AI Technical Summary
随着河砂的聚集,闸板的底部迎水侧的沉砂会越积越高,使得闸板的压力更大、闸板处的水位抬高,目前的解决办法是,下放泥沙泵抽出治理,但泥沙泵的作业面无法精准确定,泥沙抽出量无法精准控制,容易某处泥砂抽出过多,而某处泥砂抽出不足,均匀度不足;
铲砂组件的设置具有如下效果:1.1、河砂在闸板组件底部堆积过多时,能够自动伸出,从而对积砂层进行分割,使得冗余砂层与基础砂层分离,如此能够便于吸砂组件工作时,不会吸附沉淀在底部的较为固化的泥沙,只需作用至上层的冗余砂层即可,使得吸砂作业更为简便,吸附精度与吸附针对性更高,不会造成吸附组件功耗过大;1.2、在进行检修时,铲砂组件能够从底部封堵检修区,使得检修区保持封闭状态,避免外部水从底部进入检修区。
Smart Images

Figure CN117587763B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of river control technology, specifically to a flood discharge and flow control embankment. Background Technology
[0002] Flood control and discharge at dams refers to regulating water levels and flow by opening flood discharge facilities on dams, thereby reducing the pressure on the dams, protecting their safety, and controlling flood flow to minimize the impact on downstream areas. Flood discharge and flow control at dams are mainly achieved through sluice gates. However, after long-term use, sluice gates often exhibit the following defects: As river sand accumulates, the sediment on the bottom of the gate on the water-facing side will accumulate higher and higher, resulting in greater pressure on the gate and a higher water level at the gate. The current solution is to lower a sediment pump to remove the sediment. However, the working surface of the sediment pump cannot be accurately determined, and the amount of sediment removed cannot be accurately controlled. It is easy for too much sediment to be removed in some places and too little sediment to be removed in others, resulting in insufficient uniformity. During maintenance, it is necessary to regularly check the sealing of the gate, whether there are cracks or corrosion. Currently, the maintenance is mainly carried out by manual diving, which is labor-intensive and inefficient. Summary of the Invention
[0003] To address the shortcomings of existing technologies, this invention provides a flood discharge and flow control dam, which solves the problems mentioned in the background art.
[0004] To achieve the above objectives, the present invention provides the following technical solution: A flood discharge and flow control dam includes a gate assembly. The gate assembly has an upper dam body at the top and a lower dam body at the bottom. A first side dam body is provided on one side of the gate assembly and a second side dam body is provided on the other side. A first storage tank is provided inside the first side dam body and is located on the water-facing side of the gate assembly. A second storage tank is provided at the bottom of the second side dam body. The inner sides of both the first and second storage tanks are open structures. A sealing groove is provided in the middle of the top of the lower dam body, and the bottom end of the gate assembly extends into the sealing groove. A stop is provided on the surface of the lower dam body, and the stop is located on the water-facing side of the gate assembly. The bottom end of the gate assembly cooperates with the stop to stop. The first storage tank is equipped with a separator, a sand-shoveling assembly, and a first drive assembly. The sand-shoveling assembly is located at the bottom of the separator. The second storage tank is equipped with a sand-suction assembly at the bottom. The sand-suction assembly is located above the sand-shoveling assembly. The bottom water-facing side of the gate assembly is a sand accumulation layer. The upper layer of the sand accumulation layer is a redundant sand layer. The sand-suction assembly is arranged opposite to the redundant sand layer. The flood discharge device includes the following states: In the closed state, the gate assembly is closed, the separating assembly and the sand-shoveling assembly are stored in the first storage tank, and the sand-suction assembly is closed and stored in the second storage tank; During flood discharge, the gate assembly rises to carry out flood discharge operations; In the sand-cleaning state, the sand-shoveling component extends out separately, allowing it to insert into the accumulated sand layer. The top of the sand-shoveling component contains redundant accumulated sand. The sand-suction component then starts working, using negative pressure to suck out the redundant accumulated sand. In the maintenance state, the flood discharge device first performs sand removal operations. After the redundant accumulated sand is cleaned up, the sand shovel assembly and the separation assembly extend outward simultaneously. The space between the separation assembly and the gate assembly is an open maintenance area, where maintenance personnel can perform maintenance on the gate assembly.
[0005] Furthermore, the gate assembly includes a main gate, with multiple drainage holes opened inside the upper part of the main gate, and auxiliary gates rotatably installed inside each drainage hole; hydraulic rods are symmetrically installed on the back side of the auxiliary gates, with the bottom end of the hydraulic rods hinged to the back side of the auxiliary gates and the top end of the hydraulic rods hinged to the back side of the gates, and each hydraulic rod is connected in parallel to a delivery oil pipe, and each delivery oil pipe is connected to an oil pump; a gate lifting assembly is installed on the top surface of the upper dam body; The sealing groove is equipped with a lower sealing plate, and the bottom of the lower sealing plate is equipped with multiple sets of spring rods. In the closed state, the bottom end of the main gate is inserted into the sealing groove; in the flood discharge state, the main gate is lifted, and the spring rods push the lower sealing plate to lift up to seal the sealing groove.
[0006] Furthermore, the first drive assembly includes a first motor, a first rotating rod, a first positioning plate, and a second positioning plate. The first and second positioning plates are positioned opposite each other in the second storage tank. The first and second positioning plates are located inside the separator assembly. A plurality of third screws are horizontally installed above the first and second positioning plates, and a second screw is horizontally installed below the first and second positioning plates. The output end of the first motor is connected to the first screw. The first screw is vertically arranged and located in the second storage tank on the side away from the gate assembly. The first screw and the second screw are vertically meshed and connected, and the first screw and the third screw are movably meshed and connected. The sand-shoveling assembly is threadedly fitted onto the second screw, and the separator assembly is threadedly fitted onto the third screw.
[0007] Furthermore, the sand-shoveling assembly includes a shovel plate, which is horizontally arranged. A first movable seat is provided at the outer end of the surface of the shovel plate, and the first movable seat is threaded onto the second screw. In the closed state, the shovel plate is retracted into the first storage tank, and in the sand-cleaning state, the shovel plate extends out of the first storage tank.
[0008] Furthermore, the separating assembly includes a side sealing plate and a main sealing plate. The main sealing plate and the main gate are arranged parallel to each other. The outer end of the inner side of the main sealing plate is vertically provided with a side sealing plate. The inner wall of the main sealing plate is provided with a plurality of second movable seats, which are threaded onto a third screw. In the closed state, the main sealing plate is retracted into the first storage tank, the side sealing plate blocks the inner opening of the first storage tank, and the shovel is placed below the main sealing plate. In the sand-cleaning state, the side sealing plate and the main sealing plate extend out of the first storage tank, and the side sealing plate, the main sealing plate, and the main gate form a maintenance area.
[0009] Furthermore, one end of the third screw is rotatably embedded in the first translation block, and the other end is rotatably embedded in the second translation block. The first translation block is horizontally slidably embedded in the side of the first positioning plate, and the second translation block is slidably embedded in the side of the second positioning plate. The first drive rod is located on the inner wall of the first positioning plate and is connected to the first translation block. The first moving seat is a movable telescopic structure. In the sand cleaning state, the first drive rod is retracted and the first moving seat is extended, so that the third screw is disengaged from the first rotating rod to ensure that the separating assembly remains stationary. In the maintenance state, the first drive rod is extended and the first moving seat is retracted, so that the third screw is engaged with the first rotating rod.
[0010] Furthermore, the bottom end of the side sealing plate is provided with a second drive rod, the bottom end of the second drive rod is provided with a locking pin, and the outer end of the surface of the sand scraper is provided with a locking hole; in the maintenance state, the second drive rod extends, so that the locking pin is inserted into the locking hole, so that the main sealing plate and the sand scraper extend synchronously, and the scraper blocks the maintenance area from below.
[0011] Furthermore, the sand suction assembly includes an outer casing and side baffles. The bottom of the inner wall of the second side dam has vertically distributed receiving grooves, and the side baffles are slidably embedded inside the receiving grooves. The receiving grooves are located at the inner end of the second storage tank. The outer casing is fixed to the inner outer end of the second storage tank, and the inner side of the outer casing has an open structure. The inner end of the outer casing is connected to the sand suction pump. A first traction assembly is installed on the top of the upper dam, and the first traction assembly is connected to the side baffles. An agitator is installed inside the outer casing. In the closed state, the side baffles block the outer casing. In the sand cleaning state, the side baffles are lifted, and the sand suction pump and agitator operate.
[0012] Furthermore, the outlet of the sand pump is connected to a sand discharge pipe, and the outlet end of the sand discharge pipe is connected to a vibration separation box. The vibration separation box is located on the top of the second side dam. The bottom of the vibration separation box is equipped with a sand discharge pipe and a drainage pipe. The outlet of the drainage pipe extends to the water-facing side of the second side dam through the drainage pipe.
[0013] Furthermore, a second traction assembly is provided at the top of the upper dam body, and vertical guide rails are symmetrically arranged on the water-facing side of the main gate. Each vertical guide rail is equipped with a set of agitating components, including a second motor. The output end of the second motor is connected to agitating blades. In the sand-cleaning state, the agitating blades extend into the redundant sand layer and agitate the redundant sand, so that the redundant sand and water are mixed to form mortar, so that the mortar can enter the outer box under negative pressure. In the maintenance state, the agitating blades are retracted to the upper dam body.
[0014] This invention provides a flood discharge and flow control dike. Compared with the prior art, it has the following advantages: The sand-shoveling component has the following effects: 1.1 When too much river sand accumulates at the bottom of the gate assembly, it can automatically extend to divide the accumulated sand layer, separating the redundant sand layer from the base sand layer. This allows the sand suction component to work without adsorbing the more solidified silt settled at the bottom, only needing to act on the upper redundant sand layer, making the sand suction operation simpler, with higher adsorption accuracy and targeting, and without causing excessive power consumption of the adsorption component; 1.2 During maintenance, the sand-shoveling component can seal the maintenance area from the bottom, keeping the maintenance area closed and preventing external water from entering the maintenance area from the bottom.
[0015] The sand suction component has the following effects: it can actively absorb the sediment at the bottom of the main gate through negative pressure, thereby avoiding excessive accumulation of mud and sand and raising the riverbed. It effectively solves the problem of mud and sand accumulation in front of the gate. At the same time, the sediment can be directly extracted through negative pressure, making cleaning simple and efficient. The partition component has the following effects: when not in use, it can be stored in the first storage tank; when maintenance is required, the partition component can extend to separate the maintenance area, allowing workers to conveniently and quickly inspect the outer surface of the main gate without the need for traditional manual underwater maintenance, and enabling more diverse maintenance operations to be performed regularly. Attached Figure Description
[0016] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0017] Figure 1 A schematic diagram of the vertical structure of the reaction vessel of the present invention is shown; Figure 2 A schematic diagram of the reactor structure in a horizontal state according to the present invention is shown; Figure 3 A schematic diagram of the hanger structure of the present invention is shown; Figure 4A schematic diagram of the support component structure of the present invention is shown; Figure 5 A schematic diagram of the support component structure of the present invention is shown; Figure 6 A schematic diagram of the support component structure of the present invention is shown; Figure 7 A schematic diagram of the support component structure of the present invention is shown; Figure 8 A schematic diagram of the support component structure of the present invention is shown; As shown in the diagram: 11. Upper dam body; 12. Lower dam body; 121. Sealing groove; 122. Sealing plate; 123. Spring rod; 13. First side dam body; 131. First storage tank; 14. Second side dam body; 141. Second storage tank; 2. Gate assembly; 21. Main gate; 22. Auxiliary gate; 23. Hydraulic rod; 24. Oil conveying pipe; 25. Oil pump; 3. Vibration separation box; 4. Sand suction assembly; 41. Outer housing; 42. Side baffle; 43. First traction assembly; 44. Sand pump; 45. Sand discharge pipe; 5. First drive assembly; 5 1. First positioning plate; 52. Second positioning plate; 53. First motor; 54. First screw; 55. Second screw; 56. Third screw; 561. First translation block; 562. Second translation block; 57. First drive rod; 6. Separating assembly; 61. Side sealing plate; 62. Second moving seat; 63. Second drive rod; 64. Locking column; 7. Sand shoveling assembly; 71. Shovel plate; 711. Locking hole; 72. First moving seat; 8. Agitating assembly; 81. Vertical guide rail; 82. Second traction assembly; 83. Second motor; 84. Agitating blade. Detailed Implementation
[0018] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention are described clearly and completely. Obviously, the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention. Example
[0019] To address the technical problems in the background section, the following flood discharge and flow control dam is proposed: Combination Figures 1-8As shown, the present invention provides a flood discharge and flow control dam, including a gate assembly 2. The gate assembly 2 has an upper dam body 11 at the top and a lower dam body 12 at the bottom. A first side dam body 13 is provided on one side of the gate assembly 2 and a second side dam body 14 is provided on the other side. A first storage tank 131 is provided inside the first side dam body 13, and the first storage tank 131 is located on the water-facing side of the gate assembly 2. A second storage tank 141 is provided at the bottom of the second side dam body 14. The inner sides of the first storage tank 131 and the second storage tank 141 are both open structures. A sealing groove 121 is provided in the middle of the top of the lower dam body 12. The bottom end of the gate assembly 2 extends into the sealing groove 121. A stop is provided on the surface of the lower dam body 12. The stop is located on the water-facing side of the gate assembly 2. The bottom end of the gate assembly 2 cooperates with the stop to stop. The first storage tank 131 is equipped with a partition component 6, a sand-shoveling component 7 and a first drive component 5. The sand-shoveling component 7 is located at the bottom of the partition component 6. The sand-shoveling component 7 is installed at the bottom of the second storage tank 141. The sand-shoveling component 4 is located above the sand-shoveling component 7. The bottom water-facing side of the gate component 2 is a sand accumulation layer. The upper layer of the sand accumulation layer is a redundant sand layer. The sand-shoveling component 4 is arranged opposite to the redundant sand layer. The flood discharge device includes the following states: In the closed state, the gate assembly 2 is closed, the separator assembly 6 and the sand-shoveling assembly 7 are received into the first storage tank 131, and the sand-suction assembly 4 is closed and received into the second storage tank 141. During flood discharge, gate assembly 2 rises to carry out flood discharge operations; In the sand-cleaning state, the sand-shoveling component 7 extends out separately, allowing it to be inserted into the sand accumulation layer. The top of the sand-shoveling component 7 is redundant sand accumulation. The sand-suction component 4 is activated to suck out the redundant sand accumulation with negative pressure. In the maintenance state, the flood discharge device first performs sand removal operation. After the redundant accumulated sand is cleaned up, the sand shovel assembly 7 and the partition assembly 6 extend outward simultaneously. The space between the partition assembly 6 and the gate assembly 2 is an open maintenance area, where maintenance personnel can carry out maintenance on the gate assembly 2.
[0020] In the above scheme, The sand-shoveling component 7 has the following effects: 1.1 When too much river sand accumulates at the bottom of the gate component 2, it can automatically extend to divide the accumulated sand layer, separating the redundant sand layer from the base sand layer. This makes it easier for the sand suction component 4 to work without adsorbing the relatively solidified mud and sand settled at the bottom. It only needs to act on the upper redundant sand layer, making the sand suction operation simpler, with higher adsorption accuracy and targeting, and without causing excessive power consumption of the adsorption component; 1.2 During maintenance, the sand-shoveling component 7 can seal the maintenance area from the bottom, keeping the maintenance area closed and preventing external water from entering the maintenance area from the bottom.
[0021] The sand suction component 4 has the following effects: it can actively absorb the sediment at the bottom of the main gate 21 under negative pressure, thereby avoiding excessive accumulation of mud and sand and raising the riverbed. It effectively solves the problem of mud and sand accumulation in front of the gate. At the same time, the sediment can be directly extracted under negative pressure, making cleaning simple and efficient. The partition component 6 has the following effects: when not in use, it can be stored in the first storage tank 131; when maintenance is required, the partition component 6 can extend to separate the maintenance area, allowing workers to conveniently and quickly perform maintenance on the outer surface of the main gate plate 21 without the need for traditional manual underwater maintenance, and allowing for regular maintenance with corrosion-resistant paint spraying.
[0022] In this embodiment, the gate assembly 2 includes a main gate 21, with multiple drainage holes opened inside the upper part of the main gate 21. A secondary gate 22 is rotatably installed inside each drainage hole. Hydraulic rods 23 are symmetrically installed on the back side of the secondary gate 22. The bottom end of the hydraulic rod 23 is hinged to the back side of the secondary gate 22, and the top end of the hydraulic rod 23 is hinged to the back side of the gate. Each hydraulic rod 23 is connected in parallel to a conveying oil pipe 24, and each conveying oil pipe 24 is connected to an oil pump 25. A gate lifting assembly is installed on the top surface of the upper dam body 11. A lower sealing plate is installed inside the sealing groove 121. Multiple sets of spring rods 123 are installed at the bottom of the lower sealing plate. In the closed state, the bottom end of the main gate plate 21 is inserted into the sealing groove 121. In the flood discharge state, the main gate plate 21 is lifted, and the spring rods 123 push the lower sealing plate to lift up, so as to seal the sealing groove 121.
[0023] In the above scheme, When the river water level is too high, the hydraulic rod 23 works to open the auxiliary gate 22, so that the drain hole is opened and the river water is discharged through the drain hole, thus realizing the primary level output. The design of the sealing groove 121 enables the main gate plate 21 to be sealed and stopped, resulting in a better sealing effect of the main gate plate 21. When flood discharge occurs, the spring rod 123 can push the sealing plate 122 upward, thereby blocking the sealing groove 121 and preventing sediment from clogging the sealing groove 121.
[0024] In this embodiment, the first drive assembly 5 includes a first motor 53, a first rotating rod, a first positioning plate 51, and a second positioning plate 52. The first positioning plate 51 and the second positioning plate 52 are positioned opposite each other in the second storage tank 141. The first positioning plate 51 and the second positioning plate 52 are located inside the separator assembly 6. A plurality of third screws 56 are horizontally installed above the first positioning plate 51 and the second positioning plate 52. A second screw 55 is horizontally installed below the first positioning plate 51 and the second positioning plate 52. The output end of the first motor 53 is connected to a first screw 54. The first screw 54 is vertically arranged and located in the second storage tank 141 on the side away from the gate assembly 2. The first screw 54 and the second screw 55 are vertically meshed and connected. The first screw 54 and the third screw 56 are movably meshed and connected. The sand-shoveling assembly 7 is threadedly fitted onto the second screw 55, and the separator assembly 6 is threadedly fitted onto the third screw 56.
[0025] In the above scheme, During sand removal, the separator 6 disengages from the third screw 56, and the first motor 53 drives the third screw 56 to rotate. The third screw 56 then drives the sand-shoveling assembly 7 to extend, thus achieving automatic sand removal.
[0026] During maintenance, the separator assembly 6 engages with the third screw 56, the first motor 53 drives the third screw 56 to rotate, and the third screw 56 drives the sand-shoveling assembly 7 and the separator assembly 6 to extend synchronously.
[0027] In this embodiment, the sand-shoveling assembly 7 includes a shovel plate 71, which is horizontally arranged. A first movable seat 72 is provided at the outer end of the surface of the shovel plate 71, and the first movable seat 72 is threadedly fitted onto the second screw 55. In the closed state, the shovel plate 71 is retracted into the first storage tank 131, and in the sand-cleaning state, the shovel plate 71 extends out of the first storage tank 131.
[0028] In this embodiment, the separating component 6 includes a side sealing plate 61 and a main sealing plate. The main sealing plate and the main gate plate 21 are arranged parallel to each other. The side sealing plate 61 is vertically provided at the outer end of the inner side of the main sealing plate. The inner wall of the main sealing plate is provided with a plurality of second movable seats 62. The second movable seats 62 are threadedly fitted onto the third screw 56. In the closed state, the main sealing plate is retracted into the first storage tank 131, the side sealing plate 61 blocks the inner opening of the first storage tank 131, and the shovel plate 71 is placed below the main sealing plate. In the sand-cleaning state, the side sealing plate 61 and the main sealing plate extend out of the first storage tank 131, and the side sealing plate 61, the main sealing plate and the main gate plate 21 form a maintenance area.
[0029] In the above scheme, Setting up a side sealing plate 61 can form a side seal for the maintenance area and a seal for the opening when the main sealing plate is inserted into the first storage tank 131.
[0030] In this embodiment, one end of the third screw 56 is rotatably embedded in the first translation block 561, and the other end is rotatably embedded in the second translation block 562. The first translation block 561 is horizontally slidably embedded in the side of the first positioning plate 51, and the second translation block 562 is slidably embedded in the side of the second positioning plate 52. The first drive rod 57 is disposed on the inner wall of the first positioning plate 51 and is connected to the first translation block 561. The first moving seat 72 is a movable telescopic structure. In the sand cleaning state, the first drive rod 57 is retracted and the first moving seat 72 is extended, so that the third screw 56 is disengaged from the first rotating rod to ensure that the separating component 6 remains stationary. In the maintenance state, the first drive rod 57 is extended and the first moving seat 72 is retracted, so that the third screw 56 is engaged with the first rotating rod.
[0031] In this embodiment, the bottom end of the side sealing plate 61 is provided with a second drive rod 63, the bottom end of the second drive rod 63 is provided with a locking pin 64, and the outer end of the surface of the sand scraper is provided with a locking hole 711; in the maintenance state, the second drive rod 63 extends, so that the locking pin 64 is inserted into the locking hole 711, so that the main sealing plate and the sand scraper extend synchronously, and the sand scraper 71 blocks the maintenance area from below.
[0032] In the above scheme, the locking pin 64 and the locking hole 711 are designed to work together to ensure that the main sealing plate and the sand-shoveling plate can be moved out synchronously and stably during maintenance. The two can be connected as one unit, which has higher movement stability and stronger water pressure resistance.
[0033] In this embodiment, the sand suction assembly 4 includes an outer casing 41 and a side baffle 42. The bottom of the inner wall of the second side dam 14 is provided with vertically distributed receiving grooves. The side baffle 42 is slidably embedded inside the receiving grooves. The receiving grooves are located at the inner end of the second storage tank 141. The outer casing 41 is fixed to the inner outer end of the second storage tank 141. The inner side of the outer casing 41 is an open structure. The inner end of the outer casing 41 is connected to the sand suction pump 44. A first traction assembly 43 is installed on the top of the upper dam 11. The first traction assembly 43 is connected to the side baffle 42. An agitator is installed inside the outer casing 41. In the closed state, the side baffle 42 blocks the outer casing 41. In the sand cleaning state, the side baffle 42 is lifted, and the sand suction pump 44 and the agitator operate.
[0034] In the above scheme, the first traction component 43 includes a first traction motor and a first traction rope; The side baffle 42 can externally enclose the outer casing 41, preventing water and sand from entering the outer casing 41 when not cleaned, thus effectively protecting the outer casing 41. The design of the stirring rod can agitate the sucked mortar, thereby improving the mortar mixing effect, preventing mortar from clogging the outer casing 41, and accelerating the negative pressure suction effect.
[0035] In this embodiment, the outlet of the sand pump 44 is connected to the sand discharge pipe 45, and the outlet end of the sand discharge pipe 45 is connected to the vibration separation box 3. The vibration separation box 3 is located on the top of the second side dam 14. The bottom of the vibration separation box 3 is provided with the sand discharge pipe 45 and the drainage pipe. The outlet of the drainage pipe extends to the water-facing side of the second side dam 14 through the drainage pipe.
[0036] In the above scheme, The slurry pumped out by the sand pump 44 can be separated by the vibrating separation box 3, thus enabling the direct output of river sand and automatic recycling of river sand, avoiding the waste of redundant river sand; the separated river water can be directly discharged into the river, realizing the complete treatment of recycled river sand.
[0037] Although a stirring rod is installed in the outer casing 41, it is still difficult for the accumulated redundant sand layer to flow into the outer casing 41. To solve this problem, the following solution is proposed: In this embodiment, a second traction assembly 82 is provided on the top of the upper dam body 11, and vertical guide rails 81 are symmetrically provided on the water-facing side of the main gate 21. Each vertical guide rail 81 is equipped with a set of agitating assemblies 8. The agitating assembly 8 includes a second motor 83, and the output end of the second motor 83 is connected to agitating blades 84. In the sand-cleaning state, the agitating blades 84 extend into the redundant sand layer and agitate the redundant sand, so that the redundant sand and water are mixed to form mortar, so that the mortar can enter the outer box 41 under negative pressure. In the maintenance state, the agitating blades 84 are retracted into the upper dam body 11.
[0038] In the above scheme, the second traction component 82 includes a second traction motor and a traction rope; During sand cleaning, the second traction component 82 lowers the agitator component 8, causing the agitator blade 84 to sink into the redundant sand layer. The second motor 83 drives the agitator blade 84 to rotate, thereby mixing the river sand and water to produce mortar, which can then flow quickly into the outer casing 41.
[0039] Working principle and usage process of this invention: In the closed state, the gate assembly 2 is closed, the separator assembly 6 and the sand-shoveling assembly 7 are stored in the first storage tank 131, and the sand-suction assembly 4 is closed and stored in the second storage tank 141. When the river water level is too high, the hydraulic rod 23 works to open the auxiliary gate 22, so that the drain hole is opened and the river water is discharged through the drain hole, realizing the primary level output. The design of the sealing groove 121 can realize the sealing and stopping of the main gate 21, and the sealing effect of the main gate 21 is better. In the flood discharge state, the gate assembly 2 rises to carry out flood discharge operations; when discharging floodwater, the spring rod 123 can push the sealing plate 122 up to block the sealing groove 121 and prevent sediment from clogging the sealing groove 121.
[0040] In the sand-cleaning state, the sand-shoveling component 7 extends out separately, allowing it to be inserted into the sand accumulation layer. The top of the sand-shoveling component 7 is redundant sand accumulation. The sand-suction component 4 is activated to suck out the redundant sand accumulation with negative pressure. The first drive rod 57 retracts, and the first movable seat 72 extends, causing the third screw 56 to disengage from the first rotating rod, so as to ensure that the separating component 6 remains stationary. The first motor 53 drives the third screw 56 to rotate, and the third screw 56 can drive the sand-shoveling component 7 to extend, thereby realizing automatic sand shoveling.
[0041] In the maintenance state, the flood discharge device first performs sand removal operation. After the redundant accumulated sand is cleaned up, the sand shovel assembly 7 and the partition assembly 6 extend outward simultaneously. The space between the partition assembly 6 and the gate assembly 2 is an open maintenance area, where maintenance personnel can carry out maintenance on the gate assembly 2.
[0042] The first drive rod 57 extends, the first movable seat 72 retracts, so that the third screw 56 engages with the first rotating rod, the second drive rod 63 extends, so that the locking pin 64 is inserted into the locking hole 711, so that the main sealing plate and the sand-shoveling plate extend synchronously, and the sand-shoveling plate 71 blocks the maintenance area from below; the first motor 53 drives the third screw 56 to rotate, and the third screw 56 drives the sand-shoveling assembly 7 and the separating assembly 6 to extend synchronously; The second traction component 82 lowers the stirring component 8, causing the stirring blades 84 to sink into the redundant sand layer. The second motor 83 drives the stirring blades 84 to rotate, thereby mixing the river sand and water to produce slurry, which can then flow quickly into the outer casing 41. The side baffle 42 is lifted, and the sand pump 44 and stirring rod are activated. The slurry pumped out by the sand pump 44 can be separated by the vibrating separation box 3, thus enabling the direct output of river sand and automatic recycling of river sand, avoiding the waste of redundant river sand. The separated river water can be directly discharged into the river, achieving complete processing of the recycled river sand.
[0043] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes said element.
[0044] The above embodiments are only used to illustrate the technical solutions of the present invention, and are not intended to limit it. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A flood discharge and flow control embankment, characterized in that: The system includes a gate assembly, which has an upper dam body at the top and a lower dam body at the bottom. The gate assembly has a first side dam body on one side and a second side dam body on the other side. The first side dam body has a first storage tank inside, which is located on the water-facing side of the gate assembly. The second side dam body has a second storage tank at the bottom inside. The inner sides of both the first and second storage tanks are open structures. A sealing groove is provided in the middle of the top of the lower dam body, and the bottom end of the gate assembly extends into the sealing groove. A stop is provided on the surface of the lower dam body, and the stop is located on the water-facing side of the gate assembly. The bottom end of the gate assembly cooperates with the stop to stop. The first storage tank is equipped with a separator, a sand-shoveling assembly, and a first drive assembly. The sand-shoveling assembly is located at the bottom of the separator. The second storage tank is equipped with a sand-suction assembly at the bottom. The sand-suction assembly is located above the sand-shoveling assembly. The bottom water-facing side of the gate assembly is a sand accumulation layer. The upper layer of the sand accumulation layer is a redundant sand layer. The sand-suction assembly is arranged opposite to the redundant sand layer. The flood discharge device includes the following states: In the closed state, the gate assembly is closed, the separating assembly and the sand-shoveling assembly are stored in the first storage tank, and the sand-suction assembly is closed and stored in the second storage tank; During flood discharge, the gate assembly rises to carry out flood discharge operations; In the sand-cleaning state, the sand-shoveling component extends out separately, allowing it to insert into the accumulated sand layer. The top of the sand-shoveling component contains redundant accumulated sand. The sand-suction component then starts working, using negative pressure to suck out the redundant accumulated sand. In the maintenance state, the flood discharge device first performs sand removal operations. After the redundant accumulated sand is cleaned up, the sand shovel assembly and the separation assembly extend outward simultaneously. The space between the separation assembly and the gate assembly is an open maintenance area, where maintenance personnel can perform maintenance on the gate assembly.
2. The flood discharge and flow control embankment according to claim 1, characterized in that: The gate assembly includes a main gate, with multiple drainage holes on the upper part of the main gate. A secondary gate is rotatably installed inside each drainage hole. Hydraulic rods are symmetrically installed on the back side of the secondary gates. The bottom end of the hydraulic rod is hinged to the back of the secondary gate, and the top end of the hydraulic rod is hinged to the back of the gate. Each hydraulic rod is connected in parallel to a delivery oil pipe, and each delivery oil pipe is connected to an oil pump. A gate lifting assembly is installed on the top surface of the upper dam body. The sealing groove is equipped with a lower sealing plate, and the bottom of the lower sealing plate is equipped with multiple sets of spring rods. In the closed state, the bottom end of the main gate is inserted into the sealing groove; in the flood discharge state, the main gate is lifted, and the spring rods push the lower sealing plate to lift up to seal the sealing groove.
3. A flood discharge and flow control embankment according to claim 2, characterized in that: The first drive assembly includes a first motor, a first screw, a first positioning plate, and a second positioning plate. The first and second positioning plates are positioned opposite each other in the second storage tank. The first and second positioning plates are located inside the separator assembly. A plurality of third screws are horizontally installed above the first and second positioning plates, and a second screw is horizontally installed below the first and second positioning plates. The output end of the first motor is connected to the first screw. The first screw is vertically arranged and located in the second storage tank on the side away from the gate assembly. The first screw and the second screw are vertically meshed and connected, and the first screw and the third screw are movably meshed and connected. The sand-shoveling assembly is threadedly fitted onto the second screw, and the separator assembly is threadedly fitted onto the third screw.
4. A flood discharge and flow control embankment according to claim 3, characterized in that: The sand-shoveling assembly includes a shovel plate, which is horizontally arranged. A first movable seat is provided at the outer end of the surface of the shovel plate, and the first movable seat is threaded onto a second screw. In the closed state, the shovel plate is retracted into the first storage tank. In the sand-cleaning state, the shovel plate extends out of the first storage tank.
5. A flood discharge and flow control embankment according to claim 4, characterized in that: The separation assembly includes a side sealing plate and a main sealing plate. The main sealing plate and the main gate are arranged parallel to each other. The outer end of the inner side of the main sealing plate is vertically provided with a side sealing plate. The inner wall of the main sealing plate is provided with multiple second movable seats, which are threaded onto a third screw. In the closed state, the main sealing plate is retracted into the first storage tank, the side sealing plate blocks the inner opening of the first storage tank, and the shovel is placed below the main sealing plate. In the sand-cleaning state, the side sealing plate and the main sealing plate extend out of the first storage tank, and the side sealing plate, the main sealing plate, and the main gate form a maintenance area.
6. A flood discharge and flow control embankment according to claim 5, characterized in that: One end of the third screw is rotatably embedded in the first translation block, and the other end is rotatably embedded in the second translation block. The first translation block is horizontally slidably embedded in the side of the first positioning plate, and the second translation block is slidably embedded in the side of the second positioning plate. The first drive rod is located on the inner wall of the first positioning plate and is connected to the first translation block. The first moving seat is a movable telescopic structure. In the sand-cleaning state, the first drive rod is retracted and the first moving seat is extended, so that the third screw is disengaged from the first rotating rod to ensure that the separating component remains stationary. In the maintenance state, the first drive rod extends and the first moving seat retracts, so that the third screw engages with the first rotating rod.
7. A flood discharge and flow control embankment according to claim 6, characterized in that: The bottom end of the side sealing plate is provided with a second drive rod, and the bottom end of the second drive rod is provided with a locking pin. The outer end of the surface of the sand scraper is provided with a locking hole. In the maintenance state, the second drive rod extends, so that the locking pin is inserted into the locking hole, so that the main sealing plate and the sand scraper extend synchronously, and the scraper blocks the maintenance area from below.
8. A flood discharge and flow control embankment according to claim 7, characterized in that: The sand suction assembly includes an outer casing and side baffles. The bottom of the inner wall of the second side dam has vertically distributed receiving grooves, and the side baffles are slidably embedded inside the receiving grooves. The receiving grooves are located at the inner end of the second storage tank. The outer casing is fixed to the inner outer end of the second storage tank, and the inner side of the outer casing is an open structure. The inner end of the outer casing is connected to a sand pump. A first traction assembly is installed on the top of the upper dam, and the first traction assembly is connected to the side baffles. An agitator is installed inside the outer casing. In the closed state, the side baffles seal the outer casing. In the sand-cleaning state, the side baffles are lifted, and the sand pump and agitator operate.
9. A flood discharge and flow control embankment according to claim 8, characterized in that: The outlet of the sand pump is connected to the sand discharge pipe, and the outlet end of the sand discharge pipe is connected to the vibration separation box. The vibration separation box is located on the top of the second side dam. The bottom of the vibration separation box is equipped with a sand discharge pipe and a drainage pipe. The outlet of the drainage pipe extends to the water-facing side of the second side dam through the drainage pipe.
10. A flood discharge and flow control embankment according to claim 9, characterized in that: The top of the upper dam body is equipped with a second traction assembly, and the water-facing side of the main gate is symmetrically equipped with vertical guide rails. Each vertical guide rail is equipped with a set of agitation assemblies. The agitation assembly includes a second motor, and the output end of the second motor is connected to agitation blades. In the sand-cleaning state, the agitation blades extend into the redundant sand layer and agitate the redundant sand, so that the redundant sand and water are mixed to form mortar, so that the mortar can enter the outer box under negative pressure. In the maintenance state, the agitation blades are retracted to the upper dam body.
Citation Information
Patent Citations
Reservoir flood discharge device
CN116377968A
Water retaining dam for water conservancy and hydropower engineering
CN212200334U