A method for generating a simplified connection path in a substation
By simplifying substation wiring diagrams, removing single-ended devices, constructing undirected graphs to analyze bus pairing relationships, and optimizing path layout, the problems of large data volume and poor display effect of wiring diagrams are solved, and simplified wiring diagrams are generated efficiently and automatically.
Patent Information
- Application Number
- CN202311505131.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-13
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2043-11-13
AI Technical Summary
In existing technologies, the wiring diagrams of substations contain a large amount of data, have unreasonable busbar and equipment layouts, poor display effects, and are costly and prone to errors when drawn manually.
By simplifying the wiring diagram, removing unnecessary equipment, using the DFS algorithm to filter single-ended equipment, constructing an undirected graph to analyze topology connections, identifying pairing relationships between buses, and optimizing the layout based on voltage level and path type.
Reduce redundancy in wiring diagram equipment, improve display effect and clarity, reduce labor costs, and achieve automated generation of simplified wiring diagrams.
Smart Images

Figure CN117787181B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of automatic layout of substation internal diagrams, and more particularly to a method for generating simplified connection paths within a substation. Background Technology
[0002] The complete data for a substation is enormous. For thematic maps that need to display equipment from multiple substations, showing all the equipment on the map is neither practical nor reasonable. Often, different business scenarios and different personnel only need to focus on a portion of the substation's data. In some cases, technicians will omit the substation map altogether, for example, by using illustrations from academic papers. Using icons to represent substations on large-scale thematic maps, and switching to the substation's primary wiring diagram when the power supply connections within the substation are needed, is certainly a solution, but it is far less convenient than displaying all the necessary information on a single map.
[0003] Among existing patents, patent application number CN202211494151.8, published on March 7, 2023, discloses a method, device, and server for automatically generating primary wiring diagrams of substations. The method includes: acquiring equipment information and equipment topology connection information of a target substation; using the primary equipment information to determine the operating unit to which the target primary equipment belongs in the target substation, and using the operating unit to perform an overall layout of the target substation, obtaining a primary equipment layout diagram; using the secondary equipment information to perform a secondary layout of the target substation, obtaining a secondary equipment layout diagram; and using the equipment topology connection information to perform graphic splicing processing on the primary and secondary equipment layout diagrams to obtain the target wiring diagram. This patent can automatically generate wiring diagrams based on equipment and topology information within the substation. However, its drawback is that the generated wiring diagram contains data for all equipment, making it less practical for users who only care about a portion of the connection methods.
[0004] Patent application number CN202010696012.8, published on October 30, 2020, discloses a method for automatic layout of substation elements applicable to setting calculation software. This method utilizes a computer with a dedicated storage unit and supporting software to layout all electrical equipment in the equipment room, establishing a basic information database of electrical equipment containing connection relationship information, connection line information, and attraction / repulsion rule information. This database is stored in the dedicated storage unit. Based on this, the automatic layout method for substation elements includes the following sub-steps in sequence: reading data, grouping equipment elements, establishing an internal element blockchain, verifying blockchain integrity, generating busbar blocks, block layout, and element block adjustment. This patent defines the block with the most external links as the first block, and the layout method for other blocks follows the attraction / repulsion rule, without prior classification of blocks through grouping or hierarchical methods, which may lead to problems with the layout effect. Summary of the Invention
[0005] To address the problems of massive data volume, unreasonable busbar and equipment layout, poor display effect, high labor cost, and error susceptibility in manual drawing of substation wiring diagrams in existing technologies, this invention proposes a method for generating simplified connection paths within substations. This method removes unnecessary equipment from the primary wiring diagram through simplification steps, performs topology analysis on the equipment of interest to the user, identifies the pairing relationships and path types between buses, and arranges the equipment and paths through a specific layout strategy, thereby achieving a reasonable layout of data within the substation.
[0006] The specific technical solution of this invention is as follows: A method for generating simplified connection paths within a substation, specifically including the following steps: S1: Obtain the corresponding primary wiring diagram data through maintenance tools based on the equipment information and connection methods within the substation, and simplify the primary wiring diagram according to the connection relationship; S2: Analyze the simplified primary wiring diagram to obtain the corresponding equipment topology connection relationship, and analyze the type and characteristics of the connection path; S3: Sort the buses and bays according to different voltage levels, identify the relationship between different types of buses, and lay out and optimize the paths of the buses; S4: Layout the path according to different strategies for different path types.
[0007] In most application scenarios, users do not need to display all the equipment in the substation, but only need to analyze the relevant equipment and paths. In this case, simplifying the wiring diagram can reduce the redundancy of equipment in the diagram, so that the generated wiring diagram can more intuitively display the required information.
[0008] Preferably, the method for simplifying the primary wiring diagram in step S1 specifically includes the following steps: S11: Create a device adjacency matrix A for the devices in the diagram based on their connection point relationships. Where vi and vj are the i-th and j-th devices respectively, then the number of connections for the j-th device is... S12: When N=1, the device is determined to be a single-ended device; when N=2, the device is determined to be an intermediate device; when N>3, the device is determined to be a branch device. Branch devices can be deleted based on their device attributes. S13: Check the connection relationship of devices in the wiring diagram using the DFS algorithm. Record the single-ended devices in the current diagram according to the determination result in step S12. If there are no single-ended devices, proceed to step S15. S14: Delete the single-ended device, analyze whether the device connected to the deleted device is a single-ended device. If it is, repeat step S14; otherwise, go to step S13. S15: The simplified process for determining the outcome is complete.
[0009] The Depth-First Search (DFS) algorithm is a method for traversing or searching trees or graphs. It visits the nodes of the tree along its depth, searching the branches as deeply as possible. In a typical wiring diagram, single-ended devices mainly include single-ended transformers and grounding switches. These devices are generally not considered a focus when users present wiring diagrams; therefore, they can be filtered out by analyzing the site data before layout.
[0010] Preferably, the device topology connection analysis in step S2 includes: The devices in the simplified wiring diagram are set as source points, and a series of devices connected between source points are set as line segments. An undirected graph is formed by source points and line segments. The line segments constitute a path, and the path types include same-level paths, same-level path branch points, different-level paths, and outgoing paths.
[0011] By setting source points, line segments, and constructing an undirected graph, the substation data is simplified, facilitating subsequent analysis and layout. After simplification, the connections between devices are covered by three path types, allowing for better analysis of the structures of different substations and enabling targeted layout designs.
[0012] Preferably, in step S3, the busbar sorting method is to arrange the busbars according to the order in the primary wiring diagram, and the interval sorting method is to arrange the busbars according to the order on the opposite side of the corresponding path. If the current busbar and the opposite busbar are on the same side, the position of the interval is determined according to the distance between the opposite busbar and the current busbar.
[0013] The technicians have already planned the busbars reasonably when drawing the wiring diagram, and this order can also be applied in this method. The bay sorting method is based on the "nearest-farthest" strategy. If the opposite busbar is closer to this busbar, the bay is placed in the order that is closer to the opposite busbar. If the opposite busbar is farther from this busbar, the bay is placed in the order that is farther away from the opposite busbar.
[0014] Preferably, the step S3 of identifying the bus relationship specifically includes the following steps: S31: Divide the buses into different bus sets B = {b1, b2, b3, ...} according to different voltage levels, where b1, b2, and b3 are the buses within that voltage level. Construct an undirected graph for the buses in the bus sets, and obtain the bus adjacency matrix C based on the connection relationships of the buses in the undirected graph. Where bi and bj are the i-th and j-th bus respectively, and c is the number of connection paths between bus bi and bj, satisfying c≥1; S32: When C ij =1,C ik ≥2, C jk When ≥2, the corresponding busbars bi, bj and bk are determined to be a single busbar double-section connection method with bypass busbar, where bk is the bypass busbar. At this time, busbar bk has a pairing relationship with busbars bi and bj respectively. S33: When C ij ≥2, C ik ≥2, C jk When ≥2, the corresponding busbars bi, bj and bk are determined to be a single busbar and double busbar connection method with bypass busbar. At this time, there is a pairing relationship between busbars bi, bj and bk. S34: If there is no bypass bus, then for bus bi, when C ij When C = 1, it is determined that busbars bi and bj are segmented busbars and there is no pairing relationship; when C ij When the value is ≥2, it is determined that there is a pairing relationship between bus bi and bj.
[0015] In practical applications, there are different ways to connect busbars. If the same layout method is used for busbars with different connection methods, the effect is poor when the layout interval is large. Therefore, it is necessary to identify different connection methods and adopt different layout strategies.
[0016] Preferably, in step S3, the busbars are arranged from top to bottom according to the voltage level. Busbars of the same voltage level are arranged from left to right according to the busbar order in the primary wiring diagram. At the same time, buses with a pairing relationship are placed in different rows. If there is any busbar with a pairing relationship in the same row when arranging the buses, it is checked whether the next row can be laid out.
[0017] The connection paths between paired buses are complex. Placing these buses directly in the same row may cause path overlap, resulting in poor display quality. This layout method supports almost all wiring methods, while the few cases that are not supported can be identified as special cases.
[0018] Preferably, after the bus layout is completed in step S3, the different levels of paths connecting the bus are checked. If the abscissas of the starting point and the ending point of the path are different, the path is optimized in descending order of the voltage level difference between the two ends of the path.
[0019] After the busbar layout is completed, unnecessary inflection points may appear in the connection paths between busbars of different voltage levels, affecting the aesthetics of the wiring diagram. Therefore, optimization strategies are needed to address this issue.
[0020] Preferably, the path layout method in step S4 is as follows: When laying out the same-level path, the devices belonging to that interval are laid out sequentially from the left and right sides, and the paths on both sides are connected after the devices are laid out. When laying out different levels of paths, priority is given to laying out paths with a larger voltage level difference on both sides of the path. During the layout process, it is checked whether the path has been partially laid out. If it has been partially laid out, only the unlaid-out part is operated on. The outgoing path is laid out in a straight line from the bus or the branch line of the same level outwards, aligned with the external connection point.
[0021] When laying out same-level paths, priority is given to same-level paths that connect to the bus, followed by same-level paths whose starting or ending point is a branch point of the same-level path, so as to ensure that the coordinates of the starting and ending points of the same-level path are determined when laying out the same-level path.
[0022] Compared with the prior art, the beneficial effects of the present invention are as follows: This invention simplifies the primary wiring diagram through an algorithm, filters equipment within the substation, reduces equipment redundancy on the wiring diagram, and improves the display effect of the simplified diagram.
[0023] This invention analyzes the connection relationships between busbars, determines the pairing relationships of related busbars, optimizes the busbar layout, and improves the clarity and aesthetics of the wiring diagram.
[0024] This invention can be integrated into an automatic diagram generation system to automatically generate simplified wiring diagrams from a single wiring diagram, thereby reducing labor costs. Attached Figure Description
[0025] Figure 1 This is a schematic diagram illustrating one step in generating a simplified wiring diagram provided in an embodiment of the present invention; Figure 2This is a flowchart of a simplified primary wiring diagram provided in an embodiment of the present invention; Figure 3 This is a flowchart of an embodiment of the present invention for identifying the pairing relationship between buses; Figure 4 This is a schematic diagram of the wiring diagram before optimization in an embodiment of the present invention; Figure 5 This is a schematic diagram of the wiring diagram result generated in an embodiment of the present invention. Detailed Implementation
[0026] The specific implementation of the technical solution of the present invention will be further described below through examples and in conjunction with the accompanying drawings.
[0027] This invention provides a method for generating simplified connection paths within a substation. Based on an existing primary wiring diagram, this method uses algorithms to analyze and filter equipment within the substation and simplify it, identifying the busbar wiring methods and then arranging and laying them out accordingly. In the wiring diagram drawn by this invention, the y-direction is up and down, with downward being the positive y-direction; the x-direction is left and right, with right being the positive x-direction.
[0028] Reference Figure 1 The figure shows a schematic diagram of one step in generating a simplified wiring diagram according to an embodiment of the present invention. As shown, this method first requires obtaining the primary wiring diagram of the substation. For substations that require wiring diagrams, relevant personnel manually add the equipment within the substation in the software, fill in the relevant information and connection relationships of the equipment, and adjust the layout and connection paths of the equipment to complete the drawing. This primary wiring diagram includes all busbars, equipment, and their connection methods within the substation.
[0029] In practical applications, users do not need to show all the equipment when displaying the wiring diagram of a substation. If the substation contains many voltage levels or has high voltage levels, the number of busbars and equipment will increase, making the structure of the substation more complex. In this case, the primary wiring diagram will contain a large number of unnecessary parts, so it is necessary to simplify the primary wiring diagram in a specific way.
[0030] The simplification process mainly involves removing single-ended devices from the diagram. Single-ended devices include single-ended transformers and grounding switches, etc. These devices are typically not included in the main connection circuit of the substation and do not need to be shown; therefore, they can be removed from the simplified wiring diagram. Based on the device connection point relationships in the diagram, the device adjacency matrix A can be obtained. Where vi and vj are the i-th and j-th devices, respectively. The device adjacency matrix A represents the connection relationships between devices in a single wiring diagram. The number of connections for the j-th device can be obtained from the device adjacency matrix A. The type of device can be determined based on N. When N=1, the device is determined to be a single-ended device; when N=2, the device is determined to be an intermediate device; when N>3, the device is determined to be a branch device. Branch devices can be deleted based on their device attributes.
[0031] Reference Figure 2 The figure shows a flowchart of a simplified primary wiring diagram provided in an embodiment of the present invention. As shown, after obtaining the primary wiring diagram of the substation, this method analyzes and checks the primary wiring diagram using the Depth-First Search (DFS) algorithm. DFS is an algorithm used to traverse or search a tree or graph, traversing the nodes of the tree along its depth and searching the branches of the tree as deeply as possible. The DFS algorithm analyzes all connection paths in the primary wiring diagram, searching for single-ended devices with only one connected device.
[0032] Once a single-ended device is found, delete it from the wiring diagram, along with any paths connected to it. Afterward, check all devices connected to the deleted device. If the deleted device is also a single-ended device, delete it and check its connected devices. If the devices connected to the deleted device are not single-ended devices, check all devices in the wiring diagram again. If any single-ended devices are found, simplify the process until no single-ended devices exist in the simplified wiring diagram.
[0033] For the devices and connection paths retained in the wiring diagram, their topological connections are analyzed by constructing an undirected graph. The devices retained in the wiring diagram are designated as sources; here, "device" refers to busbars in a substation that do not carry voltage levels. The connection paths between devices are designated as line segments, with both the starting and ending points at the source points. The line segments include other devices between the source points. The source points and line segments constitute an undirected graph, showing the connection methods between devices and simplifying the representation of branchless paths.
[0034] After converting the wiring diagram into an undirected graph, the paths can be divided into three cases based on the structural characteristics of the substation, allowing for more targeted analysis of the substation's structure. Paths can be categorized into four types: same-level paths, same-level path branch points, different-level paths, and outgoing paths. Same-level paths are connection paths between busbars of the same voltage level, consisting of 1-2 line segments. Same-level path branch points are the junctions of different line segments when the same-level path is segmented; the connection paths between same-level path branch points are also considered same-level paths. Different-level paths are connection paths between busbars of different voltage levels. Due to the different voltage levels at their starting and ending points, this path typically includes a transformer. Outgoing paths are paths connecting from inside the substation to the outside, starting at a busbar or a same-level path branch point and ending at an external connection point within the substation.
[0035] Before laying out the equipment within the substation, it is necessary to first plan and classify the equipment to facilitate a better layout. Substations have varying numbers of busbars based on the number and level of the included voltage levels. The number of busbars constitutes a relatively small proportion of the total equipment. Staff have already rationally planned the busbars when drawing the substation's primary wiring diagram, and this order can also be used when drawing simplified wiring diagrams. The busbar order follows the sequence in the primary wiring diagram. This sequence may be represented by characters contained in the names in the original diagram. These characters may be Arabic numerals, Chinese characters, English letters, or Greek letters, depending on the region. When sorting, it is necessary to first identify the busbar names and handle different situations accordingly. The busbar order can also be determined based on the coordinate positions of the busbars in the primary wiring diagram, with the order of the coordinate changes determining the busbar order.
[0036] Substations are divided into different bays based on the combination of incoming lines, main transformer high-voltage, main transformer low-voltage, main transformer, and low-voltage outgoing lines. These bays also need to be sorted before layout. The order of the bays is determined by the order of the busbars on the opposite side of the corresponding path, and their arrangement order is the same as the busbar order on the opposite side. When the busbar order on the opposite side is the same, meaning different bays are arranged on the same side, a "nearest-farthest" strategy is used. This strategy arranges the bays according to the distance between the opposite busbar and the current busbar. If the opposite busbar is closer to the current busbar, the bay is placed in the order closer to the opposite busbar; conversely, if the opposite busbar is farther from the current busbar, the bay is placed in the order farther from the opposite busbar.
[0037] After the busbars and bays are sorted, their layout begins. Based on business requirements and the characteristics of the substation's electrical structure, buses of the same voltage level are typically grouped together. Therefore, the first step in the busbar layout strategy is to arrange the buses from top to bottom according to their voltage levels, with higher voltage level buses at the top and lower voltage level buses at the bottom. Buses of the same voltage level are arranged in the same row, following the order of the previous step. At this point, the distance between the buses is calculated on average based on the number of bays included, and the coordinates of each busbar are set.
[0038] In practical applications, there are various wiring methods between busbars, including double busbars and bypass busbars. These wiring methods can lead to chaotic connection paths within the intervals when drawing wiring diagrams, resulting in poor display quality. Therefore, it is necessary to identify the wiring methods between busbars during layout and adjust the layout accordingly.
[0039] Organize the buses into a bus set B = {b1, b2, b3, ...} according to their voltage levels, where b1, b2, and b3 are the buses within that voltage level. Construct an undirected graph for each bus set, and obtain the bus adjacency matrix C based on the connection relationships of the buses in the undirected graph. Where bi and bj are the i-th and j-th busbars respectively, and c is the number of connection paths between busbars bi and bj, satisfying c≥1.
[0040] The bus adjacency matrix C can display the connection status between different buses. For any buses bi, bj, and bk, when C... ij =1,C ik ≥2, C jk When C ≥ 2, the corresponding buses bi, bj, and bk are determined to be a single busbar double-section connection method with a bypass busbar, where bk is the bypass busbar. In this case, busbar bk has a pairing relationship with busbars bi and bj respectively. When C ij ≥2, C ik ≥2, C jk When the value is ≥2, the corresponding busbars bi, bj and bk are determined to be a single busbar and double busbar connection method with bypass busbar. At this time, there is a pairing relationship between busbars bi, bj and bk. As can be seen from the above, when there is a bypass busbar, there is a pairing relationship between the bypass busbar and the connected busbar.
[0041] If there is no bypass bus, then for bus bi, when C ij When C = 1, it is determined that busbars bi and bj are segmented busbars and there is no pairing relationship; when C ij When the value is ≥2, it is determined that there is a pairing relationship between bus bi and bj.
[0042] Reference Figure 3 The diagram illustrates a flowchart for identifying bus pairing relationships according to an embodiment of the present invention. As shown, this method first checks buses of the same voltage level and analyzes their connection paths to determine whether a pairing relationship exists between them. If two buses are different segments of the same bus (i.e., segmented busbars), then there is no pairing relationship between them. If two buses are connected in a double-busbar configuration, then there is a pairing relationship between them. Other cases are determined based on the number of connection paths between the buses. If two buses contain two or more paths that do not pass through other buses, then there is a pairing relationship between them. If a bypass busbar exists, then there is a pairing relationship between the bypass busbar and the busbar connecting to it.
[0043] After determining the pairing relationship between buses, the layout of buses is adjusted according to the results. Check whether there is a pairing relationship between two buses in the same row. If so, place the paired buses in different rows.
[0044] After the layout is completed, it needs to be optimized. The busbar layout is based on the voltage level and whether there is a pairing relationship. The spacing is calculated based on the number of intervals. At this time, the connection path between buses of different voltage levels may have unnecessary inflection points, affecting the aesthetics of the wiring diagram. Therefore, the position of the buses needs to be adjusted. In this part, this method checks the different levels of paths connecting buses in the wiring diagram. If multiple paths share the same line segment, the path with the larger voltage level difference between the start and end points is selected. The position coordinates of the two buses connected to it are calculated, and the coordinates that eliminate the inflection point of the path are calculated. The busbar that is more to the left between the two (i.e., the busbar with the smaller x-coordinate) is moved to the right. At the same time, the busbar to the right of the first busbar is also moved accordingly, reducing unnecessary inflection points between different levels of paths.
[0045] After the busbars and bays are set up, the paths are laid out according to the type of connection path, mainly including the devices on the path. When laying out sibling paths, priority is given to sibling paths whose starting and ending points are both buses. After that, sibling paths whose starting or ending points are branch points of sibling paths are laid out. For sibling paths, devices are first placed from both ends of the path. After the devices are placed, the coordinates of the path ends containing the devices are calculated. If the y-coordinates of the two ends are different, the path at the shorter end containing the device is extended so that the y-coordinates of the two ends are the same. Then, the path ends are connected by a horizontal line in the x-direction to complete the layout of the sibling paths.
[0046] For paths of different levels, since the inflection points in the path have already been reduced during the previous optimization, we only need to lay out the paths based on the voltage level difference between the two ends of the path, prioritizing the laying out of paths of different levels with larger voltage level differences. Before laying out, it is necessary to check whether the path of different levels has already been partially laid out. If it has been partially laid out, only the coordinates of the unlaid-out parts are set to avoid repeatedly executing the algorithm.
[0047] For outgoing lines, since their orientation is generally outside the substation, the probability of them intersecting with other lines in the diagram is small, and they usually do not have branches. Therefore, it is only necessary to draw a straight line from the starting bus or the branch point of the same level path and align it with the internal and external connection points of the substation in the diagram. If the interval where the path is located corresponds to multiple internal and external connection points of the substation, after the first outgoing line is drawn, only the unlaid-out parts of subsequent outgoing lines need to be drawn, and the laid-out parts do not need to be drawn.
[0048] Example: In this embodiment, the substation structure is drawn based on an actual substation. The substation contains two voltage levels, 20kV and 110kV, with four 20kV busbars and two 110kV busbars. After simplifying the equipment within the substation, the topological connections are analyzed, resulting in the following connection table: Among them, S1-S5 are the internal and external connection points of the substation, and T1 and T2 are the same-level path branch points. Analysis of the above connection table reveals three types of paths: Serial Number Point List edge list type 1 110kVⅠ, 110kVⅡ 2 sibling paths 2 20kVⅠ, T1, 20kVⅡ 6,9 sibling paths 3 20kVⅡ, 20kVⅢ 11 sibling paths 4 20kVⅢ, T2, 20kVⅣ 12,8 sibling paths 5 20kVⅠ, 20kVⅣ 7 sibling paths 6 110kVⅠ, T1 3 Different levels of paths 7 110kVⅡ, T2 5 Different levels of paths 8 110kVⅠ, S1 1 Outbound path 9 110kVⅡ, S2 5 Outbound path 10 20kVⅡ, S3 10 Outbound path 11 20kVⅢ, S4 13 Outbound path 12 20kVⅢ, S5 14 Outbound path For this substation, the busbars can be ordered according to the Greek letters following the voltage level. During the ordering process, the 110kV busbars are in one row, and the 20kV busbars are in the same row below them, with the spacing calculated based on the order and number of bays. After the busbars are arranged, analysis reveals that same-level paths 11 and 12 may intersect with outgoing paths 13 and 14. Therefore, same-level paths 11 and 12 are placed upwards, and outgoing paths 13 and 14 downwards.
[0049] Reference Figure 4 The figure shown is a schematic diagram of the wiring diagram before optimization in an embodiment of the present invention. After the initial layout of the busbar, the result is shown in the figure. At this time, there are unnecessary turning points in the two different level paths containing transformers #1 and #2. The layout is unreasonable and needs to be optimized. The starting point and ending point coordinates of the different level paths are aligned respectively.
[0050] Reference Figure 5 The diagram shown is a schematic representation of the wiring diagram generated in an embodiment of the present invention. As shown, there are no unnecessary inflection points on different levels of paths. Finally, the devices and other components included on each path are arranged.
[0051] In summary, this invention provides a method for generating simplified connection paths within a substation. The method includes acquiring and simplifying a primary wiring diagram, sorting busbars and bays, identifying busbar pairing relationships, and laying out busbars and layout paths. Acquiring and simplifying the primary wiring diagram removes single-ended devices, reducing equipment redundancy and allowing only the necessary parts to be displayed. Identifying busbar pairing relationships reduces the deterioration of the display effect caused by path intersections. This method can be used in automatic diagram generation systems to automatically analyze primary wiring diagrams and generate simplified wiring diagrams, reducing labor costs.
Claims
1. A method for generating simplified connection paths within a substation, characterized in that, Specifically, the following steps are included: S1: Obtain the corresponding primary wiring diagram data through maintenance tools based on the equipment information and connection methods within the substation, and simplify the primary wiring diagram according to the connection relationship; S2: Analyze the simplified primary wiring diagram to obtain the corresponding device topology connection relationship. Set the devices in the simplified primary wiring diagram as source points, and set a series of devices connected between source points as line segments. The source points and line segments form an undirected graph. Analyze the types and characteristics of the connection paths. S3: Sort the buses and bays according to different voltage levels, identify the relationship between different types of buses, and determine whether there is a pairing relationship between the buses; The busbars are laid out and their paths are optimized. The layout of the busbars is adjusted according to the pairing relationship between them. It is checked whether there are two pairs of buses in the same row. If so, the pairs of buses are placed in different rows. The paths are optimized in descending order of the voltage level difference between the two ends of the path. S4: For different path types, the paths are laid out according to different strategies. Specifically: When laying out paths of the same level, the equipment belonging to the interval is laid out sequentially starting from the two busbar sides. When laying out paths of different levels, the paths with larger voltage level differences on both sides of the path are laid out first. When laying out outgoing paths, the paths are laid out in a straight line from the busbar or the branch line of the same level path.
2. The method for generating simplified connection paths within a substation according to claim 1, characterized in that, The method for simplifying the primary wiring diagram in step S1 specifically includes the following steps: S11: Create a device adjacency matrix A for the devices in the diagram based on their connection point relationships. Where vi and vj are the i-th and j-th devices respectively, then the number of connections N for the j-th device = ; S12: When N=1, the device is determined to be a single-ended device; when N=2, the device is determined to be an intermediate device; when N>3, the device is determined to be a branch device. Branch devices can be deleted based on their device attributes. S13: Check the connection relationship of devices in the wiring diagram using the DFS algorithm. Record the single-ended devices in the current diagram according to the determination result in step S12. If there are no single-ended devices, proceed to step S15. S14: Delete the single-ended device, analyze whether the device connected to the deleted device is a single-ended device. If it is, repeat step S14; otherwise, go to step S13. S15: The simplified process for determining the outcome is complete.
3. The method for generating simplified connection paths within a substation according to claim 1, characterized in that, The device topology connection analysis in step S2 includes: the line segments form paths, and the path types include same-level paths, same-level path branch points, different-level paths, and outgoing paths.
4. The method for generating simplified connection paths within a substation according to claim 1, characterized in that, In step S3, the busbar sorting method is to arrange the busbars according to the order in the primary wiring diagram, and the interval sorting method is to arrange the busbars according to the order on the opposite side of the corresponding path. If the current busbar and the opposite busbar are on the same side, the position of the interval is determined according to the distance between the opposite busbar and the current busbar.
5. The method for generating simplified connection paths within a substation according to claim 1, characterized in that, The identification of bus relationships in step S3 specifically includes the following steps: S31: Divide the buses into different bus sets B={b1,b2,b3,...} according to different voltage levels, where b1, b2, and b3 are the buses within that voltage level. Construct an undirected graph for the buses in the bus sets, and obtain the bus adjacency matrix C based on the connection relationships of the buses in the undirected graph. Where bi and bj are the i-th and j-th bus respectively, and c is the number of connection paths between bus bi and bj, satisfying c≥1; S32: When C ij =1, C ik ≥2, C jk When ≥2, the corresponding busbars bi, bj and bk are determined to be a single busbar double-section connection method with bypass busbar, where bk is the bypass busbar. At this time, busbar bk has a pairing relationship with busbars bi and bj respectively. S33: When C ij ≥2, C ik ≥2, C jk When ≥2, the corresponding busbars bi, bj and bk are determined to be a single busbar and double busbar connection method with bypass busbar. At this time, there is a pairing relationship between busbars bi, bj and bk. S34: If there is no bypass bus, then for bus bi, when C ij When C = 1, it is determined that busbars bi and bj are segmented busbars and there is no pairing relationship; when C ij When the value is ≥2, it is determined that there is a pairing relationship between bus bi and bj.
6. The method for generating simplified connection paths within a substation according to claim 1 or 5, characterized in that, In step S3, the busbars are arranged from top to bottom according to the voltage level. Busbars of the same voltage level are arranged from left to right according to the busbar order in the primary wiring diagram. At the same time, buses with a pairing relationship are placed in different rows. If there is any busbar with a pairing relationship in the same row when arranging the buses, it is checked whether the next row can be laid out.
7. The method for generating simplified connection paths within a substation according to claim 1 or 3, characterized in that, After the bus layout is completed in step S3, the different levels of paths connecting the bus are checked. If the horizontal coordinates of the starting point and the ending point of the path are different, the path is optimized in descending order of the voltage level difference between the two ends of the path.
8. The method for generating simplified connection paths within a substation according to claim 7, characterized in that, The path layout method in step S4 is as follows: When laying out the same-level path, the devices belonging to that interval are laid out sequentially starting from the two busbar sides, and the paths on both sides are connected after the devices are laid out. When laying out different levels of paths, priority is given to laying out paths with a larger voltage level difference on both sides of the path. During the layout process, it is checked whether the path has been partially laid out. If it has been partially laid out, only the unlaid-out part is operated on. The outgoing path is laid out in a straight line from the bus or the branch line of the same level outwards, aligned with the external connection point.
Citation Information
Patent Citations
Method for automatically arranging primitives in transformer substation suitable for setting calculation software
CN111859589A
Method and device for automatically generating primary wiring diagram of transformer substation and server
CN115761030A
Automatic generating method of electric network station wiring diagram
CN101901492A
Intelligent identification method for main wiring of power plant and transformer substation
CN116845855A