A waterproof construction method for deep foundation pit pile combined with artificial freezing

By using zoned excavation and layered freezing methods, combined with different structured freezing pipes and condensation circulation, the problems of groundwater inflow and moisture migration were solved, and stable construction of the foundation pit was achieved.

CN117702790BActive Publication Date: 2026-11-24SHIHEZI UNIVERSITY
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410161573.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-05
Publication Date
2026-11-24
Estimated Expiration
2044-02-05

AI Technical Summary

Technical Problem

In areas with high collapsibility and high groundwater content, groundwater can flow into the borehole during foundation pit excavation, affecting the application of artificial freezing technology, and the migration of moisture around the foundation pit can lead to foundation settlement.

Method used

The method of zoned excavation and layered freezing is adopted, using two different types of freezing pipes, and a controllable closure device is set at the bottom of the casing. Combined with condensation circulation and thermal insulation layer, a closed freezing curtain is formed to prevent groundwater from entering the foundation pit.

Benefits of technology

This effectively prevents water from entering the foundation pit from the outside, avoids sudden surges of water at the bottom of the pit, and ensures the stability of the foundation pit and construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117702790B_ABST
    Figure CN117702790B_ABST
Patent Text Reader

Abstract

This invention provides a method for combined artificial freezing and waterproofing construction of deep foundation pits using pile foundations. Belonging to the field of foundation pit construction technology, the method includes: employing a zoned excavation and layered freezing approach. During excavation, the first excavation zone is filled with normal, unfrozen soil; the second excavation zone below the first is kept frozen; and the third excavation zone below the second and below is filled with normal, unfrozen soil. When construction begins on the second excavation zone after the first excavation zone is completed, the soil in the third excavation zone remains frozen. This cycle continues until the bottom of the foundation pit is reached. This method combines zoned excavation with layered freezing, employing two different types of freezing pipes. Layered freezing is carried out simultaneously with segmented excavation, effectively preventing water from entering the foundation pit from the outside and preventing sudden water surges in the lower part of the pit. Furthermore, a controllable closing device is installed at the bottom of the casing to prevent groundwater from rushing into the borehole when the drilling rig is withdrawn.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of foundation pit construction technology, specifically relating to a method for deep foundation pit pile-laying combined with artificial freezing for waterproofing construction. Background Technology

[0002] In recent years, with the development of underground space, more and more building foundation construction projects have chosen artificial freezing method to reinforce the soil. Artificial freezing method uses artificial refrigeration technology to freeze the water in the strata, turn natural rock and soil into frozen soil, increase its strength and stability, isolate the connection between groundwater and underground engineering, so that underground engineering construction can be carried out under the protection of the frozen wall. Currently, when artificial freezing technology is used in conjunction with foundation pit support, the entire excavation area is frozen. However, in some areas with high groundwater content, groundwater will flow into the borehole during excavation, affecting the application of artificial freezing technology. Furthermore, direct excavation of the foundation pit will cause the migration of water around the pit, and excessive water loss will lead to settlement of the surrounding foundation.

[0003] Currently, in the Alar region of Xinjiang, the high groundwater content makes foundation pit excavation difficult, and the region is also highly collapsible. Direct excavation could lead to a sudden surge of water in the lower part of the foundation pit. Therefore, there is an urgent need for a construction method that can prevent groundwater from flowing into the borehole and effectively solve the problems caused by water migration when excavating foundation pits in areas with high collapsibility and high groundwater content. Summary of the Invention

[0004] Based on the above-mentioned technical problems, the present invention provides a method for waterproofing construction using a combination of pile driving and artificial freezing in deep foundation pits. This method adopts a zoned excavation and layered freezing approach, and uses artificial freezing to create a freezing curtain to solve the problem caused by water migration. It also employs two different structures of freezing pipes to freeze in layers while carrying out segmented excavation, thereby effectively preventing water from entering the foundation pit from the outside and preventing sudden surges of water in the lower part of the foundation pit. Furthermore, a controllable closing device is provided at the bottom of the casing to prevent groundwater from rushing into the borehole when the drilling rig is pulled out.

[0005] The specific technical solution is as follows: A method for combined artificial freezing waterproofing construction with pile foundations in deep foundation pits includes the following steps: S1: Construction outside the foundation pit; S2: Before the foundation pit is excavated, the first casing is connected to the drilling rig. The first casing is cylindrical in shape. A controllable closing device is set at the lower end of the first casing. The closing device enters the soil along with the drilling rig. After the drilling is completed, the drilling rig is pulled out and the first casing is left. When the drill bit leaves the soil, the closing device is closed immediately to prevent groundwater from flowing into the first casing. S3: After drilling is completed, the drilling rig performs inclination measurement. After the inclination measurement is completed, the first freezing pipe is inserted into the first casing. The first freezing pipe is equipped with a condensation circulation. The end, middle and bottom of the first freezing pipe are equipped with collars. The number of collars in the middle of the first freezing pipe is adjusted according to the soil depth to facilitate the insertion of subsequent condensation pipes. S4: The freezing range of the first freezing tube needs to be determined in advance. The freezing range between two adjacent first freezing tubes needs to be greater than the tube spacing to form a closed freezing curtain area. S5: Start the refrigeration station. The refrigeration station is connected to the liquid delivery pipe, so that the low-temperature coolant is circulated and input into the condenser. S6: Foundation pit support construction, drilling and steel cage placement are carried out simultaneously. After drilling is completed, inclination is measured, then the steel cage is lowered and grouting begins. During pile construction, the verticality of the cavity must meet the requirements and reach the specified depth, exceeding a certain depth in the designed frozen bottom layer. S7: After the pre-excavation area is completed, install transverse and longitudinal internal bracing; S8: Adopt a zoned excavation and layered freezing method so that the first excavation zone is normal unfrozen soil during excavation, the second excavation zone below the first excavation zone is kept frozen, and the third excavation zone below the second excavation zone and below is normal unfrozen soil. When construction of the first excavation zone is completed and construction of the second excavation zone begins, the soil in the third excavation zone is kept frozen. This cycle continues until the bottom of the foundation pit is reached. S9: To utilize artificial freezing technology combined with zonal excavation, a second and third freezing pipe are designed. A thermal insulation layer is installed on the outside of the second freezing pipe, located at the gap between the second sleeve and the second freezing pipe. A thin base plate is installed at the lower end of the third freezing pipe, which acts as a barrier. An arc-shaped baffle is installed on the upper side of the base plate, which acts as a guide, thus facilitating the insertion of the condenser pipe into the third freezing pipe. The condenser pipe forms a U-shaped circulation, thereby recycling the cooling fluid.

[0006] In addition, the method for combined artificial freezing and waterproofing construction of deep foundation pit pile slabs provided by the present invention may also have the following additional technical features: In the above technical solution, in step S1, the east-west and north-south lengths of the foundation pit are first determined, and the topography of the area is analyzed to determine the placement of the support structure and the specific reinforcement.

[0007] In the above technical solution, in step S3, in order to prevent the freezing efficiency from being too low, the gap between the two tubes is minimized as much as possible while facilitating the insertion of the first freezing tube into the sleeve. The larger the diameter of the first freezing pipe, the larger the contact area between its outer surface and the frozen soil. At the same time, the larger the cross-sectional area of ​​the first freezing pipe, the greater the cooling capacity, the lower the flow rate of the refrigerant, and the more efficient the heat exchange. Therefore, the faster the freezing rate, the larger the freezing influence range within a certain period of time.

[0008] In the above technical solution, in step S3, the condensation cycle includes a first liquid inlet pipe and a first liquid outlet pipe. The first liquid inlet pipe is connected to a liquid delivery pipe, the first liquid outlet pipe is connected to a liquid collection pipe, and the liquid delivery pipe is connected to a cooling station, thereby forming a circulation system.

[0009] In the above technical solution, in step S3, in order to ensure the freezing rate, the condensation cycle is selected as either a unidirectional cycle or a bidirectional cycle according to actual needs.

[0010] In the above technical solution, in order to avoid problems such as lateral slippage and collapse during the excavation of the foundation pit, the stepped method is used to excavate the foundation pit during construction.

[0011] In the above technical solution, when the excavation reaches the bottom layer, a waterproof layer is laid on the inner surface of the foundation pit near the pile, thereby effectively preventing water from outside the foundation pit from entering the foundation pit. At the same time as the waterproof layer is laid, the outermost first freezing pipe is pulled out, and the frozen curtain area is thawed normally, thereby achieving the purpose of thawing the frozen state in advance.

[0012] In the above technical solution, during step S3, when measuring the deviation, the average deviation rate of the frozen holes shall not exceed 5%, and the final spacing between the frozen holes shall not exceed the design value.

[0013] In the above technical solution, in order to protect the existing freezing tube from damage during the freezing process, a pressure test is required on the freezing tube and the condenser tube. The test pressure is 0.8 MPa. The pressure drop should not exceed 0.05 MPa after 30 minutes of testing, and the pressure should remain unchanged for another 15 minutes to be considered qualified.

[0014] The present invention provides a method for combined artificial freezing and waterproofing construction of deep foundation pit piles, which has the following advantages compared with the prior art: 1. A method of sectional excavation and layered freezing is adopted, and a freezing curtain is made by artificial freezing to solve the problem caused by water migration. Two types of freezing pipes with different structures are used at the same time to freeze in layers while carrying out sectional excavation, thereby effectively preventing water from entering the foundation pit from the outside and preventing the sudden surge of water in the lower part of the foundation pit.

[0015] 2. A controllable closing device is installed at the bottom of the casing to prevent groundwater from rushing into the borehole when the drilling rig is pulled out. Attached Figure Description

[0016] Figure 1 This is a cross-sectional view of the present invention; Figure 2 This is a schematic diagram of the longitudinal section structure of the present invention; Figure 3 This is a longitudinal cross-sectional view of the present invention; Figure 4 This is the second freezing tube of the present invention; Figure 5 This is the third freezing tube of the present invention; Figure 6 This is a diagram showing the combination of the second and third freezing tubes of the present invention; Figure 7 This is a schematic diagram of the outer freezing curtain area structure of the present invention; Figure 8 This is a schematic diagram of the excavation zone freezing support structure of the present invention; in, Figures 1 to 8 The correspondence between the reference numerals and component names in the attached drawings is as follows: 1-1 First casing, 1-2 Second casing, 2-1 First freezing pipe, 2-2 Second freezing pipe, 2-3 Third freezing pipe, 3-1 First inlet pipe, 3-2 First outlet pipe, 3-3 Second inlet pipe, 3-4 Second outlet pipe, 4 Frozen curtain zone, 5 Pipeline, 6-1 Lateral internal bracing, 6-2 Longitudinal internal bracing, 7 Excavation boundary, 8 Pre-excavation zone, 9 Frozen zone, 10 Waterproof layer, 11 Protective layer, 12 Frozen bottom layer, 13 Concrete base slab, 14 Grouting pipe, 15 Threaded connection zone, 16 Coolant, 17 Thermal insulation layer, 18 Partition plate, 19 Closure device, 20 Excavated bottom layer Detailed Implementation

[0017] The following are specific implementation cases and appendices. Figure 1-8 The present invention will be further described, but the present invention is not limited to these embodiments.

[0018] The first step involves construction outside the foundation pit. The excavation depth of the foundation pit is 10m, the total depth of the artificially frozen soil area is 15m, the frozen wall is 1.5m, and the spacing between freezing holes is 0.8m, with the freezing holes evenly distributed. An XY-2 type vertical drilling rig with a motor power of 22KW is selected. Construction is carried out simultaneously in the east-west and north-south directions. When using borehole drilling technology, the east-west and north-south lengths of the foundation pit are first determined, and the topography of the area is analyzed to determine the placement position and specific reinforcement of the support structure. Drilling is then carried out outside the support structure. Before excavation, the first casing 1-1 is connected to the drilling rig. A controllable closing device 19 is installed at the lower end of the first casing 1-1. This device enters the soil along with the drilling rig. After drilling is completed, the drilling rig is withdrawn, but the casing is retained. When the drill bit leaves the soil, the closing device 19 is immediately closed to prevent groundwater from flowing into the casing.

[0019] After drilling is completed, the drilling rig performs inclination measurement, using a casing instead of a measuring tube. Inclination measurement is performed using lights, and a gyroscope inclination meter is used when necessary. After inclination measurement, a first freezing tube 2-1 is inserted into the casing. To prevent low freezing efficiency, the gap between the two tubes is minimized while facilitating insertion of the first freezing tube 2-1 into the casing. Since a relatively large amount of coolant 16 is required during construction, to avoid energy loss and improve freezing efficiency, this invention sets up a condensation cycle within the first freezing tube 2-1. The condensation cycle includes a first inlet pipe 3-1 and a first outlet pipe 3-2. The first inlet pipe 3-1 is connected to a delivery pipe, and the first outlet pipe 3-2 is connected to a collection pipe. The delivery pipe is connected to an external refrigeration station, thus forming a condensation cycle.

[0020] Specifically, collars need to be installed in advance at the ends, middle and bottom of the freezing pipe. The diameter of the collars should be slightly larger than the diameter of the inlet and outlet pipes. The number of collars in the middle of the freezing pipe should be adjusted according to the actual soil depth to facilitate the insertion of the condenser pipe.

[0021] It is important to note that the freezing range of the freezing pipes needs to be measured in advance. The freezing range between the two pipes should be greater than the pipe spacing to form a closed freezing curtain area 4. At the same time, there should be a gap between the freezing area 9 and the construction area of ​​the reinforced concrete pile 5 to avoid the freezing range being too large and hindering the subsequent drilling construction of the reinforced concrete pile. The purpose of setting up the freezing curtain is to prevent water from outside the foundation pit from flowing into the foundation pit and to prevent the foundation from settling due to excessive water migration, which could cause safety hazards. Meanwhile, after freezing is completed, the freezing holes are used for subsequent frost heave release and grouting.

[0022] Furthermore, after the freezing construction is completed, the refrigeration station is started after inspection. The refrigeration station is connected to the liquid outlet pipe, so that the low-temperature coolant 16 is circulated and input into the condenser pipe. The temperature and thickness of the frozen wall are measured. When the requirements are met, the construction of the reinforced concrete pile 5 of the foundation pit is carried out. At the same time, the depth of the frozen wall must reach the bottom of the foundation pit excavation.

[0023] Specifically, a storage tanker with a volume of not less than 25 cubic meters is set up near the excavation area to store the coolant 16, thereby preventing the supply of coolant 16 from being interrupted.

[0024] The second step is the construction of the foundation pit support, such as... Figure 2 As shown, boreholes are excavated and drilled according to the actual requirements of the foundation pit project. Reinforcing cages are fabricated according to the stress characteristics of the foundation pit. Drilling and reinforcement cage placement are carried out simultaneously. It should be noted that the drilling depth of pile 5 is generally 1.5 times the excavation depth of the foundation pit. However, since the excavation is carried out in an area with high groundwater content, the drilling depth of pile 5 needs to be increased in order to enhance the stability of the support and avoid a series of excavation problems such as piping, sudden surge, and heave. After the drilling is completed, the inclination is measured, and then the reinforcement cage is lowered and grouting begins.

[0025] Specifically, in order to improve the stability of the support, the pile diameter and pile spacing need to be strictly controlled. The foundation pit of this invention adopts a pile diameter of 1m and a pile spacing of 1.5m. The freezing curtain of the outer freezing zone 9 does not affect the construction of reinforced concrete piles. At the same time, in order to maintain the stability of the foundation pit, after the construction of the pre-excavation zone 8 is completed, transverse inner bracing 6-1 and longitudinal inner bracing 6-2 are set. In order to avoid problems such as side slippage and collapse during the excavation of the foundation pit, the step method is used to excavate the foundation pit during construction.

[0026] Specifically, the pre-excavation zone 8 is below the frozen zone 9.

[0027] The third step is to excavate the foundation pit in sections, such as... Figure 2-3 As shown, when the first excavation zone begins to be excavated, the second excavation zone remains frozen. When the construction of the first excavation zone is completed and other construction conditions are met, the second excavation zone is unfrozen, while the third excavation zone begins to remain frozen. At this time, no artificial freezing is carried out below the third excavation zone, thus greatly saving the cooling fluid 16.

[0028] Excavation is carried out in zones, using h1, h2, h3…h n The freezing process is represented by H1, H2, H3…H2. n The excavation sequence is represented by H, where H represents the excavation height and the subscripts represent the excavation order. For formal excavation excluding pre-experimentation, H1+H2+H3…+…H n The sum of the excavation heights equals the total height of the excavation area.

[0029] Before excavation, pre-excavation and pre-freezing experiments are conducted, and the environmental factors in the test area and the formal excavation area are kept consistent. A frozen zone, 9h1, is designed, located at the lower end of the first excavation zone H1. Excavation begins after freezing. When excavating to the bottom of H1, h1 is still not thawed. It is important to note that the time T from the freezing of h1 to its complete thawing needs to be calculated. Based on the construction progress of H1, the normal excavation height H within time T is calculated. Then, excavation zone H2 is designed based on H. Following the normal construction process, the sum of the time T1 used to excavate H2 and the freezing time T2 of h2 should be less than or equal to T, depending on the construction progress. Simultaneously, the excavation height of H2 must be less than H. Note that h... n The freezing time T2 needs to be determined in advance. The ultimate goal of this experiment is that when construction on H1 ends and construction on H2 begins, area h1 should be just about to thaw, while area h2 should be completely frozen. To reduce construction difficulty without affecting the construction schedule, H2 needs to be continuously adjusted during the experiment. n and h n The height of the two objects is adjusted until they are equal while maintaining the above requirements.

[0030] Before excavating the foundation pit, boreholes are drilled at equal intervals. It is crucial to pay close attention to the borehole spacing during drilling. To prevent perforation, the entire area should be frozen. Full-area freezing is necessary to prevent groundwater from suddenly entering the foundation pit. After drilling, inclination measurement is performed. To avoid the same problems mentioned above, the casing is inserted into the borehole along with the drilling rig, and the casing is retrieved and stored afterward. Note that to ensure the freezing rate, the condenser can use either unidirectional or bidirectional circulation. In this example, the foundation pit uses unidirectional circulation; the specific method will depend on the site conditions.

[0031] For the excavation area, an excavation boundary 7 is set. Excavation boundary 7 is the location of the threaded connection area 15, which is the location of the bottom of H1 during construction. When excavation reaches this location, a sleeve with a live joint and a freezing pipe are installed. The sleeve in the excavation area and the sleeve in the freezing area 9 are connected by threads, and the freezing pipe is also connected by threads. After excavation, the sleeve and freezing pipe are removed, and the condensate pipe is extracted.

[0032] The function and operation steps of nodes: First, the second casing 1-2 is similar in appearance and function to the first casing 1-1, except that it has interfaces set at intervals. For example, when excavating section H1, the upper freezing pipe of H1 is removed after excavation. Inside the second casing 1-2 is the second freezing pipe 2-2. Note that in order to utilize artificial freezing technology in conjunction with sectional excavation, two different freezing pipes were designed. The first type is the second freezing pipe 2-2, which has an insulation layer 17 on its outer side. It is located in the gap between the second casing 1-2 and the second freezing pipe 2-2. The freezing pipe with the insulation layer 17 cannot be artificially frozen. For example, when excavating H1, H1 has already been thawed. If H1 is frozen at this time, ice-breaking treatment is still required, which will affect the construction progress. The second type is the third freezing pipe 2-3. Its outer end does not have an insulation layer 17, but its lower end has a thin base plate, which acts as a barrier. An arc-shaped baffle 18 is installed on the upper side of the base plate. The base plate prevents the condenser pipe from being inserted below the threaded connection area 15, while the arc-shaped baffle 18 acts as a guide, facilitating the insertion of the condenser pipe into the freezing pipe and forming a U-shaped condensation cycle. The second inlet pipe 3-3 connects to the delivery pipe, and the second outlet pipe 3-4 connects to the collection pipe. The delivery pipe connects to an external cooling station for recycling the cooling liquid 16. When the drilling rig is removed after excavation, and the casing is retained before inserting the freezing pipe, it is important to note that to prevent groundwater from entering the freezing pipe, the bottom of the lowest casing still has a closing device 19. This device can be controlled by an external switch and closes immediately when the drilling rig leaves the soil.

[0033] Specifically, except for the first excavation zone H1, all other sections use the third freezing pipe 2-3. At the same time, the second freezing pipe 2-2 and the third freezing pipe 2-3 are the same length, which is the reason for conducting the pre-excavation experiment mentioned above.

[0034] Specifically, the thermal insulation layer 17 is selected from polystyrene, polyethylene, and polyurethane.

[0035] When excavating pre-excavation zone 8, which is before section H1, the lower freezing zone 9 of H1, i.e., section h1, is frozen in advance. The freezing method is as follows: section H1 uses the second freezing pipe 2-2, and the lower section h1 uses the third freezing pipe 2-3. The condenser pipe is inserted into the lower end of h1 to form a condensation cycle. After the excavation of H1 is completed, the condenser pipe is first removed, and then the sleeve and freezing pipe of section H1 are removed. At the same time, the third freezing pipe 2-3 at H2 is removed and replaced with the second freezing pipe 2-2. The condenser pipe is then inserted, and it just enters the bottom of h2. Then the refrigeration station is started to freeze h2. When the freezing is completed and the excavation of H2 begins, h1 has just thawed. Then the excavation of H2 begins, and the excavation method is the same as that of H1. This cycle is repeated until the bottom layer is excavated. In order to prevent the foundation pit from collapsing due to insufficient stability, a stepped excavation is used.

[0036] Step four, as Figure 3 As shown, when the excavation reaches the bottom layer, a waterproof layer is laid on the inner surface of the foundation pit near the pile 5. In order to prevent the soil layer from corroding the waterproof layer 10, a protective layer 11 is set on the surface of the waterproof layer 10 and the reinforced concrete pile 5. The waterproof layer 10 is laid according to the excavation depth of the foundation pit. At the same time as the waterproof layer 10 is laid, the outermost first freezing pipe 2-1 is pulled out, and the frozen curtain area 4 is thawed normally. The purpose of laying the waterproof layer 10 is to effectively isolate the water outside the foundation pit from entering the foundation pit. Under the premise of not affecting the construction, laying the waterproof layer 10 in advance can allow the outer side to be thawed in advance, thereby greatly saving the cooling liquid.

[0037] Specifically, during the construction of the frozen base layer 12, a concrete base slab 13 needs to be laid. Taking the bottom layer r as an example, r represents the frozen zone 9, located at the lower end of the frozen base layer 12. After excavating the base layer H... n-1 H at this time n While still frozen, when freezing begins on the region containing r, H is extracted. n The third freezing pipe 2-3 is replaced with the second freezing pipe 2-2. The freezing pipes in the area where r is located are identical to the third freezing pipe 2-3 except for their length. A condensation pipe is introduced into the bottom of r to form a condensation cycle. r needs to be continuously frozen at the start of excavation. H nAfter excavation is completed, the input of cooling fluid is stopped, but the area remains frozen. At this point, the concrete base slab 13 is laid, and the freezing pipes, sleeves, and condenser pipes are removed. Grouting is first performed on the boreholes, followed by grouting on the concrete base slab 13. The number of grouting pipes 14 depends on the east-west and north-south length of the pit. After the concrete base slab 13 reaches its design strength, the exposed freezing pipes in the pit are removed. Freezing pipes embedded in the concrete base slab 13 are filled with cement mortar. The spacing of the grouting pipes 14 is set at 800mm, and the bearing capacity of the reinforced soil must not be less than 0.8MPa. Intermittent grouting is used, with the grouting pressure controlled between 0.8 and 1MPa to avoid affecting the stability of the soil layer below the reinforced concrete base slab 13. For the concrete base slab 13, early-strength C30 concrete with an excavation depth of 300mm is used, with internal steel mesh as a temporary support structure. Simultaneously, the excavation of this pit reaches the bottom layer 20.

[0038] Compared with existing deep foundation pit horizontal freezing and sealing technology, the construction method of the present invention adopts layered freezing and vertically and spaced multiple freezing pipelines to achieve horizontal freezing of the pit bottom, which improves the installation accuracy of the freezing pipelines and the stability of the resulting frozen bottom plate. The construction method is highly operable and occupies a small area, making it suitable for foundation pit projects with limited construction sites and high groundwater content.

[0039] Specifically, the freezing tube is made of stainless steel with a diameter of 125mm, and the condenser tube is made of stainless steel with a diameter of 55mm.

[0040] As shown in Table 1, different coolants are selected based on their volume concentration, mass concentration, and freezing point.

[0041]

[0042] Table 1 During construction, different refrigerants are used according to the actual terrain and different needs. Water is used in the warm season, while ethanol, ethylene glycol, propylene glycol, calcium chloride solution, and sodium chloride solution can be selected in the cold season. The specific choice depends on the real-time temperature environment.

[0043] In an embodiment of the present invention, the final stable temperature of the low-temperature fluid circulating in the freezing pipe is no higher than -35°C, which causes frozen soil to form around the freezing pipe and creates a freezing curtain. In addition, in order to improve the freezing rate and construction progress, the condenser pipe can be divided into unidirectional circulation and bidirectional circulation.

[0044] Specifically, in the first step, during the formation of the frozen curtain, the construction of pile 5 is carried out simultaneously, so that the thickness of the frozen wall curtain covering the bottom of the pile 5 exceeds 1m, thereby forming a continuous and closed overall support structure to ensure its waterproof effect.

[0045] Specifically, in the second step, when constructing reinforced concrete piles 5, different construction machinery should be selected according to different pile formation methods, and drilling should be carried out at the determined pile points to form piles.

[0046] Specifically, in the third step, if the actual drilling process is difficult and the progress is slow, and the frozen pipe drilling is not completely completed when the reinforced concrete pile 5 reaches the design strength, and the construction period is tight, it is advisable to consider excavating in sections, and the foundation pit excavation and drilling operations can be carried out simultaneously.

[0047] Specifically, in the fourth step, when excavating to the bottom of the foundation pit and beginning to pour the concrete base slab 13, it is necessary to constantly monitor the development of the frozen bottom layer 12 to ensure construction safety. At the same time, waterproofing measures must be taken at the joint between the concrete base slab 13 and the reinforced concrete piles 5. After excavating to the bottom of the foundation pit, the reinforcing bars of the reinforced concrete base slab 13 to be constructed are tied, and multiple grouting pipes 14 are reserved. The grouting pipes 14 are vertically installed, and the bottom of the grouting pipe 14 is inserted into the frozen soil to a depth of 0.8m. The horizontal distance between two adjacent grouting pipes 14 does not exceed 3.6m. When recovering the freezing system, artificial thawing or natural thawing can be used to restore the normal flow of groundwater. The condensate pipes should be pulled out first, then the freezing pipes, and finally the casing should be pulled out. The freezing holes should be manually backfilled to complete the entire construction operation of the outer frozen zone 9.

[0048] In an embodiment of the present invention, when performing deviation measurement, the average deviation rate of the freezing holes shall not exceed 5%, the final hole spacing of the freezing holes shall not exceed the design value, otherwise additional holes shall be added, the freezing depth shall meet the design requirements, and the length of the lower pipe shall not be less than the designed freezing hole depth; at the same time, during the construction of the freezing holes, a light theodolite shall be used to measure the deviation of the final hole and the hole formation, and the deviation plan of the freezing holes shall be drawn in a timely manner.

[0049] In this embodiment of the invention, the freezing system is assembled on the ground, its total length is measured and recorded, and foreign objects are removed from the pipe before installation to facilitate the placement of the condenser pipe. The system is kept clean, and after pressure testing and sealing, the gaps around the casing are promptly filled with soil to prevent mud from seeping into the borehole. During drilling, the borehole deviation is monitored in real time to ensure the quality of the vertical freezing system's hole formation. The waterproof layer is made of a 200mm thick asphalt-polyurethane composite material. For the concrete-filled pile foundation construction, mud is used to protect the borehole walls during construction to prevent collapse.

[0050] In embodiments of the present invention, some metallic materials have advantages over others in resisting soil corrosion. Galvanized steel is a type of steel that has undergone galvanizing treatment, exhibits good corrosion resistance, performs well in saline soil environments, and is relatively inexpensive. Therefore, galvanized steel is used for both the casing and the protective layer 11. To ensure drilling quality, simple mud trenches are laid on-site. After the concrete base slab 13 of the foundation pit reaches its design strength, the exposed frozen pipes in the pit are cut off, and the pipes embedded in the concrete base slab 13 are filled with cement grout. Simultaneously, when cutting off the lower frozen pipes, it is essential to ensure that the cooling fluid 16 inside the pipes is drained to prevent leakage of the cooling fluid 16 from eroding the existing waterproof layer 10.

[0051] In this embodiment of the invention, during the construction of the reinforced concrete pile wall 5, it is essential to ensure that the verticality of the wall meets the requirements, and that the joint between adjacent pile walls in the frozen curtain has a good water-sealing effect. The pile wall 5 must be constructed to a specified depth, exceeding a certain depth in the designed frozen soil base slab. Simultaneously, care must be taken to protect existing freezing pipes from damage. Pressure testing and leak detection must be performed on the freezing pipes and condensate pipes; only after meeting the requirements can the next step of construction proceed. Furthermore, before construction, the dynamic water flow within the frozen area must be checked with relevant authorities, and corresponding measures must be taken to minimize the impact of dynamic water flow on the construction.

[0052] In embodiments of the present invention, during drilling, the number of drill collars should be increased or decreased in a timely manner according to the excavation depth of the foundation pit and the needs of the soil layers, and drilling should be carried out at a uniform speed, while the rotation speed and pressure of the drill bit should be reasonably controlled.

[0053] In the description of this invention, the term "a plurality of" refers to two or more. Unless otherwise explicitly defined, the terms "upper," "lower," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the invention. The terms "connection," "installation," "fixing," etc., should be interpreted broadly. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection or an indirect connection through an intermediate medium. For those skilled in the art, the specific meaning of the above terms in this invention can be understood according to the specific circumstances.

[0054] In the description of this invention, the terms "one embodiment," "some embodiments," "specific embodiment," etc., refer to a specific feature, structure, material, or characteristic described in connection with that embodiment or example, which is included in at least one embodiment or example of the invention. In this invention, the illustrative expressions of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the specific features, structures, materials, or characteristics described may be combined in any suitable manner in one or more embodiments or examples.

[0055] The above description is merely a preferred embodiment of the present invention and is not intended to limit the invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.

Claims

1. A method for combined artificial freezing and waterproofing construction of deep foundation pit pile banks, characterized in that, Includes the following steps: S1: Construction outside the foundation pit; S2: Before the foundation pit is excavated, the first casing is connected to the drilling rig. The first casing is cylindrical in shape. A controllable closing device is set at the lower end of the first casing. The closing device enters the soil along with the drilling rig. After the drilling is completed, the drilling rig is pulled out and the first casing is left. When the drill bit leaves the soil, the closing device is closed immediately to prevent groundwater from flowing into the first casing. S3: After drilling is completed, the drilling rig performs inclination measurement. After the inclination measurement is completed, the first freezing pipe is inserted into the first casing. The first freezing pipe is equipped with a condensation circulation. The end, middle and bottom of the first freezing pipe are equipped with collars. The number of collars in the middle of the first freezing pipe is adjusted according to the soil depth to facilitate the insertion of subsequent condensation pipes. S4: The freezing range of the first freezing tube needs to be determined in advance. The freezing range between two adjacent first freezing tubes needs to be greater than the tube spacing to form a closed freezing curtain area. S5: Start the refrigeration station. The refrigeration station is connected to the liquid delivery pipe, so that the low-temperature coolant is circulated and input into the condenser. S6: Foundation pit support construction, drilling and steel cage placement are carried out simultaneously. After drilling is completed, inclination is measured, then the steel cage is lowered and grouting begins. During pile construction, the verticality of the cavity must meet the requirements and reach the specified depth, exceeding a certain depth in the designed frozen bottom layer. S7: After the pre-excavation area is completed, install transverse and longitudinal internal bracing; S8: Adopt a zoned excavation and layered freezing method so that the first excavation zone is normal unfrozen soil during excavation, the second excavation zone below the first excavation zone is kept frozen, and the third excavation zone below the second excavation zone and below is normal unfrozen soil. When construction of the first excavation zone is completed and construction of the second excavation zone begins, the soil in the third excavation zone is kept frozen. This cycle continues until the bottom of the foundation pit is reached. S9: To utilize artificial freezing technology combined with zonal excavation, a second and third freezing pipe are designed. A thermal insulation layer is installed on the outside of the second freezing pipe, located at the gap between the second sleeve and the second freezing pipe. A thin bottom plate is installed at the lower end of the third freezing pipe, which acts as a barrier. An arc-shaped baffle is installed on the upper side of the bottom plate, which acts as a guide, thus facilitating the insertion of the condenser pipe into the third freezing pipe. The condenser pipe forms a U-shaped circulation, thereby recycling the cooling fluid. When excavating pre-excavation zone 8, which is before section H1, the lower freezing zone 9 of H1, i.e., section h1, is frozen in advance. The freezing method is as follows: section H1 uses the second freezing pipe 2-2, and the lower section h1 uses the third freezing pipe 2-3. The condenser pipe is inserted into the lower end of h1 to form a condensation cycle. After excavation of H1 is completed, the condenser pipe is first removed, then the sleeve and freezing pipe of section H1 are removed. At the same time, the third freezing pipe 2-3 at H2 is removed and replaced with the second freezing pipe 2-2. The condenser pipe is then inserted, and it just connects to the bottom of h2. Then the refrigeration station is started to freeze h2. When the freezing is completed and excavation of H2 begins, h1 has just thawed. Then H2 is excavated, and the excavation method is the same as that of H1. This cycle is repeated until the bottom layer is excavated. Excavation is carried out in sections, using h1, h2, h3...h n The freezing process is represented by H1, H2, H3...H2, where h represents the freeze height and the subscripts represent the freezing order; H1, H2, H3...H2 are used to represent the freezing sequence. n The excavation process is represented by H, where H represents the excavation height and the subscripts represent the excavation sequence. For formal excavation excluding pre-experimentation, H1+H2+H3…+…H n The sum of the excavation heights equals the total height of the excavation area.

2. The method for combined artificial freezing and waterproofing construction of deep foundation pit piles according to claim 1, characterized in that, In step S1, the east-west and north-south lengths of the foundation pit are first determined, and the topography of the area is analyzed to determine the placement of the support structure and the specific reinforcement.

3. The method for combined artificial freezing and waterproofing construction of deep foundation pit piles according to claim 1, characterized in that, In step S3, in order to prevent the freezing efficiency from being too low, the gap between the two tubes should be minimized as much as possible while facilitating the insertion of the first freezing tube into the sleeve. The larger the diameter of the first freezing pipe, the larger the contact area between its outer surface and the frozen soil. At the same time, the larger the cross-sectional area of ​​the first freezing pipe, the greater the cooling capacity, the lower the flow rate of the refrigerant, and the more efficient the heat exchange. Therefore, the faster the freezing rate, the larger the freezing influence range within a certain period of time.

4. The method for combined artificial freezing and waterproofing construction of deep foundation pit piles according to claim 1, characterized in that, In step S3, the condensation cycle includes a first inlet pipe and a first outlet pipe. The first inlet pipe is connected to a delivery pipe, the first outlet pipe is connected to a collection pipe, and the delivery pipe is connected to a cooling station, thereby forming a circulation system.

5. The method for combined artificial freezing and waterproofing construction of deep foundation pit piles according to claim 4, characterized in that, In step S3, in order to ensure the freezing rate, the condensation cycle is selected as either a unidirectional cycle or a bidirectional cycle according to actual needs.

6. The method for combined artificial freezing and waterproofing construction of deep foundation pit piles according to claim 1, characterized in that, To avoid problems such as lateral slippage and collapse during the excavation of the foundation pit, a stepped method is used for excavation during construction.

7. The method for combined artificial freezing and waterproofing construction of deep foundation pit piles according to claim 1, characterized in that, When the excavation reaches the bottom layer, a waterproof layer is laid on the inner surface of the foundation pit near the piles to effectively prevent water from outside the foundation pit from entering. At the same time as the waterproof layer is laid, the outermost first freezing pipe is pulled out, and the frozen curtain area thaws normally, thus achieving the purpose of thawing the frozen state in advance.

8. The method for combined artificial freezing and waterproofing construction of deep foundation pit piles according to claim 1, characterized in that, In step S3, when performing the skew measurement, the average skew rate of the frozen holes shall not exceed 5%, and the final hole spacing of the frozen holes shall not exceed the design value.

9. The method for combined artificial freezing and waterproofing construction of deep foundation pit pile banks according to claim 1, characterized in that, During the freezing process, in order to protect the existing freezing tubes from damage, a pressure leak test must be performed on the freezing tubes and condenser tubes. The test pressure is 0.8 MPa. If the pressure drop does not exceed 0.05 MPa after 30 minutes of testing, and the pressure remains unchanged for another 15 minutes, it is considered qualified.

Citation Information

Patent Citations

  • Freezing bottom-sealing construction method for deep foundation pit

    CN105926636A

  • Advanced reinforcement method for deep and large foundation pit soil body in soft soil area based on horizontal freezing method

    CN114134903A