Construction method of an arc-shaped roof decoration
By using Revit software and BIM-assisted layout robots, the problems of low construction efficiency and poor structural stability of ultra-long and irregular ceiling decoration were solved, achieving efficient and safe decoration construction results.
Patent Information
- Application Number
- CN202311853640.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-12-29
AI Technical Summary
Existing technologies for decorating ultra-long, irregular ceilings have low construction efficiency, make it difficult to guarantee the decorative effect, and result in poor structural connection and fixation to the building, posing safety hazards.
A 3D BIM model was created using Revit software. The BIM software was then used for detailed design and layout output. A BIM layout robot was used to generate layout points. The ceiling structure frame was erected, and the ceiling metal panels and floor tiles were installed to ensure construction accuracy and structural stability.
A unified standard construction method was implemented, which improved the ease of operation and construction efficiency, ensured the stability and safety of the decorative effect, and reduced the later maintenance cost.
Smart Images

Figure CN117552569B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of decoration engineering construction technology, specifically a construction method for arched ceiling decoration. Background Technology
[0002] Extra-long, irregularly shaped ceiling decorations are widely used in many projects such as shopping malls and public buildings due to their high visual appeal.
[0003] Currently, there is no unified construction method for this type of extra-long, irregular ceiling decoration. Due to the complexity of its structure, it can only be operated by construction workers based on experience, resulting in low construction efficiency and difficulty in guaranteeing the decorative effect. Moreover, its overall structure is poorly connected and fixed to the building, lacking stability and easily causing safety hazards. Summary of the Invention
[0004] The purpose of this invention is to provide a construction method for curved ceiling decoration to solve the problems mentioned in the background art.
[0005] To achieve the above objectives, the present invention provides the following technical solution:
[0006] A construction method for a curved ceiling decoration includes the following steps:
[0007] S1. Create a 3D model:
[0008] Based on the construction drawings, a 3D BIM model of the extra-long, irregular curved floor tiles and ceiling decoration project was created using Revit software. The curved floor tiles and ceiling decoration complement each other, and multiple light fixtures are parallel to the curved lines.
[0009] S2, Output layout diagram:
[0010] The curved floor tiles and ceiling decoration project were further refined using BIM software. The floor tiles and ceiling metal panels were numbered one by one, and the refined design layout was output.
[0011] S3. Material Production and Manufacturing:
[0012] The output detailed design layout drawings are handed over to professional manufacturers for factory production of floor tiles and ceiling metal panels. The detailed design drawings are reviewed and marked with a unique number to facilitate on-site construction. During the production process, leftover tiles are reused as much as possible.
[0013] When encountering special areas including ceiling lights, junction boxes, and floor evacuation indicator lights, use a tile cutting tool to cut and chamfer them.
[0014] S4. Ceiling installation:
[0015] First, set up a full-span scaffold and lay out the ceiling elevation line and keel dividing line; then, based on the position of the curved lines on the ceiling, use a BIM layout robot to radiate laser points every 1200mm, and install the keel hangers for the curved lines at the points. After determining the position of the curved lines, install the remaining keel hangers along the lines to both sides; then install the main keel and secondary keel in sequence; finally, install the ceiling metal panels.
[0016] S5. Lighting Fixture Installation:
[0017] During ceiling construction, large light fixture brackets are installed using laser points automatically generated by a BIM layout robot according to the design locations in the drawings. After the light fixture brackets and ceiling construction are completed, holes are drilled in the ceiling metal panels according to the size of the light fixtures, and the light fixtures are installed.
[0018] S6. Laying floor tiles:
[0019] After the scaffolding is removed, the ground base is cleaned. Then, the laser points automatically generated by the BIM layout robot are used to assist in the construction of the floor tile laying project. The floor tile laying should be carried out strictly in accordance with the numbering of the detailed drawings to ensure that the lines at both ends of each splicing module are consistent with the positions of the adjacent modules.
[0020] S7. Acceptance:
[0021] After the installation of the ceiling metal panels, lighting fixtures, and floor tiles is completed, an acceptance inspection is organized. During the inspection, a BIM layout robot is used to verify the lines of the ceiling and floor tiles and the positions of the lighting fixtures. Once it is confirmed that there are no errors, the inspection is passed.
[0022] Preferably, in step S4, the upper end of the keel hanger is installed on the concrete roof slab of the building. The main keel is installed horizontally or vertically below the concrete roof slab and parallel to the concrete roof slab. One or both ends of the main keel are fixed to the concrete beams of the building. Secondary keels are installed on both sides of the connection between the main keel and the concrete beams. The two ends of the secondary keels are respectively inclined and fixed at the connection between the two main keels and the concrete beams, or one end of the secondary keel is inclined and fixed at the connection between the two main keels and the concrete beams, and the other end is fixed to the main keel. The main keel and the secondary keel are both made of square tubing and are installed in the same plane. The lower end of the keel hanger is vertically fixed to the main keel or the secondary keel. The ceiling metal panel is installed on the lower side of the main keel and the secondary keel by screws.
[0023] Preferably, L-shaped hanger fixing plates are installed on both sides or all four sides of the top of the keel hanger. The horizontal plate of the L-shaped hanger fixing plate is fixed to the concrete top slab through an internal expansion tube. A hanger fixing bolt is provided between the vertical plates of two oppositely arranged L-shaped hanger fixing plates. The hanger fixing bolt passes through the keel hanger and fixes the two L-shaped hanger fixing plates and the keel hanger together.
[0024] Preferably, the end of the main keel is fixed to the side face of the concrete beam by expansion bolts, angle steel, and I-beams. At least two expansion bolts are provided, with their front ends installed inside the concrete beam. Two angle steels are provided, arranged back-to-back and respectively fitted onto the two expansion bolts and fixed with nuts. The I-beam is placed horizontally outside the two angle steels, and the vertical plate of the I-beam is provided with two horizontal bolt holes. The rear ends of the two expansion bolts are respectively opened through the two horizontal bolt holes of the I-beam, and the rear ends of the expansion bolts on the outside of the I-beam are fixed with nuts, so that the outer end of the angle steel is pressed against the inner wall of the vertical plate of the I-beam. The main keel is fitted onto the outside of the I-beam and fixed to the I-beam, angle steel, and concrete beam by bolts or screws.
[0025] Preferably, the two horizontal plates of the I-beam and the main keel are fixed by I-beam fastening bolts, and the connection between the outer wall of the front end of the main keel and the angle steel or concrete beam is fixed by L-shaped fixing plates and screws.
[0026] Preferably, the two I-beam fastening bolts are arranged symmetrically in opposite directions, the nuts and end caps of the I-beam fastening bolts are respectively located on the outside and inside of the main keel, and a spring is provided between the end caps of the two I-beam fastening bolts.
[0027] Preferably, one end of each of the two secondary keels is installed obliquely and symmetrically on the outer walls of both sides of the main keel, and an outer folding connecting plate and an inner folding connecting plate are respectively installed on the front and rear sides of the connection between the secondary keel and the main keel and are fixed with bolts.
[0028] Preferably, a sleeve is installed between the backrests of the two angle steels, the outer wall of the sleeve is pressed against the backrests of the angle steels, and a rigid bolt is installed at the front end of the two outward folding connecting plates. The rigid bolt is located inside the sleeve, and its two ends pass through the two side walls of the main keel and the two outward folding connecting plates respectively and are fixed by nuts. The rear end of the outward folding connecting plate is fixed to the secondary keel by an outward folding plate bolt. One end of the inner folding connecting plate is fixed to the secondary keel by an inner folding plate bolt, and the other end is fixed to the side wall of the main keel by an inner folding plate bolt.
[0029] Preferably, the end caps of the outer folding plate bolt and the inner folding plate bolt are both installed inside the secondary keel, and the nuts of the outer folding plate bolt and the inner folding plate bolt are both installed outside the side wall of the secondary keel. A Z-shaped plate is provided inside the front end of the secondary keel, and the end caps of the outer folding plate bolt and the inner folding plate bolt are respectively installed on the two horizontal plates of the Z-shaped plate by springs.
[0030] Preferably, the end caps and nuts of the inner folding plate bolts are respectively located inside the main keel and outside the side wall. A spring is provided inside the main keel, and the two ends of the spring are respectively fixed to the end caps of the inner folding plate bolts of the two inner folding connecting plates.
[0031] The beneficial effects of this invention are as follows:
[0032] This invention relates to a construction method for curved ceiling decoration. It involves creating a 3D BIM model of an ultra-long, irregular curved floor tile and ceiling decoration project using Revit software, outputting a detailed design layout drawing, and then automatically generating a list of layout points and laser points using a BIM layout robot. The method then proceeds to install the ceiling structure frame, install the ceiling metal panels, lighting fixtures, and lay the floor tiles, completing the entire decorative construction process for the irregular curved ceiling. The method is simple, standardized, easy to operate, highly feasible, structurally robust, safe and reliable, with high overall construction efficiency, good post-construction effect, durability, and low maintenance costs. Attached Figure Description
[0033] Figure 1 : Construction flowchart of this invention;
[0034] Figure 2 : A schematic diagram of the structure of the suspended ceiling decoration constructed by the method of the present invention;
[0035] Figure 3 : Figure 2 Enlarged view of the structure at point A in the middle;
[0036] Figure 4 : A front view of the connection between the main keel and the concrete beam of the suspended ceiling decoration constructed by the method of the present invention;
[0037] Figure 5 : An internal structural view of the connection between the main keel and the concrete beam of the suspended ceiling decoration constructed by the method of the present invention;
[0038] Figure 6 : A top view of the connection between the main keel and the concrete beam of the suspended ceiling decoration constructed by the method of the present invention. Detailed Implementation
[0039] Combined with appendix Figure 1-6 The specific embodiments of the present invention are described below:
[0040] Example 1:
[0041] like Figure 1 As shown, a construction method for an arched ceiling decoration includes the following steps:
[0042] S1. Create a 3D model:
[0043] Based on the construction drawings, a 3D BIM model of the extra-long, irregular curved floor tiles and ceiling decoration project was created using Revit software. The curved floor tiles and ceiling decoration complement each other, and multiple light fixtures are parallel to the curved lines.
[0044] S2, Output layout diagram:
[0045] The curved floor tiles and ceiling decoration project were further refined using BIM software. The floor tiles and ceiling metal panels were numbered one by one, and the refined design layout was output.
[0046] S3. Material Production and Manufacturing:
[0047] The detailed design layout drawings are handed over to professional manufacturers for factory production of floor tiles and ceiling metal panels. The detailed design drawings are reviewed and marked with unique numbers to facilitate on-site construction. During the production process, leftover tiles are reused as much as possible. When encountering special parts, such as ceiling lights, junction boxes, and floor evacuation indicator lights, tile cutting tools are used for cutting and chamfering.
[0048] S4. Ceiling installation:
[0049] First, set up a full-span scaffold and lay out the ceiling elevation line and keel dividing line; then, according to the position of the curved lines on the ceiling, use a BIM layout robot to radiate laser points every 1200mm, and install the keel hanger 1 of the curved lines at the points. After determining the position of the curved lines, install the remaining keel hangers 1 along the lines to both sides; then install the main keel 2 and secondary keel 3 in sequence; finally, install the ceiling metal panel 4.
[0050] S5. Lighting Fixture Installation:
[0051] During ceiling construction, large light fixture brackets are installed using laser points automatically generated by a BIM layout robot according to the design locations on the drawings. After the light fixture brackets and ceiling construction are completed, holes are drilled in the ceiling metal panels according to the size of the light fixtures, and the light fixtures are installed.
[0052] S6. Laying floor tiles:
[0053] After the scaffolding is dismantled, the ground base is cleaned. Then, laser points automatically generated by the BIM layout robot are used to assist in the construction of the floor tile laying project. The floor tile laying should be carried out strictly in accordance with the detailed drawing number to ensure that the lines at both ends of each splicing module are consistent with the positions of the adjacent modules.
[0054] S7. Acceptance:
[0055] After the installation of the ceiling metal panels, lighting fixtures, and floor tiles is completed, an acceptance inspection will be organized. During the inspection, a BIM layout robot will be used to verify the lines of the ceiling and floor tiles and the positions of the lighting fixtures. Once it is confirmed that there are no errors, the inspection will be passed.
[0056] Example 2:
[0057] like Figure 1 As shown, a construction method for an arched ceiling decoration includes the following steps:
[0058] S1. Create a 3D model:
[0059] Based on the construction drawings, a 3D BIM model of the ultra-long, irregular curved floor tiles and ceiling decoration project was created using Revit software. The length of the curved lines exceeds 120m, and the curved floor tiles and ceiling decoration complement each other, with multiple light fixtures parallel to the curved lines.
[0060] S2, Output layout diagram:
[0061] The curved floor tiles and ceiling decoration project were further refined using BIM software. The floor tiles and ceiling metal panels were numbered one by one, and the refined design layout was output.
[0062] The area where the lines intersect, consisting of two different colors—gray wood grain and white—is treated as an independent module and numbered accordingly.
[0063] S3. Material Production and Manufacturing:
[0064] The detailed design layout drawings are handed over to professional manufacturers for factory production of floor tiles and ceiling metal panels. The drawings are then reviewed and marked with unique numbers to facilitate on-site construction. During the production process, leftover tiles are reused as much as possible.
[0065] The floor tiles, which span the lines and consist of two different colors, are glued together using a special jointing adhesive and transported to the construction site as a single module.
[0066] Before materials produced by the manufacturer arrive on site, their numbers and dimensions must be inspected and verified before they can be used for construction.
[0067] In particular, it is necessary to confirm whether the side lengths of the two different colored tiles at the intersection of lines and the tile modules formed by splicing are consistent with the detailed design drawings. This will directly determine the straightness of the lines after the ordinary tiles are completed.
[0068] When encountering special areas including ceiling lights, junction boxes, and floor evacuation indicator lights, use a tile cutting tool to cut and bevel the edges.
[0069] S4. Ceiling installation:
[0070] First, set up a full-span scaffold and lay out the ceiling elevation line and keel dividing line; then, according to the position of the curved lines on the ceiling, use a BIM layout robot to radiate laser points every 1200mm, and install the keel hanger 1 of the curved lines at the points. After determining the position of the curved lines, install the remaining keel hangers 1 along the lines to both sides; then install the main keel 2 and secondary keel 3 in sequence; finally, install the ceiling metal panel 4.
[0071] Before the ceiling construction, a special construction plan is prepared and approved by experts. Then, a full-span scaffold is erected, and the ceiling elevation line and keel dividing line are laid out.
[0072] Based on the location of the curved lines on the ceiling, a BIM layout robot is used to project laser points every 1200mm, and the keel hanger 1 for the curved lines is installed at each point. After determining the location of the curved lines, the remaining keel hangers 1 are installed along the lines to both sides, with a spacing of ≤1200mm between the keel hangers 1. Then, the main keel 2, secondary keel 3 are installed in sequence, and finally, the ceiling metal panels 4 are installed.
[0073] According to the detailed design drawings, the installation of the ceiling metal panel 4 is carried out by first installing the large metal panel to reduce the cutting of the metal panel and ensure the integrity of the metal panel; when it is installed on both sides of the curved line, it is then installed symmetrically in sequence according to the detailed drawings.
[0074] S5. Lighting Fixture Installation:
[0075] Before installation, the wiring inside the ceiling should be completed and the wires should be threaded through the conduits for light fixtures that are parallel to the curved lines.
[0076] During ceiling construction, large light fixture brackets are installed using laser points automatically generated by a BIM layout robot according to the design locations on the drawings. After the light fixture brackets and ceiling construction are completed, holes are drilled in the ceiling metal panels according to the size of the light fixtures, and the light fixtures are installed.
[0077] After the lighting fixtures are installed, a BIM-based layout robot is used to verify their positions, ensuring that the fixtures are parallel to the curved lines. After the lighting system construction is completed, a 24-hour power-on test run is conducted to ensure there are no faults during the continuous test run.
[0078] S6. Laying floor tiles:
[0079] Floor tiles should be laid only after the scaffolding has been removed, the floor base has been cleaned, and any areas of the base that do not meet the requirements have been leveled and reinforced.
[0080] First, determine the construction elevation position based on the elevation benchmark. Then, according to the detailed design drawings, draw a cross line at the midpoint of the space. The layout of the floor tiles should be the same as the cross line.
[0081] Before formal construction, trial assembly and arrangement were carried out according to the detailed design drawings. The components were numbered according to their positions and then neatly stacked according to the numbers.
[0082] To ensure accurate positioning and elevation control, floor tiles are typically laid sequentially from one layer to another. During laying, laser points automatically generated by a BIM-based layout robot are used to assist in construction. A final check is performed when approaching irregular curved lines.
[0083] When constructing tile modules that span curved lines and are assembled from various pieces, the modules should be laid as a single unit. Laying should strictly follow the detailed drawing numbers, ensuring that the lines at both ends of each tile module are aligned with the adjacent modules.
[0084] S7. Acceptance:
[0085] After the installation of the ceiling metal panels, lighting fixtures, and floor tiles is completed, an acceptance inspection will be organized. During the inspection, a BIM layout robot will be used to verify the lines of the ceiling and floor tiles and the positions of the lighting fixtures. Once it is confirmed that there are no errors, the inspection will be passed.
[0086] like Figure 2 As shown, in step S4, the upper end of the keel hanger 1 is installed on the concrete roof slab 100 of the building. The main keel 2 is installed horizontally or vertically below the concrete roof slab 100 and parallel to the concrete roof slab 100. Since the edge of the ceiling is curved and not fully covered at the top, the main keel 2 may only be fixed at one end to the concrete beam 200 of the building during installation. However, in its design process, it is necessary to fix both ends to the concrete beam 200 of the building as much as possible to increase the stability of the entire structure.
[0087] Secondary keels 3 are installed on both sides of the connection between the main keel 2 and the concrete beam 200. Specifically, the two ends of the secondary keel 3 are inclined and horizontally fixed to the connection between the two main keels 2 and the concrete beam 200, or one end of the secondary keel 3 is inclined and fixed to the connection between the two main keels 2 and the concrete beam 200, and the other end is fixed to the main keel 2 by bolts or direct welding. The main keel 2 and secondary keels 3 are installed in the same plane. The lower end of the keel hanger 1 is vertically fixed to the main keel 2 or the secondary keel 3. The ceiling metal panel 4 is installed on the lower side of the main keel 2 and the secondary keel 3 by screws.
[0088] The main keel 2 and secondary keel 3 are made of square tubes of different specifications, which play a load-bearing role in the entire ceiling decoration. At the same time, as needed, several auxiliary support rods can be selectively welded between the main keel 2, the secondary keel 3, and the main keel 2 and secondary keel 3, thus forming the support system of the entire ceiling decoration structure.
[0089] like Figure 2 , 3As shown, L-shaped hanger fixing plates 11 are installed on both sides or all four sides of the top of the keel hanger 1. The horizontal plate of the L-shaped hanger fixing plate 11 is fixed to the concrete top slab 100 through the internal expansion tube 12. A hanger fixing bolt 13 is provided between the vertical plates of the two oppositely arranged L-shaped hanger fixing plates 11. The hanger fixing bolt 13 passes through the keel hanger 1 and fixes the two L-shaped hanger fixing plates 11 and the keel hanger 1 together.
[0090] like Figure 2-6 As shown, the end of the main keel 2 is fixed to the side end face of the concrete beam 200 by expansion bolts 21, angle steel 22, and I-beam 23. There are at least two expansion bolts 21, the front ends of which are installed inside the concrete beam 200. There are two angle steels 22 arranged back to back and side by side, which are respectively fitted onto the two expansion bolts 21 and fixed by nuts. The I-beam 23 is placed horizontally outside the two angle steels 22, and there are two horizontal bolt holes on the vertical plate of the I-beam 23. The rear ends of the two expansion bolts 21 are respectively opened through the two horizontal bolt holes of the I-beam 23, and the rear ends of the expansion bolts 21 on the outside of the I-beam 23 are fixed by nuts, and the outer ends of the angle steel 22 are pressed against the inner wall of the vertical plate of the I-beam 23. The main keel 2 is fitted onto the outside of the I-beam 23 and is fixed to the I-beam 23, angle steel 22 and concrete beam 200 by bolts or screws. The two angle steels 22 and the I-beam 23 are fixed together by expansion bolts 21 and form the support structure at the end of the main keel 2.
[0091] The two horizontal plates of the I-beam 23 are fixed to the main keel 2 by I-beam fastening bolts 25. The connection between the outer wall of the front end of the main keel 2 and the angle steel 22 or the concrete beam 200 is fixed by L-shaped fixing plates 26 and screws. The two I-beam fastening bolts 25 are arranged symmetrically in opposite directions. The nuts and end caps of the I-beam fastening bolts 25 are respectively located on the outside and inside of the main keel 2, and a spring 251 is installed between the end caps of the two I-beam fastening bolts 25.
[0092] Two secondary keels 3 are installed symmetrically on both sides of the outer wall of the main keel 2 at one end, and an outer folding connecting plate 31 and an inner folding connecting plate 32 are respectively installed on the front and rear sides of the connection between the secondary keel 3 and the main keel 2 and are fixed with bolts.
[0093] In the initial installation of the two angle steels 22 back-to-back, a sleeve 24 is pre-installed between the back panels of the two angle steels 22. The outer wall of the sleeve 24 is pressed and tightened against the back panel of the angle steel 22. Two outer folding connecting plates 31 are fitted with rigid bolts 36 at their front ends. The rigid bolts 36 are located inside the sleeve 24, and their two ends pass through the two side walls of the main keel 2 and the two outer folding connecting plates 31 respectively, and are fixed with nuts. The rear end of the outer folding connecting plate 31 is fixed to the secondary keel 3 by outer folding plate bolts 33. One end of the inner folding connecting plate 32 is fixed to the secondary keel 3 by inner folding plate bolt 1 34, and the other end is fixed to the side wall of the main keel 2 by inner folding plate bolt 2 37.
[0094] The end caps of the outer folding plate bolt 33 and the inner folding plate bolt 34 are installed inside the secondary keel 3. The nuts of the outer folding plate bolt 33 and the inner folding plate bolt 34 are installed outside the side wall of the secondary keel 3. A Z-shaped plate 35 is provided inside the front end of the secondary keel 3. The end caps of the outer folding plate bolt 33 and the inner folding plate bolt 34 are respectively installed on the two horizontal plates of the Z-shaped plate 35 through the spring 331.
[0095] The end caps and nuts of the inner folding plate bolts 2 and 37 are respectively set inside the main keel 2 and outside the side wall. The main keel 2 is equipped with springs 371, and the two ends of springs 371 are respectively fixed on the end caps of the inner folding plate bolts 2 and 37 of the two inner folding connecting plates 32.
[0096] Whether it's the Z-shaped plate 35, or springs 251, 331, or 371, their purpose is to facilitate the installation of the I-beam fastening bolts 25, outer folding plate bolts 33, inner folding plate bolts 34 or 37, and the tightening of their nuts. For example, the installation and fixing process for the I-beam fastening bolts 25 and springs 251 is as follows: First, compress the two I-beam fastening bolts 25 and springs 251 that are fixed together, and make the heads of the two I-beam fastening bolts 25 pass through the bolt holes of the two horizontal plates of the I-beam 23 respectively; then, the front end of the main keel 2 is fitted upwards from the outer end of the I-beam 23. At this time, the heads of the two I-beam fastening bolts 25 protrude from the bolt holes of the two horizontal plates of the I-beam 23, forming a barrier. The I-beam fastening bolts can be tightened by hand or other tools. Slightly press down the head of bolt 25 so that the front end of the main keel 2 passes over the head of the pressed I-beam fastening bolt 25 until the front end of the main keel 2 abuts against the angle steel 22 and the head of the pressed I-beam fastening bolt 25 is engaged in the bolt hole on the main keel 2 under the rebound action of spring 251; finally, put a nut on the exposed head of the I-beam fastening bolt 25 on the side wall of the main keel 2, tighten one end of the two I-beam fastening bolts 25 and tighten the nut at the other end, or tighten both nuts at the same time.
[0097] This invention relates to a construction method for curved ceiling decoration. It involves creating a 3D BIM model of an ultra-long, irregular curved floor tile and ceiling decoration project using Revit software, outputting a detailed design layout drawing, and then automatically generating a list of layout points and laser points using a BIM layout robot. The method then proceeds to install the ceiling structure frame, install the ceiling metal panels, lighting fixtures, and lay the floor tiles, completing the entire decorative construction process for the irregular curved ceiling. The method is simple, standardized, easy to operate, highly feasible, structurally robust, safe and reliable, with high overall construction efficiency, good post-construction effect, durability, and low maintenance costs.
[0098] The invention has been described above by way of example in conjunction with the accompanying drawings. Obviously, the specific implementation of the invention is not limited to the above-described manner. Any non-substantial improvement made by adopting the inventive concept and technical solution of the invention, or the direct application of the inventive concept and technical solution to other situations without modification, is within the protection scope of the invention.
Claims
1. A construction method for an arched ceiling decoration, characterized in that, Includes the following steps: S1. Create a 3D model: Based on the construction drawings, a 3D BIM model of the extra-long, irregular curved floor tiles and ceiling decoration project was created using Revit software. The curved floor tiles and ceiling decoration complement each other, and multiple light fixtures are parallel to the curved lines. S2, Output layout diagram: The curved floor tiles and ceiling decoration project were further refined using BIM software. The floor tiles and ceiling metal panels were numbered one by one, and the refined design layout was output. S3. Material Production and Manufacturing: The detailed design layout drawings are handed over to professional manufacturers for factory production of floor tiles and ceiling metal panels. The detailed design drawings are reviewed and marked with unique numbers to facilitate on-site construction. During the production process, leftover tiles are reused as much as possible. When encountering special areas, such as ceiling lights, junction boxes, and floor evacuation indicator lights, tile cutting tools are used for cutting and chamfering. S4. Ceiling installation: First, set up a full-span scaffold and lay out the ceiling elevation line and keel dividing line; then, according to the position of the curved lines on the ceiling, use a BIM layout robot to radiate laser points every 1200mm, and install the keel hangers (1) of the curved lines at the points. After determining the position of the curved lines, install the remaining keel hangers (1) along the lines to both sides; then install the main keel (2) and secondary keel (3) in sequence; finally, install the ceiling metal panels (4). S5. Lighting Fixture Installation: During ceiling construction, large light fixture brackets are installed using laser points automatically generated by a BIM layout robot according to the design locations in the drawings. After the light fixture brackets and ceiling construction are completed, holes are drilled in the ceiling metal panels according to the size of the light fixtures, and the light fixtures are installed. S6. Laying floor tiles: After the scaffolding is removed, the ground base is cleaned. Then, the laser points automatically generated by the BIM layout robot are used to assist in the construction of the floor tile laying project. The floor tile laying should be carried out strictly in accordance with the numbering of the detailed drawings to ensure that the lines at both ends of each splicing module are consistent with the positions of the adjacent modules. S7. Acceptance: After the construction of the ceiling metal panel (4), lighting fixtures and floor tiles is completed, an acceptance inspection is organized. During the inspection, a BIM layout robot is used to check the ceiling and floor tile lines and the position of the lighting fixtures. After confirming that there are no errors, the inspection is passed. In step S4, the upper end of the keel hanger (1) is installed on the concrete roof slab (100) of the building. The main keel (2) is installed horizontally or vertically below the concrete roof slab (100) and parallel to the concrete roof slab (100). One or both ends of the main keel (2) are fixed to the concrete beam (200) of the building. Secondary keels (3) are installed on both sides of the connection between the main keel (2) and the concrete beam (200), and the two ends of the secondary keels (3) are respectively inclined and fixed to two At the connection between the main keel (2) and the concrete beam (200), or at one end of the secondary keel (3), it is fixed at an angle to the connection between the two main keels (2) and the concrete beam (200), and at the other end is fixed to the main keel (2); the main keel (2) and the secondary keel (3) are both made of square tubes and are installed in the same plane; the lower end of the keel hanger (1) is vertically fixed to the main keel (2) or the secondary keel (3); the ceiling metal panel (4) is installed on the lower side of the main keel (2) and the secondary keel (3) by screws; The end of the main keel (2) is fixed to the side end face of the concrete beam (200) by expansion bolts (21), angle steel (22), and I-beam (23). At least two expansion bolts (21) are provided, with their front ends installed inside the concrete beam (200). Two angle steels (22) are provided and are arranged back to back, respectively fitted onto the two expansion bolts (21) and fixed by nuts. The I-beam (23) is placed horizontally outside the two angle steels (22), and the vertical of the I-beam (23) is... The plate is provided with two horizontal bolt holes, and the rear ends of the two expansion bolts (21) are respectively opened through the two horizontal bolt holes of the I-beam (23). The rear ends of the expansion bolts (21) on the outside of the I-beam (23) are fixed by nuts and the outer end of the angle steel (22) is pressed against the inner wall of the vertical plate of the I-beam (23). The main keel (2) is fitted on the outside of the I-beam (23) and is fixed to the I-beam (23), angle steel (22) and concrete beam (200) by bolts or screws. The two horizontal plates of the I-beam (23) and the main keel (2) are fixed by I-beam fastening bolts (25). The connection between the outer wall of the front end of the main keel (2) and the angle steel (22) or the concrete beam (200) is fixed by L-shaped fixing plate (26) and screws.
2. The construction method for an arc-shaped ceiling decoration according to claim 1, characterized in that, L-shaped rod fixing plates (11) are installed on both sides or all four sides of the top of the keel rod (1). The horizontal plate of the L-shaped rod fixing plate (11) is fixed to the concrete top plate (100) through the inner expansion tube (12). A rod fixing bolt (13) is provided between the vertical plates of the two L-shaped rod fixing plates (11) arranged opposite to each other. The rod fixing bolt (13) passes through the keel rod (1) and fixes the two L-shaped rod fixing plates (11) and the keel rod (1) together.
3. The construction method for an arched ceiling decoration according to claim 1, characterized in that, The two steel fastening bolts (25) are arranged in opposite symmetrical positions. The nuts and end caps of the steel fastening bolts (25) are respectively located on the outside and inside of the main keel (2), and a spring (251) is provided between the end caps of the two steel fastening bolts (25).
4. The construction method for an arc-shaped ceiling decoration according to claim 1, characterized in that, The two secondary keels (3) are installed symmetrically on both sides of the outer wall of the main keel (2) at one end, and the front and rear sides of the connection between the secondary keel (3) and the main keel (2) are respectively equipped with an outer folding connecting plate (31) and an inner folding connecting plate (32) and fixed with bolts.
5. The construction method for an arc-shaped ceiling decoration according to claim 4, characterized in that, A sleeve (24) is installed between the backrests of the two angle steels (22). The outer wall of the sleeve (24) is pressed against the backrest of the angle steel (22). A rigid bolt (36) is installed at the front end of the two outer folding connecting plates (31). The rigid bolt (36) is set inside the sleeve (24), and its two ends pass through the two side walls of the main keel (2) and the two outer folding connecting plates (31) respectively and are fixed by nuts. The rear end of the outer folding connecting plate (31) is fixed to the secondary keel (3) by the outer folding plate bolt (33). One end of the inner folding connecting plate (32) is fixed to the secondary keel (3) by the inner folding plate bolt one (34), and the other end is fixed to the side wall of the main keel (2) by the inner folding plate bolt two (37).
6. The construction method for an arched ceiling decoration according to claim 5, characterized in that, The end caps of the outer folding plate bolt (33) and the inner folding plate bolt (34) are installed inside the secondary keel (3). The nuts of the outer folding plate bolt (33) and the inner folding plate bolt (34) are installed outside the side wall of the secondary keel (3). A Z-shaped plate (35) is provided inside the front end of the secondary keel (3). The end caps of the outer folding plate bolt (33) and the inner folding plate bolt (34) are respectively installed on the two horizontal plates of the Z-shaped plate (35) by the second spring (331).
7. The construction method for an arched ceiling decoration according to claim 5, characterized in that, The end caps and nuts of the inner folding plate bolts (37) are respectively set inside the main keel (2) and outside the side wall. The main keel (2) is provided with springs (371), and the two ends of the springs (371) are respectively fixed on the end caps of the inner folding plate bolts (37) of the two inner folding connecting plates (32).