Electric locomotive braking system troubleshooting system and troubleshooting method thereof
By using a road condition simulator and controller system, the vibration road conditions of electric locomotives are simulated, and faults in the braking system of electric locomotives are automatically detected. This solves the problem that it is difficult to accurately and timely detect IPM power-on faults in existing technologies, and improves fault detection efficiency and safety.
Patent Information
- Application Number
- CN202311524281.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-16
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2043-11-16
AI Technical Summary
Existing technologies make it difficult to accurately and promptly diagnose faults when dealing with IPM power-up and penalty braking faults in the CCBⅡ braking system of electric locomotives, which affects locomotive operation and driving safety.
Using a road condition simulator and controller system, the system simulates various road condition vibrations of electric locomotives. Combined with a human-machine interaction module and a communication module, it automatically retrieves the troubleshooting path and gradually checks each component of the braking system, including the external and internal electrical wiring of the brake cabinet, until the fault point is identified.
This improved the accuracy and efficiency of fault diagnosis, reduced the cost of troubleshooting, and ensured the safe operation of electric locomotives.
Smart Images

Figure CN117606827B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of system fault diagnosis technology, specifically to a fault diagnosis system and method for electric locomotive braking systems. Background Technology
[0002] The CCBⅡ braking system of electric locomotives is a network-based electro-pneumatic braking control system. It is an internationally advanced and mature braking control system characterized by high control accuracy, rapid response, high safety, high component integration, and simple maintenance. It is widely used in various types of locomotives both domestically and internationally. The system mainly consists of five parts: Electronic Brake Valve (EBV), Relay Interface Module (RIM), Brake Display Screen (LCDM), Electro-pneumatic Control Unit (EPCU), and Integrated Processor Module (IPM). The IPM acts as the main computer; if it malfunctions or fails during locomotive operation, it will affect the normal operation of the locomotive and even compromise driving safety. Among them, the "IPM power-on, penalty braking: power-on" fault is a difficult and time-consuming fault to handle. It often recovers automatically in a short time after it occurs. In order to ensure driving safety, it is necessary to eliminate the fault in time. Existing technology has little research on the troubleshooting methods for locomotives with this type of fault. The solution adopted on site is to replace the IPM preventively. However, when the fault point is not the IPM, it will lead to the fault not being handled accurately and in time, affecting the operation of the locomotive and even driving safety. Summary of the Invention
[0003] The purpose of this invention is to overcome the deficiencies of the prior art and provide a fault diagnosis system and method for electric locomotive braking systems to solve the problems mentioned in the background art.
[0004] To achieve the above objectives, the technical solution of the present invention is as follows:
[0005] This invention provides a fault diagnosis system for the braking system of an electric locomotive, including a road condition simulator and a controller. A simulation pit is created on the ground, and the road condition simulator is set inside the simulation pit. It includes traction devices symmetrically arranged at both ends of the electric locomotive, a test track, and wheel-bearing devices that fit and support the locomotive wheels. The test track is vertically adjustable within the simulation pit, with its ends extending to connect to the vehicle rails. The wheel-bearing devices include twelve bearing wheels, evenly divided into two groups, symmetrically installed on both sides of the test track via the vibration devices. During road condition simulation, the test track is lowered below the vehicle rail plane, and the wheel surfaces of the bearing wheels are higher than the test track plane. The wheel surfaces of the bearing wheels are L-shaped, with the outer rim higher than the wheel surface. The wheels fit snugly against the L-shaped wheel surface and are secured between the flanges of the two load-bearing wheels. The controller includes a human-machine interface module, a communication module, a road condition plan execution module, and a troubleshooting guidance module. The communication module is connected to the integrated processor module of the electric locomotive, receives fault data from the integrated processor module, and feeds it back to the road condition plan execution module and the troubleshooting guidance module. The road condition plan execution module is electrically connected to the vibration device. The troubleshooting guidance module presets a troubleshooting path and is connected to the human-machine interface module. The road condition plan execution module sends control signals to the vibration device based on the input data from the human-machine interface module. At the same time, the troubleshooting guidance module sends guidance information to the human-machine interface module for display according to the preset troubleshooting path and the input information from the human-machine interface module, and receives feedback data from the communication module to confirm the fault.
[0006] The troubleshooting method using the aforementioned electric locomotive braking system fault diagnosis system includes the following steps:
[0007] A. Preparation; Drive the electric locomotive from the test track onto the road condition simulator, complete the positioning, lower it onto the test track, connect the couplers at both ends of the electric locomotive through the traction device, and lock the longitudinal position of the electric locomotive; The controller connects to the integrated processor module of the electric locomotive through the communication module; Start the electric locomotive.
[0008] B. Fault Reproduction under Vibration Road Condition Simulation: Based on national standards, three vibration levels are preset for the vibration road condition simulation, along with the simulation time for each level. The road condition simulator is started via the human-machine interface module. The vibration device moves up and down according to the vibration frequency, driving the electric locomotive to vibrate. Road condition simulation is performed level by level according to the three vibration levels, and step D (fault troubleshooting and confirmation) is performed step by step. If the power-on fault recurs, the fault information received by the integrated processor module is fed back to the controller's human-machine interface module via the communication module. The troubleshooting guidance module automatically retrieves the preset troubleshooting path and performs fault troubleshooting according to the method in step D. If no power-on fault recurs at any of the three levels, proceed to step C.
[0009] C. Fault reproduction under other road condition simulations; Based on the preset joint road condition simulation and corner road condition simulation data, and their preset simulation time, local vibration and lateral vibration are simulated sequentially. The case where no fault reproduction occurred in step B is continuously simulated. If the fault recurs after power-on, the fault information received by the integrated processor module is fed back to the human-machine interaction module of the controller through the communication module. The troubleshooting guidance module automatically retrieves the preset troubleshooting path and performs fault troubleshooting according to the fault troubleshooting method in step D. If no fault recurs after power-on, it is determined that there is no fault.
[0010] D. Troubleshooting and Confirmation: After the road condition simulator stops vibrating, keep the electric locomotive running during the troubleshooting process. Troubleshoot according to the troubleshooting path, which includes: a) checking the external IPM power supply device and its wiring in the brake cabinet; b) checking the IPM-related wiring inside the brake cabinet; c) replacing the IPM; d) sequentially checking for faults in the relay interface module RIM, LON network cable, EPCU intelligent node module, brake controller EBV, and brake display LCDM node; e) sequentially replacing the relay interface module RIM, LON network cable, EPCU intelligent node module, brake controller EBV, and brake display LCDM; f) replacing the DC110V wiring to temporarily connect the PJB power supply box and control cabinet.
[0011] Fault confirmation method: When a power failure occurs during any of steps a, b, or d, after relevant rectification, the rectification information data is fed back through the human-machine interaction module. The road condition plan execution module automatically repeats the road condition simulation data of the previous fault. If the fault does not reappear, it is determined that the fault has been eliminated after rectification. The road condition plan execution module starts the road condition simulator to repeat steps B to D until all faults are identified.
[0012] If any of steps c, e, or f is performed, the human-machine interaction module provides feedback on rectification information data. The road condition plan execution module automatically repeats the road condition simulation data of the previous fault. If no fault reappears, it is determined that the fault has been eliminated. The road condition plan execution module starts the road condition simulator to repeat steps B to D until all faults are identified. If the fault reappears, the next step is performed.
[0013] E. Offline: After repeated checks confirm that no fault reappears under the road condition simulation in steps B to C, the electric locomotive is deemed to have completed the fault investigation. The investigation guidance module sends the end-of-investigation information to the human-machine interaction module and the road condition scheme execution module, provides a completion prompt, and ends the vibration simulation of the road condition simulator. The electric locomotive is shut down, the control frame rails are returned to their original position, and the communication connection between the controller and the integrated processor module is manually disconnected, causing the couplers at both ends of the electric locomotive to disengage from the traction device, and driving the electric locomotive away from the road condition simulator.
[0014] Preferably, the investigation of the IPM-related electrical circuits inside the brake cabinet in step b includes the connection between the J1 pin of the IPM and the J4 pin of the CJB, the connection between the J6 pin of the IPM and the J1 pin of the RIM, and the connection between the J4 pin of the IPM and the J2 pin of the RIM.
[0015] Compared with existing technologies, the electric locomotive braking system fault diagnosis system of the present invention can provide various road condition simulations for electric locomotives through a road condition simulator, including bumpy road conditions, turning road conditions, and joint road conditions, so as to reproduce power failures and assist troubleshooters in fault diagnosis. With the troubleshooting guidance and road condition simulation support of the fault diagnosis system, through a series of troubleshooting steps, some hidden or covered electrical line faults that cannot be disassembled and replaced in routine maintenance are discovered, and the fault point is finally determined. This method improves the fault diagnosis rate, increases the efficiency of fault diagnosis and handling, reduces the troubleshooting cost, and ensures the safe operation of electric locomotives. Attached Figure Description
[0016] Figure 1 This is an overall structural diagram of the road condition simulator of the present invention;
[0017] Figure 2 This is a topological diagram of the braking system relationships.
[0018] Figure 3 This is a flowchart illustrating the implementation of the fault diagnosis path of the present invention.
[0019] In the diagram: 1. Electric locomotive; 2. Traction device; 3. Track test bench; 4. Road condition simulator; 41. Load-bearing wheel; 42. Vibration device. Detailed Implementation
[0020] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are merely the best embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0021] This embodiment provides a fault diagnosis system for the braking system of an electric locomotive 1, including a road condition simulator 4 and a controller. A simulated pit is created on the ground at the end of the track. The road condition simulator 4 is placed inside the simulated pit and should be equipped with a hydraulic system to supply driving power to the lifting frame and the vibration device 42. The structure of the road condition simulator 4 is as follows: Figure 1As shown, it includes traction devices 2 symmetrically arranged at both ends of the electric locomotive 1 and wheel bearing devices that fit and support the wheels of the electric locomotive 1. The traction devices 2 are connected to the couplers at both ends of the electric locomotive 1, and their traction couplings can be extended and retracted to apply a balancing force at both ends of the electric locomotive 1 to prevent the electric locomotive 1 from deviating from the detection position. The test platform rail 3 is erected on the lifting frame, and its end should be connected to the vehicle rail. When the electric locomotive 1 goes up and down the test platform, the lifting frame drives the test platform rail 3 to return to its original position and rise to be flush with the vehicle rail plane.
[0022] The wheel-bearing device includes a bearing wheel 41 and a vibration device 42 supporting the bearing wheel 41. Twelve bearing wheels 41 are arranged and distributed at corresponding intervals, corresponding to the number of wheels in the electric locomotive 1 car unit. When the electric locomotive 1 is mounted on and dismounted from the test platform, all bearing wheels 41 are at the same support height, and their support plane should be lower than the test platform rail 3 plane. During road condition simulation, the test platform rail 3 is lowered to below the vehicle rail plane, and the wheel surface of the bearing wheel 41 is higher than the test platform rail 3 plane to contact the wheel and ensure no interference occurs during the road condition simulation process. The wheel surface of the bearing wheel 41 is L-shaped, with the outer rim higher than the wheel surface. The wheels on both sides of the electric locomotive 1 are in contact with the L-shaped wheel surface and are confined between the rims of the bearing wheels 41 on both sides. The bearing wheels 41 support the wheels to adapt to road condition simulation when the electric locomotive 1 is in the starting state.
[0023] The controller includes a human-machine interface module, a communication module, a road condition plan execution module, and a troubleshooting guidance module. The communication module can be connected to the integrated processor module of the electric locomotive 1 via a signal data cable or wireless communication protocol. It receives fault data from the integrated processor module and feeds it back to the road condition plan execution module and the troubleshooting guidance module. The vibration device 42 uses an electro-hydraulic lifting mechanism. The road condition plan execution module sends control signals to control the lifting amplitude and frequency of the vibration device 42. The troubleshooting guidance module has a preset troubleshooting path and is connected to the human-machine interface module. The road condition plan execution module sends control signals to the vibration device 42 based on the input data from the human-machine interface module. At the same time, the troubleshooting guidance module sends guidance information to the human-machine interface module for display according to the preset troubleshooting path sequence. It also confirms the fault troubleshooting status based on the input information from the human-machine interface module and triggers the sending of the next guidance information. Simultaneously, it receives feedback data from the communication module to confirm the fault. The road condition plan execution module performs simulation tests based on preset road condition simulation data until it receives fault information data from the communication module, triggering the entry into the next road condition simulation data.
[0024] If, during locomotive operation, the LCDM records "IPM powered on, penalty braking: powered on" and the TCMS display shows "brake malfunction," then high-speed operation should be stopped immediately, and the locomotive should be taken to the nearest maintenance workshop to troubleshoot the problem using the aforementioned electric locomotive 1 braking system fault diagnosis system. The specific troubleshooting method includes the following steps:
[0025] A. Preparation: Drive the electric locomotive 1 from the test track 3 onto the road condition simulator 4, ensuring that the twelve wheels at the bottom of the electric locomotive 1 are directly above the bearing wheels 41. Lower the test track 3 so that the wheel surfaces of the bearing wheels 41 are in contact with the wheels for support, completing the positioning of the electric locomotive 1. Connect the couplers at both ends of the electric locomotive 1 through the traction device 2. The length of the front traction coupling should be exactly adapted to the position of the electric locomotive 1 after positioning. When locking the longitudinal position of the electric locomotive 1, simply retract the rear traction coupling to gradually increase the balance force until the maximum traction force is reached during actual traction. Manually connect the controller and the integrated processor module of the electric locomotive 1 through the communication module. Start the electric locomotive 1 and keep it in the start-up state throughout the entire troubleshooting process.
[0026] B. Fault reproduction under bumpy and vibration road condition simulation; According to the national standard GB / T 21563-2008 "Impact and Vibration Test of Rail Transit Locomotives and Rolling Stock Equipment", there are three vibration levels for the impact and vibration test of locomotives and rolling stock, with level one being the highest and level three being the lowest. The bumpy and vibration road condition simulation conforms to the national vibration test standard. Three vibration levels are set for the vibration road condition simulation, and the single simulation time for each level is preset. If no fault is reproduced within the single simulation time, the simulation proceeds to the next level. The road condition simulator 4 is started through the human-computer interaction module. Combined with the fault troubleshooting method and confirmation in step D, the road condition simulation is carried out step by step from level three to level one to troubleshoot the fault step by step. All the bearing wheels 41 of the vibration device 42 move up and down synchronously according to the vibration frequency law, driving the electric locomotive 1 to vibrate.
[0027] When a power-on fault reappears at a certain vibration level, the fault information received by the integrated processor module is fed back to the human-machine interaction module of the controller through the communication module, reminding the troubleshooting personnel of the fault information. At the same time, the troubleshooting guidance module automatically recalls the preset troubleshooting path and guides the troubleshooting personnel to troubleshoot the fault according to the fault troubleshooting method in step D.
[0028] Bumpy and vibrating road conditions are the main cause of power failure. If no power failure is reproduced in any of the three vibration levels, then proceed to step C to simulate other road conditions.
[0029] C. Fault Reproduction under Other Road Condition Simulations; Based on the preset turning road condition simulation and joint road condition simulation data, and their preset single simulation time, joint road condition simulation and turning road condition simulation are performed sequentially. The turning road condition simulation is used to simulate the lateral vibration generated when the electric locomotive 1 turns and straightens during extreme design curves. When the road condition scheme execution module is controlled, it is achieved by controlling the bearing wheels 41 on both sides to be at different vibration amplitudes. The joint road condition simulation is used to simulate the local vibration generated when the electric locomotive 1 passes through the rail gap. When the road condition scheme execution module is controlled, it is achieved by sequentially increasing the vibration amplitude of each pair of symmetrical bearing wheels. The vibration amplitude of wheel 41 is achieved, and the situation in step B where no fault is reproduced is continuously simulated; if the power failure is reproduced during the joint road condition simulation, the fault information received by the integrated processor module is fed back to the human-machine interaction module of the controller through the communication module. The troubleshooting guidance module automatically retrieves the preset troubleshooting path and performs fault troubleshooting according to the fault troubleshooting method in step D. If no power failure is reproduced during the joint road condition simulation, then the turning road condition simulation is performed. If the power failure is reproduced, then the fault troubleshooting method in step D is performed. If no power failure is reproduced, then it is determined that there is no fault, and step E is performed to take the system offline.
[0030] D. Fault Troubleshooting and Confirmation: Upon receiving a power-on fault message from the communication module, the road condition simulator 4 stops vibrating to facilitate in-vehicle troubleshooting by personnel. During the troubleshooting process, the electric locomotive 1 must remain running. The troubleshooting process should be based on the braking system topology diagram (e.g., ...). Figure 2 As shown), based on the difficulty of troubleshooting and past experience, a pre-set troubleshooting path is established for the troubleshooting guidance module. This module, according to the troubleshooting path, fault information data sent by the communication module, and feedback data from the human-machine interaction module, sequentially triggers the sending of guidance information to the human-machine interaction module. Troubleshooters do not require extensive professional knowledge or experience; they can complete the troubleshooting and rectification by following the guidance information. Figure 3 As shown, according to the troubleshooting sequence, the troubleshooting path is as follows: a) Inspect the external IPM power supply device and its wiring of the brake cabinet, shaking the IPM power supply device to search for faults; b) Inspect the IPM-related wiring inside the brake cabinet, mainly checking the connection lines between IPM pin J1 and CJB pin J4, IPM pin J6 and RIM pin J1, and IPM pin J4 and RIM pin J2; c) Replace the IPM; d) Inspect the relay interface module RIM, LON network cable, EPCU intelligent node module, brake controller EBV, and brake display LCDM node faults in sequence; e) Replace the relay interface module RIM, LON network cable, EPCU intelligent node module, brake controller EBV, and brake display LCDM in sequence; f) Replace the DC110V wiring to temporarily connect the PJB power supply box and control cabinet. It should be noted that the above troubleshooting path is a sequential troubleshooting activity based on fault confirmation and fault rectification. Figure 3As shown; the troubleshooting of lines, nodes, and interfaces includes visual inspection for damage and manual application of external shaking and dragging force to locate the fault point; in addition, for the methods of troubleshooting by replacing components in c, e, and f, if the fault recurs during replacement, it is initially assumed that the component is not faulty and proceeds to the next step of troubleshooting. If the component also has a fault, it will be confirmed through repeated troubleshooting processes, such as... Figure 3 As shown; in addition, the rectification method for fault f is to temporarily rewire to replace the DC110V power line connecting the PJB power box and the control electrical cabinet, and then carry out standardized wiring after the locomotive enters C6 for maintenance.
[0031] Fault Confirmation Method: If a power failure occurs during any step a, b, or d, corresponding rectification should be carried out by re-plugging or reconnecting, replacing damaged connectors, etc. The human-machine interaction module should confirm the completion of the rectification steps and provide feedback on the rectification confirmation data. The road condition plan execution module will automatically repeat the road condition simulation data of the previous fault. If the fault does not reappear, it is determined that the fault has been eliminated after rectification. The road condition plan execution module will start the road condition simulator 4 to repeat steps B to D until all faults are identified.
[0032] When performing any step c, e, or f, if the rectification information data for that step is confirmed through the human-machine interaction module, the road condition plan execution module automatically repeats the road condition simulation data of the previous fault. If no fault recurs, it is determined that the fault has been eliminated, and the road condition plan execution module starts the road condition simulator 4 to repeat steps B to D until all faults are identified. If the fault recurs, the component replacement in the corresponding step is canceled, and the next step is performed according to the guidance information displayed on the human-machine interaction interface.
[0033] E. Offline: After repeated checks confirm that no fault reappears under the road condition simulation in steps B to C, it is determined that the electric locomotive 1 has completed the fault check. The check guidance module sends the end check information to the human-machine interaction module and the road condition scheme execution module, provides a completion prompt, and ends the vibration simulation of the road condition simulator 4. The electric locomotive 1 stops, the control frame rail 3 returns to its original position, and the communication connection between the controller and the integrated processor module is manually disconnected, so that the couplers at both ends of the electric locomotive 1 are uncoupled from the traction device 2, and the electric locomotive 1 is driven away from the road condition simulator 4.
[0034] The directional words "front," "back," "inner," "end," "side," "up," "down," "vertical," and "horizontal" mentioned in this article are based on... Figure 1 The coordinates or orientations shown are not intended to limit the indicated devices, elements, or components to having a particular orientation or to be constructed and operated in a particular orientation.
[0035] Furthermore, in addition to indicating direction or positional relationship, some of the aforementioned terms may also have other meanings. For example, the terms "above" and "inside" may, in certain circumstances, indicate a certain dependency or connection relationship. Those skilled in the art can understand the specific meaning of these terms in this invention based on the specific circumstances.
[0036] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A fault diagnosis system for electric locomotive braking systems, characterized in that, include: A road condition simulator and controller are provided. A simulation pit is created on the ground. The road condition simulator is located within the simulation pit and includes traction devices symmetrically positioned at both ends of an electric locomotive, a test track, and wheel-bearing devices that fit and support the locomotive's wheels. The test track is vertically adjustable within the simulation pit, with its ends extending to connect to the vehicle rails. The wheel-bearing devices include twelve bearing wheels, divided into two groups, symmetrically installed on both sides of the test track via the vibration devices. During road condition simulation, the test track is lowered below the vehicle rail plane, and the wheel surfaces of the bearing wheels are higher than the test track plane. The wheel surfaces of the bearing wheels are L-shaped, with their outer rims higher than the wheel surface. The wheels fit against the L-shaped wheel surfaces and are secured to the sides. The controller comprises a human-machine interface module, a communication module, a road condition plan execution module, and a troubleshooting guidance module. The communication module is connected to the integrated processor module of the electric locomotive, receives fault data from the integrated processor module, and feeds it back to the road condition plan execution module and the troubleshooting guidance module. The road condition plan execution module is electrically connected to the vibration device. The troubleshooting guidance module has a preset troubleshooting path and is connected to the human-machine interface module. The road condition plan execution module sends control signals to the vibration device according to the input data from the human-machine interface module. At the same time, the troubleshooting guidance module sends guidance information to the human-machine interface module for display according to the preset troubleshooting path and the input data from the human-machine interface module, and receives feedback data from the communication module to confirm the fault.
2. A method for troubleshooting electric locomotive braking system fault diagnosis system as described in claim 1, characterized in that, Includes the following steps: A. Preparation; Drive the electric locomotive from the test track onto the road condition simulator, and after positioning, lower it onto the test track. Connect the couplers at both ends of the electric locomotive through the traction device to lock the longitudinal position of the electric locomotive. The controller is connected to the integrated processor module of the electric locomotive via the communication module; The electric locomotive was started; B. Fault Reproduction under Vibration Road Condition Simulation: Based on national standards, three vibration levels are preset for the vibration road condition simulation, along with the simulation time for each level. The road condition simulator is started via the human-machine interface module. The vibration device moves up and down according to the vibration frequency, driving the electric locomotive to vibrate. The road condition simulation is performed level by level according to the three vibration levels, and the fault investigation and confirmation in step D are performed step by step. If the power-on fault recurs, the fault information received by the integrated processor module is fed back to the human-machine interface module of the controller via the communication module. The troubleshooting guidance module automatically retrieves the preset troubleshooting path and performs fault troubleshooting according to the fault troubleshooting method in step D. If no power-on fault recurs in any of the three levels, proceed to step C; C. Fault Reproduction under Other Road Condition Simulations: Based on the preset joint road condition simulation and corner road condition simulation data, and their preset simulation time, local vibration and lateral vibration are simulated sequentially. The case where no fault reproduction occurred in step B is continuously simulated. If the fault recurs after power-on, the fault information received by the integrated processor module is fed back to the human-machine interaction module through the communication module. The troubleshooting guidance module automatically retrieves the preset troubleshooting path and performs fault troubleshooting according to the fault troubleshooting method in step D. If no fault recurs after power-on, it is determined that there is no fault. D. Troubleshooting and Confirmation: The road condition simulator stops vibrating. During the troubleshooting process, the electric locomotive remains powered on. Troubleshooting is carried out sequentially according to the troubleshooting path, which includes: a) troubleshooting the power supply device and wiring of the external IPM (i.e., the integrated processor module) of the brake cabinet; b) troubleshooting the IPM-related wiring inside the brake cabinet; c) replacing the IPM; d) sequentially troubleshooting the relay interface module RIM, LON network cable, EPCU intelligent node module, brake controller EBV, and brake display LCDM node faults; e) sequentially replacing the relay interface module RIM, the LON network cable, the EPCU intelligent node module, the brake controller EBV, and the brake display LCDM; f) replacing the DC110V wiring to temporarily connect the PJB power supply box and the control electrical cabinet. Fault confirmation method: When a power failure occurs during any step a, b, or d, after relevant rectification, the rectification information data is fed back through the human-machine interaction module. The road condition scheme execution module automatically repeats the road condition simulation data of the previous fault. If no fault recurs, it is determined that the fault has been eliminated after rectification. The road condition scheme execution module starts the road condition simulator to repeat steps B to D until all faults are identified. If any step c, e, or f is performed, the human-computer interaction module provides feedback on rectification information data. The road condition plan execution module automatically repeats the road condition simulation data of the previous fault. If no fault recurs, it is determined that the fault has been eliminated. The road condition plan execution module then starts the road condition simulator to repeat steps B to D until all faults are identified. If the fault recurs, the next step is performed. E. Offline: After repeated checks confirm that no fault reappears under the road condition simulation in steps B to C, the electric locomotive is deemed to have completed the fault investigation. The investigation guidance module sends the investigation completion information to the human-machine interaction module and the road condition scheme execution module, provides a completion prompt, and ends the vibration simulation of the road condition simulator. The electric locomotive is shut down, the control frame rails are returned to their original position, and the communication connection between the controller and the integrated processor module is manually disconnected, causing the couplers at both ends of the electric locomotive to disengage from the traction device, and driving the electric locomotive away from the road condition simulator.
3. The fault diagnosis method according to claim 2, characterized in that: The troubleshooting of the IPM-related electrical circuits inside the brake cabinet in step b includes the connection between the J1 pin of the IPM and the J4 pin of the CJB, the connection between the J6 pin of the IPM and the J1 pin of the RIM, and the connection between the J4 pin of the IPM and the J2 pin of the RIM.
Citation Information
Patent Citations
Remote vehicle-mounted troubleshooting and repairing method and system
CN112146885A
Method and device for monitoring abnormality of direct-current circuit of converter
CN112345917A