套筒式塔吊预埋螺栓固定模具
By using a sleeve-type tower crane pre-embedded bolt fixing mold, the problem of low installation accuracy of tower crane pre-embedded bolts is solved, achieving high-precision installation and improved safety, complying with relevant safety regulations, and featuring a simple structure and low cost.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- ANHUI CONSTRUCTION ENGINEERING SHUNAN EQUIPMENT LEASING CO LTD
- Filing Date
- 2023-12-29
- Publication Date
- 2026-07-17
AI Technical Summary
The low installation accuracy of the pre-embedded bolts in tower cranes leads to installation difficulties and safety risks, which are difficult to effectively solve with existing technologies.
The mold is fixed by pre-embedded bolts of the tower crane using a sleeve-type design. The design of the mold base and the sleeve of the assembly ensures the accuracy of the pre-embedded bolts and allows for segmented disassembly and fine-tuning of the mold, thereby improving installation accuracy and safety.
This improved the installation accuracy of the pre-embedded bolts, reduced safety risks, enabled rapid positioning and reuse, and met the requirements of relevant safety regulations.
Smart Images

Figure CN117605304B_ABST