Pipe curtain method comprehensive pipe gallery construction method
By reinforcing and dividing the irregular end areas and setting up support structures in the pipe jacking construction, the problem of non-vertical ends in the pipe jacking tunnel construction was solved, thus improving the construction quality and speed of the integrated utility tunnel.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- TWENTY METALLURGICAL GRP (SHENZHEN) CONSTR DEV CO LTD
- Filing Date
- 2023-11-30
- Publication Date
- 2026-07-21
AI Technical Summary
When constructing integrated utility tunnels using the pipe jacking method, it is impossible to guarantee construction quality when the end of the tunnel is not perpendicular to the working shaft.
The irregular end is placed on one side of the receiving well, the area of the irregular end is reinforced, and the pipe gallery is divided into three chambers. The pipe curtain is constructed from the launching well to the receiving well. High-pressure jet grouting piles are used to reinforce the area above the center line. Support structures are set up, including the first, second and third steel frames. The gradually inclined second steel frame is connected to the third steel frame to ensure that each chamber is constructed through.
Even if the irregular end is not perpendicular to the pipe gallery channel, the construction quality can be guaranteed, and the construction speed and ease of operation can be improved.