A method for processing tunnel basement loose layer grouting foundation in operation period
By employing a segmented grouting method in the loose layer of the tunnel foundation, and utilizing a combination of sealing and grouting zones, the problem of uncontrollable grout diffusion was solved, achieving efficient reinforcement and increased bearing capacity of the tunnel foundation. This method is suitable for safe construction of tunnels during operation.
Patent Information
- Application Number
- CN202311295396.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-08
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-10-08
AI Technical Summary
In existing tunnel construction processes, the grout cannot be effectively contained, causing the grout to spread freely in the soil. This makes it difficult to control the grouting range, resulting in poor reinforcement of loose soil foundations, insufficient bearing capacity, and a tendency for tunnel settlement and other defects to occur.
The grouting method is divided into a sealing zone and a filling zone. The sealing zone uses pre-drilled hole technology and fast-consolidating materials to limit the diffusion of grout. The filling zone uses a combination of low-pressure and high-pressure grouting. The distribution of grout is controlled by drilling and grouting pipes to ensure that the grout fills the trapezoidal load-bearing zone of the tunnel foundation.
It achieves full utilization and uniform distribution of grout, increases grouting density, enhances the bearing capacity of the tunnel foundation, reduces construction disturbance and secondary diseases, and is suitable for safe and efficient construction in confined spaces.
Smart Images

Figure CN117569833B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel foundation treatment technology, and in particular to a method for grouting foundation treatment of loose layers in tunnel foundations during operation. Background Technology
[0002] Loose layers refer to Quaternary and Neogene strata, composed of soil, sand, gravel, and pebble layers. Their strength is far less than that of ordinary rock strata, and they do not produce a stratification effect. Loose soil layers have poor bearing capacity and high compressibility, making them unsuitable for direct use as foundations for structures. If a loose layer in the tunnel foundation is not treated before construction, it usually leads to large tunnel settlement and is prone to cracking, deformation, displacement, and other defects. Currently, the two common methods for treating loose foundation layers are backfilling and compaction. Backfilling requires a large amount of space to stockpile excavated soil and replace it with new soil, but tunnel construction operations are limited in size and have a high risk factor, making both excavation and backfilling difficult to implement. Compaction usually requires the use of impact hammers or the placement of heavy objects, which is obviously unsuitable in the limited space of tunnel construction.
[0003] During tunnel construction, grouting is often used to reinforce the loose foundation layer. However, due to the high porosity of the loose soil layer, the grout cannot be effectively constrained. The grout diffuses freely in the soil, making it difficult to effectively control the grouting range. Consequently, the reinforcement effect of the loose foundation layer cannot be guaranteed, and insufficient bearing capacity leads to frequent foundation subsidence and other problems. Summary of the Invention
[0004] The purpose of this invention is to provide a method for treating loose soil layers in tunnel foundations during operation, solving the technical problem that existing grouting methods in tunnel construction cannot effectively constrain the grout, allowing it to diffuse freely in the soil and making it difficult to effectively control the grouting range. Commonly used grouting reinforcement methods result in radial grouting areas, low grout density, and minimal improvement in soil bearing capacity.
[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows:
[0006] A method for treating loose soil layers in tunnel foundations during operation involves dividing the grouting foundation into a sealing zone and a grouting and filling zone. The sealing zone is located on both sides of the grouting and filling zone. The sealing zone is first grouted by drilling, and then the grouting and filling zone is filled by grouting.
[0007] Furthermore, the sealing zone extends to the left and right sides of the grouting area. The drilling adopts pre-drilling technology. The sealing zone plays a role in restricting the diffusion of grout and improving the grouting effect. The grouting material needs to solidify quickly to block the diffusion of grout in the filling area. The grouting material is cement-water glass two-liquid grout or chemical grout.
[0008] Furthermore, the grouting and filling area is divided into a shallow low-pressure grouting area and a deep composite borehole high-pressure grouting area. The shallow low-pressure grouting area extends from the tunnel secondary lining base to 5m below the base, while the deep composite borehole high-pressure grouting area extends below the shallow low-pressure grouting area and above the bedrock or impermeable layer. The grouting material is a single-liquid grout. Through the voids in the rock blocks at the bottom of the tunnel in the grouting and filling area, the grout has fluidity, so the grout can fill the filling area.
[0009] Furthermore, the grouting range of the shallow low-pressure grouting zone is the shallow filling zone in the middle. Drilling starts from the road surface and goes downwards. The grouting material in the shallow low-pressure grouting zone is cement slurry or cement mortar, which is fluid and inexpensive. The purpose of shallow low-pressure grouting in the shallow low-pressure grouting zone is, on the one hand, to pre-reinforce the loose layer of the base, so that the re-forming holes drilled in the deep grouting will collapse and reduce the construction difficulty; on the other hand, to pre-reinforce the loose layer of the shallow layer, so as to avoid secondary diseases such as base heave or cracking caused by subsequent high-pressure grouting.
[0010] The grouting range of the deep composite hole high-pressure grouting zone is the middle deep filling zone. The grouting material can be cement grout or cement mortar, etc. The purpose of the composite hole high-pressure grouting in the deep composite hole high-pressure grouting zone is to fill the pores of the loose layer with grout and improve the quality of the grouting project.
[0011] Furthermore, when designing the borehole layout, the spacing of the central grouting holes is calculated based on the penetration radius r of the grouting material. Assuming the penetration radius is r, the grouting hole spacing is d, and the width of the overlapping area is taken as s = 2r - d (s > 0), the proportion of the overlapping area with the grouting penetration radius is k.
[0012]
[0013] k is taken as 20%. Since the cross-section of the grouting range is trapezoidal, additional grouting holes are needed on both sides of the trapezoid. Therefore, the grouting holes are arranged to be dense on both sides and sparse in the middle. The interval between the grouting holes on both sides is half of the interval between the central grouting holes, d / 2.
[0014] Furthermore, when designing the depth or height of grouting holes, the grouting depth is calculated using the bearing capacity after grouting. The bearing capacity of the foundation after grouting is calculated according to the specifications to meet the requirements. There should be an impermeable layer below the grouting holes, and the grouting holes should be drilled to the impermeable layer to prevent the grout from spreading in the vertical direction.
[0015] Furthermore, during drilling, the diameter of the grouting hole should be controlled within 2-10cm, and the grouting pipe should be a steel perforated pipe with a diameter of 2-10cm. The bottom of the grouting hole should extend 50cm beyond the loose layer of the base. When drilling the secondary lining, impact drills are not allowed; rotary drills should be used instead. If the drilling process encounters reinforcing bars, the position of the grouting hole should be moved.
[0016] Furthermore, during grouting, a skip-hole grouting method is adopted, using adjacent holes as vent holes. The grouting follows a four-order hole principle, which is to first grout single-row single-number holes as the first order, then grout double-row double-number holes as the second order, then grout single-row double-number holes as the third order, and finally grout double-row single-number holes as the fourth order.
[0017] Furthermore, during grouting, grouting is carried out in sections from bottom to top. The borehole is drilled to the designed depth in one go, and then grouting plugs are installed section by section from bottom to top for grouting. When grouting from bottom to top, if the grouting plug cannot be plugged in the predetermined position, the position plug is moved up or down until a position that can be plugged is found. When the length of the grouting section is greater than 10m, remedial measures are taken. The remedial measures are to set up inspection holes on the side to check the impact data and to carry out supplementary grouting at the same time.
[0018] Furthermore, the construction process is as follows:
[0019] Step 1: Before construction, conduct indoor grout mix proportion tests and in-situ construction process tests, and determine the parameters of grouting pressure, water-cement ratio, and grout mix proportion based on the test results;
[0020] The sealing area can be grouted using a cement-water glass double-liquid grout double-pipe method. The cement used is 42.5 grade ordinary Portland cement with a water-cement ratio of 1:0.75. The water glass has a modulus of 2.2 to 3.4 and a concentration of 38 to 43°Be'. The water glass and water are mixed in a 1:2 volume ratio to form a mixture. The volume ratio of water glass mixture to cement grout is 1:1. The setting time is controlled at 120 to 150 seconds. The grouting pressure in the sealing area is controlled at 0.6 to 1 MPa.
[0021] The filling zone can use ordinary silicate cement grout of grade 42.5. The water-cement ratio for both shallow low-pressure grouting and deep composite hole high-pressure grouting is 1:0.75.
[0022] Step 2: Enclosing the sealing area. First, drill holes from both ends of the smaller and larger piles towards the center using a rotary drill. The holes are located at the arch feet on both sides, at an angle of 10° to 45° downwards, with a diameter of 50mm for grouting. Drill to the designed depth. For localized hole collapse, use casing to follow the drilling. After drilling, grout is injected symmetrically from both ends of the larger and smaller piles towards the center, using 42mm diameter steel pipes inserted into the drilled holes. Grouting is carried out in sections from bottom to top in one continuous operation. The grouting pressure is controlled at...
[0023] 0.6~1Mpa
[0024] The grouting uses cement-water glass dual-liquid grout. If a casing is used during drilling, the casing should be pulled out during the grouting process. After the grouting is completed, the grout diffuses and surrounds the loose layer to form the grouting boundary.
[0025] Step 3: During shallow grouting, the shallow hole low-pressure grouting zone is the area 5m below the foundation elevation of the tunnel secondary lining. After the sealing zone construction is completed and the grout has formed strength, shallow drilling is carried out, grouting pipes are inserted, and shallow low-pressure cement grout is injected. The low-pressure grouting pressure is controlled at 0.2-0.5 MPa and stabilized for no less than 30 minutes. The grouting volume should be recorded during the grouting process. Grouting is carried out from both ends to the middle in a skip-hole grouting manner.
[0026] Step 4: When drilling in the high-pressure zone of the re-forming hole, after the shallow low-pressure grouting is completed and the grout has formed strength, test drilling in the high-pressure zone of the re-forming hole is carried out. When drilling, drilling is carried out from the two ends of the small pile number and the large pile number towards the middle. If the hole collapses locally, the casing is used to follow the drilling. If the hole fails to be formed after multiple drilling attempts, the collapsed hole is re-grouted and then drilled again.
[0027] Step 5: During high-pressure grouting, after drilling is completed, cement grout is injected symmetrically from both ends of the large and small piles into the middle of the skip hole. Grouting is carried out in sections from bottom to top using steel pipes. If a casing is used during drilling, the casing should be pulled out during the grouting process. The grouting pressure is controlled at 1-2 MPa.
[0028] Boundary constraints are used in the field of grouting reinforcement.
[0029] In the horizontal direction, sealing zones are set up on both sides of the grouting range to constrain the grout; in the depth direction, grouting is carried out on the upper part of the loose layer, which not only strengthens the shallow base and protects the invert arch from secondary diseases caused by subsequent high-pressure grouting, but also reduces the probability of borehole collapse and facilitates subsequent drilling construction; the lower constraint cleverly utilizes impermeable strata to constrain the grout to flow downward, such as clay layers, bedrock, etc.
[0030] The present invention, by adopting the above-described technical solution, has the following beneficial effects:
[0031] (1) Compared with conventional grouting reinforcement grouting which has radial penetration and waste of grout, this invention applies boundary constraints to the grouting and makes full use of all the grout in the filling area;
[0032] (2) Compared with conventional grouting reinforcement which relies solely on permeation and diffusion, and where the grouting density decreases as it gets further from the grouting center, this method uses high-pressure grouting in the filling area under the constraints of grouting on both sides and in the shallow layer, so that the trapezoidal load-bearing area of the tunnel foundation can be uniformly grouted with high density.
[0033] (3) Compared with the traditional large-scale replacement of lining, this technical method causes less disturbance to the strata, does not require damage to the arch ring, and reinforces the invert arch by grouting the shallow filling area in advance. It is safe, efficient and can be constructed in the narrow space of the tunnel.
[0034] (4) This technology has little impact on tunnel operation. During construction, the tunnel can be constructed in lanes and sections. With proper management, the tunnel may not be closed or may be closed less. Under the condition of good safety measures, the tunnel can be passed through at low speed in a single lane.
[0035] (5) The main construction process is simple and can be completed with small machinery and equipment, making construction convenient and the construction period short. Attached Figure Description
[0036] Figure 1 This is a schematic diagram of the substrate grouting reinforcement method of the present invention;
[0037] Figure 2 This is a plan view of the grouting hole arrangement of the present invention;
[0038] Figure 3 This is a schematic diagram of the grouting steel perforated pipe structure of the present invention;
[0039] Figure 4 This is a schematic diagram of the grouting hole structure of the base of this invention.
[0040] In the attached diagram, 1-blocking area, 2-shallow low-pressure grouting area, 3-deep composite high-pressure grouting area, 4-tunnel centerline, 5-grouting hole, 6-grouting steel pipe outlet hole. Detailed Implementation
[0041] To make the objectives, technical solutions, and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and preferred embodiments. However, it should be noted that many details listed in the specification are merely to provide the reader with a thorough understanding of one or more aspects of the present invention, and these aspects of the invention can be implemented even without these specific details.
[0042] like Figure 1-4 As shown, a method for treating loose soil layers in tunnel foundations during operation is divided into three steps: "sealing", "grouting" and "injection". The method of grouting is carried out in sections and phases to fill the trapezoidal load-bearing zone of the tunnel foundation with grout, which greatly improves the grouting density.
[0043] The key technical points for grouting foundation treatment of loose layers in tunnel foundations during operation are as follows:
[0044] (1) To control the grouting area, prevent the grout from spreading horizontally, and facilitate foundation reinforcement construction, the grouting area should be divided into zones before construction, which can be divided into a sealing zone and a filling zone. See [link to grouting zone division] for details. Figure 1 .
[0045] (2) Sealing Zone 1. The sealing zone extends to the left and right sides of the grouting area. Pre-drilling technology is preferred for drilling. The sealing zone serves to limit the diffusion of grout and improve the grouting effect. Therefore, the grouting material needs to solidify quickly to block the diffusion of grout in the filling area. Grouting materials with rapid solidification characteristics (such as cement-water glass two-liquid grout, chemical grout, etc.) should be used.
[0046] (3) Grouting and Filling Zone. The filling zone is divided into a shallow low-pressure grouting zone and a deep composite borehole high-pressure grouting zone. The boundary between these two zones is mainly determined based on geological conditions, grouting pressure, and engineering experience. The shallow low-pressure grouting zone can be defined as the area from the tunnel secondary lining base to 5m below the base, while the deep composite borehole high-pressure grouting zone can be defined as the area below the low-pressure zone and above the bedrock or impermeable layer. Single-component grout is used as the grouting material in this zone. This technology fills the voids in the rock blocks at the bottom of the tunnel through the grouting filling zone. The grout has high fluidity, while the loose cavitation muck has large voids, thus the grout can effectively fill the filling zone.
[0047] (4) Shallow low-pressure grouting zone 2. The grouting area is the shallow filling zone in the middle. Drilling starts from the road surface and goes downwards. Since the shallow filling zone in the middle is large and deep, in order to fully fill the grouting zone, the grouting material can be a grout with good fluidity and low cost (such as cement grout, cement mortar, etc.). The function of shallow low-pressure grouting is to pre-reinforce the loose layer of the base layer, so that the composite holes drilled for deep grouting are less likely to collapse, reducing the difficulty of construction; on the other hand, pre-reinforcing the loose layer of the shallow layer can avoid secondary diseases such as base heave or cracking caused by subsequent high-pressure grouting.
[0048] (5) Deep composite borehole high-pressure grouting zone 3. The grouting area is the central deep filling zone. Due to the large area and depth of the central deep filling zone, in order to ensure that the grout fully fills the grouting zone, the grouting material can be a grout with good fluidity and low cost (such as cement grout, cement mortar, etc.). The purpose of composite borehole high-pressure grouting is to fill the pores of the loose layer with grout and improve the quality of the grouting project.
[0049] (6) Drilling layout. The spacing between grouting holes should not be too far. The spacing of the central grouting holes should be calculated based on the penetration radius r of the grouting material. Assuming the penetration radius is r, the grouting hole spacing is d, the width of the overlapping area is s = 2r - d (s > 0), and the proportion of the overlapping area of the grouting penetration radius is k.
[0050]
[0051] k is preferably 20%; since the cross-section of the grouting area is trapezoidal, additional grouting holes are needed on both sides of the trapezoid, so the grouting holes are often arranged more densely on both sides. Based on experience, the spacing between the grouting holes on both sides can be half the spacing of the central grouting hole, d / 2. See the borehole plan layout. Figure 2 .
[0052] (7) Arrangement of grouting hole depth (arrangement of grouting hole height). The grouting depth can be calculated using the bearing capacity after grouting. The bearing capacity of the foundation after grouting should be calculated according to the specifications to meet the requirements. It is best if there is an impermeable layer below the grouting hole. At this time, the grouting hole can be drilled to the impermeable layer to prevent the grout from spreading in the vertical direction.
[0053] (8) Drilling. The diameter of the grouting hole 4 can be controlled within 2-10cm. The grouting pipe can be a steel perforated pipe with a diameter of 2-10cm. The bottom of the grouting hole 4 should extend 50cm beyond the loose layer of the base. When drilling the secondary lining, impact drills are not allowed; rotary drills should be used instead. If reinforcing bars are encountered during drilling, the position of the grouting hole can be moved appropriately, but the reinforcing bars should not be cut.
[0054] (9) Skip-hole grouting. Skip-hole grouting is preferred during the grouting process, using adjacent holes as venting holes. The grouting follows a four-stage hole principle. The four-stage hole principle is to first grout the single-row odd-numbered holes as the first stage, then grout the double-row even-numbered holes as the second stage, then grout the single-row even-numbered holes as the third stage, and finally grout the double-row odd-numbered holes as the fourth stage.
[0055] (10) Bottom-up segmented grouting. Bottom-up grouting (also known as ascending grouting) involves drilling to the designed depth in one go, then installing grouting plugs segment by segment from bottom to top for grouting. Obviously, when using bottom-up grouting, the grouting plugs may not be able to be inserted at the intended position. The adjustment method is to move them appropriately up or down until a suitable position is found. The "Technical Specification for Cement Grouting Construction of Hydraulic Structures" stipulates that when the length of the grouting section exceeds 10m, remedial measures should be taken. The remedial method generally involves arranging inspection holes nearby to assess the extent of the impact and to perform supplementary grouting. For example... Figure 4 The diagram shows the specific layout of the grout outlet holes in the grouting steel pipe, with a structure that varies according to the intervals between each column.
[0056] The construction steps for grouting foundation treatment of the loose layer of the tunnel base during the operation period are as follows:
[0057] (1) Before construction, conduct indoor grout mix ratio test and in-situ construction process test, and determine various parameters such as grouting pressure, water-cement ratio and grout mix ratio based on the test results.
[0058] (2) Enclosure of the sealing area. First, drill holes from both ends of the small and large pile numbers towards the center using a rotary drill. The holes are located at the arch feet on both sides, at a suitable angle (preferably 10° to 45°) downwards. The grouting holes are 50mm in diameter and drilled to the designed depth. For local hole collapse, casing can be used for follow-up drilling. After drilling is completed, grouting is performed symmetrically from both ends of the large and small pile numbers towards the center. A 42mm diameter steel pipe is inserted into the drilled hole for grouting, and grouting is carried out in sections from bottom to top in one go. The grouting pressure can be controlled at 0.6 to 1 MPa. Cement-water glass dual-liquid grout is preferred for grouting. If casing was used during drilling, the casing should be pulled out during grouting. After grouting is completed, the grout diffuses and encloses the loose layer to form the grouting boundary.
[0059] Shallow grouting. The preferred shallow-hole low-pressure grouting zone is...
[0060] Tunnel secondary lining foundation elevation
[0061] Within a 5m range downwards. After the sealing area construction is completed and the grout has gained strength, shallow drilling is performed, grouting pipes are inserted, and shallow low-pressure cement grout is injected. The low-pressure grouting pressure is preferably 0.2–0.5 MPa.
[0062] And stabilize the voltage for no less than 30 minutes.
[0063] (3) The amount of grouting should be recorded during the grouting process. Grouting should be carried out from both ends to the middle in a skip-hole grouting manner.
[0064] (4) Drilling in the high-pressure zone for re-forming the borehole. After the shallow low-pressure grouting is completed and the grout has gained strength, test drilling in the high-pressure zone for re-forming the borehole is carried out. When drilling can be performed without casing, large-scale drilling is carried out. Drilling proceeds from both ends of the small and large pile numbers towards the middle. If a hole collapses in a local area, casing can be used for follow-up drilling. If multiple drilling attempts fail, the collapsed holes are re-grouted and then drilled again.
[0065] High-pressure grouting. After drilling is completed, cement grout is injected symmetrically from both ends of the large and small piles towards the middle of the hole. Grouting can be carried out in sections from bottom to top using a steel pipe. If a casing was used during drilling, it should be pulled out during the grouting process. The grouting pressure is preferably controlled at 1-2 MPa.
[0066] Boundary constraints are used in the field of grouting reinforcement. Laterally, sealing zones are set on both sides of the grouting range to constrain the grout; in the depth direction, grouting is carried out on the upper part of the loose layer, which not only reinforces the shallow base and protects the invert arch from secondary damage caused by subsequent high-pressure grouting, but also reduces the probability of borehole collapse and facilitates subsequent drilling construction; the lower constraint cleverly utilizes impermeable strata to constrain the grout to flow downwards, such as clay layers, bedrock, etc.
[0067] The above description is only a preferred embodiment of the present invention. It should be noted that for those skilled in the art, several improvements and modifications can be made without departing from the principle of the present invention, and these improvements and modifications should also be considered within the scope of protection of the present invention.
Claims
1. A method for treating the loose foundation layer of a tunnel base during operation, characterized in that: The grouting foundation is divided into a sealing zone and a grouting and filling zone. The sealing zone is set on both sides of the grouting and filling zone. The sealing zone is first drilled and grouted, and then the grouting and filling zone is filled with grout. The sealing zone extends to the left and right sides of the grouting area. The drilling adopts pre-drilling technology. The sealing zone plays a role in limiting the diffusion of grout and improving the grouting effect. The grouting material needs to solidify quickly to block the diffusion of grout in the filling area. The grouting material is cement-water glass two-liquid grout or chemical grout. The grouting and filling area is divided into a shallow low-pressure grouting area and a deep composite borehole high-pressure grouting area. The shallow low-pressure grouting area extends from the tunnel secondary lining base to 5m below the base, while the deep composite borehole high-pressure grouting area extends below the shallow low-pressure grouting area and above the bedrock or impermeable layer. The grouting material is a single-liquid grout. Through the voids in the rock blocks at the bottom of the tunnel in the grouting and filling area, the grout has fluidity, so the grout can fill the filling area. The shallow low-pressure grouting zone is the shallow filling area in the middle. Drilling starts from the road surface and goes downwards. The grouting material used in the shallow low-pressure grouting zone is cement slurry or cement mortar, which is fluid and inexpensive. The purpose of shallow low-pressure grouting in the shallow low-pressure grouting zone is to pre-reinforce the loose layer of the base, so that the re-forming holes drilled in the deep grouting will collapse and reduce the construction difficulty. On the other hand, pre-reinforcing the loose layer of the shallow layer can avoid secondary diseases such as base heave or cracking caused by subsequent high-pressure grouting. The grouting range of the deep composite hole high-pressure grouting zone is the middle deep filling zone. The grouting material can be cement grout or cement mortar, etc. The purpose of the composite hole high-pressure grouting in the deep composite hole high-pressure grouting zone is to fill the pores of the loose layer with grout and improve the quality of the grouting project.
2. The method for treating loose foundation layers in tunnel bases during operation, as described in claim 1, is characterized in that: When designing the borehole layout, the spacing between the central grouting holes is calculated based on the penetration radius r of the grouting material. Assuming the penetration radius is r and the hole spacing is d, the width of the overlapping area is taken as... The proportion of overlapping areas of grouting penetration radius, k. k is taken as 20%. Since the cross-section of the grouting range is trapezoidal, additional grouting holes are needed on both sides of the trapezoid. Therefore, the grouting holes are arranged to be dense on both sides and sparse in the middle. The interval between the grouting holes on both sides is half of the interval between the grouting holes in the middle, d / 2.
3. The method for treating loose foundation layers in tunnel bases during operation, as described in claim 2, is characterized in that: When designing the depth or height of grouting holes, the grouting depth should be calculated based on the bearing capacity after grouting. The bearing capacity of the foundation after grouting should be calculated according to the specifications to meet the requirements. There should be an impermeable layer below the grouting holes, and the grouting holes should be drilled to the impermeable layer to prevent the grout from spreading in the vertical direction.
4. The method for treating loose foundation layers in tunnel base during operation according to claim 3, characterized in that: When drilling, the diameter of the grouting hole should be controlled within 2-10cm. The grouting pipe should be a steel perforated pipe with a diameter of 2-10cm. The bottom of the grouting hole should extend 50cm beyond the loose layer. When drilling the secondary lining, impact drills are not allowed. Rotary drills should be used instead. If the drilling process encounters reinforcing bars, the position of the grouting hole should be moved.
5. The method for treating loose foundation layers in tunnel bases during operation, as described in claim 4, is characterized in that: During grouting, a skip-hole grouting method is adopted, using adjacent holes as vent holes. The grouting follows the four-order hole principle, which is to first grout the single-row single-numbered holes as the first order, then grout the double-row double-numbered holes as the second order, then grout the single-row double-numbered holes as the third order, and finally grout the double-row single-numbered holes as the fourth order.
6. The method for treating loose foundation layers in tunnel bases during operation, as described in claim 5, is characterized in that: During grouting, grouting is carried out in sections from bottom to top. The borehole is drilled to the designed depth in one go, and then grouting plugs are installed section by section from bottom to top for grouting. When grouting from bottom to top, if the grouting plug cannot be plugged in the predetermined position, the position plug is moved up or down until a position that can be plugged is found. When the length of the grouting section is greater than 10m, remedial measures are taken. The remedial measures are to set up inspection holes on the side to check the impact data and at the same time, supplementary grouting can be carried out.
7. The method for treating loose soil layers in tunnel foundations during operation, as described in claim 1, is characterized in that: The construction process is as follows: Step 1: Before construction, conduct indoor grout mix proportion tests and in-situ construction process tests, and determine the parameters of grouting pressure, water-cement ratio, and grout mix proportion based on the test results; Step 2: Enclosing the sealing area. First, drill holes from both ends of the small and large pile numbers towards the center using a rotary drill. The holes are located at the arch feet on both sides, with an angle of 10° to 45° downwards and a radius of 50mm for grouting. Drill to the designed depth. If there is local hole collapse, use casing to follow the drilling. After drilling, grouting is carried out symmetrically from both ends of the large and small pile numbers towards the center. A 42mm diameter steel pipe is inserted into the drilled hole. Grouting is carried out in sections from bottom to top in one go. The grouting pressure is controlled at 0.6-1Pa. Cement-water glass double liquid grout is used for grouting. If casing is used during drilling, the casing should be pulled out during grouting. After grouting is completed, the grout diffuses in the loose layer to form the grouting boundary. Step 3: During shallow grouting, the shallow hole low-pressure grouting zone is the area 5m below the foundation elevation of the tunnel secondary lining. After the sealing zone construction is completed and the grout has formed strength, shallow drilling is carried out, grouting pipes are inserted, and shallow low-pressure cement grout is injected. The low-pressure grouting pressure is controlled above 0.2~0.5Mpa and stabilized for no less than 30 minutes. The grouting volume should be recorded during the grouting process. Grouting is carried out from both ends to the middle in a skip-hole grouting manner. Step 4: When drilling in the high-pressure zone of the re-forming hole, after the shallow low-pressure grouting is completed and the grout has formed strength, test drilling in the high-pressure zone of the re-forming hole is carried out. When drilling, drilling is carried out from the two ends of the small pile number and the large pile number towards the middle. If the hole collapses locally, the casing is used to follow the drilling. If the hole fails to be formed after multiple drilling attempts, the collapsed hole is re-grouted and then drilled again. Step 5: During high-pressure grouting, after drilling is completed, cement grout is injected symmetrically from both ends of the large and small piles into the middle of the skip hole. Grouting is carried out in sections from bottom to top using steel pipes. If a casing is used during drilling, the casing should be pulled out during the grouting process. The grouting pressure is controlled at 1-2 MPa.