上下保通条件下跨既有高速桥梁拆除施工工法

By employing construction methods such as erecting protective scaffolding, traffic diversion, and mechanical segmented demolition during the demolition of existing highway bridges, the interference and environmental impact of road closure blasting and mechanical demolition on the operation of existing highways were resolved. This approach achieved safe and efficient bridge demolition and is suitable for projects with urgent expansion and renovation needs but challenging organizational structures for maintaining traffic flow.

CN117513193BActive Publication Date: 2026-07-17CHINA RAILWAY 23RD BUREAU GRP 4TH ENG CO LTD

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
CHINA RAILWAY 23RD BUREAU GRP 4TH ENG CO LTD
Filing Date
2023-11-22
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

Existing road closure blasting and mechanical demolition methods have problems such as significant disruption to the operation of existing highways, long periods of road closure for overpasses, and significant impact on the surrounding environment when demolishing existing highway bridges.

Method used

The construction method for demolishing existing highway bridges under the condition of maintaining traffic flow on both sides is adopted, including the erection of protective scaffolding, traffic diversion and mechanical demolition, to ensure the safe operation of the existing highway and the overpass during the bridge demolition process. A traffic diversion method of half-width closure and half-width traffic is adopted, and mechanical equipment is used to demolish the bridge in sections.

Benefits of technology

The bridge was demolished safely and efficiently without affecting the normal operation of existing highways and overpasses, reducing construction safety risks and environmental impact, shortening construction time, reducing negative public opinion, improving construction efficiency and reducing costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117513193B_ABST
    Figure CN117513193B_ABST
Patent Text Reader

Abstract

本发明公开了上下保通条件下跨既有高速桥梁拆除施工工法,其包括:步骤1、准备工作,预先确定进场人员数量、进场材料和进场机械拆除设备数量;步骤2、防护棚架搭设,于跨既有高速桥梁桥位投影区域内安装防护棚架;步骤3、交通导改,对跨既有高速桥梁桥采取“半幅封闭施工,半幅双向通行”的方式进行交通疏导;步骤4、桥梁拆除,利用机械拆除设备对桥梁进行分段拆除;上下保通条件下跨既有高速桥梁拆除施工工法具有保障交叉道路通行、低风险性、可靠性、可推广性等特点,特别适用于尤其对扩容提升改造需求迫切、但保通施工组织难度较大的既有高速改造施工,在后期项目承揽市场空间中优势巨大。