Rail mounting method and connecting clamp

By using connecting clamps and robotic arms inside the elevator shaft, the guide rail installation process is simplified, solving the problems of complex structure and insufficient precision in existing technologies, and achieving efficient and low-cost guide rail installation.

CN117775927BActive Publication Date: 2026-11-20HITACHI LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410173540.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-07
Publication Date
2026-11-20
Estimated Expiration
2044-02-07

AI Technical Summary

Technical Problem

Existing guide rail mounting devices are complex in structure, costly, and have limited lifting positions, making it difficult to achieve high-precision installation.

Method used

A connecting fixture is used, and a robotic arm installs the connecting fixture onto a pre-fixed first guide rail and connecting plate. A camera device is used to identify and adjust the position of the second guide rail, thereby aligning and securing the second guide rail with the first guide rail, simplifying the device structure.

Benefits of technology

This technology enables high-precision installation of the guide rails, reduces installation steps, improves installation efficiency, and lowers device costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117775927B_ABST
    Figure CN117775927B_ABST
Patent Text Reader

Abstract

The present application provides a connection jig for rail installation capable of achieving high-precision installation of a rail by a simple device configuration, and a rail installation method using the same. The rail installation method includes the steps of: installing the connection jig having a guide-in portion and a holding portion to a first rail fixed in advance and a connection plate fixed to an upper end of a back surface of the first rail in advance by a first fastening member, the holding portion clamping the first rail and the connection plate; hoisting a second rail above the first rail, inserting the second rail into the guide-in portion for guiding the second rail above the first rail and aligning with the first rail; and fastening the second rail and the connection plate by a second fastening member.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to a guide rail installation method and a connecting clamp for automatically installing elevator structural components such as guide rails in an elevator shaft. Background Technology

[0002] In order to maintain construction capacity with a reduced workforce, the construction industry is exploring automation of operations. This is also true in the field of guide rail installation within elevator shafts.

[0003] Patent Document 1 discloses a guide rail connection device comprising a first guide rail holding mechanism for holding an existing guide rail, a second guide rail holding mechanism for holding a guide rail to be lifted, and a third guide rail holding structure that can move in the front-back direction between a position directly above the second guide rail holding mechanism and a position directly above the first guide rail holding mechanism, and when lifting the guide rail held by the second guide rail holding mechanism by steel wire, has a guide rail holding device that holds the lower part of the guide rail and moves it on the same axis as the guide rail erected along the inner wall of the lifting path.

[0004] Existing technical documents

[0005] Patent documents

[0006] Patent Document 1: Japanese Patent JP3034960B2 Summary of the Invention

[0007] The problem the invention aims to solve

[0008] However, in Patent Document 1, multiple holding mechanisms (auxiliary devices) are required, resulting in a complex overall structure and increased costs. Furthermore, the presence of a third rail holding mechanism directly above the second rail holding mechanism restricts the rail's lifting position. Additionally, when using the rail installation device disclosed in Patent Document 1, there is play in the rail's longitudinal direction, making precise positioning difficult.

[0009] The present invention is proposed to solve the above-mentioned problems, and its purpose is to provide a guide rail mounting connection clamp that can achieve high-precision installation of guide rails through a simple device and a guide rail mounting method using the connection clamp.

[0010] Technical means to solve the problem

[0011] A first aspect of the present invention is a guide rail installation method for installing guide rails in an elevator shaft, characterized by comprising the following steps: installing a connecting clamp having an inlet portion and a retaining portion onto a pre-fixed first guide rail and a connecting plate pre-fixed to the upper end of the back side of the first guide rail by a first fastening member, wherein the retaining portion clamps the first guide rail and the connecting plate; suspending a second guide rail above the first guide rail, such that the second guide rail is inserted into the inlet portion, wherein the inlet portion guides the second guide rail above the first guide rail and aligns it with the first guide rail; and fastening the second guide rail and the connecting plate using a second fastening member.

[0012] In one possible implementation of the first aspect described above, the installation of the connecting clamp and the fastening of the second guide rail to the connecting plate are performed by a robotic arm.

[0013] In one possible implementation of the first aspect described above, the following steps are also included: setting a camera device at the front end of the robot arm, identifying and exporting the position of the first fastening member through the image captured by the camera device, and generating an action command based on the position to guide the robot arm's movement, so that the robot arm installs the connecting clamp to the installation position.

[0014] In one possible implementation of the first aspect described above, the following steps are further included: A camera device is installed at the front end of the robotic arm; the image captured by the camera device is used to identify and determine whether the second guide rail is in a position where it can be inserted into the inlet portion; when the horizontal deflection angle of the second guide rail relative to the first guide rail is less than a predetermined angle and the forward offset distance of the second guide rail relative to the first guide rail is less than a predetermined distance, it is determined that the second guide rail is in a position where it can be inserted into the inlet portion, thereby inserting the second guide rail into the inlet portion; when the horizontal deflection angle of the second guide rail relative to the first guide rail is greater than or equal to a predetermined angle or the forward offset distance of the second guide rail relative to the first guide rail is greater than or equal to a predetermined distance, it is determined that the second guide rail is not in a position where it can be inserted into the inlet portion, thereby adjusting the posture of the second guide rail.

[0015] In one possible implementation of the first aspect described above, the following steps are also included: setting a camera device at the front end of the robotic arm, and observing whether the second guide rail is positioned above the first guide rail through the image captured by the camera device.

[0016] In one possible implementation of the first aspect described above, the following steps are also included: when the second guide rail is positioned above the first guide rail, the position of the through hole for the insertion of the second fastening member is identified and exported from the image captured by the camera device. Based on the position, an action command is generated to guide the movement of the robot arm, so that the robot arm inserts the second fastening member into the through hole of the second guide rail and the connecting plate.

[0017] In one possible implementation of the first aspect described above, the following step is also included: after the robotic arm secures the second guide rail and the connecting plate using the second fastening member, it retrieves the connecting clamp.

[0018] A second aspect of the present invention is a connecting clamp for connecting a pre-fixed first guide rail and a second guide rail within an elevator shaft, characterized in that it comprises: an inlet portion having a guiding passage for guiding the second guide rail from a direction or position deviating from the first guide rail to above the first guide rail and aligned with the first guide rail; and a retaining portion disposed below the inlet portion for clamping the first guide rail and the connecting plate when the connecting clamp is installed onto the first guide rail and the connecting plate, wherein the connecting plate is pre-fixed to the upper end of the back side of the first guide rail by a first fastening member.

[0019] In one possible implementation of the second aspect described above, the inlet portion has two inlet blocks disposed on the left and right sides of the inlet of the guide passage. The opposite sides of the inlet blocks, separated from the inlet, are respectively formed in a shape that tilts towards each other as they move upwards. The rear sides of the inlet blocks are respectively formed in a shape that tilts towards the front as they move upwards.

[0020] In one possible implementation of the second aspect described above, the inlet portion has a plurality of openings that, when the connecting clamp is mounted on the first guide rail and the connecting plate, correspond to the positions of through holes provided on the second guide rail and the connecting plate for insertion of the second fastening member.

[0021] In one possible implementation of the second aspect described above, the retaining part simultaneously presses down on the front side of the first guide rail and the left and right sides of the back side of the connecting plate when clamping the first guide rail and the connecting plate.

[0022] In one possible implementation of the second aspect described above, the retaining part has two arms that can extend and retract as movable mechanisms, which, by retracting, press down on the left and right sides of the back of the connecting plate respectively.

[0023] In one possible implementation of the second aspect described above, the retaining portion has a recess in which the head of the first fastening member engages when the connecting clamp is mounted on the first guide rail and the connecting plate.

[0024] In one possible implementation of the second aspect described above, the retaining portion has a receiving portion that communicates with the guide passage in the vertical direction, and the first guide rail is inserted into the receiving portion when the connecting clamp is mounted on the first guide rail and the connecting plate.

[0025] In one possible implementation of the second aspect described above, the retaining portion has two retaining blocks disposed on the left and right sides of the receiving portion, and the opposing sides of the retaining blocks across the receiving portion are shaped to be inclined in a direction that moves further back and further away from each other.

[0026] The effects of the invention

[0027] According to the present invention, a guide rail mounting connection clamp that enables high-precision installation of guide rails through a simple device configuration and a guide rail mounting method using the connection clamp are provided. Attached Figure Description

[0028] Figure 1 This is a schematic diagram of the structure of the guide rail and the connection method between the guide rails.

[0029] Figure 2 This is a diagram showing the overall distribution of the guide rail installation devices inside the elevator shaft.

[0030] Figure 3 This is a frontal perspective view of the connecting fixture.

[0031] Figure 4 This is a three-dimensional view of the back of the connecting clamp.

[0032] Figure 5 This is the main view of the connecting fixture.

[0033] Figure 6 This is the right view of the connecting fixture.

[0034] Figure 7 This is the rear view of the connecting fixture.

[0035] Figure 8 This is a top view of the connecting clamp installed on the first guide rail and the connecting plate. Detailed Implementation

[0036] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and do not limit the scope of protection of this invention.

[0037] The terms “vertical,” “horizontal,” “left,” “right,” and similar expressions used herein are for illustrative purposes only and are not intended to indicate or imply that the device or element referred to must have a specific orientation, be constructed or operated in a specific orientation, and therefore should not be construed as limiting the scope of this application.

[0038] In the description of this application, it should be noted that, unless otherwise explicitly specified and limited, the terms "set," "install," "connect," and "engage" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this application according to the specific circumstances.

[0039] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains. The terminology used herein in the description of the invention is for the purpose of describing particular embodiments only and is not intended to limit the invention. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.

[0040] <The structure of the guide rail and the connection method of the guide rail>

[0041] To better understand this invention, the structure of the elevator guide rails and the connection method between the guide rails in this embodiment will first be described. For example... Figure 1 As shown, the guide rail includes multiple guide rail segments that are connected one after another in a vertical direction starting from the bottom of the shaft. Each guide rail segment includes a fixing part 12 with a cross-section of "—" and a sliding rail part 11 with a cross-section of "|". The fixing part 12 and the sliding rail part 11 are connected to form a "T" shaped cross-section.

[0042] The fixing part 12 has a support frame (bracket) on the back opposite to the slide rail part 11, and the guide rail section can be fixed to the inner wall of the shaft or the crossbeam in the shaft by the support frame.

[0043] A connecting plate 3 is provided at the joint A between the previous fixed guide rail segment 1 (referred to as the "first guide rail" in this embodiment) and the next guide rail segment 2 (referred to as the "second guide rail" in this embodiment). The connecting plate 3 is connected to the upper end of the fixing part 12 on the previous fixed guide rail segment 1 and the lower end of the fixing part 12 on the next guide rail segment 2 by fastening members (such as bolts), and is located on the back of the two fixing parts 12. For ease of explanation, the fastening member that fastens the previous fixed guide rail segment 1, i.e., the first guide rail, and the connecting plate 3 is referred to as the "first fastening member", and the fastening member that fastens the next guide rail segment 2, i.e., the second guide rail, and the connecting plate 3 is referred to as the "second fastening member".

[0044] <Overview of the Shaft>

[0045] Next, the overall distribution of the guide rail installation device within the elevator shaft in this embodiment will be described. For example... Figure 2 As shown, the guide rail mounting device can be simply divided into a traction section and a robot section.

[0046] The traction unit is located at the top of the guide rail mounting device and typically includes traction devices such as winches. The traction device is used to lift the guide rail section.

[0047] The robot unit is located at the lower part of the guide rail installation device. It is pre-installed with an installation robot and other automated mechanical devices. Many steps in the method of this invention are performed by this robot, such as the installation of the connecting clamp 100 for connecting the guide rail segments, the fastening of the guide rail segments to the connecting plate 3, and the retrieval of the connecting clamp 100, thereby achieving automatic installation of the guide rail. Specific details will be described in detail later.

[0048] <Connecting clamp 100>

[0049] Next, use Figures 3-8 The structure of the connecting clamp 100 used in the guide rail installation method of this embodiment will be described in detail.

[0050] Figure 3 This is a front perspective view of the connecting clamp 100. Figure 4 This is a three-dimensional view of the back of the connecting clamp 100. Figure 5 This is the main view of the connecting clamp 100. Figure 6 This is the right view of the connecting clamp 100. Figure 7 This is a rear view of the connecting clamp 100. Figure 8 This is a top view of the connecting clamp 100 mounted on the first guide rail and the connecting plate 3. Among them, [the following text appears to be a separate, unrelated section:] Figure 5Based on this, the upper side in the figure is the upward direction, the lower side is the downward direction, the left side is the left direction, the right side is the right direction, the direction perpendicular to the paper and outward is the forward direction, and the direction perpendicular to the paper and inward is the backward direction. Furthermore, in this invention, the upward and downward directions have the same meaning as the vertical direction and the direction of gravity; the surface connecting the clamp 100 in the forward direction is also called the front side, and the surface connecting the clamp 100 in the backward direction is also called the back side.

[0051] like Figure 3 , Figure 5 and Figure 6 As shown, the connecting clamp 100 can be broadly divided into an inlet section 110 and a retaining section 120. The inlet section 110 is used to guide the insertion of the second guide rail, so that the second guide rail sits on the first guide rail and is aligned with the first guide rail. The retaining section 120 is used to hold the connecting clamp 100, clamping the first guide rail and the connecting plate 3 from three directions.

[0052] The inlet portion 100 is located above the connecting clamp 100, and has two openings 111 on each of the left and right sides. The openings 111 on each side are distributed in the vertical direction, for a total of four openings 111. The number of openings 111 is not limited to four, as long as it corresponds to the number of through holes provided on the second guide rail and the connecting plate 3 for the insertion of the second fastening member.

[0053] For example, when the connecting clamp 100 is installed on the first guide rail and the connecting plate 3, the positions of the four openings 111 are respectively opposite to the positions of the through holes on the connecting plate 3 for the insertion of the second fastening member.

[0054] For example, when the second guide rail is already inserted into the connecting clamp 100, the positions of the four openings 111 are respectively opposite to the positions of the through holes on the second guide rail into which the second fastening member is inserted. Therefore, when fastening the second guide rail and the connecting plate 3 using the second fastening member, it is not necessary to remove the connecting clamp 100; the second guide rail and the connecting plate 3 can be fastened while the second guide rail is inserted into the connecting clamp 100. This reduces the number of installation steps and improves the installation efficiency of the guide rail section.

[0055] like Figure 4As shown, the inlet portion 110 has a guide passage that opens to the rear and upward and extends vertically. The guide passage functions to guide the movement of the guide rail portion 11 and the fixing portion 12. A first inlet block 112 and a second inlet block 113 are provided on the left and right sides of the inlet opening of the guide passage of the inlet portion 110. The opposing sides of the first inlet block 112 and the second inlet block 113, separated by the inlet opening, are respectively shaped to be inclined towards each other in a direction that moves further away from each other towards the top, and the rear sides of the first inlet block 112 and the second inlet block 113 are respectively shaped to be inclined towards the front towards the top. Specifically, the first inlet block 112 and the second inlet block 113 of the inlet section 110 each have multiple upwardly inclined (expanded) slopes. For example, the first inlet block 112 has slopes indicated by arrows A and C, and the second inlet block 113 has slopes indicated by arrows B and C. The slope indicated by arrow A is inclined to the upper left, the slope indicated by arrow B is inclined to the upper right, and the slope indicated by arrow C is inclined to the upper front. In other words, the inlet section 110 has a shape that is inclined (expanded) upwards in at least three directions. For ease of description, the slope indicated by arrow A will be referred to as slope A, the slope indicated by arrow B as slope B, and the slope indicated by arrow C as slope C.

[0056] For example, when the second guide rail is inserted into the connecting clamp 100 from above, even if the slide rail portion 11 of the second guide rail is offset to the left or right by a certain distance in the horizontal direction or deflected to the left or right by a certain angle, it can be automatically guided to the correct position by contacting the inclined surface A of the first guide block 112 or the inclined surface B of the second guide block 113. Furthermore, when the second guide rail is inserted into the connecting clamp 100 from above, even if the fixing portion 12 of the second guide rail is offset forward by a certain distance in the front-back direction, for example, it can be automatically guided to the correct position by contacting the inclined surface C of the first guide block 112 and the second guide block 113. Thus, when the second guide rail is inserted into the connecting clamp 100, it can be automatically positioned by its own weight, and its posture can be automatically adjusted, achieving automatic alignment between the second and first guide rails. This enables high-precision guide rail installation.

[0057] It is understandable that not all the inclined surfaces in the inlet portion 110 are marked with arrows in the figure. Any part that may come into contact with the guide passage of the inlet portion 110 when the second guide rail is inserted into the inlet portion 110 of the connecting clamp 100 can be provided with an upwardly expanding inclined surface (opposite to the insertion direction of the second guide rail).

[0058] The retaining part 120 is located below the connecting clamp 100 and has two extendable and retractable arms on the left and right sides as movable mechanisms. Here, the arm on the left is referred to as "first arm 121" and the arm on the right is referred to as "second arm 122". The retaining part 120 has, for example, a cylinder. By opening the intake valve to allow air to enter the cylinder, the movable mechanism extends. By closing the intake valve and opening the exhaust valve to release air, the movable mechanism retracts.

[0059] It is understood that the movement of the movable mechanism of the retaining part 120 is not limited to this, and also includes any way that allows the first arm 121 and the second arm 122 to extend and retract.

[0060] The retaining part 120 also has a passage that opens to the rear and communicates with the guide passage of the inlet part 110 in the vertical direction. This passage of the retaining part 120 is used to accommodate the slide rail part 11 of the first guide rail when the connecting clamp 100 is mounted on the first guide rail and the connecting plate 3, so this passage of the retaining part 120 can also be called a receiving part. On the left and right sides of the receiving part of the retaining part 120, a first retaining block 124 and a second retaining block 125 are provided. The opposing sides of the first retaining block 124 and the second retaining block 125 across the receiving part are formed in a shape that is inclined towards each other as it moves further back. Specifically, at the opening edge of the receiving part near the rear direction, there is a slope that is inclined to the left and right directions in the vertical direction. For example, the first retaining block 124 has the slope indicated by arrow D, and the second retaining block 125 has the slope indicated by arrow E. The slope indicated by arrow D is inclined to the left rearward, and the slope indicated by arrow E is inclined to the right rearward. In other words, the retaining part 120 has a shape that is inclined (expanded) in at least two directions facing rearward. Hereinafter, for ease of description, the inclined plane indicated by arrow D will be referred to as inclined plane D, and the inclined plane indicated by arrow E will be referred to as inclined plane E.

[0061] For example, when installing the connecting clamp 100 onto the first guide rail and connecting plate 3, even if the connecting clamp 100 is offset to the left or right in the horizontal direction by a certain distance, it can be guided to the correct position by making the inclined surface D of the first retaining block 124 or the inclined surface E of the second retaining block 125 contact the slide rail portion 11 of the first guide rail. Therefore, when installing the connecting clamp 100 onto the first guide rail and connecting plate 3, a certain margin of error is allowed in the left and right directions of the connecting clamp 100, making it easier to install.

[0062] It is understandable that not all the inclined surfaces in the holding part 120 are marked with arrows in the figure. As long as the connecting clamp 100 may come into contact with the receiving part of the holding part 120 when it is installed on the first guide rail and the connecting plate 3, an inclined surface that expands and tilts backward (opposite to the moving direction of the connecting clamp 100 when it is installed) can be provided.

[0063] In addition, such as Figure 4 and Figure 7 As shown, the retaining part 120 also has two recesses 123 on the left and right sides of the back surface. The shape of the recesses 123 is, for example, generally circular or elliptical, and preferably, the opening edge of the recesses 123 near the rear has an enlarged diameter portion.

[0064] For example, when the connecting clamp 100 is installed onto the first guide rail and the connecting plate 3, the slide rail portion 11 of the first guide rail is gradually inserted into the receiving portion of the retaining portion 120. As the slide rail portion 11 is further inserted, the two recesses 120 engage with the heads of the first fastening members on the surface of the first guide rail. This increases the contact area between the rear surface of the retaining portion 120, where the recesses 123 are located, and the first guide rail, allowing for a more secure press against the surface of the first guide rail. Furthermore, by engaging the first fastening members in the recesses, sliding of the connecting clamp 100 in the vertical direction is prevented, and the connecting clamp 100 is prevented from detaching from the first guide rail due to the downward force caused by the insertion of the second guide rail. This improves the reliability of the connecting clamp 100.

[0065] Furthermore, since the opening edge near the rear of the recess 123 has an enlarged diameter portion, the engagement of the head of the first fastening member becomes easier, making it easier to install the connecting clamp 100.

[0066] In addition, such as Figure 4 and Figure 8As shown, the first arm 121 of the retaining part 120 has multiple trapezoidal first claw portions 1211 at its rearward end, and the second arm 122 of the retaining part 120 has multiple trapezoidal second claw portions 1221 at its rearward end. For example, when the connecting clamp 100 is mounted on the first guide rail and the connecting plate 3, the movable mechanism of the retaining part 120, namely the first arm 121 and the second arm 122, retracts. At this time, the multiple first claw portions 1211 and the multiple second claw portions 1221 clamp the left and right sides of the connecting plate 3 near the rear. Therefore, when the connecting clamp 100 is mounted on the first guide rail and the connecting plate 3, not only will the rear surface of the retaining part 120 with the recess 123 press against the front surface of the first guide rail, but the first claw portions 1211 and the second claw portions 1221 will also clamp the left and right sides of the connecting plate 3 near the rear. Because the connecting clamp 100 clamps the first guide rail and the connecting plate 3 from three directions, the connecting clamp 100 can be installed more securely. When the second guide rail is subsequently inserted into the connecting clamp 100, it is beneficial to make the second guide rail more accurately positioned (alignment) relative to the first guide rail. Thus, high-precision guide rail installation can be achieved.

[0067] It is understandable that the shape of the first claw 1211 and the second claw 1221 is not limited to trapezoidal, as long as it can firmly clamp the connecting plate 3.

[0068] <Guide Rail Installation Method>

[0069] The following describes in detail a method for automatically installing guide rails within an elevator shaft using the connecting clamp 100 described above. This method includes the following steps:

[0070] Step S1: Identify the position of the first guide rail;

[0071] Step S2: Confirm the installation position of the connecting clamp 100;

[0072] Step S3: The robotic arm holds the connecting clamp 100 and installs it on the first guide rail and the connecting plate 3;

[0073] Step S4: Hoist the second guide rail above the first guide rail, lower the second guide rail, and move it towards the installation position;

[0074] Step S5: Confirm the movement of the second guide rail and adjust its posture.

[0075] In step S6, the second guide rail is lowered further and inserted into the guide passage of the inlet 110 of the connecting clamp 100. The second guide rail is automatically positioned (aligned) in the connecting clamp 100 by its own weight, and thus sits above the first guide rail.

[0076] Step S7: Secure the second guide rail to the connecting plate 3;

[0077] Step S8: Retrieve the connecting clamp 100.

[0078] Repeat the above steps to install other guide rail sections, and continue this cycle until the predetermined height in the elevator shaft is reached.

[0079] The following provides a detailed explanation of the specific operations for each step.

[0080] First, let's explain the specific operations of steps S1 to S2. An RGB-D camera is installed on the upper part of the front end of the robotic arm. The image captured by the camera is used to locate the position of the first guide rail, which is not yet installed with the second guide rail, in real time.

[0081] Understandably, the type of camera device is not limited to RGB-D camera devices; any camera device that can identify guide rail sections in real time by capturing images is acceptable.

[0082] After identifying the position of the first guide rail, the fastening point between the first guide rail and the connecting plate 3 is located. In the case where bolts are used as the first fastening component, this fastening point is the position where the first guide rail is threadedly engaged with the connecting plate 3. This position where the first guide rail is threadedly engaged with the connecting plate 3 is the installation position of the connecting fixture 100. This installation position is then exported to the installation robot.

[0083] Next, the specific operation of step S3 will be explained. After identifying the installation position of the connecting fixture 100, the connecting fixture 100 is installed at the front end of the robot arm. The installation robot outputs action commands to the robot arm based on the installation position, so that the robot arm holds the connecting fixture 100 and moves it toward the installation position.

[0084] It should be noted that when installing the connecting fixture 100, there is no need to remove the camera device previously installed on the upper front end of the robot arm; both can be installed on the robot arm simultaneously.

[0085] At this time, the movable mechanism of the connecting clamp 100 is in the extended state. The connecting clamp 100 moves further toward the first guide rail, and the slide rail portion 11 of the first guide rail contacts the inclined surface D of the first retaining block 124 or the inclined surface E of the second retaining block 125 on both sides of the receiving portion on the back of the retaining portion 120 of the connecting clamp 100 and is guided into the receiving portion. As a result, as described in the <Connecting Clamp 100> section above, the contact area between the rear surface of the retaining portion 120 with the recess 123 and the first guide rail can be increased, and the surface of the first guide rail can be pressed more firmly. Furthermore, by engaging the head of the first fastening member in the recess, the connecting clamp 100 can be prevented from sliding in the vertical direction, and the connecting clamp 100 can be prevented from falling off the first guide rail due to the downward force caused by the insertion of the second guide rail. This improves the reliability of the connecting clamp 100.

[0086] It is understandable that the slide rail portion 11 of the first guide rail may be inserted directly and accurately into the receiving portion without contacting the inclined surface D of the first retaining block 124 or the inclined surface E of the second retaining block 125.

[0087] After the slide rail portion 11 of the first guide rail is inserted into the receiving portion, the head of the bolt on the surface of the fixing portion 12 of the first guide rail engages with the recess 123 of the retaining portion 120. Then, the movable mechanism retracts, and the first arm 121 and the second arm 122 move toward the first guide rail. Finally, the first claw portion 1211 of the first arm 121 and the second claw portion 1221 of the second arm 122 contact the left and right sides of the connecting plate 3 near the rear, thereby clamping the connecting plate 3. Thus, the installation of the connecting fixture 100 is completed, and the connecting fixture 100 is removed from the robot arm.

[0088] Next, the specific operations of steps S4 to S6 will be explained. After the installation of the connecting fixture 100 is completed, the second guide rail is hoisted above the first guide rail, which has just been installed with the connecting fixture 100, by the traction device in the traction unit located above the robot part where the manipulator is located. The center of the second guide rail (e.g., the slide rail part 11 of the second guide rail) is observed to be directly facing the camera device using an RGB-D camera device. At this time, the second guide rail is allowed to shift a certain distance to the left or right in the horizontal direction or to the left or right at a certain angle. In addition, the second guide rail is also allowed to shift a certain distance forward in the horizontal direction. The certain distance shifted to the left or right is, for example, 10 mm, and the certain distance shifted forward is, for example, 15 mm, but it is not limited to these and other suitable distances are also possible. The certain angle shifted to the left or right is preferably less than 45°, but it is not limited to these and other suitable angles are also possible.

[0089] If the distance of the second guide rail offset observed by the RGB-D camera exceeds the aforementioned distance, the position of the second guide rail can be further adjusted by the traction device; if the angle of the second guide rail deflection observed by the RGB-D camera exceeds the aforementioned angle, the angle of the second guide rail can be adjusted by the rotation mechanism mounted on the traction unit. That is, the posture of the second guide rail can be adjusted by the cooperation of the traction device and the rotation mechanism.

[0090] After the posture of the second guide rail is adjusted, the traction device lowers the second guide rail further. The slide rail portion 11 and the fixing portion 12 of the second guide rail contact the inclined surface of the first guide block 112 or the second guide block 113 of the guide portion 110 of the connecting clamp 100 and are guided into the guide passage. Thus, as described in the <Connecting Clamp 100> section above, when the second guide rail is inserted into the connecting clamp 100, it can be automatically positioned by its own weight, and its posture can be automatically adjusted, realizing automatic alignment between the second guide rail and the first guide rail. This enables high-precision guide rail installation.

[0091] It is understandable that the slide rail portion 11 and the fixing portion 12 of the second guide rail may also be inserted directly and accurately into the guide passage without contacting the inclined surface of the first guide block 112 or the second guide block 113.

[0092] After the second guide rail is inserted into the inlet 110 of the connecting fixture 100, the RGB-D camera device is used to observe whether the second guide rail is positioned above the first guide rail. For example, this can be achieved by observing whether the position of the through hole on the second guide rail for inserting the second fastening member corresponds to the position of the through hole on the connecting plate 3 for inserting the second fastening member. When the position of the through hole on the second guide rail for inserting the second fastening member corresponds to the position of the through hole on the connecting plate 3 for inserting the second fastening member, the position of the through hole on the second guide rail and the connecting plate 3 is derived as the fastening position of the second guide rail and the connecting plate 3 and output to the installation robot.

[0093] Next, the specific operation of step S7 will be explained. After observing through the RGB-D camera that the position of the through hole for inserting the second fastening member on the second guide rail corresponds to the position of the through hole for inserting the second fastening member on the connecting plate 3, that is, after the second guide rail is seated above the first guide rail, the installation robot outputs an action command to the robot arm based on the fastening position of the second guide rail and the connecting plate 3. The robot arm then uses a power tool mounted at the front end of the robot arm to thread the second fastening member, such as a bolt, through the opening 111 of the inlet 110 and into the through hole of the second guide rail and the connecting plate 3. After the fastening of the second guide rail and the connecting plate 3 is completed, the power tool is removed from the front end of the robot arm.

[0094] Understandably, there are no particular limitations on the type of power tool, as long as it can screw the second fastening component, such as a bolt, into the through hole of the second guide rail and the connecting plate 3. There are also no particular limitations on the installation time of the power tool; for example, it can be installed immediately after removing the connecting clamp 100 in step S3, or it can be installed before step S7. From the viewpoint of improving installation efficiency, it is preferable to install the power tool before the second guide rail is fully seated on the first guide rail in step S6.

[0095] Next, the specific operation of step S8 will be explained. After the second guide rail is placed on top of the first guide rail and the second guide rail is fastened to the connecting plate 3, the connecting clamp 100 is removed from the docking point A between the first guide rail and the second guide rail by the robotic arm, thereby completing the recycling operation of the connecting clamp 100.

[0096] Repeat steps S1 to S8 until all guide rail sections are installed.

[0097] According to the guide rail installation method of this embodiment, the installation between guide rail segments is mainly achieved using the connecting clamp 100. There is no need to use a complex device structure to hold the second guide rail, so the lifting position of the second guide rail is not limited by other structural components. Automatic installation of the guide rail segments can be achieved through a simple device structure. Therefore, the overall cost of the device can be reduced.

[0098] According to the guide rail installation method of this embodiment, since the connecting clamp 100 can firmly clamp the first guide rail and the connecting plate 3, and can automatically position the second guide rail, the guide rail installation method using the connecting clamp 100 can perform high-precision guide rail installation operations.

[0099] The embodiments of this application have been described above with reference to specific examples. Those skilled in the art can easily understand other advantages and effects of this application from the content disclosed in this specification. Although the description of this application is presented in conjunction with the embodiments, this does not mean that the features of this application are limited to these embodiments. In addition, in order to avoid confusion or obscuring the focus of this application, some specific details have been omitted in the description.

[0100] Obviously, those skilled in the art can make various modifications and variations to this application without departing from the spirit and scope of this application. Therefore, if such modifications and variations fall within the scope of the claims of this application and their equivalents, this application also intends to include such modifications and variations.

[0101] The embodiments of the present invention have been described above, but these embodiments are merely illustrative and are not intended to limit the scope of the present invention. These embodiments and their variations are included within the scope and spirit of the present invention, as well as within the scope of the invention described in the claims and its equivalents.

[0102] Symbol Explanation

[0103] 1. The upper fixed guide rail section

[0104] 2 Next guide rail segment

[0105] 3 Connecting plate

[0106] A docking point

[0107] 11. Slide rail section

[0108] 12 Fixing Part

[0109] 100 Connecting clamps

[0110] 110 Import Department

[0111] 111 Opening

[0112] 112 First Import Block

[0113] 113 Second Import Block

[0114] 120 Maintenance Section

[0115] 121 First Arm

[0116] 122 Second Arm

[0117] 123 recess

[0118] 124 First Holding Block

[0119] 125 Second Holding Block

[0120] 1211 First Claw

[0121] 1221 Second claw.

Claims

1. A guide rail installation method for installing guide rails in an elevator shaft, characterized in that, Includes the following steps: A connecting clamp having an inlet and a retaining part is installed onto a pre-fixed first guide rail and a connecting plate pre-fixed to the upper end of the back of the first guide rail by a first fastening member, wherein the retaining part clamps the first guide rail and the connecting plate; The second guide rail is suspended above the first guide rail, so that the second guide rail is inserted into the inlet, and the inlet is used to guide the second guide rail above the first guide rail and align it with the first guide rail; as well as The second guide rail is fastened to the connecting plate using the second fastening member.

2. The guide rail installation method according to claim 1, characterized in that, The installation of the connecting clamp and the fastening of the second guide rail to the connecting plate are carried out by a robotic arm.

3. The guide rail installation method according to claim 2, characterized in that, It also includes the following steps: A camera device is installed at the front end of the robotic arm. The position of the first fastening component is identified and exported from the image captured by the camera device. Based on the position, motion commands are generated to guide the robotic arm to install the connecting clamp at the position.

4. The guide rail installation method according to claim 2, characterized in that, It also includes the following steps: A camera device is installed at the front end of the robotic arm. The image captured by the camera device is used to identify and determine whether the second guide rail is in a position where it can be inserted into the inlet portion. When the horizontal deflection angle of the second guide rail relative to the first guide rail is less than a predetermined angle and the forward offset distance of the second guide rail relative to the first guide rail is less than a predetermined distance, it is determined that the second guide rail is in a position where it can be inserted into the inlet portion, thereby allowing the second guide rail to be inserted into the inlet portion. When the horizontal deflection angle of the second guide rail relative to the first guide rail is greater than a predetermined angle or the forward offset distance of the second guide rail relative to the first guide rail is greater than a predetermined distance, it is determined that the second guide rail is not in a position where it can be inserted into the inlet part, and the posture of the second guide rail is adjusted.

5. The guide rail installation method according to claim 2, characterized in that, It also includes the following steps: A camera device is installed at the front end of the robotic arm, and the image captured by the camera device is used to observe whether the second guide rail is positioned above the first guide rail.

6. The guide rail installation method according to claim 5, characterized in that, It also includes the following steps: When the second guide rail is positioned above the first guide rail, the image captured by the camera device is used to identify and export the position of the through hole set on the second guide rail and the connecting plate for the insertion of the second fastening member. Based on this position, an action command is generated to guide the movement of the robot arm, causing the robot arm to insert the second fastening member into the through hole of the second guide rail and the connecting plate.

7. The guide rail installation method according to claim 2, characterized in that, It also includes the following steps: After the robotic arm uses the second fastening member to fasten the second guide rail to the connecting plate, it retrieves the connecting clamp.

8. A connecting clamp for connecting a pre-fixed first guide rail and a second guide rail within an elevator shaft, characterized in that, include: An inlet section having a guiding passage for guiding the second guide rail from a direction or position deviating from the first guide rail to above the first guide rail and aligned with the first guide rail; as well as A retaining part is provided below the inlet part, which clamps the first guide rail and the connecting plate when the connecting clamp is installed on the first guide rail and the connecting plate. The connecting plate is pre-fixed to the upper end of the back of the first guide rail by a first fastening member.

9. The connecting clamp according to claim 8, characterized in that, The inlet section has two inlet blocks, which are disposed on the left and right sides of the inlet of the guide passage. The opposite sides of the inlet blocks, separated by the inlet, are respectively shaped to be inclined towards each other as they move upward. The rear sides of the inlet blocks are respectively shaped to be inclined towards the front as they move upward.

10. The connecting clamp according to claim 8, characterized in that, The inlet portion has multiple openings. When the connecting clamp is installed on the first guide rail and the connecting plate, the openings correspond to the positions of the through holes provided on the second guide rail and the connecting plate for the insertion of the second fastening member. The second fastening member is used to fasten the second guide rail and the connecting plate.

11. The connecting clamp according to claim 8, characterized in that, When the retaining part clamps the first guide rail and the connecting plate, it simultaneously presses down on the front side of the first guide rail and the left and right sides of the back side of the connecting plate.

12. The connecting clamp according to claim 11, characterized in that, The retaining part has two arms that can extend and retract as movable mechanisms. The arms retract to press down on the left and right sides of the back of the connecting plate, respectively.

13. The connecting clamp according to claim 8, characterized in that, The retaining part has a recess, and when the connecting clamp is installed on the first guide rail and the connecting plate, the head of the first fastening member engages in the recess.

14. The connecting clamp according to claim 8, characterized in that, The retaining part has a receiving part that communicates with the guide passage in the vertical direction, and when the connecting clamp is installed on the first guide rail and the connecting plate, the first guide rail is inserted into the receiving part.

15. The connecting clamp according to claim 14, characterized in that, The retaining part has two retaining blocks, which are disposed on the left and right sides of the receiving part. The opposite sides of the retaining blocks across the receiving part are shaped to be inclined towards each other as they move further back.

Citation Information

Patent Citations

  • Hoistway equipment installation device

    JP3034960B2

  • Counterweight receiving fixture of elevator and installation method of counterweight receiving fixture

    CN110526074A

  • Elevator guide rail support assemblies

    CN111039126A