A method for intelligent management and control of waste heat power generation in a steel enterprise
By using intelligent management and control methods to automatically monitor and control the turbine startup process, remote one-button startup of waste heat power generation turbines in steel enterprises has been achieved. This solves the problems of cumbersome startup process and misoperation, improves the safety and efficiency of the startup process, and reduces costs.
Patent Information
- Application Number
- CN202410023883.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-08
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-01-08
AI Technical Summary
The current waste heat power generation turbine startup process in steel enterprises is cumbersome, requires a lot of manual intervention, poses a risk of misoperation, and results in serious resource waste.
Design a smart management and control method for waste heat power generation in steel enterprises. By monitoring and controlling the on/off status of valves and pumps, automatically adjust the pressure and temperature of steam pipelines, and realize remote one-button start-up of steam turbines, including parameter monitoring, automatic speed-up warm-up, disengagement of turning gear, and grid connection after meeting start-up conditions, to achieve fully automatic operation.
It reduces the risk of human error, improves the safety and efficiency of the startup process, lowers operating costs, optimizes equipment operation, and enhances the unit's economy and safety.
Smart Images

Figure CN117685074B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of waste heat power generation control system technology, and specifically to a method for intelligent management and control of waste heat power generation in steel enterprises. Background Technology
[0002] The waste heat steam generator set for steelmaking is a pure condensing unit with no regenerative turbine. The steam sources for this generator set include steam generated from the converter vaporization and cooling in the plant area and steam generated from the heating furnace vaporization and cooling. Considering the overall steam volume and parameters, a 10MW rated power saturated steam turbine with a rated steam inlet flow rate of 70t / h (1.3MPa(a) saturated steam) is selected. The saturated steam from each source is fed into a steam-water separator via a DN350 main pipe, and after steam-water separation, it enters the turbine through the main steam valve to perform work.
[0003] With the increasing level of automation in industrial processes, the demand for one-button start-stop configurations for small-capacity industrial steam turbines is growing stronger. How to configure steam turbines to enable remote one-button start-up is a problem we urgently need to solve. Currently, the turbine startup process still requires on-site human intervention. Because the turbine startup process involves numerous steam pipelines and surrounding equipment, it requires a large number of personnel, is cumbersome, wastes human resources, and necessitates strict adherence to operating procedures, which carries the risk of misoperation.
[0004] Therefore, it is necessary to design a method for intelligent management and control of waste heat power generation in steel enterprises. This method would enable the system to monitor and control the turbine to start with a single click, thereby solving the problem of cumbersome processes and wasted human resources caused by the manual allocation and completion of the start-up of existing steam waste heat power generation turbines and the preparatory work. Summary of the Invention
[0005] In view of the problems existing in the prior art, the purpose of this invention is to provide a method for intelligent management and control of waste heat power generation in steel enterprises.
[0006] The technical solution adopted by this invention to solve its technical problem is: a method for intelligent management and control of waste heat power generation in steel enterprises, comprising the following steps:
[0007] S1. Parameter monitoring and control: Monitor the on / off status of valves and pumps, and establish an electrical connection to automatically control and display the on / off status within the intelligent power generation management system.
[0008] S2. Collect the pressure and temperature values in the main steam pipeline, determine that the pressure and temperature values have reached the set start-up values, and enter the start-up preparation stage;
[0009] S3. Monitor the operating status of the steam turbine, display the steam turbine speed in the intelligent power generation control system, and perform electro-hydraulic regulation;
[0010] S4. Automatic speed-up warm-up, automatic disengagement of the disc carriage;
[0011] S5. The turbine start-up conditions meet the set start-up speed, power oil pressure and lubricating oil temperature.
[0012] S6. The generator circuit breaker closes, the excitation circuit breaker closes, the voltage is increased, the synchronous power is applied, the grid connection subroutine is started, the DEH switches to automatic valve position control, and the turbine operates normally and automatically.
[0013] Specifically, the types and on / off states of the valves and pumps in step S1 include opening the solenoid valve of the turbine's condensate expansion tank, opening the circulating water electric valve, starting the turbine's auxiliary oil pump, and starting the exhaust fan.
[0014] Specifically, in step S2, the starting pressure in the main steam pipeline is set to 0.25 MPa, and the starting temperature in the main steam pipeline is set to 85°C.
[0015] Specifically, in step S3, monitoring the turbine's operating status and automatically warming up and turning the turbine involves starting the lubricating oil tank electric heater, starting the turning device, closing the main steam valve 1 of the steam pipeline, opening the steam vent valve 2 of the steam pipeline, opening the bypass valve 3 of the steam pipeline and the warming pipe, opening the water supply valve to supply water, closing the water supply valve after water supply is completed, opening the return water pneumatic valve, opening the electric valve before the condensate pump, starting the condensate pump, equalizing the pressure in the equalization tank, starting the shaft fan, opening the electric valve before the vacuum pump, starting the vacuum pump to establish a vacuum environment, and finally confirming that the warming pipe temperature, vacuum degree, and turning time all meet the requirements.
[0016] Specifically, in step S5, the turbine start-up conditions include a starting speed of 3000 r / min, a power oil pressure of 0.2-0.5 MPa, and a lubricating oil temperature of 80-100℃. Once the power oil pressure and lubricating oil temperature meet the requirements, the valve is quickly closed and the brake is engaged.
[0017] Specifically, in step S6, after the generator circuit breaker is closed and the excitation is closed, the drain pneumatic valve is opened, the return water pneumatic valve is closed, the condensate pump PID control system is put into operation, the high-pressure regulating valve is opened to continue the start-up and warm-up, and finally the grid is connected and the load is increased so that the generator turbine can start normally and automatically.
[0018] The present invention has the following beneficial effects:
[0019] The intelligent management and control method for waste heat power generation in steel enterprises designed in this invention reduces human factors in the unit startup process by objectively judging and adjusting the conditions, process variables and adjustment parameters in real time, thereby reducing the risks caused by subjective errors in judgment and misoperation, and improving the inherent safety of the unit startup process.
[0020] This invention presents a method for intelligent management and control of waste heat power generation in steel enterprises. This method automatically adjusts and optimizes the start-up efficiency of generator sets, ensuring that the equipment operates at its optimal state. It collects parameters such as main steam pressure, temperature, vacuum, and turbine vibration, and uses a data analysis model to adjust the generator set's start-up efficiency in real time. The data analysis model connects the proposed adjustment measures to the unit's automatic adjustment system, ensuring the generator set always operates in its optimal state. This reduces operational steps, allowing operators to monitor the correct execution of operating procedures instead of frequent manual intervention, thus avoiding malfunctions caused by frequent manual operations.
[0021] The intelligent management and control method for waste heat power generation in steel enterprises designed in this invention effectively reduces personnel delays and improves operational efficiency through process design adjustments, thereby effectively reducing start-up costs and potentially further improving the economic efficiency of unit start-up. Attached Figure Description
[0022] Figure 1 This is an automatic control flowchart of a method for intelligent management and control of waste heat power generation in steel enterprises. Detailed Implementation
[0023] The technical solutions of the embodiments of the present invention will be described in further detail below with reference to the accompanying drawings. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0024] Example 1:
[0025] A method for intelligent management and control of waste heat power generation in steel enterprises includes the following steps:
[0026] S1. Parameter monitoring and control: Monitor the on / off status of valves and pumps, and establish an electrical connection within the intelligent power generation management system to automatically control and display the on / off status.
[0027] S2. Collect the pressure and temperature values in the main steam pipeline, and determine that the pressure and temperature values have reached the set start-up values to enter the start-up preparation stage; the start-up value of the pressure in the main steam pipeline is set to 0.25MPa, and the start-up value of the temperature in the main steam pipeline is set to 85℃.
[0028] S3. Monitor the operating status of the steam turbine, display the turbine speed in the intelligent power generation control system, and perform electro-hydraulic regulation.
[0029] S4, automatic speed-up warm-up, automatic disengagement of the disc carriage.
[0030] S5. Based on the turbine start-up conditions, the set starting speed, power oil pressure, and lubricating oil temperature are met. The turbine start-up conditions include a starting speed of 3000 r / min, a power oil pressure of 0.2-0.5 MPa, and a lubricating oil temperature of 80-100℃. Once the power oil pressure and lubricating oil temperature meet the requirements, the valve should be closed and the brake engaged immediately.
[0031] S6. The generator circuit breaker closes, the excitation circuit breaker closes, the voltage is increased, the synchronous power is applied, the grid connection subroutine is started, the DEH switches to automatic valve position control, and the turbine operates normally and automatically.
[0032] Example 2: Figure 1 As shown, the automatic control process for intelligent management and control of waste heat power generation in steel enterprises is realized by adopting the steps of Example 1.
[0033] Open the solenoid valve of the turbine's expansion tank, open the circulating water electric valve, start the turbine's auxiliary oil pump, start the exhaust fan, start the lubricating oil tank electric heater, start the turning gear, close the main steam valve 1 of the steam pipeline, open the steam vent valve 2 of the steam pipeline, open the bypass valve 3 of the steam pipeline and warm up the pipes, open the water supply valve to supply water, close the water supply valve after water supply is completed, open the return water pneumatic valve, open the electric valve before the condensate pump, start the condensate pump, equalize the pressure in the equalization tank, start the shaft fan, open the electric valve before the vacuum pump, start the vacuum pump to establish a vacuum environment, finally confirm that the warm-up temperature, vacuum degree and turning time all meet the requirements, after the generator circuit breaker and excitation circuit breaker are closed, open the drain pneumatic valve, close the return water pneumatic valve, put the condensate pump's PID control system into operation, open the high-pressure regulating valve to continue the revving and warm-up, and finally connect to the grid and increase the load to enable the generator turbine to start normally and automatically.
[0034] The invention categorizes power-on into two types: cold power-on and hot power-on. Taking cold power-on as an example, the invention solidifies the optimal and most complete operation sequence. Based on different power-on types, the system automatically detects the operating conditions and selects one of the two models. It then automatically performs subsequent operations based on the conditions already met in this model.
[0035] 1. It is divided into four modules: parameter detection and control, turbine speed electro-hydraulic regulation, turbine ETS system, excitation, synchronization, boosting, and grid connection operation.
[0036] 2. The main steam pressure and temperature reach the start-up values, the main reset valve signal is normal, and the start-up preparation subroutine is initiated. This includes the logic programs for the circulating pump, vacuum pump, condensate pump, exhaust fan, equalizing tank condensate drain, equalizing tank, and main unit condensate drain.
[0037] 3. Set all parameters and establish related models. Based on the start-up conditions, set the rotation bar and start the power oil start-up subroutine.
[0038] 4. Automatic speed-up warm-up and automatic disengagement of the turning gear system model.
[0039] 5. When the main steam pressure and temperature rise to a specific value, the speed will automatically increase to warm up the system.
[0040] 6. After reaching 3000 RPM, an automatic grid connection condition detection subroutine will be implemented.
[0041] 7. The generator circuit breaker closes, the excitation circuit breaker closes, the voltage is increased, the synchronous power is applied, the grid connection subroutine is started, and the DEH switches to automatic valve position control.
[0042] 8. Normal automatic operation.
[0043] One-key start is a complex system engineering project that requires advanced concepts and a hardware system as its foundation, supported by a software system as its platform. Currently, the unit lacks a software system, necessitating the development of a hardware system. Therefore, this discussion focuses on how to integrate the one-key start concept throughout the entire process, considering the one-key start objective during hardware system design to ensure the hardware system meets the one-key start requirements. Furthermore, when developing the PLC control system, its openness and scalability should be fully considered to facilitate the configuration and debugging of the one-key start sequential control logic.
[0044] High reliability of hardware equipment, especially valve operation in auxiliary equipment, is fundamental to one-button start-up. When selecting auxiliary equipment, highly reliable devices should be chosen to prevent redundant investment due to poor initial equipment reliability.
[0045] Developing one-click start sequential control logic is an optimized startup process, which implements the optimal operation process for operators using sequential logic control. Therefore, a one-click start project should be led by operators with the cooperation of other personnel. One-click start completed under the leadership of operators ensures that it is an optimized startup process. At the same time, the full participation of operators in the one-click start project eliminates the need for one-click start training for operators.
[0046] By analyzing the current operating status of the equipment and historical data, and predicting the operation for the next period, parameters such as the main steam temperature, pressure, vibration, and vacuum of the unit are predicted. The predicted parameters are then connected to the automatic start-up model to achieve optimal automatic adjustment of the unit.
[0047] This invention can stabilize and improve the safety factor of generator sets, which not only reduces power generation costs but also extends equipment lifespan. Once the project is completed, it can be replicated for other waste heat steam generator sets, bringing significant social benefits.
[0048] By combining theoretical derivation with field operation data, and using historical data of unit operation as the research platform, a digital model describing the corresponding optimization problem is summarized. Then, a multi-objective optimization method applicable to various complex constraints is selected to conduct corresponding optimization calculations and analysis on the project content, thereby drawing corresponding conclusions.
[0049] This invention is not limited to the above-described embodiments. Anyone should know that any structural changes made under the guidance of this invention, and any technical solutions that are the same as or similar to this invention, fall within the protection scope of this invention.
[0050] The technologies, shapes, and structures not described in detail in this invention are all known technologies.
Claims
1. A method for intelligent management and control of waste heat power generation in steel enterprises, characterized in that, Includes the following steps: S1. Parameter monitoring and control: Monitor the on / off status of valves and pumps, and establish an electrical connection to automatically control and display the on / off status within the intelligent power generation management system. S2. Collect the pressure and temperature values in the main steam pipeline, determine that the pressure and temperature values have reached the set start-up values, and enter the start-up preparation stage; S3. Monitor the turbine's operating status and perform automatic warm-up and turning gear operation. Specifically, start the lubricating oil tank electric heater, start the turning gear device, close the main steam valve 1 of the steam pipeline, open the steam vent valve 2 of the steam pipeline, open the bypass valve 3 of the steam pipeline and warm up the pipes, open the water supply valve to supply water, close the water supply valve after water supply is completed, open the return water pneumatic valve, open the electric valve before the condensate pump, start the condensate pump, equalize the pressure in the equalization tank, start the shaft fan, open the electric valve before the vacuum pump, start the vacuum pump to establish a vacuum environment, and finally determine that the warm-up temperature, vacuum degree and turning gear time all meet the requirements. Display the turbine speed in the power generation intelligent control system and perform electro-hydraulic regulation. S4. Automatic speed-up warm-up, automatic disengagement of the disc carriage; S5. The turbine start-up conditions meet the set start-up speed, power oil pressure and lubricating oil temperature. S6. The generator circuit breaker is closed, the excitation circuit breaker is closed, the drain pneumatic valve is opened, the return water pneumatic valve is closed, the condensate pump PID control system is put into operation, the high-pressure regulating valve is opened to continue the start-up and warm-up, the pressure is increased, the power is simultaneously supplied, the grid connection subroutine is started, the DEH switches to automatic valve position control, and finally the grid connection and load increase enable the generator turbine to start normally and run normally.
2. The method for intelligent management and control of waste heat power generation in steel enterprises according to claim 1, characterized in that, The types and on / off states of the valves and pumps in step S1 include opening the solenoid valve of the turbine's hydrophobic expansion tank, opening the electric valve of the circulating water, starting the turbine's auxiliary oil pump, and starting the exhaust fan.
3. The method for intelligent management and control of waste heat power generation in steel enterprises according to claim 1, characterized in that, In step S2, the starting pressure in the main steam pipeline is set to 0.25 MPa, and the starting temperature in the main steam pipeline is set to 85°C.
4. The method for intelligent management and control of waste heat power generation in steel enterprises according to claim 1, characterized in that, In step S5, the turbine start-up conditions include a starting speed of 3000 r / min, a power oil pressure of 0.2-0.5 MPa, and a lubricating oil temperature of 80-100℃. Once the power oil pressure and lubricating oil temperature meet the requirements, the valve should be closed and the brake engaged immediately.
Citation Information
Patent Citations
Full-automatic control method and full-automatic control system for cement waste heat power generation station
CN104564188A
Steam turbine sequential control starting method
CN108678814A