海上浮式结构定位及过缆施工方法

By employing offshore floating structure positioning and cable transfer methods, and utilizing the coordinated operation of multiple force anchors and offshore floating platforms, the positioning accuracy and cable stability issues of ultra-large caissons under ultra-deep water conditions were resolved, achieving efficient and accurate caisson positioning and cable transfer.

CN117602034BActive Publication Date: 2026-07-17CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1

Patent Information

Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD
Filing Date
2024-01-03
Publication Date
2026-07-17

AI Technical Summary

Technical Problem

Under conditions of ultra-deep water and high flow velocity, the positioning accuracy of ultra-large caissons is poor, the cable condition is unstable, the hoisting and connection operation is difficult, and the positioning of the cable is difficult. Existing positioning and cable-passing construction methods cannot meet the accurate positioning requirements of ultra-large caissons.

Method used

The floating platform is positioned and cable-laying is carried out using a floating structure positioning and cable-laying method. Multiple gravity anchors are used to connect the platform to the floating platform. Anchor boats and tugboats work together to connect the anchor cables in a specific sequence and use winches to pull them, so as to achieve precise positioning of the floating platform and cable connection.

Benefits of technology

It achieves efficient and accurate caisson positioning for ultra-large caissons, reduces engineering workload and costs, improves positioning accuracy and cable stability, and simplifies the cable laying process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117602034B_ABST
    Figure CN117602034B_ABST
Patent Text Reader

Abstract

本申请公开一种海上浮式结构定位及过缆施工方法,包括:在低平潮及涨潮期间,将第一重力锚和第三重力锚的锚缆与海上浮式平台相连;在高平潮及退潮期间,将第六重力锚和第七重力锚的锚缆与海上浮式平台相连;在低平潮及涨潮期间,将第二重力锚和第四重力锚的锚缆与海上浮式平台相连;在高平潮及退潮期间,将第五重力锚和第八重力锚的锚缆与海上浮式平台相连;在低平潮及涨潮期间,将第九重力锚和第十重力锚的锚缆与海上浮式平台相连;在高平潮及退潮期间,将第十一重力锚和第十二重力锚的锚缆与海上浮式平台相连。浮运编队包括海上浮式平台、第一拖轮、两个第二拖轮和第三拖轮。该方法能高效顺利地实现海上浮式平台的转缆,使超大沉井顺利准确地进行沉井定位。