Construction method of large-span special-shaped steel structure roof
By constructing a 3D model and optimizing the steel structure unit division, combined with BIM technology and hoisting simulation, the problem of difficult steel component installation in the construction of large-span irregular steel structure roofs was solved, achieving an efficient and precise construction process.
Patent Information
- Application Number
- CN202410050881.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-12
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-01-12
AI Technical Summary
During the construction of large-span irregular steel structure roofs, steel components are easily blocked by concrete structures, making normal installation impossible. Setting up roof support lattice columns is difficult, and the lifting radius of hoisting machinery increases, making construction more challenging.
By constructing a 3D model, optimizing the steel structure unit division and weight, using BIM technology for clash detection and finite element analysis, and employing hoisting simulation and micro-rotation technology, combined with adjustable prefabricated support devices, the installation process of the steel structure is precisely controlled.
This solved the collision problem during the installation of steel components, improved installation accuracy and efficiency, and reduced construction difficulty and cost.
Smart Images

Figure CN117627170B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of building construction technology, and specifically relates to a construction method for a large-span irregular steel structure roof. Background Technology
[0002] With the development of construction technology, the architectural shapes of sports stadiums are becoming increasingly novel. The realization of these design concepts relies on the smooth installation of the structure, and the construction difficulty of sports stadiums increases accordingly with changes in the building's structural shape. Large-span irregular-shaped steel structure roof construction is a building construction technology applied in large public buildings, sports stadiums, exhibition halls, and other fields. It has advantages such as flexible structural design, rapid construction, and low construction costs, and therefore has been widely used in modern architecture. The definition of an irregular-shaped steel structure roof refers to the transformation of traditional rectangular or circular shapes into complex irregular structures based on traditional steel structure roofs through design and technical means. This structure can better adapt to the building's shape and functional requirements, while also improving the building's aesthetics and artistry. Irregular-shaped steel structure roofs can be customized according to the building's shape and functional requirements, thus better meeting the building's usage requirements. Compared with traditional steel structure roofs, irregular-shaped steel structure roofs have a faster construction speed, shortening the construction period and reducing construction costs. The construction process of irregular-shaped steel structure roofs is relatively simple, with high material utilization, thus reducing construction costs.
[0003] However, during the construction of existing large-span irregular steel structure roofs, steel components are often blocked by the concrete structure, making normal installation impossible. Setting up roof support lattice columns is difficult, and the lifting radius of hoisting machinery is increased, making construction more challenging. Summary of the Invention
[0004] In view of this, the present invention provides a construction method for large-span irregular steel structure roofs, which can solve the problems that often occur during the construction of existing large-span irregular steel structure roofs, such as steel components being blocked by concrete structures and unable to be installed normally, difficulty in setting up roof support grid columns, and increased lifting radius of hoisting machinery, resulting in high construction difficulty.
[0005] This invention is implemented as follows:
[0006] This invention provides a construction method for a large-span irregular steel structure roof, which includes the following steps;
[0007] S10: Construction personnel construct a three-dimensional model based on the design drawings of the large-span irregular steel structure roof to determine the structure of the large-span irregular steel structure roof;
[0008] S20: Based on the on-site construction conditions and the capacity of the lifting equipment, the construction personnel shall initially determine the number and weight of the steel structure units, optimize the segmentation position of the vertical structure sections, and calculate the strength, stiffness, and stability of the steel structure, thereby optimizing the division of the steel structure units and the processing and installation process of each steel structure unit.
[0009] S30: After moving the processed steel structure units to the construction site of the large-span irregular steel structure roof, the steel structure units are assembled.
[0010] S40: After the assembly is completed, install the first and second column sections;
[0011] S50: Install the internal cantilever truss;
[0012] S60: Install the external cantilever truss;
[0013] S70: Unload temporary supports to complete the construction of the large-span irregular steel structure roof.
[0014] The technical advantages of the construction method for a large-span irregular steel structure roof provided by this invention are as follows: Construction personnel construct a three-dimensional model based on the design drawings of the large-span irregular steel structure roof to determine its structure. Based on site conditions and lifting equipment capabilities, the construction personnel initially determine the number and weight of steel structure units, optimize the segmentation positions of vertical structural sections, and calculate the strength, stiffness, and stability of the steel structure. This optimizes the division of steel structure units and the processing and installation techniques for each unit. After moving the processed steel structure units to the construction site of the large-span irregular steel structure roof, the units are assembled. After assembly, the first and second column sections are installed. The inner cantilever truss is installed. The outer cantilever truss is installed. Temporary supports are unloaded, completing the construction of the large-span irregular steel structure roof. This method solves the problems often encountered in the construction of existing large-span irregular steel structure roofs, such as steel components being blocked by concrete structures, making normal installation impossible, difficulties in setting up roof support lattice columns, and increased lifting radius of hoisting machinery, leading to high construction difficulty.
[0015] Based on the above technical solution, the construction method for a large-span irregular steel structure roof of the present invention can be further improved as follows:
[0016] The construction personnel, based on on-site construction conditions and lifting equipment capabilities, initially determine the number and weight of steel structure units, optimize the segmentation positions of vertical structural sections, and calculate the strength, stiffness, and stability of the steel structure. The specific steps for optimizing the division of steel structure units and the processing and installation technology of each steel structure unit include:
[0017] The first step is for the construction workers to make preliminary divisions of the three-dimensional model of the steel structure roof according to its shape and weight, ensuring that the steel structure units are uniform in shape and have a weight difference of less than 5% after division.
[0018] The second step is for the construction personnel to determine the center of gravity position of each steel structure unit and add counterweights so that the center of gravity position will not shift when the lifting equipment hoists the steel structure unit.
[0019] The third step involves the construction workers conducting hoisting tests on each steel structure unit on the three-dimensional model of the large-span irregular steel structure roof to determine the stability of its stiffness.
[0020] The fourth step involves the construction team using TEKLA software to perform a collision check between the 3D model of the large-span irregular steel structure roof and the concrete structure, thereby optimizing the segmentation positions of the vertical structural sections.
[0021] The fifth step involves construction personnel using finite element software to calculate the structural strength, stiffness, and stability, and then optimizing the processing and installation techniques of the steel structure units based on the calculation results.
[0022] The sixth step involves the construction personnel obtaining the optimal three-dimensional coordinates of the segmented component nodes based on the three-dimensional simulation of the large-span irregular steel structure roof. The overall three-dimensional coordinates are then converted into local three-dimensional coordinates for each segment during assembly, serving as the basis for node positioning and alignment control during segment assembly, thereby accurately controlling the steel structure alignment.
[0023] Furthermore, the specific steps taken by the construction personnel to conduct hoisting tests on each steel structure unit on the three-dimensional model of the large-span irregular steel structure roof to determine its stiffness stability include:
[0024] The first step is for the construction personnel to import the 3D model of each steel structure unit into CATIA software, perform geometric modeling and material property settings for each steel structure unit, and add material properties to the 3D model.
[0025] The second step is for the construction personnel to import the three-dimensional model into ABAQUS software to perform structural strength and stability analysis.
[0026] The third step involves the construction team determining the load and support conditions for each unit based on the model and analysis results, and then conducting tests by simulating the hoisting process.
[0027] The fourth step involves the construction personnel determining the stiffness and stability of each steel structure unit based on the test results, and then making appropriate adjustments and optimizations.
[0028] Furthermore, the construction personnel used TEKLA software to perform collision checks between the 3D model of the large-span irregular steel structure roof and the concrete structure, and the specific steps for optimizing the segment positions of the vertical structure sections included:
[0029] The first step is for the construction workers to open the TEKLA software, create a new project, and import the 3D model of the large-span irregular steel structure roof.
[0030] The second step involves the construction team creating a concrete structure model and associating it with the three-dimensional model of the large-span irregular steel structure roof.
[0031] The third step involves the construction personnel setting collision inspection parameters, including collision type, detection range, and detection accuracy.
[0032] The fourth step involves the construction personnel performing a collision check and reviewing the results. Based on the results, they determine the gap and overlap between the three-dimensional model of the large-span irregular steel structure roof and the concrete structure model.
[0033] The fifth step involves the construction team analyzing the collision results to identify the vertical structural segments that need optimization.
[0034] Furthermore, the specific steps by which the construction personnel determine the center of gravity position of each steel structure unit and apply counterweights to ensure that the center of gravity position does not shift when the lifting equipment hoists the steel structure unit include:
[0035] The first step is to accurately measure each steel structure unit to obtain its size, shape, and mass distribution;
[0036] The second step is to calculate the center of gravity position of each unit based on the measurement results. The center of gravity position refers to the center of mass of all parts of the object.
[0037] The third step is to add weight to each unit based on the calculated center of gravity position, adding a smaller object above the center of gravity position and a larger object below the center of gravity position.
[0038] The fourth step is to measure the steel structure unit again after counterweighting to ensure that its center of gravity position matches the calculated center of gravity position.
[0039] Furthermore, the specific steps for assembling the steel structure units after moving them to the construction site of the large-span irregular steel structure roof include:
[0040] The first step is to pre-set the frame embedding parts on a flat ground, and then arrange the movable flat assembly frame on top. Use thin steel plates to tightly fill the gaps. Use a level to measure the flatness of the four corners and the middle of the movable flat assembly frame to ensure that the movable flat assembly frame is level.
[0041] The second step is to initially adjust the position of the mobile planar assembly frame according to the shape and stress characteristics of the steel structure unit, and install the facade height adjustment device. After the steel structure unit is accurately positioned, use a mounting plate to fix the bottom of the facade height adjustment device and the planar truss beam. Avoid damaging the pulleys and tracks during fixing.
[0042] The third step is to adjust the position of each beam of the movable planar assembly frame according to the size of the steel structure unit, and then adjust the height of the height adjustment device according to the spatial position of the steel structure unit.
[0043] Furthermore, the specific steps for installing the first and second column sections after the assembly are completed include:
[0044] The first step is to hoist the steel structure unit at an angle. The center of gravity of the steel structure unit is selected according to the TEKLA software, the specific position of the lifting lugs is designed according to the length of the slings, and the lifting lugs are welded on both sides of the steel structure unit.
[0045] The second step is to open an elongated hole at the bottom of the steel structure unit, pass the bottom of the steel structure unit through the anchor bolt, and then slowly straighten it by adjusting the hand chain hoist to ensure that the screw rod passes smoothly through the bottom surface of the steel structure unit. After the correction is completed, tighten the anchor bolt nuts to complete the installation of one column section.
[0046] The third step is to use lifting machinery to install the second column section. After installation, the lower part is temporarily fixed to the first column section using clamps.
[0047] Furthermore, the specific steps for installing the internal cantilever truss include:
[0048] The first step is to lay out the positioning lines on the ground, calculate and adjust the height of the non-standard sections of the lattice column in advance according to the installation elevation of the components, and ensure the installation elevation of the upper support.
[0049] The second step involves installing connecting steel plates using rebar anchoring and then using lifting equipment to install the lattice column conversion system into place.
[0050] The third step is to use a level to check the flatness and a total station to check the installation position of the lattice column.
[0051] The fourth step involves using a bracket method to install the internal cantilever truss. Based on the positioning elevation, the height of the non-standard section of the lattice column is adjusted to match the structural elevation. The gap between the lattice column and the internal cantilever truss is filled with thin steel plates. After positioning, the internal cantilever truss is fixed to the two-section column using clamps.
[0052] Furthermore, the specific steps for installing the external cantilever truss include:
[0053] The positions of the inner cantilever truss and the two-section column are adjusted according to the thermal expansion and contraction deformation of the structure itself. Mechanical equipment is used to install the outer cantilever truss, and a total station is used for precision control during the installation.
[0054] Furthermore, the specific steps for unloading the temporary supports and completing the construction of the large-span irregular steel structure roof include:
[0055] Following the principle of unloading the part with the greatest final deformation first, jacks are used in conjunction with steel plate removal. The jacks lift the truss vertically upwards, and the supporting steel plates are removed piece by piece until the entire structure is unloaded.
[0056] Compared with existing technologies, the beneficial effects of the construction method for a large-span irregular steel structure roof provided by this invention are as follows: By utilizing BIM technology, the irregular component hoisting units are rationally divided, and calculations and analyses are performed and compared with theoretical models. This allows for rapid and convenient measurement and inspection of each assembly unit, saving on hoisting machinery and trial-and-error costs, and solving the problems of complex installation processes and difficult precision and quality control for irregular components. The invention employs hoisting simulation and irregular column aerial micro-rotation technology to accurately calculate the tilt angle of the irregular column, the length of each wire rope, and the position of the hoisting points, enabling the irregular column to be lowered at an incline. During hoisting, a hand-operated hoist is used to adjust the column's posture, allowing the column base to smoothly pass through the dense bolts without colliding with the concrete beam, thus solving the problem of collisions between the irregular column and the already installed concrete beam during installation. Furthermore, the invention utilizes a rapid and high-precision positioning construction technology for a double-cantilever single-column structure. By employing a "height-adjustable prefabricated lattice column temporary support conversion device" and an "adjustable support positioning device for steel components," the lattice column can be stably installed on complex ground, achieving rapid and accurate positioning of the double-cantilever single-column structure. Attached Figure Description
[0057] To more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the description of the embodiments of the present invention will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0058] Figure 1 This is a flowchart illustrating the construction method for a large-span, irregularly shaped steel structure roof. Detailed Implementation
[0059] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings.
[0060] like Figure 1 The diagram shows an operation flowchart of a construction method for a large-span irregular steel structure roof provided by the present invention, which includes the following steps;
[0061] S10: Construction workers build a three-dimensional model based on the design drawings of the large-span irregular steel structure roof to determine the structure of the large-span irregular steel structure roof;
[0062] S20: Based on the on-site construction conditions and the capacity of the lifting equipment, the construction personnel initially determine the number and weight of the steel structure units, optimize the segmentation position of the vertical structure sections, and calculate the strength, stiffness, and stability of the steel structure. They also optimize the division of the steel structure units and the processing and installation process of each steel structure unit.
[0063] S30: After moving the processed steel structure units to the construction site of the large-span irregular steel structure roof, the steel structure units are assembled.
[0064] S40: After the assembly is completed, install the first and second column sections;
[0065] S50: Install the internal cantilever truss;
[0066] S60: Install the external cantilever truss;
[0067] S70: Unload temporary supports to complete the construction of the large-span irregular steel structure roof.
[0068] During use, construction personnel build a 3D model based on the design drawings of the large-span irregular steel structure roof to determine its structure. Based on site conditions and lifting equipment capabilities, they initially determine the number and weight of steel structure units, optimize the vertical structural segment positions, and calculate the strength, stiffness, and stability of the steel structure. This optimizes the division of steel structure units and the processing and installation techniques for each unit. After moving the processed steel structure units to the construction site, they assemble them. Following assembly, the first and second column sections are installed; the inner cantilever trusses are installed; the outer cantilever trusses are installed; and temporary supports are removed, completing the construction of the large-span irregular steel structure roof.
[0069] In the aforementioned technical solution, construction personnel, based on on-site construction conditions and lifting equipment capabilities, initially determine the number and weight of steel structure units, optimize the segmentation positions of vertical structural sections, and calculate the strength, stiffness, and stability of the steel structure. The specific steps for optimizing the division of steel structure units and the processing and installation of each unit include:
[0070] The first step is for the construction workers to make preliminary divisions of the three-dimensional model of the steel structure roof according to its shape and weight, ensuring that the steel structure units are uniform in shape and have a weight difference of less than 5%.
[0071] The second step is for the construction workers to determine the center of gravity of each steel structure unit and add counterweights to ensure that the center of gravity does not shift when the lifting equipment hoists the steel structure unit.
[0072] The third step involves the construction team conducting hoisting tests on each steel structure unit on a three-dimensional model of the large-span irregular steel structure roof to determine its stiffness stability.
[0073] The fourth step involves the construction team using TEKLA software to perform a collision check between the 3D model of the large-span irregular steel structure roof and the concrete structure, thereby optimizing the segmentation positions of the vertical structural sections.
[0074] The fifth step involves construction personnel using finite element software to calculate the structural strength, stiffness, and stability, and then optimizing the processing and installation techniques of the steel structure units based on the calculation results.
[0075] The sixth step involves the construction team obtaining the optimal three-dimensional coordinates of the segmented component nodes based on the three-dimensional simulation of the large-span irregular steel structure roof. The overall three-dimensional coordinates are then converted into local three-dimensional coordinates for each segment during assembly, serving as the basis for node positioning and alignment control during segment assembly, thereby accurately controlling the steel structure alignment.
[0076] Furthermore, in the above technical solution, the specific steps for construction personnel to conduct hoisting tests on each steel structure unit on a three-dimensional model of the large-span irregular steel structure roof to determine its stiffness and stability include:
[0077] The first step is for the construction workers to import the 3D model of each steel structure unit into CATIA software, perform geometric modeling and material property settings for each steel structure unit, and add material properties to the 3D model.
[0078] The second step is for the construction workers to import the 3D model into ABAQUS software to perform structural strength and stability analysis.
[0079] The third step involves the construction team determining the load and support conditions for each unit based on the model and analysis results, and then conducting tests by simulating the hoisting process.
[0080] The fourth step involves the construction team determining the stiffness and stability of each steel structure unit based on the test results, and then making appropriate adjustments and optimizations.
[0081] Furthermore, in the above technical solution, the construction personnel used TEKLA software to perform collision checks between the 3D model of the large-span irregular steel structure roof and the concrete structure, and the specific steps for optimizing the segment positions of the vertical structure sections included:
[0082] The first step is for the construction workers to open the TEKLA software, create a new project, and import the 3D model of the large-span irregular steel structure roof.
[0083] The second step is for the construction team to create a concrete structure model and link it with the three-dimensional model of the large-span irregular steel structure roof.
[0084] The third step involves the construction personnel setting collision inspection parameters, including collision type, detection range, and detection accuracy.
[0085] The fourth step is for the construction personnel to run a collision check and check the collision results. Based on the collision results, they determine the gap and overlap between the three-dimensional model of the large-span irregular steel structure roof and the concrete structure model.
[0086] The fifth step involves the construction team analyzing the collision results to identify the vertical structural segments that need optimization.
[0087] Furthermore, in the above technical solution, the specific steps for construction personnel to determine the center of gravity position of each steel structure unit and apply counterweights to ensure that the center of gravity position does not shift when the lifting equipment hoists the steel structure unit include:
[0088] The first step is to accurately measure each steel structure unit to obtain its size, shape, and mass distribution;
[0089] The second step is to calculate the center of gravity position of each unit based on the measurement results. The center of gravity position refers to the center of mass of all parts of the object.
[0090] The third step is to add weight to each unit based on the calculated center of gravity position, adding a smaller object above the center of gravity position and a larger object below the center of gravity position.
[0091] The fourth step is to measure the steel structure unit again after counterweighting to ensure that its center of gravity position matches the calculated center of gravity position.
[0092] Furthermore, in the above technical solution, after moving the fabricated steel structure units to the construction site of the large-span irregular steel structure roof, the specific steps for assembling the steel structure units include:
[0093] The first step is to pre-set the embedded parts of the jig on a flat ground, and then place the movable flat assembly jig on top. Use thin steel plates to tightly fill the gaps. Use a level to measure the flatness of the four corners and the middle of the movable flat assembly jig to ensure that the movable flat assembly jig is level.
[0094] The second step is to initially adjust the position of the movable planar assembly frame according to the shape and stress characteristics of the steel structure unit, and install the facade height adjustment device. After the steel structure unit is accurately positioned, use the mounting plate to fix the bottom of the facade height adjustment device and the planar truss beam. Avoid damaging the pulleys and tracks during fixing.
[0095] The third step is to adjust the position of each beam of the movable planar assembly frame according to the size of the steel structure unit, and then adjust the height of the height adjustment device according to the spatial position of the steel structure unit.
[0096] Furthermore, in the above technical solution, the specific steps for installing the first and second column sections after assembly include:
[0097] The first step is to hoist the steel structure unit at an angle. The center of gravity of the steel structure unit is selected according to the TEKLA software, the specific position of the lifting lugs is designed according to the length of the slings, and the lifting lugs are welded on both sides of the steel structure unit.
[0098] The second step is to open an elongated hole at the bottom of the steel structure unit, pass the bottom of the steel structure unit through the anchor bolts, and then slowly straighten it by adjusting the hand chain hoist to ensure that the screw rod passes smoothly through the bottom surface of the steel structure unit. After the correction is completed, tighten the anchor bolt nuts to complete the installation of one column section.
[0099] The third step is to use lifting machinery to install the second column section. After installation, the lower part is temporarily fixed to the first column section using clamps.
[0100] Furthermore, in the above technical solution, the specific steps for installing the internal cantilever truss include:
[0101] The first step is to lay out the positioning lines on the ground, calculate and adjust the height of the non-standard sections of the lattice column in advance according to the installation elevation of the components, and ensure the installation elevation of the upper support.
[0102] The second step involves installing connecting steel plates using rebar anchoring and then using lifting equipment to install the lattice column conversion system into place.
[0103] The third step is to use a level to check the flatness and a total station to check the installation position of the lattice columns.
[0104] The fourth step involves using a bracket method to install the internal cantilever truss. Based on the positioning elevation, the height of the non-standard section of the lattice column is adjusted to match the structural elevation. The gap between the lattice column and the internal cantilever truss is filled with thin steel plates. After positioning, the internal cantilever truss is fixed to the two-section column using clamps.
[0105] Furthermore, in the above technical solution, the specific steps for installing the external cantilever truss include:
[0106] The positions of the inner cantilever truss and the two-section column are adjusted according to the thermal expansion and contraction deformation of the structure itself. Mechanical equipment is used to install the outer cantilever truss, and a total station is used for precision control during the installation.
[0107] Furthermore, in the above technical solution, the specific steps for unloading the temporary supports and completing the construction of the large-span irregular steel structure roof include:
[0108] Following the principle of unloading the part with the greatest final deformation first, jacks are used in conjunction with steel plate removal. The jacks lift the truss vertically upwards, and the supporting steel plates are removed piece by piece until the entire structure is unloaded.
[0109] Example:
[0110] Based on the on-site construction conditions and the lifting equipment capacity, the number and weight of the steel column hoisting units are initially determined. The hoisting units should be as uniform in shape as possible; if necessary, counterweights should be added to the components to avoid excessive center of gravity offset. After the initial division of the hoisting units, it should be considered whether the stiffness of each unit meets the hoisting conditions; if necessary, additional constraints should be added to ensure the overall stiffness and stability of the hoisting units. The safety of the lattice column support and temporary fixing measures during the gradual installation of each hoisting unit should be considered. The cumulative deformation of each hoisting unit during gradual installation should be considered for the final insertion member. The influence of component dimensions and overall steel column stress; appropriate reinforcement is required at the joints of each unit; a steel structure model is established using TEKLA software, and collision checks are performed with the concrete structure to optimize the segment positions of the vertical structure; structural strength, stiffness, and stability are calculated using finite element software, and the steel structure processing and installation technology is optimized based on the calculation results; the optimal three-dimensional coordinates of the segmented component nodes are obtained from the three-dimensional simulation, and the overall three-dimensional coordinates are transformed into local three-dimensional coordinates for each segment during assembly, serving as the basis for node positioning and alignment control during segment assembly, thereby accurately controlling the steel frame alignment. Embedded parts for the jig or roadbed boxes are pre-installed on a flat ground, and a movable planar assembly jig is placed on top, with thin steel plates used to tightly seal the gaps. The flatness of the four corners and the middle of the jig is measured using a level to ensure the planar jig is level. Based on the shape and stress characteristics of the hoisting unit, the position of the planar truss beams is initially adjusted, and the facade height adjustment device is installed. After the hoisting unit is precisely positioned, the bottom of the facade height adjustment device and the planar truss beams are fixed using clamps, taking care to avoid damage to the pulleys and tracks during fixing. The hoisting unit is assembled in the order of planar component assembly → spatial component assembly. During assembly, the position of each beam of the planar assembly jig is adjusted according to the size of the hoisting unit, and the height of the height adjustment device is adjusted according to the spatial position of the hoisting unit. The two lower beams are placed on the planar jig according to the theoretical position on the drawings, and the two lower beams are temporarily fixed to the jig beams using clamps. The position of the height adjustment device is adjusted according to the position of the spatial beam, and the spatial beam is supported on the lower beam and the height adjustment device. The adjuster on the device is rotated to make fine adjustments to the steel beam, leaving room for welding shrinkage deformation. The distance between each corner point of the spatial hoisting unit and the flatness of the two lower beams are checked using a total station and a level. After the inspection is completed, the hoisting unit fitting components are installed and welded.
[0111] To prevent collisions with the concrete beams during the steel column lifting process, the irregularly shaped column is lifted at an angle. After the column is lifted to a certain height, a 100mm gap must be maintained between them to avoid collisions. Therefore, the column is lifted at a 5° angle along the outer side of the base plate. Based on the Tekla-selected center of gravity of the column, the specific locations of the lifting lugs are designed according to the length of the slings, and lifting lugs are welded to both sides of the column. A truck crane is used for four-point lifting of the column. Two lifting points are set at the top of the column on the side furthest from the concrete beam, and the other two are set on the lifting lugs on both sides of the column. The column is slowly lowered at a 5° outward angle. Since the column cannot be lowered vertically, the anchor bolt holes in the column base plate must be elongated, and the size of the holes needs to be designed based on the actual simulation. After the anchor bolts have completely passed through the column base plate, the column is slowly straightened by adjusting the hand-operated hoist, ensuring that the bolts pass smoothly through the bottom surface of the column base, completing the lifting of the column. After the column base is finally aligned, tighten the anchor bolts and nuts to secure the irregular column. Use lifting machinery to install the two-section column. Once in place, temporarily fix the lower part to the first section using clamps. To ensure construction safety, connect the upper part to the existing structure using pins. The conversion tooling needs to be designed based on the existing structure and undergo technical calculations and verification, especially at the contact points between the conversion tooling and the existing structure. Before pouring the main load-bearing concrete components, pre-embed steel parts for the conversion system, or use rebar to install connecting steel plates. Use lifting equipment to install the lattice column conversion system in place, use a level to check the flatness, and use a total station or measuring tape to verify the installation position of the lattice column. Before installing the lattice column, lay out the positioning lines on the ground. Calculate and adjust the height of the non-standard sections of the lattice column in advance according to the component installation elevation to ensure the installation elevation of the upper support. The bottom section is connected to the base beam via flanges, and fasteners are tightened. After tightening, the standard section and adjusting section are hoisted. Once the standard section is in place, it is immediately secured with pins. The installation of the upper standard section, non-standard section, and top beam section is completed sequentially. Mechanical equipment uses a bracket method to install the inner cantilever truss. Based on the positioning elevation, the height of the non-standard lattice column is adjusted to match the structural elevation. The gap between the lattice column and the inner cantilever truss is filled with thin steel plates. After positioning, the inner cantilever truss is fixed to the second-section column using clamps. The completed structure is fully utilized, and mechanical equipment is used to install the outer cantilever truss. Since the installed structure has already deformed due to its own weight, if the outer cantilever truss is fitted with members according to the installed structure, the internal forces of the structure after installation will not match the design. The positions of the inner cantilever truss and the second-section column are adjusted according to the structure's thermal expansion and contraction. The final outer cantilever truss is installed at an appropriate time, and total station and 3D scanner monitoring technologies are used for precision control during installation.Temporary support unloading follows the principles of "zoning, segmentation, equal quantity, balance, and slowness" to ensure coordinated and balanced stress and deformation of structural components during unloading, gradual changes, and multiple cyclical, incremental descents of the structure to facilitate on-site construction. It also prioritizes unloading the sections with the greatest final deformation first. Unloading is achieved using jacks in conjunction with steel plate removal. During unloading, the jacks vertically lift the truss slightly, removing one steel plate at a time, followed by a slow descent of the jacks, until complete unloading.
[0112] Specifically, the principle of this invention is as follows: Construction personnel construct a three-dimensional model based on the design drawings of the large-span irregular steel structure roof to determine its structure; based on site conditions and lifting equipment capabilities, they preliminarily determine the number and weight of steel structure units, optimize the segmentation positions of vertical structural sections, and calculate the strength, stiffness, and stability of the steel structure, optimizing the division of steel structure units and the processing and installation techniques for each unit; after moving the processed steel structure units to the construction site of the large-span irregular steel structure roof, they assemble the units; after assembly, the first and second column sections are installed; the inner cantilever truss is installed; the outer cantilever truss is installed; temporary supports are unloaded, completing the construction of the large-span irregular steel structure roof.
Claims
1. A construction method for a large-span, irregularly shaped steel structure roof, characterized in that, Includes the following steps: S10: Construction personnel construct a three-dimensional model based on the design drawings of the large-span irregular steel structure roof to determine the structure of the large-span irregular steel structure roof; S20: Based on the on-site construction conditions and the capacity of the lifting equipment, the construction personnel shall initially determine the number and weight of the steel structure units, optimize the segmentation position of the vertical structure sections, and calculate the strength, stiffness, and stability of the steel structure, thereby optimizing the division of the steel structure units and the processing and installation process of each steel structure unit. S30: After moving the processed steel structure units to the construction site of the large-span irregular steel structure roof, the steel structure units are assembled. S40: After the assembly is completed, install the first and second column sections; S50: Install the internal cantilever truss; S60: Install the external cantilever truss; S70: Unload temporary supports to complete the construction of a large-span irregular steel structure roof; The specific steps of S20 include: The first step involves the construction team initially dividing the 3D model of the steel structure roof into sections based on its shape and weight, ensuring that the divided steel structure units have uniform shapes and weight differences of less than 5%. The second step is for the construction personnel to determine the center of gravity position of each steel structure unit and add counterweights so that the center of gravity position will not shift when the lifting equipment hoists the steel structure unit. The third step involves the construction workers conducting hoisting tests on each steel structure unit on the three-dimensional model of the large-span irregular steel structure roof to determine the stability of its stiffness. The fourth step involves the construction team using TEKLA software to perform a collision check between the 3D model of the large-span irregular steel structure roof and the concrete structure, thereby optimizing the segmentation positions of the vertical structural sections. The fifth step involves construction personnel using finite element software to calculate the structural strength, stiffness, and stability, and then optimizing the processing and installation techniques of the steel structure units based on the calculation results. The sixth step involves the construction personnel obtaining the optimal three-dimensional coordinates of the segmented component nodes based on the three-dimensional simulation of the large-span irregular steel structure roof. The overall three-dimensional coordinates are then converted into local three-dimensional coordinates for each segment during assembly, serving as the basis for node positioning and alignment control during segment assembly, thereby accurately controlling the steel structure alignment. The specific steps of the third step in S20 include: The first step is for the construction personnel to import the 3D model of each steel structure unit into CATIA software, perform geometric modeling and material property settings for each steel structure unit, and add material properties to the 3D model. The second step is for the construction personnel to import the three-dimensional model into ABAQUS software to perform structural strength and stability analysis. The third step involves the construction team determining the load and support conditions for each unit based on the model and analysis results, and then conducting tests by simulating the hoisting process. The fourth step involves the construction personnel determining the stiffness and stability of each steel structure unit based on the test results, and then making appropriate adjustments and optimizations accordingly. The specific steps of S50 include: The first step is to lay out the positioning lines on the ground, calculate and adjust the height of the non-standard sections of the lattice column in advance according to the installation elevation of the components, and ensure the installation elevation of the upper support. The second step involves installing connecting steel plates using rebar anchoring and then using lifting equipment to install the lattice column conversion system into place. The third step is to use a level to check the flatness and a total station to check the installation position of the lattice column. The fourth step involves using a bracket method to install the internal cantilever truss. Based on the positioning elevation, the height of the non-standard section of the lattice column is adjusted to match the structural elevation. The gap between the lattice column and the internal cantilever truss is filled with thin steel plates. After positioning, the internal cantilever truss is fixed to the two-section column using clamps. The specific steps of S60 include: The positions of the inner cantilever truss and the two-section column are adjusted according to the thermal expansion and contraction deformation of the structure itself. Mechanical equipment is used to install the outer cantilever truss, and a total station is used for precision control during the installation.
2. The construction method for a large-span irregular steel structure roof according to claim 1, characterized in that, The construction workers used TEKLA software to perform collision checks between the 3D model of the large-span irregular steel structure roof and the concrete structure, and the specific steps for optimizing the segment positions of the vertical structure sections included: The first step is for the construction workers to open the TEKLA software, create a new project, and import the 3D model of the large-span irregular steel structure roof. The second step involves the construction team creating a concrete structure model and associating it with the three-dimensional model of the large-span irregular steel structure roof. The third step involves the construction personnel setting collision inspection parameters, including collision type, detection range, and detection accuracy. The fourth step involves the construction personnel performing a collision check and reviewing the results. Based on the results, they determine the gap and overlap between the three-dimensional model of the large-span irregular steel structure roof and the concrete structure model. The fifth step involves the construction team analyzing the collision results to identify the vertical structural segments that need optimization.
3. The construction method for a large-span irregular steel structure roof according to claim 2, characterized in that, The specific steps by which the construction personnel determine the center of gravity position of each steel structure unit and apply counterweights to ensure that the center of gravity position does not shift when the lifting equipment hoists the steel structure unit include: The first step is to accurately measure each steel structure unit to obtain its size, shape, and mass distribution; The second step is to calculate the center of gravity position of each unit based on the measurement results. The center of gravity position refers to the center of mass of all parts of the object. The third step is to add weight to each unit based on the calculated center of gravity position, adding a smaller object above the center of gravity position and a larger object below the center of gravity position. The fourth step is to measure the steel structure unit again after counterweighting to ensure that its center of gravity position matches the calculated center of gravity position.
4. The construction method for a large-span irregular steel structure roof according to claim 3, characterized in that, The specific steps for assembling the pre-fabricated steel structure units after moving them to the construction site of the large-span irregular steel structure roof include: The first step is to pre-set the frame embedding parts on a flat ground, and then arrange the movable flat assembly frame on top. Use thin steel plates to tightly fill the gaps. Use a level to measure the flatness of the four corners and the middle of the movable flat assembly frame to ensure that the movable flat assembly frame is level. The second step is to initially adjust the position of the mobile planar assembly frame according to the shape and stress characteristics of the steel structure unit, and install the facade height adjustment device. After the steel structure unit is accurately positioned, use a mounting plate to fix the bottom of the facade height adjustment device and the planar truss beam. Avoid damaging the pulleys and tracks during fixing. The third step is to adjust the position of each beam of the movable planar assembly frame according to the size of the steel structure unit, and then adjust the height of the height adjustment device according to the spatial position of the steel structure unit.
5. The construction method for a large-span irregular steel structure roof according to claim 4, characterized in that, The specific steps for installing the first and second column sections after the assembly is completed include: The first step is to tilt and hoist the steel structure unit. The center of gravity of the steel structure unit is selected according to the TEKLA software, the specific position of the lifting lugs is designed according to the length of the slings, and the lifting lugs are welded on both sides of the steel structure unit. The second step is to open an elongated hole at the bottom of the steel structure unit, pass the bottom of the steel structure unit through the anchor bolt, and then slowly straighten it by adjusting the hand chain hoist to ensure that the screw rod passes smoothly through the bottom surface of the steel structure unit. After the correction is completed, tighten the anchor bolt nuts to complete the installation of one column section. The third step is to use lifting machinery to install the second column section. After installation, the lower part is temporarily fixed to the first column section using clamps.
6. The construction method for a large-span irregular steel structure roof according to claim 5, characterized in that, The specific steps for unloading the temporary supports and completing the construction of the large-span irregular steel structure roof include: Following the principle of unloading the part with the greatest final deformation first, jacks are used in conjunction with steel plate removal. The jacks lift the truss vertically upwards, and the supporting steel plates are removed piece by piece until the entire structure is unloaded.
Citation Information
Patent Citations
Construction method for hoisting bridge type crane in high-rise well tower type building
CN103086276A
Construction method of multi-line long span inverted trapezoidal space truss roof system
CN111851746A
Construction method of rose-shaped special-shaped space grid steel structure
CN113431340A
Hoisting construction method for complex large-span steel roof
CN115467421A