Construction procedure for cross operation of heat exchange hole of building foundation ground source heat pump
By employing cross-operation construction procedures, the problems of mud foaming and mechanical damage to heat exchange tubes in ground source heat pump construction were solved, thereby stabilizing the foundation bearing capacity and improving the construction progress, simplifying the procedures, and saving construction costs.
Patent Information
- Application Number
- CN202410018742.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-05
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-01-05
AI Technical Summary
Given the site constraints around the building, the existing construction process for ground source heat pump buried pipes has problems such as mud soaking the foundation ground, affecting the bearing capacity of the foundation and the construction progress. In addition, mechanical excavation is prone to damaging the heat exchange pipes, resulting in low construction efficiency and complicated procedures.
The construction process adopts a cross-operation approach. First, the original ground is excavated to the first excavation elevation, and mud pits and mud ditches are set up. Holes are drilled to form heat exchange holes. Then, vertical buried pipes are grouted and backfilled. Then, a second excavation is carried out to the theoretical elevation, combined with the construction of horizontal buried pipes. Waterproof sleeves are used to cover the ground source heat pump pipes. The civil engineering unit and the ground source heat pump unit cooperate in the construction.
It improves construction safety and quality, stabilizes foundation bearing capacity, simplifies construction procedures, shortens construction cycle, and saves costs.
Smart Images

Figure CN117781490B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the technical field of ground source heat pump buried pipe heat exchange hole, specifically involving a cross-operation construction process for ground source heat pump heat exchange holes under building foundation. Background Technology
[0002] Ground source heat pump technology is a green, low-carbon, highly efficient, and energy-saving renewable energy utilization technology that has been widely applied in recent years. When there is sufficient space around the building, outdoor open space is often chosen for the placement of the heat exchange holes. When space around the building is limited, the ground source heat pump buried pipe heat exchange holes can be arranged under the building foundation, such as in a garage, thereby improving land resource utilization. However, it is necessary to avoid conflicts between the construction of the heat exchange holes and the excavation of the garage, which involves cross-construction issues between different units.
[0003] Currently, there are two construction procedures for laying ground source heat pump underground pipes under building foundations: one is that the civil engineering unit excavates to the theoretical elevation in one go and then lays the underground pipe heat exchange holes. This requires setting up mud pits and mud ditches on the foundation. To solve the problem of foundation ground foaming caused by mud pits, mud ditches and drilling heat exchange holes, which disturbs the foundation and affects the bearing capacity of the foundation, mud pits and mud ditches are set up at a distance and connected remotely by pipelines. Therefore, this procedure requires high coordination between different units in each link and is difficult. Moreover, there is still a risk of mud leaking from the pipeline and foaming the foundation ground. The construction efficiency is low and the procedure is cumbersome.
[0004] Secondly, the heat exchange pipes are buried underground first, and then the foundation is excavated to the theoretical elevation. However, during the foundation excavation operation, the heat exchange pipes are easily damaged by mechanical excavation, which affects the construction progress and construction cost. Summary of the Invention
[0005] This invention aims to provide a construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundations, which results in high efficiency in cooperation among various units. The cross-operation has low safety risks and solves the problems of the following: the civil engineering unit excavates to the theoretical elevation in one go and then constructs the buried heat exchange holes, which causes the foundation ground to be disturbed by mud foaming, affecting the foundation bearing capacity; and the mechanical excavation of the heat exchange pipes is prone to damage when the heat exchange pipes are constructed first and then the foundation is excavated to the theoretical elevation.
[0006] Therefore, the technical solution adopted in this invention is as follows: a construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation, comprising the following steps:
[0007] Step S1: Excavate from the original ground to the first excavation elevation, and set up mud pits and mud ditches on the excavated surface. Mark the location of the excavation area and drill holes to form heat exchange holes. Then, pressurize and lower the vertical buried pipe.
[0008] Step S2: After the vertical buried pipe is grouted and backfilled, it is excavated again to the theoretical excavation elevation;
[0009] Step S3: Assess the original bearing conditions of the foundation. When the requirements are met, the trench for the horizontal buried pipe is directly excavated, and then the horizontal buried pipe is constructed and connected to the top of the vertical buried pipe. After the pressure test is qualified, the trench for the horizontal buried pipe is backfilled with fine sand, and the fine sand backfill layer and the original soil layer are compacted.
[0010] Step S4: First, the civil engineering unit backfills the concrete cushion layer. Then, the civil engineering unit ties the raft foundation steel bars to carry out the raft foundation construction. At the same time, the ground source heat pump construction unit cooperates in the construction of the waterproof sleeve that passes through the raft foundation. The waterproof sleeve is used to install the ground source heat pump pipeline. Finally, the civil engineering unit continues to construct the backfill layer of the raft foundation and the underground layer, completing the cross-operation construction of the ground source heat pump heat exchange hole under the building foundation.
[0011] As a preferred embodiment of the above scheme, in step S1, the vertical buried pipe is circumferentially bound with inverted "L"-shaped anti-buoyancy bending pipes at intervals along the top and bottom of the pipe body.
[0012] More preferably, the inverted "L"-shaped bend has an obtuse angle, and the obtuse angle range is 100° to 135°. The angle range is reasonable and can ensure the anti-buoyancy effect and structural strength. The vertical end of the inverted "L"-shaped bend is pre-tied to the vertical buried pipe body with tape. The distance between the farthest end of the inverted "L"-shaped bend and the central axis of the heat exchange hole is greater than the radius of the heat exchange hole, so that it can abut against the inner wall of the heat exchange hole and ensure the anti-buoyancy effect.
[0013] A further preferred embodiment is that, in step S1, the vertical buried pipe adopts a double U-shaped buried pipe, which is a reasonable selection.
[0014] More preferably, in step S3, when the original bearing conditions of the foundation do not meet the requirements, the excavation continues downward to the replacement elevation that meets the bearing capacity requirements of the foundation, and then the horizontal buried pipe trench is excavated, the horizontal buried pipe is constructed normally, and after the fine sand backfill layer and the original soil layer are compacted, a cushion layer to improve the bearing capacity of the foundation is backfilled.
[0015] More preferably, the trench depth for the horizontal buried pipe is 450mm to 550mm, and the spacing between the horizontal buried pipes is 40mm to 60mm. This range is reasonable and ensures the safety of the horizontal pipes after backfilling when the original bearing conditions of the original soil layer are not met.
[0016] Further preferably, in step S3, the excavation depth of the horizontal buried pipe trench is 200mm to 220mm, and the spacing between the horizontal buried pipes is 40mm to 60mm, which is a reasonable range and simplifies the construction time.
[0017] More preferably, in step S3, the thickness of the concrete cushion layer is 100mm to 120mm, which is a reasonable range, and the horizontal buried pipe is firmly laid.
[0018] The beneficial effects of this invention are:
[0019] (1) Compared with the process of excavating to the theoretical elevation by the civil engineering unit and then constructing the buried pipe heat exchange hole, which causes the foundation ground to be soaked by mud, resulting in foundation disturbance and affecting the foundation bearing capacity, and the process of constructing the buried pipe heat exchange hole first and then excavating the foundation to the theoretical elevation, which is easy to damage the heat exchange pipe by mechanical excavation, this scheme adopts the method of excavating the foundation to the first excavation elevation, drilling holes to form heat exchange holes, grouting and backfilling the vertical buried pipe, and then excavating a second time to the theoretical excavation elevation. With two excavations, since the mud and cement slurry pool is set on the foundation ground after the first excavation, the silt can be directly dug away during the second excavation, so there is no need to worry about the foundation ground being soaked, thus solving the problem of the foundation ground being soaked and affecting the foundation bearing capacity, and ensuring construction safety and construction quality.
[0020] (2) The civil engineering unit backfills the concrete cushion layer, and then the civil engineering unit ties the raft foundation steel bars to carry out the raft foundation construction. At the same time, the ground source heat pump construction unit cooperates in the construction of the waterproof sleeve that passes through the raft. The waterproof sleeve is used to install the ground source heat pump pipeline. In the process of cross-operation between the ground source heat pump construction unit and the civil engineering unit, the construction procedures are simplified, the amount of repeated work is reduced, the construction cycle is shortened, and the construction cost is saved.
[0021] In summary, it has advantages such as stable foundation bearing capacity, high construction safety, high construction quality, reduced construction procedures, shortened construction period, and reduced construction costs. Attached Figure Description
[0022] Figure 1 This is a schematic diagram of the vertical buried pipe pressure-maintaining lowering pipe structure in step S1 of the present invention.
[0023] Figure 2 This is a schematic diagram of the cross-section of a horizontal buried pipe trench when the original bearing conditions are met.
[0024] Figure 3 This is a schematic diagram of a horizontal buried pipe trench when the original bearing conditions are not met.
[0025] Figure 4 This is a partial structural diagram of a vertical buried pipe with an inverted "L"-shaped anti-buoyancy bend installed. Detailed Implementation
[0026] The present invention will be further described below with reference to the embodiments and accompanying drawings:
[0027] Combination Figure 1 — Figure 4As shown, a construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation is implemented as follows:
[0028] Step S1: Excavate from the original ground level c to the first excavation elevation a, and set up mud pits and mud ditches on the excavated surface. Mark the location of the excavation area and drill holes to form heat exchange holes 9. Then, pressurize and lower the vertical buried pipe 1.
[0029] In step S1, the vertical buried pipe 1 adopts a double U-shaped buried pipe.
[0030] In step S1, the vertical buried pipe 1 is circumferentially tied with inverted "L"-shaped anti-buoyancy bending pipes 11 at intervals along the upper and lower parts of the pipe body.
[0031] The inverted "L"-shaped bent tube 11 has an obtuse angle, and the range of the obtuse angle is preferably 100° to 135°.
[0032] The vertical end of the inverted "L"-shaped bent pipe 11 is pre-tied to the body of the vertical buried pipe 1 with tape. The distance between the farthest end of the inverted "L"-shaped bent pipe 11 and the central axis of the heat exchange hole 9 is greater than the radius of the heat exchange hole 9.
[0033] Step S2: After grouting and backfilling of the vertical buried pipe 1, excavate again to the theoretical excavation elevation b.
[0034] Step S3: Assess the original bearing conditions of the foundation. When the requirements are met, the horizontal buried pipe trench 2 is directly excavated, and then the horizontal buried pipe 3 is constructed and connected to the top of the vertical buried pipe 1. After the pressure test is qualified, the horizontal buried pipe trench 2 is backfilled with fine sand, and the fine sand backfill layer and the original soil layer 4 are compacted.
[0035] In step S3, the preferred excavation depth of the horizontal buried pipe trench 2 is 200mm to 220mm, and the preferred spacing between the horizontal buried pipes 3 is 40mm to 60mm.
[0036] In step S3, when the original bearing conditions of the foundation do not meet the requirements, the excavation continues downward to the replacement elevation that meets the bearing capacity requirements of the foundation. Then, the horizontal buried pipe trench 2 is excavated, the horizontal buried pipe 3 is constructed normally, and the cushion layer 8 to improve the bearing capacity of the foundation is backfilled after the fine sand backfill layer and the original soil layer 4 are compacted.
[0037] In step S3, the thickness of the concrete cushion layer 5 is preferably 100mm to 120mm.
[0038] The preferred excavation depth for the horizontal buried pipe trench 2 is 450mm to 550mm, and the preferred spacing between the horizontal buried pipes 3 is 40mm to 60mm.
[0039] Step S4: First, the civil engineering unit backfills the concrete cushion layer 5. Then, the civil engineering unit ties the raft foundation steel bars to carry out the raft foundation construction. At the same time, the ground source heat pump construction unit cooperates in the construction of the waterproof sleeve that passes through the raft foundation. The waterproof sleeve is used to install the ground source heat pump pipeline. Finally, the civil engineering unit continues to construct the backfill of the raft foundation layer 6 and the underground layer 7, completing the cross-operation construction of the ground source heat pump heat exchange holes under the building foundation.
Claims
1. A construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation, characterized in that, Includes the following steps: Step S1: Excavate from the original ground (c) to the first excavation elevation (a), and set up mud pits and mud ditches on the excavated ground surface. Mark the location of the excavation area and drill holes to form heat exchange holes (9). Then, pressurize and lower the vertical buried pipe (1). Step S2: After grouting and backfilling the vertical buried pipe (1), excavate again to the theoretical excavation elevation (b). Step S3: Assess the original bearing conditions of the foundation. When the requirements are met, the horizontal buried pipe trench (2) is directly excavated, and then the horizontal buried pipe (3) is constructed. The horizontal buried pipe (3) is connected to the top of the vertical buried pipe (1). After the pressure test is qualified, the horizontal buried pipe trench (2) is backfilled with fine sand, and the fine sand backfill layer and the original soil layer (4) are compacted. Step S4: First, the civil engineering unit backfills the concrete cushion layer (5). Then, the civil engineering unit ties the raft foundation steel bars and carries out the raft foundation construction. At the same time, the ground source heat pump construction unit cooperates in the construction of the waterproof sleeve that passes through the raft. The waterproof sleeve is used to install the ground source heat pump pipeline. Finally, the civil engineering unit continues to carry out the construction of the backfill raft layer (6) and the underground layer (7) to complete the cross-operation construction of the ground source heat pump heat exchange hole under the building foundation.
2. The construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation as described in claim 1, characterized in that: In step S1, the vertical buried pipe (1) is circumferentially tied with an inverted "L"-shaped anti-buoyancy bending pipe (11) at intervals along the pipe body.
3. The construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation as described in claim 2, characterized in that: The inverted "L"-shaped anti-buoyancy bend (11) has an obtuse angle, and the obtuse angle ranges from 100° to 135°. The vertical end of the inverted "L"-shaped anti-buoyancy bend (11) is pre-tied to the body of the vertical buried pipe (1) with tape. The distance between the farthest end of the inverted "L"-shaped anti-buoyancy bend (11) and the central axis of the heat exchange hole (9) is greater than the radius of the heat exchange hole (9).
4. The construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation as described in claim 1, characterized in that: In step S1, the vertical buried pipe (1) adopts a double U-shaped buried pipe.
5. The construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation as described in claim 1, characterized in that: In step S3, when the original bearing conditions of the foundation do not meet the requirements, the excavation continues downward to the replacement elevation that meets the bearing capacity requirements of the foundation. Then, the horizontal buried pipe trench (2) is excavated, the horizontal buried pipe (3) is constructed normally, and the cushion layer (8) to improve the bearing capacity of the foundation is backfilled after the fine sand backfill layer and the original soil layer (4) are compacted.
6. The construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation as described in claim 5, characterized in that: The trench (2) for the horizontal buried pipe has an excavation depth of 450mm to 550mm, and the spacing between the horizontal buried pipes (3) is 40mm to 60mm.
7. The construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation as described in claim 1, characterized in that: In step S3, the excavation depth of the horizontal buried pipe trench (2) is 200mm to 220mm, and the spacing between the horizontal buried pipes (3) is 40mm to 60mm.
8. The construction procedure for cross-operation of ground source heat pump heat exchange holes under building foundation as described in claim 1, characterized in that: In step S3, the thickness of the concrete cushion layer (5) is 100mm to 120mm.
Citation Information
Patent Citations
Space-time conversion construction method of vertical underground pipe of deep foundation pit
CN102433883A
Ground-source well digging construction technology
CN103742715A