
[0004] To address the aforementioned problems, this invention provides a method for delineating ore bodies. This method overcomes the problem of human displacement, reduces the difficulties for mining technicians in planning mining operations, and enables the economical and rational recovery of ore bodies.
[0005] To solve the above problems, the technical solution adopted by the present invention is as follows: A method for delineating ore bodies includes the following steps: Step 1: Layout exploration line B according to the strike perpendicular to the ore body, and arrange fan-shaped boreholes on exploration line B to form a complete borehole columnar section; Step 2: Geological technicians reflect the data of the borehole columnar section onto the exploration line profile based on the inclination survey data, and at the same time form a small planar section below the profile. Then, based on the elevation of the ore-bearing points and ore-extracting points of the boreholes, reflect them onto the small planar section, and measure the vertical distance of the ore-bearing points and ore-extracting points from the exploration line.
[0006] If the vertical distance is greater than the reference distance, the data on the ore-bearing and ore-producing points of the borehole can only be used as a reference and cannot be directly projected onto the profile. It needs to be processed before being reflected on the profile. If the vertical distance is less than the reference distance, the data on the ore-bearing and ore-producing points of the borehole can be used without processing. It can be projected onto the profile or directly used to form an exploration line profile.
[0007] The above scheme allows for adaptation to the width of the mining area based on the vertical ore body, making the ore body delineation more consistent with the actual profile state. It also reduces the layout of mining and cutting operations, lowers the workload of workers in the early stages of mining and cutting, and makes the overall mining layout more reasonable. This is conducive to improving the recovery rate, reducing the dilution rate, lowering the mining-cutting ratio, reducing mining costs, and improving profitability.
[0008] Preferably, in step one, boreholes are drilled on the surface of exploration line B. After the drilling is completed, surveying technicians re-measure the three-dimensional coordinates of the borehole openings. Geological technicians then compile a complete borehole columnar section based on the borehole core logging results and the re-measurement results from the surveying technicians.
[0009] The above method enables the re-measurement of the three-dimensional coordinates of the borehole opening, ensuring the accuracy of the three-dimensional coordinates of the borehole opening, the borehole core logging results, and related data, thus ensuring the accuracy of the formed borehole columnar section and contributing to the accuracy of the overall ore delineation results of the mining area.
[0010] Preferably, the aforementioned reference distance is selected as 1 / 2 of the width of the stope arranged vertically to the ore body. Selecting the reference distance as 1 / 2 of the width of the stope arranged vertically to the ore body makes the ore body delineation more consistent with the actual profile state, while reducing the layout of mining and cutting projects, reducing the workload of workers in the early stages of mining and cutting projects, and making the overall mining layout more reasonable.
[0011] Preferably, after the B exploration line profile is completed, boreholes with ore-seeking points and ore-producing points that are at a vertical distance greater than the reference distance from the exploration line are represented by dashed lines on the B exploration line profile. Dashed lines can accurately and intuitively distinguish the relevant data obtained at different vertical distances, which is convenient for delineating the ore body after the overall data is marked, thus improving the overall efficiency of delineation.
[0012] Preferably, a guiding instrument is used to guide the drilling direction during the drilling process, and a unidirectional mining device is used to sample the ore body. Using a unidirectional mining device to sample the ore body can prevent the ore from overflowing or blocking during transportation, which could lead to reduced production or transportation interruption, especially for ore bodies with large spans. This ensures the accuracy of drilling and improves the efficiency of sampling.
[0013] Preferably, exploration line A is formed on the first side of exploration line B according to the methods in steps one and two, and exploration line C is formed on the second side of exploration line B. Exploration line B is corrected by exploration line A and exploration line C. By setting exploration lines A and C on both sides of exploration line B to correct the results, the accuracy of the overall results can be further guaranteed, and the delineation of the ore body can be made more consistent with the actual state.
[0014] Preferably, based on the level of the ore-bearing points in the boreholes, temporary planes for the ore-bearing points of exploration lines A and C are cut. Then, the positions of the ore-bearing points of the boreholes on the small plane of exploration line B are reflected on the temporary plane. The ore body boundary points of exploration lines A, B, and C are connected by a smooth curve. Finally, the intersection of exploration line B and the ore body boundary on the temporary plane is reflected on exploration line B. The ore body boundary is corrected in this way.
[0015] The beneficial effects of this invention are as follows: 1. In the cross-section, the delineation of the ore body is made to better reflect its actual state; 2. It facilitates the layout of mining and cutting projects, making the layout more rational; 3. It helps to improve the recovery rate and reduce the dilution rate; 4. It helps to reduce the cutting-to-mining ratio, lower mining costs, and improve profitability. Attached Figure Description
[0016] Figure 1 This is a flowchart of the method of the present invention. Detailed Implementation
[0017] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0018] See attached document Figure 1 A method for delineating ore bodies, taking a stope with a width of 12m perpendicular to the ore body as an example, is carried out according to the following steps: 1. After drilling is completed, surveying technicians re-measure the three-dimensional coordinates of the borehole opening. During drilling, a guiding instrument is used to guide the drilling direction, and a unidirectional mining device is used to sample the ore body. The guiding instrument can guide the drilling direction to ensure the accuracy of the drilling direction and the accuracy of subsequent data. At the same time, the use of a unidirectional mining device to sample the ore body can prevent ore from overflowing or blocking during transportation, which could lead to reduced production or transportation interruption, especially for ore bodies with large spans. This ensures the accuracy of ore encounter during drilling and improves the efficiency of sampling.
[0019] 2. The surveying personnel shall conduct inclination surveys on the borehole in accordance with the specifications.
[0020] 3. Geological technicians, based on the borehole core logging results and the re-measurement results of surveying technicians, will compile a complete borehole columnar section.
[0021] 4. Geological technicians will reflect the data from the borehole columnar section onto the exploration line profile based on the inclination data. At the same time, a small plan view will be formed below the profile. Then, based on the elevation of the ore-bearing points and ore-producing points in the borehole, they will be reflected onto the small plan view, and the vertical distance of the ore-bearing points and ore-producing points from the exploration line will be measured.
[0022] 5. If the vertical distance is less than 6m, the data on the ore-bearing points and ore-producing points of the borehole can be used without processing. They can be projected onto the profile or used directly on the map.
[0023] 6. If the vertical distance is greater than 6m, the data on ore-bearing and mineral-producing points from that borehole can only be used as a reference and cannot be directly projected onto the profile. It needs to be processed before being reflected on the profile. Specific processing method: For borehole data with a vertical distance less than 6m, project it onto the profile or use it directly to form an exploration line profile. The same method is used to create two adjacent profiles (exploration line A and exploration line C). Based on the level of the ore-bearing points in the boreholes, temporary planes for the ore-bearing points of the two exploration lines (exploration line A and exploration line C) are cut. Then, the locations of the ore-bearing points of the boreholes (the boreholes of exploration line B) on the small plane are reflected on the temporary plane. The ore body boundary points of the three profiles are connected by a smooth curve. Then, the intersection of exploration line B and the ore body boundary on the temporary plane is reflected on exploration line B. By correcting the ore body boundary in this way, the ore body can be delineated more accurately.
[0024] 7. After the B exploration line profile is completed, boreholes with a vertical distance of more than 6m from the exploration line where mineralization occurs or where mineralization occurs will be represented by dashed lines when reflected on the B exploration line profile.
[0025] Key points of this invention; 1. The borehole survey data must be accurate.
[0026] 2. The original logging data for boreholes must be accurate.
[0027] 3. The vertical distance is set at 6m (1 / 2 of the width of the mining area arranged vertically to the ore body).
[0028] 4. Geological technicians should have a high sense of responsibility.
[0029] Effects of the present invention; 1. In the cross-section, the delineation of the ore body is made to better reflect its actual state; 2. It facilitates the layout of mining and cutting projects, making the layout more rational; 3. It helps to improve the recovery rate and reduce the dilution rate; 4. It helps to reduce the cutting-to-mining ratio, lower mining costs, and improve profitability.
[0030] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A method for delineating ore bodies, characterized in that, Includes the following steps: Step 1: Lay out exploration line B according to the vertical strike of the ore body, and arrange fan-shaped boreholes on exploration line B to form a complete borehole columnar section. Step 2: Geological technicians reflect the data from the borehole columnar section onto the exploration line profile based on the inclination data. At the same time, a small plan view is formed below the profile. Then, based on the elevation of the ore-bearing and ore-producing points in the borehole, they are reflected onto the small plan view, and the vertical distance of the ore-bearing and ore-producing points from the exploration line is measured. If the vertical distance is greater than the reference distance, the data on the ore-bearing and ore-producing points of the borehole can only be used as a reference and cannot be directly projected onto the profile for use. It needs to be processed before being reflected on the profile. If the vertical distance is less than the reference distance, the data of the ore-bearing points and ore-producing points of the borehole do not need to be processed. They can be projected onto the profile or directly used to form an exploration line profile. In step one, boreholes were drilled on the surface of exploration line B. After the drilling was completed, surveying technicians remeasured the three-dimensional coordinates of the borehole openings. Geological technicians then compiled a complete borehole columnar section based on the borehole core logging results and the remeasurement results from the surveying technicians. Following the methods in steps one and two, exploration line A is formed on the first side of exploration line B, and exploration line C is formed on the second side of exploration line B. Exploration line B is then corrected using exploration line A and exploration line C. The aforementioned reference distance is selected as 1 / 2 of the width of the stope arranged vertically to the ore body.
2. The method for delineating ore bodies according to claim 1, characterized in that, After the B exploration line profile is completed, boreholes with ore-seeking points and ore-producing points that are at a vertical distance greater than the reference distance from the exploration line are represented by dashed lines on the B exploration line profile.
3. The method for delineating ore bodies according to claim 1, characterized in that, During the drilling process, a guiding instrument is used to guide the drilling direction, and a unidirectional mining device is used to sample the ore body.
4. The method for delineating an ore body according to claim 1, characterized in that, Based on the level of the ore-bearing points in the boreholes, temporary planes of the ore-bearing points in the A and C exploration lines are cut. Then, the locations of the ore-bearing points in the small plane of the B exploration line are reflected on the temporary plane. The ore body boundary points of the A, B, and C exploration lines are connected by a smooth curve. Finally, the intersection of the B exploration line and the ore body boundary on the temporary plane is reflected on the B exploration line profile. The ore body boundary is corrected in this way.
Citation Information
Patent Citations
Method for delineating ore body
CN113338935A