Multiple-input multiple-output scheduling method and apparatus

By reducing the scheduling priority of only some users in the MU-MIMO user group and adjusting the priority according to channel quality and historical data volume, the problem of insufficient resource allocation in the existing technology of MU-MIMO user group is solved, and cell throughput and resource utilization are improved.

CN117580182BActive Publication Date: 2026-11-20CHINA MOBILE COMM LTD RES INST +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202210931952.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-04
Publication Date
2026-11-20
Estimated Expiration
2042-08-04

AI Technical Summary

Technical Problem

In multi-user multiple-input multiple-output (MU-MIMO) scheduling, existing technologies that only use proportional fairness algorithms result in poor cell throughput and resource utilization. In particular, after the priority of MU-MIMO users is reduced, the PRB resource allocation is insufficient, which affects the improvement of cell throughput.

Method used

In MU-MIMO user groups, the scheduling priority of only some users is reduced, rather than all users. Priority is calculated by adjusting channel quality and historical data volume, and the priority of other users is kept unchanged in subsequent time units to improve the scheduling probability and resource utilization of MU-MIMO user groups.

Benefits of technology

This increased the number of scheduling operations and PRB resource allocation for MU-MIMO user groups, improved cell throughput and resource utilization efficiency, and ensured the data transmission needs of MU-MIMO user groups.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117580182B_ABST
    Figure CN117580182B_ABST
Patent Text Reader

Abstract

The application discloses a multiple-input multiple-output scheduling method and device, which is applied to scheduling multiple users, and the multiple users at least include users in a first MU-MIMO user group, and the method comprises the following steps: in the case that the first MU-MIMO user group is scheduled in a first time unit, the scheduling priority of a first part of users in the first MU-MIMO user group is reduced; target users scheduled in a second time unit are determined according to the scheduling priority of each candidate user, and the target users are scheduled in the second time unit, wherein the candidate users include each MU-MIMO user group and / or each SU-MIMO user in the multiple users, and the scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the users in the MU-MIMO user group. The application can improve the cell throughput.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of mobile communication technology, specifically to a multiple-input multiple-output scheduling method and device. Background Technology

[0002] With the continuous increase of 5G users, in order to improve cell throughput, the Multiple-User Multiple-Input Multiple-Output (MU-MIMO) technology has been introduced. Its main principle is that multiple users are scheduled on the same time-frequency resource. Compared with the previous scheduling of only one user on one time-frequency resource, the cell throughput will increase exponentially.

[0003] Traditional Media Access Control (MAC) scheduling methods mainly include three types: maximum C / I algorithm, round-robin scheduling algorithm, and proportional fairness algorithm. Currently, the proportional fairness algorithm is more widely used in product implementation. In this algorithm, the base station MAC layer assigns a scheduling priority (hereinafter referred to as "priority") to each user in the system. Every Transmission Time Interval (TTI), the user with the highest priority is scheduled and allocated Physical Resource Block (PRB) resources. Each user's priority is dynamically allocated. After user 1, who has good channel quality or high service priority, is scheduled, its priority decreases as more PRB resources are allocated to it. When user 1's priority drops below user 2's priority, user 2 will be scheduled first. This ensures a balance between multi-user diversity gain and fairness.

[0004] If MU-MIMO scheduling only uses the proportional fairness algorithm, very few PRBs will be used for MU-MIMO, resulting in the cell throughput not reaching the optimal level. Summary of the Invention

[0005] At least one embodiment of this application provides a multiple-input multiple-output scheduling method and apparatus for improving cell throughput.

[0006] To solve the above-mentioned technical problems, this application is implemented as follows:

[0007] In a first aspect, embodiments of this application provide a multiple-input multiple-output (MIMO) scheduling method for scheduling multiple users, wherein the multiple users include at least users in a first MU-MIMO user group, including:

[0008] If the first MU-MIMO user group is scheduled in the first time unit, the scheduling priority of the first part of the users in the first MU-MIMO user group is reduced.

[0009] Based on the scheduling priority of each candidate user, the target user to be scheduled in the second time unit is determined, and the target user is scheduled in the second time unit. The candidate users include each MU-MIMO user group and / or each SU-MIMO user among the plurality of users. The scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the user in the MU-MIMO user group.

[0010] Optionally, the first group of users can be any of the following:

[0011] The first N1 MU-MIMO users in the first MU-MIMO user group are sorted from high to low according to scheduling priority, where N1 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group;

[0012] N2 MU-MIMO users are randomly selected from the first MU-MIMO user group, where N2 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group.

[0013] Optionally, N1 is 1.

[0014] Optionally, determining the target user to be scheduled in the second time unit based on the scheduling priority of each candidate user includes:

[0015] Based on the scheduling priority of each candidate user, the candidate user with the highest scheduling priority is selected as the target user for scheduling in the second time unit.

[0016] Optionally, reducing the scheduling priority of the first group of users in the first MU-MIMO user group includes:

[0017] Based on the channel quality and historical scheduling data volume of MU-MIMO users, the scheduling priority of each user in the first group of users is calculated, wherein the scheduling priority is positively correlated with the channel quality and negatively correlated with the historical scheduling data volume.

[0018] Optionally, when reducing the scheduling priority of some MU-MIMO users in the first MU-MIMO user group, the scheduling priority of other users among the plurality of users, excluding the first group of users, remains unchanged.

[0019] Optionally, the method further includes:

[0020] When the target user is scheduled on the second time unit, the scheduling priority of the target user is reduced. Specifically, when the target user is any MU-MIMO user group, only the scheduling priority of the second part of the MU-MIMO users in the MU-MIMO user group is reduced, and the number of the second part of the MU-MIMO users is less than the total number of MU-MIMO users in the MU-MIMO user group.

[0021] Secondly, embodiments of this application provide a network device, including a transceiver and a processor, wherein...

[0022] The processor is configured to schedule multiple users, including at least users in a first MU-MIMO user group, wherein, when the first MU-MIMO user group is scheduled in a first time unit, the scheduling priority of a first portion of users in the first MU-MIMO user group is reduced; and the target user to be scheduled in a second time unit is determined based on the scheduling priority of each candidate user.

[0023] The transceiver is used to schedule the target user in the second time unit;

[0024] The candidate users include each MU-MIMO user group and / or each SU-MIMO user among the plurality of users, and the scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the user in the MU-MIMO user group.

[0025] Optionally, the first group of users can be any of the following:

[0026] The first N1 MU-MIMO users in the first MU-MIMO user group are sorted from high to low according to scheduling priority, where N1 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group;

[0027] N2 MU-MIMO users are randomly selected from the first MU-MIMO user group, where N2 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group.

[0028] Optionally, N1 is 1.

[0029] 11. The network device according to claim 8, wherein the processor is further configured to select the candidate user with the highest scheduling priority as the target user to be scheduled in the second time unit according to the order of scheduling priorities of each candidate user.

[0030] Optionally, the processor is further configured to calculate the scheduling priority of each user in the first group of users based on the channel quality and historical scheduling data volume of the MU-MIMO users, wherein the scheduling priority is positively correlated with the channel quality and negatively correlated with the historical scheduling data volume.

[0031] Optionally, the processor is further configured to maintain the scheduling priority of other users among the plurality of users, excluding the first group of users, unchanged when reducing the scheduling priority of some MU-MIMO users in the first MU-MIMO user group.

[0032] Optionally, the processor is further configured to reduce the scheduling priority of the target user when the target user is scheduled on the second time unit, wherein when the target user is any MU-MIMO user group, the scheduling priority of only the second part of the MU-MIMO users in the any MU-MIMO user group is reduced, and the number of the second part of the MU-MIMO users is less than the total number of MU-MIMO users in the any MU-MIMO user group.

[0033] Thirdly, embodiments of this application provide a network device, including: a processor, a memory, and a program stored in the memory and executable on the processor, wherein the program, when executed by the processor, implements the steps of the method as described in any of the first aspects.

[0034] Fourthly, embodiments of this application provide a computer-readable storage medium storing a computer program that, when executed by a processor, implements the steps of the method described in any of the first aspects.

[0035] Compared with the prior art, the multiple input multiple output scheduling method and device provided in this application, after scheduling a MU-MIMO user group in a certain scheduling time unit, no longer reduces the scheduling priority of all users in the MU-MIMO user group, but only reduces the scheduling priority of some users. This has a certain probability of increasing the scheduling priority of the MU-MIMO user group, thereby increasing the probability of the MU-MIMO user group being scheduled in subsequent scheduling time units, thus improving cell throughput and resource utilization. Attached Figure Description

[0036] Various other advantages and benefits will become apparent to those skilled in the art upon reading the following detailed description of preferred embodiments. The accompanying drawings are for illustrative purposes only and are not intended to limit the scope of this application. Furthermore, the same reference numerals denote the same parts throughout the drawings. In the drawings:

[0037] Figure 1 This is a schematic diagram illustrating an application scenario according to an embodiment of this application;

[0038] Figure 2 This is a flowchart of a multiple-input multiple-output scheduling method according to an embodiment of this application;

[0039] Figure 3 This is a schematic diagram of the structure of a network device according to an embodiment of this application;

[0040] Figure 4 This is a schematic diagram of the structure of a network device according to another embodiment of this application;

[0041] Figure 5 This is a schematic diagram of the structure of a network device according to another embodiment of this application. Detailed Implementation

[0042] Exemplary embodiments of the present application will now be described in more detail with reference to the accompanying drawings. While exemplary embodiments of the present application are shown in the drawings, it should be understood that the present application may be implemented in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this application will be thorough and complete, and will fully convey the scope of the present application to those skilled in the art.

[0043] The terms “first,” “second,” etc., used in the specification and claims of this application are used to distinguish similar objects and are not necessarily used to describe a specific order or sequence. It should be understood that such data can be interchanged where appropriate so that the embodiments of this application described herein can be implemented, for example, in orders other than those illustrated or described herein. Furthermore, the terms “comprising” and “having,” and any variations thereof, are intended to cover a non-exclusive inclusion; for example, a process, method, system, product, or apparatus that comprises a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to such processes, methods, products, or apparatus. The terms “and / or” in the specification and claims indicate at least one of the connected objects.

[0044] The technologies described in this document are not limited to NR systems and Long Time Evolution (LTE) / LTE-Advanced (LTE-A) systems, but can also be used in various wireless communication systems such as Code Division Multiple Access (CDMA), Time Division Multiple Access (TDMA), Frequency Division Multiple Access (FDMA), Orthogonal Frequency Division Multiple Access (OFDMA), Single-carrier Frequency-Division Multiple Access (SC-FDMA), and other systems. The terms "system" and "network" are often used interchangeably. CDMA systems can implement radio technologies such as CDMA2000 and Universal Terrestrial Radio Access (UTRA). UTRA includes Wideband Code Division Multiple Access (WCDMA) and other CDMA variants. TDMA systems can implement radio technologies such as the Global System for Mobile Communication (GSM). OFDMA systems can implement radio technologies such as Ultra Mobile Broadband (UMB), Evolution-UTRA (E-UTRA), IEEE 802.21 (Wi-Fi), IEEE 802.16 (WiMAX), IEEE 802.20, and Flash-OFDM. UTRA and E-UTRA are part of the Universal Mobile Telecommunications System (UMTS). LTE and more advanced LTE (such as LTE-A) are newer versions of UMTS that use E-UTRA. UTRA, E-UTRA, UMTS, LTE, LTE-A, and GSM are described in documents from an organization called the 3rd Generation Partnership Project (3GPP). CDMA2000 and UMB are described in documents from an organization called 3rd Generation Partnership Project 2 (3GPP2).The techniques described herein can be used with the systems and radio technologies mentioned above, as well as with other systems and radio technologies. However, the following description describes NR systems for illustrative purposes, and NR terminology is used in most of the following description, although these techniques can also be applied to applications beyond NR systems.

[0045] The following description provides examples and is not intended to limit the scope, applicability, or configuration set forth in the claims. Changes may be made to the function and arrangement of the elements discussed without departing from the spirit and scope of this disclosure. Various procedures or components may be appropriately omitted, substituted, or added to the examples. For example, the described methods may be performed in a different order than described, and various steps may be added, omitted, or combined. Furthermore, features described with reference to certain examples may be combined in other examples.

[0046] Please see Figure 1 , Figure 1 This diagram illustrates a block diagram of a wireless communication system applicable to embodiments of this application. The wireless communication system includes a terminal 11 and a network device 12. The terminal 11 can also be referred to as a user terminal or user equipment (UE). The terminal 11 can be a mobile phone, tablet computer, laptop computer, personal digital assistant (PDA), mobile internet device (MID), wearable device, or in-vehicle device, etc. It should be noted that the specific type of terminal 11 is not limited in this embodiment. Network device 12 can be a base station and / or a core network element. The base station can be a 5G or later version base station (e.g., gNB, 5G NR NB, etc.), or a base station in other communication systems (e.g., eNB, WLAN access point, or other access point, etc.). The base station can be referred to as a node B, evolved node B, access point, base transceiver station (BTS), radio base station, radio transceiver, basic service set (BSS), extended service set (ESS), B node, evolved B node (eNB), home B node, home evolved B node, WLAN access point, WiFi node, or any other suitable term in the field. As long as the same technical effect is achieved, the base station is not limited to specific technical terms. It should be noted that in this embodiment of the application, only a base station in an NR system is used as an example, but the specific type of base station is not limited.

[0047] The base station can communicate with terminal 11 under the control of a base station controller, which in various examples may be part of the core network or some base stations. Some base stations may communicate control information or user data with the core network via backhaul. In some examples, some of these base stations may communicate with each other directly or indirectly via backhaul links, which may be wired or wireless communication links. The wireless communication system may support operation on multiple carriers (waveform signals of different frequencies). A multi-carrier transmitter can transmit modulated signals on multiple carriers simultaneously. For example, each communication link may be a multi-carrier signal modulated according to various radio technologies. Each modulated signal may be transmitted on a different carrier and may carry control information (e.g., reference signals, control channels, etc.), overhead information, data, etc.

[0048] The base station can wirelessly communicate with terminal 11 via one or more access point antennas. Each base station can provide communication coverage for its respective coverage area. The coverage area of ​​an access point can be divided into sectors that constitute only a part of that coverage area. The wireless communication system may include different types of base stations (e.g., macro base stations, micro base stations, or pico base stations). Base stations may also utilize different radio technologies, such as cellular or WLAN radio access technologies. Base stations may be associated with the same or different access networks or operator deployments. The coverage areas of different base stations (including coverage areas of the same or different types of base stations, coverage areas using the same or different radio technologies, or coverage areas belonging to the same or different access networks) may overlap.

[0049] Communication links in a wireless communication system may include an uplink for carrying uplink (UL) transmissions (e.g., from terminal 11 to network device 12) or a downlink for carrying downlink (DL) transmissions (e.g., from network device 12 to terminal 11). UL transmissions may also be referred to as reverse link transmissions, and DL transmissions may also be referred to as forward link transmissions. Downlink transmissions may be carried out using licensed frequency bands, unlicensed frequency bands, or both. Similarly, uplink transmissions may be carried out using licensed frequency bands, unlicensed frequency bands, or both.

[0050] MU-MIMO scheduling employs a proportional fairness algorithm. When MU-MIMO is scheduled in TTI N, since all MU-MIMO users have already been scheduled, the allocated PRB resources for them increase. In TTI N+1, their priorities decrease by deltaWeight(ue_index). Thus, as the priority of MU-MIMO users decreases, even if these UEs meet the MU-MIMO criteria in subsequent TTIs, their priority is lower than that of single-user multiple-input multiple-output (SU-MIMO) users. Ultimately, the MAC layer prioritizes SU-MIMO scheduling, leaving little or no PRB for MU-MIMO, resulting in suboptimal cell throughput.

[0051] As mentioned above, existing technologies struggle to achieve high cell throughput in MU-MIMO scheduling scenarios. To address at least one of these issues, this application provides a multiple-input multiple-output scheduling method that can improve cell throughput and enhance resource utilization efficiency.

[0052] Please refer to Figure 2 This application provides a multiple-input multiple-output (MIMO) scheduling method, which can be executed by a network device (such as a base station). This method is used to schedule multiple users, wherein the multiple users include at least users in a first MU-MIMO user group. Figure 2 As shown, the method includes:

[0053] Step 21: If the first MU-MIMO user group is scheduled in the first time unit, reduce the scheduling priority of the first part of the users in the first MU-MIMO user group.

[0054] In this embodiment of the application, when a MU-MIMO user group (referred to as the first MU-MIMO user group for ease of description) is scheduled in a first time unit (e.g., a first scheduling TTI), the scheduling priority of each user in the first MU-MIMO user group is not reduced; instead, the scheduling priority of only a first subset of users is reduced. The number of the first subset of users is less than the total number of MU-MIMO users in the first MU-MIMO user group. In other words, while reducing the scheduling priority of some MU-MIMO users in the first MU-MIMO user group, the scheduling priority of the other users besides the first subset remains unchanged.

[0055] Specifically, the first group of users can be any of the following:

[0056] (1) The top N1 MU-MIMO users in the first MU-MIMO user group are sorted from high to low according to their scheduling priority, where N1 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group. For example, if N1 is 1, then only the scheduling priority of the user with the highest scheduling priority in the first MU-MIMO user group is reduced.

[0057] (2) N2 MU-MIMO users are randomly selected from the first MU-MIMO user group, where N2 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group.

[0058] Here, the specific values ​​of N1 and N2 mentioned above can be set according to the preset proportion of the total number of MU-MIMO users, or they can be a fixed value. This article does not make any specific restrictions on this.

[0059] Step 22: Determine the target user to be scheduled in the second time unit according to the scheduling priority of each candidate user, and schedule the target user in the second time unit. The candidate user includes each MU-MIMO user group and / or each SU-MIMO user among the multiple users. The scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the user in the MU-MIMO user group.

[0060] Here, when scheduling is performed in a subsequent time unit after the first time unit (e.g., the second scheduling TTI after the first scheduling TTI), the network device determines the target user to be scheduled in the second time unit based on the scheduling priority of each candidate user, and schedules the target user in the second time unit. Candidate users include each MU-MIMO user group and / or each SU-MIMO user among the plurality of users. That is, if the plurality of users includes only one or more MU-MIMO user groups, the candidate user is that one or more MU-MIMO user groups; if the plurality of users includes both MU-MIMO user groups and SU-MIMO users, both MU-MIMO user groups and SU-MIMO users are considered candidate users.

[0061] When determining the target user from the candidate users, the scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the users in the MU-MIMO user group. Then, according to the order of scheduling priorities of the candidate users, the candidate user with the highest scheduling priority is selected as the target user scheduled in the second time unit. In this way, the target user scheduled in the second time unit can be a certain MU-MIMO user group or a certain SU-MIMO user.

[0062] Through the above steps, this application embodiment can avoid the situation where the scheduling priority of all users in a certain MU-MIMO user group is reduced after a certain MU-MIMO user group is scheduled once. Instead, it only adjusts the scheduling priority of some users, and the scheduling priority of the MU-MIMO user group is the scheduling priority of the user with the highest priority. This makes the updated scheduling priority of the MU-MIMO user group more reasonable, increases the number of times MU-MIMO users are scheduled and the allocation of PRB resources, better guarantees the data transmission needs of the MU-MIMO user group, improves the overall throughput of the cell, and improves resource utilization efficiency.

[0063] In this embodiment of the application, the scheduling priority of the first part of users in the first MU-MIMO user group is reduced. Specifically, the scheduling priority of each user in the first part of users can be calculated based on the channel quality and the amount of historical scheduling data of the MU-MIMO users. The scheduling priority is positively correlated with the channel quality and negatively correlated with the amount of historical scheduling data.

[0064] Following step 22 above, if the target user is scheduled in the second time unit, this embodiment of the application can further update the scheduling priority of the target user. Similarly, when the target user is any MU-MIMO user group, only the scheduling priority of the second part of the MU-MIMO users in that MU-MIMO user group is reduced, where the number of the second part of the MU-MIMO users is less than the total number of MU-MIMO users in that MU-MIMO user group. Then, according to the updated scheduling priority, the next scheduling continues. The selection method for the second part of the MU-MIMO users can be referred to the description of the selection method for the first part of the users above, and will not be repeated here.

[0065] As can be seen, this application's embodiment adds a priority consideration factor unique to MU-MIMO to the traditional scheduling algorithm. After the base station MAC layer schedules n MU-MIMO users in a certain MU-MIMO user group in TTI N, it only reduces the priority of some users when calculating the priority in TTI N+1. Here, the users in the MU-MIMO user group are sorted according to their scheduling priority, with the first user referring to the user with the highest scheduling priority in the MU-MIMO user group. According to the MAC scheduling algorithm, the reduction in scheduling priority is deltaWeight(ue1), and a priority calculation formula for a MAC scheduling (proportional fairness algorithm) is as follows:

[0066] Weight = f1(ChCond) / f2(Th), where Weight represents user priority, ChCond represents the user's current channel conditions, and Th represents the user's current historical data traffic. The specific implementation algorithms differ among base station manufacturers, but generally f1(ChCond) is proportional to ChCond, increasing as ChCond improves; f2(Th) is proportional to Th, increasing as Th increases. As more PRB resources are allocated to users, Th increases, leading to an increase in f2(Th) and a decrease in Weight. Therefore, after scheduling users in TTI N, the priority of user N+1 decreases, deltaWeight(ue_index) = Weight(N) - Weight(N+1).

[0067] However, in this embodiment of the application, the users other than the first group of users in the MU-MIMO user group do not consider that the MAC layer has allocated PRB resources to them because they share PRB resources with the first group of users. Therefore, in TTI N+1, the priority of these other users will not decrease deltaWeight(ue_index). In other words, the priority of these users remains consistent with that in TTI N.

[0068] This improves the priority of MU-MIMO users in the overall cell compared to the traditional MAC algorithm. When the priority of any one of the n MU-MIMO users in a MU-MIMO user group is higher than that of a SU-MIMO user, the MAC layer can prioritize scheduling the MU-MIMO group, thereby increasing the number of times MU-MIMO users are scheduled and the allocation of PRB resources.

[0069] The above method will be further illustrated with a more specific example below. In this example, after scheduling the MU-MIMO user group, only the scheduling priority of the highest priority user among them is reduced.

[0070] Assuming there are 5 users in the cell, during each TTI MAC scheduling, users UE1, UE2, UE3, and UE4 all meet the MU-MIMO condition and are scheduled for MU-MIMO; user UE5 is scheduled for SU-MIMO. Assume the initial priorities are:

[0071] Weight(UE1)>Weight(UE2)>Weight(UE3)>Weight(UE4)>Weight(UE5).

[0072] When MU-MIMO is scheduled in TTI N, during priority calculation in TTI N+1, among the four users performing MU-MIMO (UE1, UE2, UE3, UE4), only the first user, UE1, has its priority reduced by deltaWeight(ue1), while the priorities of UE2, UE3, and UE4 remain unchanged. Thus, UE2 has the highest priority in TTI N+1, and the MAC layer prioritizes MU-MIMO scheduling. Similarly, in TTI N+2, only the first user, UE2, has its priority reduced by deltaWeight(ue2), while the priorities of UE3, UE4, and UE1 remain unchanged, and the MAC layer still prioritizes MU-MIMO scheduling. Only after the priorities of all four MU-MIMO users in TTI N+4 are lower than the priority of SU-MIMO user UE5 does the MAC layer prioritize SU-MIMO scheduling.

[0073] The following is an example of the MAC layer scheduling enhancement scheme. It can be seen that there is an 80% probability of prioritizing MU-MIMO scheduling.

[0074]

[0075] The traditional MAC layer scheduling scheme is as follows: there is a 50% probability that MU-MIMO will be scheduled first. If TTI N+1 or TTI N+3 SU-MIMO UE5 occupies all PRBs after being scheduled by MAC, then MU-MIMO users may not be scheduled.

[0076]

[0077] The various methods of the embodiments of this application have been described above. Apparatus for implementing the above methods will now be provided.

[0078] Please refer to Figure 3 This application embodiment also provides a network device 300 for scheduling multiple users, wherein the multiple users include at least users in a first MU-MIMO user group, and the network device 300 includes:

[0079] The first update module 301 is used to reduce the scheduling priority of the first part of users in the first MU-MIMO user group when the first MU-MIMO user group is scheduled in the first time unit.

[0080] The first scheduling module 302 is used to determine the target user to be scheduled in the second time unit according to the scheduling priority of each candidate user, and to schedule the target user in the second time unit. The candidate user includes each MU-MIMO user group and / or each SU-MIMO user among the plurality of users, and the scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the user in the MU-MIMO user group.

[0081] Through the above modules, the embodiments of this application can improve the scheduling probability of MU-MIMO user groups, thereby increasing cell throughput.

[0082] Optionally, the first group of users can be any of the following:

[0083] The first N1 MU-MIMO users in the first MU-MIMO user group are sorted from high to low according to scheduling priority, where N1 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group;

[0084] N2 MU-MIMO users are randomly selected from the first MU-MIMO user group, where N2 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group.

[0085] Optionally, N1 is 1.

[0086] Optionally, the first scheduling module is further configured to select the candidate user with the highest scheduling priority as the target user for scheduling in the second time unit, based on the order of scheduling priorities of each candidate user.

[0087] Optionally, the first update module is further configured to calculate the scheduling priority of each user in the first group of users based on the channel quality and historical scheduling data volume of the MU-MIMO users, wherein the scheduling priority is positively correlated with the channel quality and negatively correlated with the historical scheduling data volume.

[0088] Optionally, the first update module is further configured to maintain the scheduling priority of other users among the plurality of users, excluding the first group of users, unchanged when reducing the scheduling priority of some MU-MIMO users in the first MU-MIMO user group.

[0089] Optionally, the network device further includes:

[0090] The second update module is used to reduce the scheduling priority of the target user when the target user is scheduled in the second time unit. When the target user is any MU-MIMO user group, the scheduling priority of only the second part of the MU-MIMO users in the MU-MIMO user group is reduced, and the number of the second part of the MU-MIMO users is less than the total number of MU-MIMO users in the MU-MIMO user group.

[0091] It should be noted that the device in this embodiment corresponds to the method described above, and the implementation methods in each of the above embodiments are applicable to the device embodiment and can achieve the same technical effect. The device provided in this application embodiment can implement all the method steps implemented in the above method embodiments and can achieve the same technical effect. Therefore, the parts that are the same as those in the method embodiments and the beneficial effects will not be described in detail here.

[0092] Please refer to Figure 4 This application embodiment also provides a network device 400 for scheduling multiple users, wherein the multiple users include at least users in a first MU-MIMO user group, including: transceiver 401 and processor 402;

[0093] The processor 402 is used to schedule multiple users, including at least users in a first MU-MIMO user group. When the first MU-MIMO user group is scheduled in a first time unit, the scheduling priority of a first part of the users in the first MU-MIMO user group is reduced. The target user to be scheduled in a second time unit is determined according to the scheduling priority of each candidate user.

[0094] The transceiver 401 is used to schedule the target user in the second time unit.

[0095] The candidate users include each MU-MIMO user group and / or each SU-MIMO user among the plurality of users, and the scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the user in the MU-MIMO user group.

[0096] Optionally, the first group of users can be any of the following:

[0097] The first N1 MU-MIMO users in the first MU-MIMO user group are sorted from high to low according to scheduling priority, where N1 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group;

[0098] N2 MU-MIMO users are randomly selected from the first MU-MIMO user group, where N2 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group.

[0099] Optionally, N1 is 1.

[0100] Optionally, the processor is further configured to select the candidate user with the highest scheduling priority as the target user for scheduling in the second time unit, based on the order of scheduling priorities of each candidate user.

[0101] Optionally, the processor is further configured to calculate the scheduling priority of each user in the first group of users based on the channel quality and historical scheduling data volume of the MU-MIMO users, wherein the scheduling priority is positively correlated with the channel quality and negatively correlated with the historical scheduling data volume.

[0102] Optionally, the processor is further configured to maintain the scheduling priority of other users among the plurality of users, excluding the first group of users, unchanged when reducing the scheduling priority of some MU-MIMO users in the first MU-MIMO user group.

[0103] Optionally, the processor is further configured to reduce the scheduling priority of the target user when the target user is scheduled on the second time unit, wherein when the target user is any MU-MIMO user group, the scheduling priority of only the second part of the MU-MIMO users in the any MU-MIMO user group is reduced, and the number of the second part of the MU-MIMO users is less than the total number of MU-MIMO users in the any MU-MIMO user group.

[0104] It should be noted that the device in this embodiment corresponds to the method described above, and the implementation methods in each of the above embodiments are applicable to the device embodiment and can achieve the same technical effect. The device provided in this application embodiment can implement all the method steps implemented in the above method embodiments and can achieve the same technical effect. Therefore, the parts that are the same as those in the method embodiments and the beneficial effects will not be described in detail here.

[0105] Please refer to Figure 5 This application also provides a network device 500, including a processor 5201, a memory 502, and a computer program stored in the memory 502 and executable on the processor 501. When the computer program is executed by the processor 501, it implements the various processes of the method embodiments executed by the network device described above and can achieve the same technical effect. To avoid repetition, it will not be described again here.

[0106] This application also provides a computer-readable storage medium storing a computer program. When executed by a processor, the computer program implements the various processes of the above-described multiple-input multiple-output scheduling method embodiments and achieves the same technical effects. To avoid repetition, it will not be described again here. The computer-readable storage medium may be a read-only memory (ROM), a random access memory (RAM), a magnetic disk, or an optical disk.

[0107] It should be noted that, in this document, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Unless otherwise specified, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes that element.

[0108] Through the above description of the embodiments, those skilled in the art can clearly understand that the methods of the above embodiments can be implemented by means of software plus necessary general-purpose hardware platforms. Of course, they can also be implemented by hardware, but in many cases the former is a better implementation method. Based on this understanding, the technical solution of this application, in essence, or the part that contributes to the prior art, can be embodied in the form of a software product. This computer software product is stored in a storage medium (such as ROM / RAM, magnetic disk, optical disk) and includes several instructions to cause a terminal (which may be a mobile phone, computer, server, air conditioner, or network device, etc.) to execute the methods described in the various embodiments of this application.

[0109] The embodiments of this application have been described above with reference to the accompanying drawings. However, this application is not limited to the specific embodiments described above. The specific embodiments described above are merely illustrative and not restrictive. Those skilled in the art can make many other forms under the guidance of this application without departing from the spirit and scope of the claims, and all of these forms are within the protection scope of this application.

Claims

1. A multiple-input multiple-output (MIMO) scheduling method, applied to scheduling multiple users, wherein the multiple users include at least users in a first MU-MIMO user group, characterized in that, include: When the first MU-MIMO user group is scheduled in the first time unit, the scheduling priority of the first part of the MU-MIMO users in the first MU-MIMO user group is reduced; wherein, when reducing the scheduling priority of the first part of the MU-MIMO users in the first MU-MIMO user group, the scheduling priority of the other users among the plurality of users other than the first part of the MU-MIMO users remains unchanged. Based on the scheduling priority of each candidate user, the target user to be scheduled in the second time unit is determined, and the target user is scheduled in the second time unit. The candidate user includes each MU-MIMO user group and / or each SU-MIMO user among the plurality of users. The scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the user in the MU-MIMO user group. The first group of MU-MIMO users can be any of the following: The first N1 MU-MIMO users in the first MU-MIMO user group are sorted from high to low according to scheduling priority, where N1 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group; N2 MU-MIMO users are randomly selected from the first MU-MIMO user group, where N2 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group.

2. The method according to claim 1, characterized in that, The value of N1 is 1.

3. The method according to claim 1, characterized in that, The step of determining the target user to be scheduled in the second time unit based on the scheduling priority of each candidate user includes: Based on the scheduling priority of each candidate user, the candidate user with the highest scheduling priority is selected as the target user for scheduling in the second time unit.

4. The method according to claim 1, characterized in that, The reduction of the scheduling priority of the first portion of MU-MIMO users in the first MU-MIMO user group includes: Based on the channel quality and historical scheduling data volume of the MU-MIMO users, the scheduling priority of each user in the first part of MU-MIMO users is calculated, wherein the scheduling priority is positively correlated with the channel quality and negatively correlated with the historical scheduling data volume.

5. The method according to claim 1, characterized in that, Also includes: When the target user is scheduled on the second time unit, the scheduling priority of the target user is reduced. Specifically, when the target user is any MU-MIMO user group, only the scheduling priority of the second part of the MU-MIMO users in the MU-MIMO user group is reduced, and the number of the second part of the MU-MIMO users is less than the total number of MU-MIMO users in the MU-MIMO user group.

6. A network device, characterized in that, Includes transceivers and processors, among which, The processor is configured to schedule multiple users, including at least users in a first MU-MIMO user group. When the first MU-MIMO user group is scheduled in a first time unit, the scheduling priority of a first subset of MU-MIMO users within the first MU-MIMO user group is reduced. While reducing the scheduling priority of the first subset of MU-MIMO users in the first MU-MIMO user group, the scheduling priorities of the other users (excluding the first subset of MU-MIMO users) remain unchanged. Based on the scheduling priorities of each candidate user, the processor determines the target user to be scheduled in a second time unit. The transceiver is used to schedule the target user in the second time unit; The candidate users include each MU-MIMO user group and / or each SU-MIMO user among the plurality of users, wherein the scheduling priority of the MU-MIMO user group is equal to the highest scheduling priority of the users in the MU-MIMO user group; the first part of MU-MIMO users is any one of the following: The first N1 MU-MIMO users in the first MU-MIMO user group are sorted from high to low according to scheduling priority, where N1 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group; N2 MU-MIMO users are randomly selected from the first MU-MIMO user group, where N2 is a preset positive integer and is less than the total number of MU-MIMO users in the first MU-MIMO user group.

7. The network device according to claim 6, characterized in that, The value of N1 is 1.

8. The network device according to claim 6, characterized in that, The processor is further configured to select the candidate user with the highest scheduling priority as the target user for scheduling in the second time unit, based on the order of scheduling priorities of each candidate user.

9. The network device according to claim 6, characterized in that, The processor is further configured to calculate the scheduling priority of each user in the first group of MU-MIMO users based on the channel quality and historical scheduling data volume of the MU-MIMO users, wherein the scheduling priority is positively correlated with the channel quality and negatively correlated with the historical scheduling data volume.

10. The network device according to claim 6, characterized in that, The processor is further configured to reduce the scheduling priority of the target user when the target user is scheduled on the second time unit, wherein when the target user is any MU-MIMO user group, the scheduling priority of only the second part of the MU-MIMO users in the any MU-MIMO user group is reduced, and the number of the second part of the MU-MIMO users is less than the total number of MU-MIMO users in the any MU-MIMO user group.

11. A network device, characterized in that, include: A processor, a memory, and a program stored in the memory and executable on the processor, wherein the program, when executed by the processor, implements the steps of the method as described in any one of claims 1 to 5.

12. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores a computer program that, when executed by a processor, implements the steps of the method as described in any one of claims 1 to 5.

Citation Information

Patent Citations

  • Resource scheduling method and device for multiple input multiple output (MIMO) system

    CN102316597A

  • Dispatching method, dispatching device and base station

    CN103621171A