Tunnel steel pipe yielding support arch device and yielding support arch construction method

By setting cavities and filling them with concrete in the steel pipe arch section and the pressure relief connection joint of the tunnel to form an integral structure, the problem of insufficient compressive strength of the tunnel support structure in soft rock with large deformation is solved, and the support capacity and stability are improved.

CN117605503BActive Publication Date: 2026-11-24SHIJIAZHUANG TIEDAO UNIV +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202311550881.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-20
Publication Date
2026-11-24
Estimated Expiration
2043-11-20

AI Technical Summary

Technical Problem

Existing tunnel support structures lack sufficient compressive strength in soft rock areas with large deformation, making them prone to damage and unable to meet the safety requirements of tunnel construction.

Method used

A tunnel steel pipe pressure relief support arch frame device is designed. By setting cavities in the steel pipe arch frame section and the pressure relief connection joint, and connecting them through a reinforcement channel, concrete is poured to form an integral structure, thereby enhancing the support capacity.

Benefits of technology

It improves the structural strength and stability of the support arch, enabling it to resist the prestress generated by soft rock deformation and ensuring tunnel construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117605503B_ABST
    Figure CN117605503B_ABST
Patent Text Reader

Abstract

This invention provides a tunnel steel pipe pressure-relief support arch device and a construction method for the pressure-relief support arch. The tunnel steel pipe pressure-relief support arch device includes multiple steel pipe arch segments and multiple pressure-relief connecting joints. The multiple steel pipe arch segments and the multiple pressure-relief connecting joints are alternately connected in a ring structure. A first cavity is formed inside each steel pipe arch segment, and a second cavity is formed inside each pressure-relief connecting joint. The first cavity and the second cavity are sequentially connected to form a ring-shaped reinforcement channel, which is filled with concrete. The tunnel steel pipe pressure-relief support arch device provided by this invention has a second cavity within the pressure-relief connecting joint, which is connected to the steel pipe arch segments, allowing the concrete poured into each steel pipe arch segment to form a whole through the second cavity.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of tunnel construction technology, specifically relating to a tunnel steel pipe pressure relief support arch frame device and a pressure relief support arch frame construction method. Background Technology

[0002] Tunnel excavation alters the initial stress state of the surrounding rock. After excavation, the tangential stress of the surrounding rock along the tunnel cross-section increases, while the radial stress decreases to zero. To ensure the stability of the surrounding rock after excavation, a support structure must be constructed quickly to seal the rock and prevent rockfalls. As the surrounding rock deforms after excavation, it gradually forms a pressure arch, which, together with the support structure, forms a composite load-bearing structure to support the load on top of the pressure arch. During the formation of this pressure arch, the initial support structure, completed during rock deformation, must not only provide sufficient support but also deform with the surrounding rock to allow for the gradual release of initial stress and the formation of the supporting pressure arch. Therefore, the tunnel support structure must possess stiffness, strength, stability, and toughness adapted to the deformation of the surrounding rock, and be able to deform accordingly.

[0003] Existing tunnel initial support structures include grid steel frame anchor-sprayed support and I-beam steel frame anchor-sprayed support. Under normal surrounding rock conditions, these initial support structures can meet the requirements. However, in soft rock with large deformation geological conditions, existing support structures are unable to withstand the pressure after soft rock deformation. In severe cases, excessive stress can lead to damage to the support structure, affecting tunnel construction safety. Therefore, it is necessary to develop a new type of steel arch frame device for tunnel initial support that is adaptable to soft rock with large deformation, to meet the requirements for stiffness, strength, deformation, and toughness of tunnel initial support structures in soft rock with large deformation sections. Summary of the Invention

[0004] This invention provides a tunnel steel pipe pressure relief support arch frame device, which aims to solve the technical problem that existing support structures in soft rock with large deformation have insufficient compressive strength and are easily damaged.

[0005] To achieve the above objectives, the technical solution adopted by the present invention is as follows:

[0006] In a first aspect, a tunnel steel pipe pressure relief support arch frame device is provided, comprising multiple steel pipe arch frame segments and multiple pressure relief connection joints, wherein the multiple steel pipe arch frame segments and the multiple pressure relief connection joints are alternately connected to form a ring structure, a first cavity is formed inside the steel pipe arch frame segment, a second cavity is formed inside the pressure relief connection joint, the first cavity and the second cavity are sequentially connected to form a ring-shaped reinforcement channel, and the reinforcement channel is filled with concrete;

[0007] Grouting holes are provided on the bottom section of the steel pipe arch frame and / or the pressure relief connection joint, and grout outlet holes are provided on the top section of the steel pipe arch frame and / or the pressure relief connection joint.

[0008] In conjunction with the first aspect, in one possible implementation, the steel pipe arch segment includes a steel pipe body and a skeleton disposed within the steel pipe body, the steel pipe body forming the first cavity, the skeleton being placed within the first cavity and spaced apart from the steel pipe body.

[0009] In conjunction with the first aspect, in one possible implementation, a connecting pipe is provided between the pressure relief connection joint and the steel pipe arch segment, one end of the connecting pipe is connected to the pressure relief connection joint, and the other end of the connecting pipe is sleeved on the outer periphery of the steel pipe arch segment.

[0010] In conjunction with the first aspect, in one possible implementation, a filling gap is formed between the connecting pipe and the steel pipe arch section, the two ends of the filling gap are closed, and the connecting pipe is provided with an outlet hole and an injection hole on the pipe wall corresponding to the filling gap, the injection hole and the outlet hole respectively communicating with the filling gap.

[0011] In conjunction with the first aspect, in one possible implementation, a sealing plate is provided on one end face of the connecting pipe facing the pressure relief connection joint, one end of the sealing plate is sealed and abuts against the end of the steel pipe arch section, the other end of the sealing plate is fixedly connected to the pressure relief connection joint, and a through hole is provided in the center of the sealing plate, the through hole communicating with the second cavity;

[0012] A first sealing ring is provided between the connecting pipe and the steel pipe arch section, and the first sealing ring and the sealing plate cooperate to seal the filling gap.

[0013] In conjunction with the first aspect, in one possible implementation, the wall of the connecting pipe is hinged to a screw, and a nut is threaded onto the screw;

[0014] The outer circumferential surface of the steel pipe arch frame section is provided with a connecting plate. The connecting plate is provided with a through hole corresponding to the screw. The screw passes through the through hole and is threadedly engaged with the nut. The nut applies a force to the connecting plate toward the connecting pipe.

[0015] In conjunction with the first aspect, in one possible implementation, the pressure-relief connection includes:

[0016] The connector body includes a support plate and four buffer members disposed on the same side of the support plate. The edges of the four buffer members abut against each other in sequence to form a rectangular channel. The abutting edges of the buffer members form buffer grooves. The support plate has a through hole corresponding to the rectangular channel. The other side of the support plate is connected to the corresponding connecting pipe.

[0017] The upper sleeve is fixedly connected at one end to the sealing plate and at the other end to the end face of the buffer component away from the support plate.

[0018] A lower sleeve is fitted around the four buffer members and the outer periphery of the upper sleeve, with one end of the lower sleeve facing the support plate fixedly connected to the support plate; and

[0019] A telescopic tube is disposed within the rectangular channel, with both ends of the telescopic tube extending out of the rectangular channel and respectively connecting to two through holes located at both ends of the telescopic tube, forming the second cavity inside the telescopic tube.

[0020] In conjunction with the first aspect, in one possible implementation, a second sealing ring is provided between the upper sleeve and the lower sleeve.

[0021] In conjunction with the first aspect, in one possible implementation, the steel pipe arch segment is provided with a prestressed channel, and the steel pipe arch segment also includes prestressed tendons, which are inserted into the prestressed channel.

[0022] The tunnel steel pipe pressure relief support arch frame device provided by this invention, compared with the prior art, has a second cavity opened in the pressure relief connection joint. The second cavity and the first cavity in the steel pipe arch frame section are connected to form a reinforcement channel, which connects multiple steel pipe arch frame sections. The concrete poured in each steel pipe arch frame section can form a whole through the reinforcement channel, which increases the structural strength of the support arch frame. The skeleton ensures the structural strength of the steel pipe arch frame section. The concrete forms a circular structure that runs through all steel pipe arch frame sections and the pressure relief connection joint, which greatly improves the support capacity of the support arch frame. It will not deform in soft rock with large deformation and can resist the prestress generated by soft rock deformation.

[0023] Secondly, a method for constructing a pressure-relief arch frame is provided, based on any one of the possible implementations of a tunnel steel pipe pressure-relief arch frame device, characterized by comprising the following steps:

[0024] The steel pipe arch frame section and the pressure relief connection joint are assembled on site to form a support arch frame. The support arch frame is fixed to the surrounding rock surface, and longitudinal connecting steel frames are provided between the support arch frames.

[0025] Concrete is filled into the steel pipe arch section from the grouting hole until concrete flows out of the grout outlet hole of the support arch;

[0026] Spray a protective layer onto the outer perimeter of the support arch frame.

[0027] The tunnel steel pipe pressure-relief support arch frame device provided by the present invention has the following advantages compared with the prior art:

[0028] (1) A second cavity is opened in the pressure relief connection joint. The second cavity and the first cavity in the steel pipe arch frame section are connected to form a reinforcement channel, so that multiple steel pipe arch frame sections are connected. The concrete poured in each steel pipe arch frame section can form a whole through the reinforcement channel, which increases the structural strength of the support arch frame. The skeleton ensures the structural strength of the steel pipe arch frame section. The concrete forms a ring structure that runs through all steel pipe arch frame sections and the pressure relief connection joint, which greatly improves the support capacity of the support arch frame. It will not deform in soft rock with large deformation and can resist the prestress caused by soft rock deformation.

[0029] (2) First, install the steel pipe arch frame section and the pressure relief connection joint to connect the inside of the steel pipe arch frame section and the second cavity of the pressure relief connection joint. The poured concrete can fill the entire reinforcement channel, and the concrete inside the first cavity and the second cavity forms a circular whole. By enhancing the overall structural strength of the concrete, the connection strength of the steel pipe arch frame section and the pressure relief connection joint is improved, and the overall structural stability and structural strength of the support arch frame are improved. In turn, the support arch frame of this application can resist the prestress generated by soft rock deformation, and improve the applicability of the support arch frame. The grouting hole is opened at the bottom of the support arch frame, so that there are no gaps or air bubbles inside the poured concrete, which improves the structural strength of the concrete. Attached Figure Description

[0030] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0031] Figure 1 This is a schematic diagram of the main structure of the tunnel steel pipe pressure relief support arch frame device provided in Embodiment 1 of the present invention;

[0032] Figure 2 This is a schematic diagram showing the pressure exerted by the strata on the top steel pipe arch section used in Embodiment 1 of the present invention.

[0033] Figure 3 This is a schematic cross-sectional view of the steel pipe arch frame section used in Embodiment 1 of the present invention;

[0034] Figure 4 This is a schematic diagram of the assembly of the connecting pipe and the steel pipe arch frame section used in Embodiment 1 of the present invention;

[0035] Figure 5 This is an assembly diagram of the pressure-relief connection joint and connecting pipe used in Embodiment 1 of the present invention;

[0036] Figure 6This is a cross-sectional schematic diagram of the pressure-relief connection joint and connecting pipe used in Embodiment 1 of the present invention;

[0037] Figure 7 This is a schematic cross-sectional view of the connecting pipe used in Embodiment 1 of the present invention;

[0038] Figure 8 This is a schematic diagram of the pressure relief connection joint used in Embodiment 1 of the present invention;

[0039] Figure 9 This is a cross-sectional schematic diagram of the pressure relief connection joint used in Embodiment 1 of the present invention;

[0040] Figure 10 This is a schematic diagram of the structure of the buffer used in Embodiment 1 of the present invention;

[0041] Figure 11 This is a schematic diagram of the main structure of the tunnel steel pipe pressure relief support arch frame device provided in Embodiment 2 of the present invention;

[0042] Figure 12 This is a schematic cross-sectional view of the steel pipe arch frame section used in Embodiment 2 of the present invention;

[0043] Figure 13 This is a cross-sectional view of the steel pipe arch frame section used in Embodiment 3 of the present invention;

[0044] Figure 14 This is an assembly cross-sectional view of the connecting pipe and steel pipe arch frame section used in Embodiment 4 of the present invention;

[0045] Figure 15 This is a cross-sectional view of the pressure relief connection joint used in Embodiment 5 of the present invention.

[0046] Explanation of reference numerals in the attached figures:

[0047] 1. Steel pipe arch frame section; 11. Prestressed channel; 12. Connecting plate; 13. First cavity; 14. Grouting hole; 15. Grout outlet hole;

[0048] 2. Pressure-relief connection joint; 21. Joint body; 211. Support plate; 2111. Perforation; 212. Buffer element; 2121. Buffer groove; 2122. Support plate; 2123. Arc-shaped plate; 22. Upper sleeve; 23. Lower sleeve; 24. Telescopic tube; 241. Second cavity;

[0049] 3. Skeleton;

[0050] 4. Connecting pipe; 41. Injection hole; 42. Sealing plate; 421. Through hole; 43. Screw; 44. Nut; 45. Discharge hole;

[0051] 5. Washer ring;

[0052] 6. First sealing ring;

[0053] 7. Second sealing ring;

[0054] 8. Third sealing ring. Detailed Implementation

[0055] To make the technical problems to be solved, the technical solutions, and the beneficial effects of the present invention clearer, the present invention will be further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present invention and are not intended to limit the present invention.

[0056] It should be noted that the terms "length", "width", "height", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "head", and "tail" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on the invention.

[0057] It should also be noted that, unless otherwise explicitly specified and limited, terms such as "installation," "connection," "linking," "fixing," and "setting" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral part; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; they can refer to the internal communication of two components or the interaction between two components. Those skilled in the art can understand the specific meaning of the above terms in this invention according to the specific circumstances.

[0058] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. Additionally, "multiple" and "several" mean two or more, unless otherwise explicitly specified.

[0059] Please refer to the following: Figures 1 to 15The tunnel steel pipe pressure-relief support arch frame device provided by the present invention will now be described. The tunnel steel pipe pressure-relief support arch frame device includes multiple steel pipe arch frame sections 1 and multiple pressure-relief connection joints 2. The multiple steel pipe arch frame sections 1 and multiple pressure-relief connection joints 2 are alternately connected to form a ring structure. A first cavity 13 is formed inside the steel pipe arch frame section 1, and a second cavity 241 is formed inside the pressure-relief connection joint 2. The first cavity 13 and the second cavity 241 are sequentially connected to form a ring-shaped reinforcement channel, which is filled with concrete. Grouting holes 14 are opened on the bottom steel pipe arch frame section 1 and / or the pressure-relief connection joint 2, and grout outlet holes 15 are opened on the top steel pipe arch frame section 1 and / or the pressure-relief connection joint 2.

[0060] It should be noted that the number of steel pipe arch frame section 1 and pressure relief connection joint 2 is determined based on the tunnel cross-sectional area and the tunnel excavation construction method.

[0061] It should be noted that the positions of the grouting hole 14 and the grout outlet hole 15 in this embodiment are as follows: Figure 1 As shown, the grout outlet 15 is located on the top section of the steel pipe arch frame 1, and the grout injection hole 14 is located on the bottom section of the steel pipe arch frame 1. After the reinforced channel is filled with concrete, the grout injection hole 14 and the grout outlet 15 are sealed.

[0062] In specific implementation, the stress condition of steel pipe arch section 1 is as follows: Figure 2 As indicated by the middle arrow.

[0063] In practice, Figure 1 The steel pipe arch frame section 1 at the top and bottom is long, and its stress under pressure from the surrounding rock above is described in the reference section. Figure 2 As shown by the middle arrow, the steel pipe arch frame section 1 bears the pressure. The connection between the steel pipe arch frame section 1 and the pressure relief connection joint 2 is not directly subjected to the pressure from above, which is conducive to improving the use effect of the support frame.

[0064] In the specific implementation process, please refer to Figure 14 The steel pipes can be square, rectangular, or round. The dimensions of square or rectangular steel pipes and the diameter and wall thickness of round steel pipes are determined according to the stress conditions of the tunnel structure.

[0065] In practice, ordinary high-performance concrete or fiber-reinforced concrete should be selected.

[0066] It should be noted that the concrete grouting path formed by the first cavity 13 and the second cavity 241 is a near-circular shape. After the concrete grouting, the steel pipe arch segment 1, the pressure relief connection joint 2, and the concrete form a steel-concrete composite structural system. The overall structure formed by the concrete connects the steel pipe arch segment 1 and the pressure relief connection joint 2, which greatly improves the overall strength of the structure.

[0067] It should be noted that the concrete is concrete grout, which is poured into the bottom of the support structure formed by the steel pipe arch section 1 and the pressure relief connection joint 2. After the concrete grout solidifies, it connects the steel pipe arch section 1 and the pressure relief connection joint 2.

[0068] Compared with the prior art, the tunnel steel pipe pressure relief support arch device provided in this embodiment has a second cavity 241 opened in the pressure relief connection joint 2. The second cavity 241 and the first cavity 13 in the steel pipe arch section 1 are connected to form a reinforcement channel, so that multiple steel pipe arch sections 1 are connected. The concrete poured in each steel pipe arch section 1 can form a whole through the reinforcement channel, which increases the structural strength of the support arch. The skeleton 3 ensures the structural strength of the steel pipe arch section 1. The concrete forms a ring structure that runs through all the steel pipe arch sections 1 and the pressure relief connection joint 2, which greatly improves the support capacity of the support arch. It will not deform in soft rock with large deformation and can resist the prestress caused by soft rock deformation.

[0069] In some embodiments, the steel pipe arch segment 1 includes a steel pipe body (not shown in the figure) and a frame 3 disposed within the steel pipe body. The steel pipe body forms a first cavity, and the frame 3 is placed within the first cavity and spaced apart from the steel pipe body. The frame 3 has high structural strength and can restrain the concrete, thereby improving the overall integrity of the concrete molding.

[0070] During the assembly process, the frame 3 is welded and fixed to the first cavity so that the frame 3 and the steel pipe body are spaced apart.

[0071] It should be noted that the skeleton 3 is a steel reinforcement skeleton or a steel reinforcement truss. The steel reinforcement skeleton inside the steel pipe arch section 1 can improve the structural strength of the steel pipe arch section 1. The steel reinforcement truss can withstand high-intensity loads and can ensure that the pressure-relief connection joint 2 and the steel pipe arch section 1 do not deform when supporting soft rock with large deformation.

[0072] In practice, the steel truss can be a four-limb longitudinal reinforcement skeleton or a three-limb longitudinal reinforcement skeleton.

[0073] In some embodiments, see Figure 5 and Figure 7 A connecting pipe 4 is provided between the pressure relief joint 2 and the steel pipe arch section 1. One end of the connecting pipe 4 is connected to the pressure relief joint 2, and the other end of the connecting pipe 4 is sleeved on the outer circumference of the steel pipe arch section 1. The connecting pipe 4 is installed between the pressure relief joint 2 and the steel pipe arch section 1, and is fixed to both the pressure relief joint 2 and the steel pipe arch section 1 through the connecting pipe, which facilitates the fixation of the pressure relief joint 2 and the steel pipe arch section 1 and improves the structural strength of the connection between the pressure relief joint 2 and the steel pipe arch section 1.

[0074] In the specific implementation process, such as Figure 5As shown, one pressure relief connector 2 corresponds to two connecting pipes 4. The two connecting pipes 4 are respectively located at both ends of the pressure relief connector 2 and are sleeved on the outer periphery of the corresponding steel pipe connector 2.

[0075] In practice, the shape of the connecting pipe 4 is the same as that of the steel pipe arch frame section 1, and the inner diameter of the connecting pipe 4 is larger than the outer diameter of the steel pipe arch frame section 1, so that the connecting pipe 4 can be fitted around the outer periphery of the steel pipe arch frame section 1.

[0076] In some embodiments, see Figure 4 A filling gap is formed between the connecting pipe 4 and the steel pipe arch section 1. The two ends of the filling gap are closed. The connecting pipe 4 is provided with an outlet hole 45 and an injection hole 41 on the pipe wall corresponding to the filling gap. The injection hole 41 and the outlet hole 45 are respectively connected to the inside of the connecting pipe 4. The outlet hole 45 can maintain the same pressure inside and outside the connecting pipe 4, so that the concrete slurry can be injected into the connecting pipe 4 normally.

[0077] In practice, adhesive cement grout is injected through injection hole 41 to fill the gap between connecting pipe 4 and steel pipe arch frame section 1, as well as the interior of connecting pipe 4, thereby improving the structural strength of connecting pipe 4, increasing the connection strength between pressure-relief connecting joint 2 and steel pipe arch frame section 1, and ensuring the stability of the overall support structure.

[0078] It should be noted that the injection hole 41 and the outlet hole 45 are the same size and are spaced apart along the length of the connecting pipe 4. After the connecting pipe 4 and the steel pipe arch section 1 are inserted and fitted together, the hole at the lower position is the injection hole 41 and the hole at the higher position is the outlet hole 45. The horizontal height of the injection hole 41 is lower than that of the outlet hole 45, so that the injected adhesive cement grout can fill the gap and avoid air bubbles or gaps between the connecting pipe 4 and the steel pipe arch section 1, which would affect the structural strength.

[0079] In some embodiments, see Figure 6 and Figure 7 A sealing plate 42 is provided on one end face of the connecting pipe 4 facing the pressure relief connecting joint 2. One end of the sealing plate 42 is sealed and abuts against the end of the steel pipe arch section 1, and the other end of the sealing plate 42 is fixedly connected to the pressure relief connecting joint 2. A through hole 421 is opened in the center of the sealing plate 42, and the through hole 421 communicates with the second cavity 241. A first sealing ring 6 is provided between the connecting pipe 4 and the steel pipe arch section 1. The first sealing ring 6 and the sealing plate 42 cooperate to seal and fill the gap.

[0080] In this embodiment, the first sealing ring 6 and the sealing plate 42 seal the gaps between the connecting pipe 4 and the steel pipe arch section 1, and between the connecting pipe 4 and the pressure relief connection joint 2, respectively, from both ends inside the connecting pipe 4. On the one hand, this seals the inside of the connecting pipe 4 into a sealed space, facilitating the injection of adhesive cement grout into the connecting pipe 4; on the other hand, it separates the outside from the inside of the connecting pipe 4, preventing the adhesive cement grout inside the connecting pipe 4 from connecting with the curing layer when it is subsequently added, thus avoiding difficulties in the subsequent removal of the support structure. The sealing plate 42 provides a connection position, facilitating the connection and fixation of the connecting pipe 4 and the pressure relief connection joint 2. Simultaneously, the sealing plate 42 prevents the steel pipe arch section 1 from excessively extending into the connecting pipe 4.

[0081] As another way of forming grouting space, see [reference]. Figure 14 A gasket 5 is coaxially connected to the outer periphery of the sealing plate 42. A third sealing ring 8 is sealed between the gasket 5 and the connecting pipe 4, and the third sealing ring 8 and the first sealing ring 6 enclose a grouting space.

[0082] In some embodiments, see Figure 4 A screw 43 is hinged to the wall of the connecting pipe 4, and a nut 44 is threaded onto the screw 43. A connecting plate 12 is provided on the outer circumference of the steel pipe arch section 1. A through hole is provided on the connecting plate 12 corresponding to the screw 43. The screw 43 passes through the through hole and is threadedly engaged with the nut 44. The nut 44 applies a force toward the connecting pipe 4 to the connecting plate 12. The screw 43 and the connecting plate 12 provided in this embodiment cooperate to form a reinforcing assembly. The screw 43 is provided on the connecting pipe 4, and the connecting plate 12 is fixed on the steel pipe arch section 1. The nut 44 limits the connection of the connecting plate 12 from the other end, preventing the steel pipe arch section 1 from detaching from the connecting pipe 4, thereby achieving a fixed connection between the screw 43 and the connecting plate 12 and improving the connection strength between the steel pipe arch section 1 and the connecting pipe 4.

[0083] It should be noted that there are two sets of reinforcement components, which are symmetrically arranged. When the steel pipe arch section 1 abuts against the surrounding rock surface, the side of the steel pipe arch section 1 that is in contact with the surrounding rock surface is provided with a connecting plate 12, and the side of the steel pipe arch section 1 that is away from the surrounding rock surface is provided with a connecting plate 12. The pipe wall of the connecting pipe 4 is provided with two screws 43 corresponding to the two connecting plates 12.

[0084] As another implementation of the reinforcement component, the pipe wall of the connecting pipe 4 is hinged to a fixing rod, the outer periphery of the steel pipe arch section 1 is provided with a first fixing plate, and the end of the fixing rod is provided with a second fixing plate. The first fixing plate is provided with a first through hole, and the second fixing plate is provided with a second through hole corresponding to the first through hole. The first through hole and the second through hole are fixed together by a locking device. The locking device is a connecting lock.

[0085] In some embodiments, see Figure 6 , Figure 8 and Figure 9The pressure connection joint 2 includes a joint body 21, an upper sleeve 22, a lower sleeve 23, and a telescopic tube 24. The connector body 21 includes a support plate 211 and four buffer members 212 disposed on the same side of the support plate 211. The edges of the four buffer members 212 abut against each other in sequence to form a rectangular channel. The abutting edges of the buffer members 212 form buffer grooves 2121. The support plate 211 has a through hole 2111 corresponding to the rectangular channel. The other side of the support plate 211 is connected to the corresponding connecting pipe 4. One end of the upper sleeve 22 is fixedly connected to the sealing plate 42, and the other end is connected to the end face of the buffer member 212 away from the support plate 211. The lower sleeve 23 is sleeved on the outer periphery of the four buffer members 212 and the upper sleeve 22. The end of the lower sleeve 23 facing the support plate 211 is fixedly connected to the support plate 211. The telescopic pipe 24 is disposed in the rectangular channel. The two ends of the telescopic pipe 24 extend out of the rectangular channel and are respectively connected to the through holes 421 on the two connecting pipes 4 located at the two ends of the telescopic pipe 24. A second cavity 241 is formed inside the telescopic pipe 24.

[0086] For specific implementation, please refer to Figure 10 The buffer element 212 includes two support plates 2122 and two arc-shaped plates 2123. The two support plates 2122 are parallel to each other, with the upper surface of the upper support plate 2122 connected to the end face of the upper sleeve 22, and the lower surface of the lower support plate 2122 connected to the support plate 211. The two ends of the arc-shaped plates 2123 are respectively connected to the ends of the two support plates 2122, and the arc-shaped openings of the two arc-shaped plates 2123 are far apart from each other, forming a buffer groove 2121. The two support plates 2122 and the two arc-shaped plates 2123 together form the buffer element 212. The two support plates 2122 are respectively connected to the bottom surface of the upper sleeve 22 and the upper surface of the support plate 211. When the upper sleeve 22 is subjected to a force that moves towards the support plate 211, the arc-shaped plates 2123 are compressed and deformed to counteract the force applied to the upper sleeve 22, achieving a buffering effect. The edges of the support plates 2122 on the same plane abut against each other sequentially.

[0087] In practice, the telescopic tube 24 is a corrugated tube.

[0088] It should be noted that, for reference Figure 6 The two ends of the telescopic pipe 24 are respectively installed on the connecting pipes 4 located on both sides of the pressure relief connection joint 2, and are welded to the sealing plate 42 of the connecting pipe 4 to ensure the connection between the second cavity 241 and the inside of the steel pipe arch section 1.

[0089] It should be noted that the buffer component 212 deforms at the position of the buffer groove 2121 under the action of the upper sleeve 22, thereby offsetting the load energy brought by the surrounding rock.

[0090] The pressure-relief connection joint 2 provided in this embodiment has a simple structure and is easy to manufacture. The buffer member 212 deforms under force, causing the upper sleeve 22 to slide into the lower sleeve 23. The deformation of the buffer member 212 weakens the load energy of the surrounding rock. The support plate 211 supports the lower sleeve 23 and the buffer member 212, and limits the upper sleeve 22 to prevent it from over-extending. The lower sleeve 23 is fitted around the outer periphery of the upper sleeve 22, which can guide the upper sleeve 22 to move along the extension path of the lower sleeve 23 after being stressed, thereby squeezing the buffer member 212 to weaken the load energy brought by the surrounding rock. The telescopic pipe 24 is telescopic and is not affected by the sliding of the upper sleeve 22 and the lower sleeve 23, ensuring the stable formation of the second cavity 241. Rectangular channels extend from both ends of the telescopic pipe 24 to connect the second cavity 241 with the interior of the steel pipe arch frame sections 1 at both ends, thereby enabling the concrete slurry in each steel pipe arch frame section 1 to be connected through the corresponding second cavity 241, so that the concrete slurry solidifies to form a ring concrete component, which improves the structural strength of the support device.

[0091] In some embodiments, see Figure 7 A second sealing ring 7 is provided between the upper sleeve 22 and the lower sleeve 23. The second sealing ring 7 prevents impurities from entering the interior of the lower sleeve 23 from between the upper sleeve 22 and the lower sleeve 23, which would affect the buffer 212 and prevent it from working properly.

[0092] In some embodiments, see Figure 11 The steel pipe arch frame section 1 is provided with a prestressing channel 11, and the steel pipe arch frame section 1 also includes prestressing tendons, which are inserted into the prestressing channel 11. The prestressing tendons can further enhance the structural strength of the support arch frame. After the concrete grout fills and fixes the channel, the prestressing channel 11 is opened. The prestressing tendons placed in the prestressing channel 11 can resist the prestress on the support arch frame.

[0093] In specific implementation, the extension direction of the prestressed channel 11 is as follows: Figure 11 As shown. The prestressing tendons inserted in this direction can extend into the first cavity and the frame 3, enabling the prestressing tendons to resist the force exerted on the support arch frame by the surrounding rock, thereby improving the structural strength of the steel pipe arch frame section 1.

[0094] Based on the same inventive concept, this application also provides a method for constructing a pressure-relief support arch, which is implemented based on the tunnel steel pipe pressure-relief support arch device as described in any of the embodiments, including the following steps: assembling the steel pipe arch section 1 and the pressure-relief connecting joint 2 on site to form a support arch, fixing the support arch to the surrounding rock surface, and providing longitudinal connecting steel frames between the support arches; filling concrete into the steel pipe arch section 1 through the grouting hole 14 until concrete flows out of the grout outlet hole 15 of the support arch; and spraying a protective layer onto the outer periphery of the support arch.

[0095] In practice, the protective layer is a concrete layer. After the support arch is filled with concrete, concrete is sprayed around the outer perimeter of the support arch to enhance the structural strength of the support arch.

[0096] The pressure-relief support arch frame construction method provided in this embodiment has the following advantages compared with the prior art:

[0097] (1) A second cavity 241 is opened in the pressure relief connection joint 2. The second cavity 241 is connected to the steel pipe arch frame section 1, so that multiple steel pipe arch frame sections 1 are connected. The concrete poured in each steel pipe arch frame section 1 can form a whole through the second cavity 241, which increases the structural strength of the support arch frame. The skeleton 3 ensures the structural strength of the steel pipe arch frame section 1. The concrete forms a ring structure that runs through all the steel pipe arch frame sections 1 and the pressure relief connection joint 2, which greatly improves the support capacity of the support arch frame. It will not deform in soft rock with large deformation and can resist the prestress caused by soft rock deformation.

[0098] (2) First, install the steel pipe arch frame section 1 and the pressure relief connection joint 2 to connect the inside of the steel pipe arch frame section 1 and the second cavity 241 of the pressure relief connection joint 2. The poured concrete can fill the entire reinforcement channel, and the concrete inside the first cavity 13 and the second cavity 241 forms a ring. By enhancing the overall structural strength of the concrete, the connection strength between the steel pipe arch frame section 1 and the pressure relief connection joint 2 is improved, and the overall structural stability and structural strength of the support arch frame are improved. In turn, the support arch frame of this application can resist the prestress generated by soft rock deformation, and improve the applicability of the support arch frame. The grouting hole 14 is opened at the bottom of the support arch frame, so that there are no gaps or air bubbles inside the poured concrete, which improves the structural strength of the concrete.

[0099] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, and improvements made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

Claims

1. A tunnel steel pipe pressure relief support arch frame device, characterized in that, It includes multiple steel pipe arch frame segments and multiple pressure relief connection joints. The multiple steel pipe arch frame segments and the multiple pressure relief connection joints are alternately connected to form a ring structure. A first cavity is formed inside the steel pipe arch frame segment, and a second cavity is formed inside the pressure relief connection joint. The first cavity and the second cavity are connected sequentially to form a ring-shaped reinforcement channel. The reinforcement channel is filled with concrete. Grouting holes are provided on the bottom section of the steel pipe arch frame and / or the pressure relief connection joint, and grout outlet holes are provided on the top section of the steel pipe arch frame and / or the pressure relief connection joint. A connecting pipe is provided between the pressure relief connection joint and the steel pipe arch section. One end of the connecting pipe is connected to the pressure relief connection joint, and the other end of the connecting pipe is sleeved on the outer periphery of the steel pipe arch section. A filling gap is formed between the connecting pipe and the steel pipe arch section. The two ends of the filling gap are closed. The connecting pipe is provided with an outlet hole and an injection hole on the pipe wall corresponding to the filling gap. The injection hole and the outlet hole are respectively connected to the filling gap. The connecting pipe is provided with a sealing plate on one end face facing the pressure relief connection joint. One end of the sealing plate is sealed and abuts against the end of the steel pipe arch section. The other end of the sealing plate is fixedly connected to the pressure relief connection joint. A through hole is opened in the center of the sealing plate, and the through hole communicates with the second cavity. A first sealing ring is provided between the connecting pipe and the steel pipe arch section, and the first sealing ring and the sealing plate cooperate to seal the filling gap; The pressure relief connection joint includes a joint body, an upper sleeve, a lower sleeve, and a telescopic tube. The joint body includes a support plate and four buffer members disposed on the same side of the support plate. The buffer includes two parallel support plates and two arc-shaped plates. The two ends of the two arc-shaped plates are respectively connected to the ends of the two support plates, and the arc-shaped openings of the two arc-shaped plates are far apart from each other to form a buffer groove. The upper surface of the upper support plate is connected to the end face of the upper sleeve, and the lower surface of the lower support plate is connected to the support plate; when the upper sleeve is subjected to a force that moves toward the support plate, the arc-shaped plate is squeezed and deformed.

2. The tunnel steel pipe pressure relief support arch frame device as described in claim 1, characterized in that, The steel pipe arch section includes a steel pipe body and a skeleton disposed within the steel pipe body. The steel pipe body forms the first cavity, and the skeleton is placed within the first cavity and spaced apart from the steel pipe body.

3. The tunnel steel pipe pressure relief support arch frame device as described in claim 1, characterized in that, The wall of the connecting pipe is hinged with a screw, and a nut is threaded onto the screw; The outer circumferential surface of the steel pipe arch frame section is provided with a connecting plate. The connecting plate is provided with a through hole corresponding to the screw. The screw passes through the through hole and is threadedly engaged with the nut. The nut applies a force to the connecting plate toward the connecting pipe.

4. The tunnel steel pipe pressure relief support arch frame device as described in claim 1, characterized in that, The edges of the four buffer members abut against each other in sequence to form a rectangular channel. The abutting edges of the buffer members form buffer grooves. The support plate has a through hole corresponding to the rectangular channel. The other side of the support plate is connected to the corresponding connecting pipe. One end of the upper sleeve is fixedly connected to the sealing plate, and the other end is connected to the end face of the buffer component away from the support plate. The lower sleeve is fitted around the four buffer components and the upper sleeve, and the end of the lower sleeve facing the support plate is fixedly connected to the support plate. The telescopic tube is disposed within the rectangular channel, with both ends of the telescopic tube extending out of the rectangular channel and respectively connecting with two through holes located at both ends of the telescopic tube, forming the second cavity inside the telescopic tube.

5. The tunnel steel pipe pressure relief support arch frame device as described in claim 4, characterized in that, A second sealing ring is provided between the upper sleeve and the lower sleeve.

6. The tunnel steel pipe pressure relief support arch frame device as described in claim 1, characterized in that, The steel pipe arch frame section is provided with a prestressing channel, and the steel pipe arch frame section also includes prestressing tendons, which are inserted into the prestressing channel.

7. A method for constructing a pressure-relief support arch, based on the tunnel steel pipe pressure-relief support arch device as described in any one of claims 1 to 6, characterized in that, Includes the following steps: The steel pipe arch frame section and the pressure relief connection joint are assembled on site to form a support arch frame. The support arch frame is fixed to the surrounding rock surface, and longitudinal connecting steel frames are provided between the support arch frames. Concrete is filled into the steel pipe arch section from the grouting hole until concrete flows out from the grout outlet hole of the supporting arch; Spray a protective layer onto the outer perimeter of the support arch frame.