Full-automatic supporting installation equipment for tunnel steel arch
By designing a fully automated support and installation device for tunnel steel arch frames, and utilizing hydraulic telescopic rods and a flipping positioning mechanism, the automatic lifting and flipping of the steel arch frames is achieved, solving the problems of high labor intensity and high risk in existing technologies, and improving installation efficiency and safety.
Patent Information
- Application Number
- CN202311439820.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-01
- Publication Date
- 2026-11-20
- Estimated Expiration
- 2043-11-01
AI Technical Summary
The existing steel arch frame installation method is labor-intensive, slow and dangerous, especially in tunnel environments with unstable surrounding rock, where there is a risk of rock falling.
A fully automated support and installation device for tunnel steel arch frames was designed. It utilizes hydraulic telescopic rods, a flipping and positioning mechanism, and a spacing adjustment mechanism to achieve automatic lifting, flipping, and positioning of the steel arch frames, simplifying the installation process.
It reduces labor intensity, improves installation efficiency, reduces the danger of manual operation, and adapts to the installation needs of different steel arch frame diameters.
Smart Images

Figure CN117627686B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of steel arch frame installation technology, and more specifically, to a fully automatic support and installation device for tunnel steel arch frames. Background Technology
[0002] Initial support methods for tunnel engineering include shotcrete and anchor mesh support and steel frame shotcrete and anchor support. If the geological conditions are poor, initial support should adopt steel grid arch frame or steel arch frame shotcrete and anchor support. The steel arch frame is processed in sections at the tunnel outside the tunnel. Before installation, it is transported to the tunnel face excavation site and manually assembled into two sections on the ground. Then it is erected and assembled, welded and positioned with the anchor rods on the excavation face, longitudinal connecting steel bars are installed between the steel frames, steel mesh is installed, and finally initial support concrete is sprayed.
[0003] The existing steel arch frame installation platform only allows workers to climb to the installation position on the inner wall of the tunnel. Then, each steel arch frame segment is manually lifted to the installation position and assembled. This installation method is labor-intensive, slow, and the arch frame installation work surface is the newly excavated section with unstable surrounding rock, which is prone to problems such as falling rock blocks injuring people, making it very dangerous.
[0004] No effective solutions have yet been proposed to address the problems in the relevant technologies. Summary of the Invention
[0005] To address the shortcomings of existing technologies, the purpose of this invention is to propose a fully automated support and installation device for tunnel steel arch frames.
[0006] To achieve the above objectives, the present invention provides a fully automatic support and installation device for tunnel steel arch frames, comprising a support horizontal plate, a hydraulic telescopic rod installed at the top center of the support horizontal plate, a connecting plate connected to the top of the hydraulic telescopic rod, an arc-shaped support frame installed at the top of the connecting plate, reinforcing columns symmetrically connected between the connecting plate and the arc-shaped support frame, two lower support columns movably connected to the bottom of the support horizontal plate, a lower connecting horizontal column between the bottom of the lower support columns, a spacing adjustment mechanism connected to the lower support columns within the lower connecting horizontal column, installation boxes installed at the center of both sides of the lower connecting horizontal column, a moving mechanism installed at the bottom of the installation boxes, a lifting mechanism within the bottom end of the lower support columns, a drive motor connected to one end of the lifting mechanism, and a flipping positioning mechanism connected to the output end of the drive motor.
[0007] Preferably, the bottom of the supporting horizontal plate is symmetrically provided with movable horizontal grooves, and the top of the lower supporting column is integrally connected with a movable block, which is movably installed in the movable horizontal groove.
[0008] Preferably, the spacing adjustment mechanism includes a second drive motor installed on the top of the lower connecting cross column. The lower connecting cross column has openings at both ends, and a gear plate passes through the opening. A gear connected to the gear plate is located at the center of the lower connecting cross column, and a transmission shaft connected to the second drive motor is located at the center of the gear.
[0009] Preferably, the lifting mechanism includes a cavity located within the lower support column, a motor is installed in the cavity, a bearing is provided at the bottom center of the cavity, a threaded rod is connected between the output end of the motor and the inner ring of the bearing, a threaded sleeve is fitted on the external thread of the threaded rod, a strip groove is provided on one side of the cavity, and a connecting column is connected to the drive motor by passing through the strip groove at one end of the threaded sleeve.
[0010] Preferably, the other end of the threaded sleeve is connected to a guide sliding block via a connecting shaft, and a guide sliding groove matching the guide sliding block is provided on one side of the inner wall of the cavity.
[0011] Preferably, the flipping positioning mechanism includes an outer shell with an arched opening through the center of the outer shell. The inner walls of the arched opening are provided with grooves on both sides. A positioning support plate is provided in the groove. The positioning support plate has an arc-shaped surface. A connecting post is provided on the other side of the positioning support plate. The connecting post is connected to an elastic arc-shaped metal plate located at the bottom of the groove.
[0012] Preferably, the positioning support plate is symmetrically provided with fixed blocks, the groove is symmetrically provided with movable blocks, and a support rod is connected between the fixed blocks and the movable blocks.
[0013] Preferably, a return spring is connected between the bottom of the movable block two and the inner bottom of the groove, a T-shaped block is provided on one side of the movable block two, and a T-shaped groove matching the T-shaped block is provided on the inner sidewall of the groove.
[0014] Preferably, the moving mechanism includes an opening two located at the bottom of the mounting box, a hydraulic telescopic rod two installed at the top center of the opening two, a mounting plate movably connected to the bottom end of the hydraulic telescopic rod two, and a traveling wheel installed at the bottom end of the mounting plate via a mounting frame.
[0015] This invention provides a fully automatic support and installation device for tunnel steel arch frames, with the following beneficial effects: A hydraulic telescopic rod is installed at the top center of the supporting horizontal plate. This rod drives the connecting plate and its arc-shaped support frame to rise. The arc-shaped support frame supports the bottom of the steel arch frame, allowing the steel arch frame to continuously rise until it contacts the top of the tunnel. Afterward, it is manually welded and fixed. Two lower support columns are movably connected to the bottom of the supporting horizontal plate. An adjustable spacing mechanism is installed within the lower connecting horizontal column, allowing the spacing between the two lower support columns to be adjusted according to the diameter of different steel arch frames. A movable mechanism located at the bottom of the mounting box facilitates the movement of the entire equipment. The lifting mechanism, which is set up, moves and drives the drive motor and the tilting and positioning mechanism to lift and lower the steel arch frame. In use, the drive motor can drive the tilting and positioning mechanism to complete a 90-degree tilt, so that the steel arch frame is tilted and erected from the ground and is in a vertical state. In conjunction with the arc-shaped support frame, the device of this application has a simple structure and is easy to use. It can effectively adjust the spacing according to the diameter of different steel arch frames to adapt to the support and installation of different steel arch frames. With the tilting and positioning mechanism, the steel arch frame can be positioned and tilted 90 degrees at the same time, so that it can be erected directly from the ground. Finally, it can be used with the hydraulic telescopic rod to complete the lifting and installation work. Attached Figure Description
[0016] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0017] Figure 1 This is a front view of a fully automatic support and installation device for tunnel steel arch frames according to an embodiment of the present invention; Figure 2 This is a schematic diagram of the connection structure of the lower support column in a fully automatic support and installation equipment for tunnel steel arch frames according to an embodiment of the present invention; Figure 3 This is a schematic diagram of the center distance adjustment mechanism of a fully automatic support and installation equipment for tunnel steel arch frames according to an embodiment of the present invention; Figure 4 This is an enlarged view of point A in a fully automatic support and installation device for tunnel steel arch frames according to an embodiment of the present invention; Figure 5 This is a schematic diagram of the lifting mechanism in a fully automatic support and installation device for tunnel steel arch frames according to an embodiment of the present invention; Figure 6 This is a schematic diagram of the flipping and positioning mechanism in a fully automatic support and installation device for tunnel steel arch frames according to an embodiment of the present invention; Figure 7This is a schematic diagram of the moving mechanism in a fully automatic support and installation device for tunnel steel arch frames according to an embodiment of the present invention.
[0018] In the picture: 1. Supporting horizontal plate; 2. Hydraulic telescopic rod one; 3. Connecting plate; 4. Arc-shaped support frame; 5. Reinforcing column; 6. Lower support column; 7. Lower connecting horizontal column; 8. Mounting box; 9. Moving mechanism; 10. Lifting mechanism; 11. Drive motor one; 12. Tilting and positioning mechanism; 13. Movable block one; 14. Movable horizontal groove; 15. Spacing adjustment mechanism; 16. Drive motor two; 17. Opening one; 18. Gear plate; 19. Transmission shaft; 20. Gear; 21. Cavity; 22. Motor; 23. Bearing; 24. Threaded rod; 25. 26. Threaded sleeve; 27. Connecting shaft; 28. Guide sliding block; 29. Guide sliding groove; 30. Strip groove; 31. Connecting column one; 32. Outer shell; 33. Arch frame through-hole; 34. Groove; 35. Positioning support plate; 36. Arc-shaped surface; 37. Connecting column two; 38. Elastic arc-shaped metal plate; 39. Movable block two; 40. Fixed block; 41. Support rod; 42. Return spring; 43. T-shaped block; 44. T-shaped groove; 45. Hydraulic telescopic rod two; 46. Mounting plate; 47. Mounting bracket; 48. Traveling wheel; 49. Opening two. Detailed Implementation
[0019] To make the technical means, creative features, objectives and effects of this invention easier to understand, the invention will be further described below in conjunction with specific embodiments.
[0020] Please see Figure 1-7According to an embodiment of the present invention, a fully automatic support and installation device for a tunnel steel arch frame includes a support plate 1. A hydraulic telescopic rod 2 is installed at the top center of the support plate 1. A connecting plate 3 is connected to the top of the hydraulic telescopic rod 2. An arc-shaped support frame 4 is installed on the top of the connecting plate 3. Reinforcing columns 5 are symmetrically connected between the connecting plate 3 and the arc-shaped support frame 4. By installing the hydraulic telescopic rod 2 at the top center of the support plate 1, the hydraulic telescopic rod 2 drives the connecting plate 3 and the arc-shaped support frame 4 on it to be lifted. The arc-shaped support frame 4 then... The bottom support of the steel arch frame allows it to be continuously lifted upwards until it contacts the top of the tunnel, where it is then manually welded and fixed. Two lower support columns 6 are movably connected to the bottom of the supporting horizontal plate 1. A lower connecting horizontal column 7 is located between the bottom of the lower support columns 6. The lower connecting horizontal column 7 contains a spacing adjustment mechanism 15 connected to the lower support columns 6. The two lower support columns 6 are movably connected to the bottom of the supporting horizontal plate 1, and the spacing adjustment mechanism 15 within the lower connecting horizontal column 7 allows the spacing between the two lower support columns 6 to be adjusted. The spacing of the joints can be adjusted according to the diameter of different steel arch frames. Mounting boxes 8 are installed at the center of both sides of the lower connecting cross column 7. A moving mechanism 9 is installed at the bottom of the mounting box 8, facilitating the movement of the entire equipment. A lifting mechanism 10 is provided at the bottom end of the lower support column 6. One end of the lifting mechanism 10 is connected to a drive motor 11, and the output end of the drive motor 11 is connected to a tilting and positioning mechanism 12. The lifting mechanism 10 moves and drives the drive motor 11 and the tilting and positioning mechanism 12. 2. Lifting and lowering: During use, the drive motor 11 can drive the flipping and positioning mechanism 12 to complete a 90-degree flip, so that the steel arch frame is flipped and erected from the ground and is in a vertical state. In conjunction with the arc-shaped support frame 4, the device of this application has a simple structure and is easy to use. It can effectively adjust the spacing according to the diameter of different steel arch frames to adapt to the support and installation of different steel arch frames. In conjunction with the flipping and positioning mechanism 12, the steel arch frame can be positioned and flipped 90 degrees at the same time, so that it can be erected directly from the ground. Finally, in conjunction with the hydraulic telescopic rod 2, the lifting and installation work is completed.
[0021] In one embodiment, please refer to the appendix to the specification. Figure 2-4As shown, the bottom of the supporting horizontal plate 1 is symmetrically provided with movable horizontal grooves 14. The top of the lower supporting column 6 is integrally connected with a movable block 13, which is movably installed in the movable horizontal groove 14. The spacing adjustment mechanism 15 includes a second drive motor 16 installed on the top of the lower connecting horizontal column 7. The two ends of the lower connecting horizontal column 7 are provided with openings 17, and a gear plate 18 is provided through the openings 17. A gear 20 connected to the gear plate 18 is provided at the center of the lower connecting horizontal column 7. A transmission shaft 19 connected to the second drive motor 16 is provided at the center of the gear 20. The second drive motor 16 drives the gear 20 to rotate, thereby causing the gear plate 18 to extend to both sides simultaneously. In conjunction with the movable block 13 and the movable horizontal groove 14, the lower supporting column 6 expands to both sides simultaneously, thereby increasing the spacing between the flipping positioning mechanisms 12 installed on it, and thus adapting to the use of steel arch frames of different diameters.
[0022] In one embodiment, please refer to the appendix to the specification. Figure 5 As shown, the lifting mechanism 10 includes a cavity 21 located within the lower support column 6. A motor 22 is installed inside the cavity 21. A bearing 23 is located at the center of the bottom of the cavity 21. A threaded rod 24 is connected between the output end of the motor 22 and the inner ring of the bearing 23. A threaded sleeve 25 is threaded onto the external thread of the threaded rod 24. A strip groove 29 is formed on one side of the cavity 21. One end of the threaded sleeve 25 is connected to a connecting column 30 that passes through the strip groove 29 and connects to the drive motor 11. The other end of the threaded sleeve 25 is connected to a guide sliding block 27 via a connecting shaft 26. A guide sliding groove 28 matching the guide sliding block 27 is formed on the inner wall of one side of the cavity 21. The threaded rod 24 is driven to rotate by the motor 22. With the cooperation of the guide sliding block 27 and the guide sliding groove 28, the threaded sleeve 25 is raised and lowered. This causes the connecting column 30 to drive the drive motor 11 to rise and fall. The drive motor 11 then drives the flipping positioning mechanism 12 to rise and fall, and then lowers it to the designated position during use.
[0023] In one embodiment, please refer to the appendix to the specification. Figure 6As shown, the flipping positioning mechanism 12 includes a housing 31. An arched through-hole 32 is provided through the center of the housing 31. Grooves 33 are provided on both sides of the inner wall of the arched through-hole 32. A positioning support plate 34 is provided in the groove 33. An arc-shaped surface 35 is provided on the positioning support plate 34. A connecting column 36 is provided on the other side of the positioning support plate 34. The connecting column 36 is connected to an elastic arc-shaped metal plate 37 located at the bottom of the groove 33. Fixed blocks 39 are symmetrically provided on the positioning support plate 34. Movable blocks 38 are symmetrically provided in the groove 33. A support rod 40 is connected between the fixed block 39 and the movable block 38. A return spring 41 is connected between the bottom of the movable block 38 and the inner bottom of the groove 33. A T-shaped block 42 is provided on one side of the movable block 38. A T-shaped groove 43 matching the T-shaped block 42 is provided on the inner side wall of the groove 33. The two ends of the steel arch frame are inserted through the arch frame through the through-hole 32. The positioning support plate 34, combined with the elasticity of the elastic arc-shaped metal plate 37, provides a certain positioning effect on the two ends of the steel arch frame without affecting its subsequent extraction during lifting. With the help of the arc-shaped surface 35, the positioning support plate 34 will retract inward when the ends of the steel arch frame enter. Since the fixed block 39 and the movable block 38 are connected by the support rod 40, the movable block 38 will descend, causing the return spring 41 to generate a reaction force. The T-shaped block 42 and the T-shaped groove 43 ensure the stability of the descent of the movable block 38.
[0024] In one embodiment, please refer to the appendix to the specification. Figure 7 As shown, the moving mechanism 9 includes an opening 48 located at the bottom of the mounting box 8. A hydraulic telescopic rod 44 is installed at the top center of the opening 48. A mounting plate 45 is movably connected to the bottom end of the hydraulic telescopic rod 44. A traveling wheel 47 is mounted on the bottom end of the mounting plate 45 via a mounting bracket 46. In use, the hydraulic telescopic rod 44 drives the traveling wheel 47 to extend, thereby enabling movement. When not in use, the traveling wheel 47 retracts, ensuring the overall stability of the setup.
[0025] In practical applications, after assembling the various steel arch segments on the ground, a hydraulic telescopic rod 2 is installed at the top center of the supporting horizontal plate 1. The hydraulic telescopic rod 2 drives the connecting plate 3 and the arc-shaped support frame 4 on it to rise. The arc-shaped support frame 4 supports the bottom of the steel arch, thus continuously lifting the steel arch until it contacts the top of the tunnel. Afterward, it is manually welded and fixed. Two lower support columns 6 are movably connected to the bottom of the supporting horizontal plate 1. A spacing adjustment mechanism 15 connected to the lower support columns 6 is provided inside the lower connecting horizontal column 7, allowing the spacing between the two lower support columns 6 to be adjusted according to the diameter of different steel arches. The movable mechanism is located at the bottom of the mounting box 8. Mechanism 9 facilitates the movement of the entire equipment. The lifting mechanism 10 moves and drives the drive motor 11 and the flipping positioning mechanism 12 to lift and lower the equipment. In use, the drive motor 11 can drive the flipping positioning mechanism 12 to complete a 90-degree flip, so that the steel arch frame is flipped and erected from the ground in a vertical state. It works in conjunction with the arc-shaped support frame 4. The device of this application has a simple structure and is easy to use. It can effectively adjust the spacing according to the diameter of different steel arch frames to adapt to the support installation of different steel arch frames. With the flipping positioning mechanism 12, the steel arch frame can be positioned and flipped 90 degrees at the same time, so that it can be erected directly from the ground. Finally, it works in conjunction with the hydraulic telescopic rod 2 to complete the lifting and installation work.
[0026] Although this specification describes embodiments, not every embodiment contains only one independent technical solution. This narrative style is merely for clarity. Those skilled in the art should consider the specification as a whole, and the technical solutions in each embodiment can also be appropriately combined to form other embodiments that can be understood by those skilled in the art.
Claims
1. A fully automatic support and installation device for tunnel steel arch frames, characterized in that, The system includes a supporting horizontal plate (1), a hydraulic telescopic rod (2) installed at the top center of the supporting horizontal plate (1), a connecting plate (3) connected to the top of the hydraulic telescopic rod (2), an arc-shaped support frame (4) installed on the top of the connecting plate (3), reinforcing columns (5) symmetrically connected between the connecting plate (3) and the arc-shaped support frame (4), two lower support columns (6) movably connected to the bottom of the supporting horizontal plate (1), a lower connecting horizontal column (7) provided between the bottoms of the lower support columns (6), a spacing adjustment mechanism (15) connected to the lower support columns (6) provided inside the lower connecting horizontal column (7), and the two sides of the lower connecting horizontal column (7) An installation box (8) is installed at the center, and a moving mechanism (9) is installed at the bottom of the installation box (8). A lifting mechanism (10) is provided at the bottom end of the lower support column (6). One end of the lifting mechanism (10) is connected to a drive motor (11). The output end of the drive motor (11) is connected to a flipping positioning mechanism (12). The spacing adjustment mechanism (15) includes a drive motor (16) installed at the top of the lower connecting column (7). An opening (17) is provided at both ends of the lower connecting column (7). A gear plate (18) is provided through the opening (17). A gear plate (18) is provided at the center of the lower connecting column (7). The gear plate (18) is connected to the gear (20). The center of the gear (20) is provided with a transmission shaft (19) connected to the second drive motor (16). The lifting mechanism (10) includes a cavity (21) located in the lower support column (6). A motor (22) is installed in the cavity (21). A bearing (23) is provided at the bottom center of the cavity (21). A threaded rod (24) is connected between the output end of the motor (22) and the inner ring of the bearing (23). A threaded sleeve (25) is threaded on the outer thread of the threaded rod (24). A strip groove (29) is opened on one side of the cavity (21). The threaded sleeve (25) One end is connected to a connecting post (30) that passes through the strip groove (29) and connects to the drive motor (11). The flipping positioning mechanism (12) includes an outer shell (31). An arch frame through-hole (32) is provided through the center of the outer shell (31). Grooves (33) are provided on both sides of the inner wall of the arch frame through-hole (32). A positioning support plate (34) is provided in the groove (33). An arc surface (35) is provided on the positioning support plate (34). A connecting post (36) is provided on the other side of the positioning support plate (34). The connecting post (36) is connected to an elastic arc-shaped metal plate (37) located at the bottom of the groove (33).
2. The fully automatic support and installation equipment for tunnel steel arch frames according to claim 1, characterized in that, The bottom of the support plate (1) is symmetrically provided with movable horizontal grooves (14), and the top of the lower support column (6) is integrally connected with a movable block (13), which is movably installed in the movable horizontal groove (14).
3. The fully automatic support and installation equipment for tunnel steel arch frames according to claim 2, characterized in that, The other end of the threaded sleeve (25) is connected to a guide sliding block (27) via a connecting shaft (26), and a guide sliding groove (28) matching the guide sliding block (27) is provided on one side of the inner wall of the cavity (21).
4. The fully automatic support and installation equipment for tunnel steel arch frames according to claim 3, characterized in that, The positioning support plate (34) is symmetrically provided with fixed blocks (39), and the groove (33) is symmetrically provided with movable blocks (38). A support rod (40) is connected between the fixed blocks (39) and the movable blocks (38).
5. The fully automatic support and installation equipment for tunnel steel arch frames according to claim 4, characterized in that, A reset spring (41) is connected between the bottom of the movable block 2 (38) and the inner bottom of the groove (33). A T-shaped block (42) is provided on one side of the movable block 2 (38), and a T-shaped groove (43) matching the T-shaped block (42) is provided on the inner side wall of the groove (33).
6. The fully automatic support and installation equipment for tunnel steel arch frames according to claim 5, characterized in that, The moving mechanism (9) includes an opening two (48) located at the bottom of the mounting box (8). A hydraulic telescopic rod two (44) is installed at the top center of the opening two (48). The bottom end of the hydraulic telescopic rod two (44) is movably connected to a mounting plate (45). The bottom end of the mounting plate (45) is equipped with a traveling wheel (47) through a mounting bracket (46).
Citation Information
Patent Citations
Novel multi-functional operation trolley used for tunnel construction
CN107514264A
Tunnel vault steel arch frame mounting machine for existing railway tunnel disease repairing
CN202926344U