A ventilation member for natural ventilation of a building unit and a ventilation method thereof
By combining the design of the exhaust chimney and the heat accumulation climbing channel, the problem of the lack of general exhaust components and insufficient thermal pressure suction in building ventilation design is solved. This enables cross ventilation from north to south in low-density and high-rise residential buildings, replacing air conditioning, improving ventilation effect and saving energy.
Patent Information
- Application Number
- CN202410016818.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-04
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-01-04
AI Technical Summary
Existing building ventilation designs lack universal air-drawing components. Atrium air-drawing affects airflow in sunny rooms. The thermal pressure suction of the solar collector is insufficient. Axial fans occupy the chimney flow channel, reducing suction. It is difficult to maintain thermal pressure and air pressure continuously, and cannot completely replace air conditioning.
The design employs a combination of a blower chimney, a main air duct, a heat accumulation and climbing unit, and a variable frequency fan. The heat accumulation and climbing duct establishes thermal pressure ventilation, and the blower chimney enhances thermal pressure air intake and exhaust, ensuring continuous ventilation in the room. The fan is used without occupying the space of the chimney duct.
It enables cross ventilation from north to south in low-density and high-rise residential buildings, continuously maintaining thermal and wind pressure, and can completely replace air conditioning, saving energy and improving ventilation.
Smart Images

Figure CN117824050B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building ventilation, and more specifically to a drafting component for natural ventilation of building units and a ventilation method thereof. Background Technology
[0002] Natural ventilation utilizes naturally occurring airflow in the environment, guiding this airflow through building layout, form, and component design. By leveraging wind pressure and thermal pressure to enhance this airflow, natural ventilation can be achieved. Under suitable external environmental conditions, wind pressure can be the primary method of building ventilation. When a building is subjected to wind pressure, the front experiences positive pressure, while the sides and back experience negative pressure. This pressure difference creates airflow, achieving ventilation. Alternatively, a pressure difference between the entrance and exit of a passageway also creates airflow, achieving ventilation. Thermal pressure is another principle of natural ventilation. Thermal pressure difference is also known as the "chimney effect." Warmer, less dense air rises and exits from the top of the building, creating a negative pressure zone where the low-density air is located. This draws in denser fresh air from outside the building, creating ventilation. Mechanical ventilation is an auxiliary method to natural ventilation. Due to the large depth of buildings, long and complex airflow routes, and significant airflow resistance in many spaces, using mechanical ventilation for natural ventilation is often necessary.
[0003] Existing technologies, with their diverse array of building ventilation designs, present the following technical problems: (1) Lack of universal wind-drawing components.
[0004] Hiroshima Corporation of Japan disclosed a ventilated building (Publication No.: JP2000320031A, Publication Date: November 21, 2000). To solve the technical problem of replacing forced ventilation with natural ventilation in multi-story buildings such as office buildings, the building 1 comprises four floors, each with a living room 4. A transparent glass outer wall 2 forms at the front of the building 1, creating a longitudinally penetrating airflow channel 3 between the transparent outer wall 2 and the upper three floors. An air inlet 7 is located at the bottom of the airflow channel 3, and an exhaust vent 6 is located above the air inlet 3. An opening 20 connecting the airflow channel 5 is formed between the partition 19 of each living room 4 and the ceiling. Due to solar radiation on the outer wall 2, heat accumulates within the airflow channel 5. The thermal pressure causes the solar heat entering the airflow channel 5 from the outer wall 2 to create a chimney effect, continuously drawing air from the air inlet 7 towards the exhaust vent 6. Its disadvantage is that the ventilation channels between the transparent glass outer wall 2 and the rooms on each floor 4 are not universal. Each building has its own architectural design characteristics and cannot be used in other architectural designs.
[0005] (2) The upward draft in the atrium weakens the airflow from south to north in the sunny rooms, which is caused by the cross breeze from north to south through the open doors and windows. Sekisui House KK Co., Ltd. of Japan disclosed a natural ventilation building structure for low-density residential buildings (JP2000081237A, March 21, 2000). This structure addresses the problem of insufficient ventilation in second-floor rooms of low-density residences due to small temperature or pressure differences. The low-density residence comprises at least two floors, with a ridge roof at the top containing an exhaust chamber. A central atrium 3 connects directly to the exhaust chamber at ground level. Air supply vents 1 connecting to the outside are located at the bottom of the exterior walls of each room on the first floor. Ventilation vents 4 connecting to the central atrium 3 are located at the bottom of the interior walls of each room on each floor. Ventilation holes connecting to the ridge roof are located at the top of the interior walls of each room on the top floor. The exhaust chamber includes three stepped chambers, with a minimum cross-section chamber 8 connecting to a roof chimney 7. Sufficient ventilation is ensured by designing a suitable chimney diameter. Insufficient ventilation in the absence of wind is mitigated by incorporating a fan and airflow sensor within the minimum cross-section chamber 8. However, the aforementioned airflow channels mainly pass through the atrium, drawing air to the roof ridge and then releasing it back into the atmosphere. Because the atrium is located in the middle of the building, the airflow paths to and from the rooms on the sunny side are opposite to the normal through-drafts from open doors and windows, and are weakened by these through-drafts, resulting in poor air circulation.
[0006] (3) The collector generates thermal pressure on the continuously flowing air, but the continuous suction force is obviously insufficient. Beijing University of Technology disclosed a solar-enhanced natural ventilation system (CN1844788A, publication date: October 11, 2006). The system features a sloping roof with a ventilation duct 5 connecting to the rooms. The top wall of the ventilation duct 5 is a heat storage wall 12, and a solar collector 4 is installed on the heat storage wall 12. The solar collector 4 collects heat and conducts it to the heat storage wall 12, which heats the air inside the ventilation duct 5, enhancing natural ventilation and expelling hot, humid air from the room. While the still air inside the ventilation duct 5 can be heated by the heat storage wall 12, the heat exchange time is very short when air continuously flows through it. This insufficient time to continuously heat the air to the required temperature results in insufficient sustained suction power because the air cannot be heated and expand.
[0007] (4) The installation of axial flow fans should at least occupy the chimney flow channel with the rotating shaft and fan blades to reduce the suction force of natural ventilation in the chimney. Axial flow fans are typically installed at the top of chimneys to increase ventilation flow. At least the rotating shaft and fan blades of the axial flow fan are located in the chimney flow channel, and even the motor may occupy part of the chimney flow channel. This means that the chimney flow channel is largely occupied, which reduces the ventilation cross-section of the chimney during natural ventilation.
[0008] Therefore, there is an urgent need in this field for a drafting component and ventilation method that aims to replace the natural ventilation of air conditioning, can continuously maintain thermal pressure and wind pressure, thereby creating a cross breeze that runs from north to south through each room, and can use a fan without encroaching on the chimney flow space. This has become a key technical breakthrough in the design of natural ventilation that completely replaces air conditioning in traditional buildings. Summary of the Invention
[0009] To address the shortcomings of the existing technology, the present invention aims to provide a draft member and ventilation method for natural ventilation of building units, which is intended to replace the natural ventilation of air conditioning. It can continuously maintain thermal pressure and wind pressure, thereby creating a cross ventilation that runs from north to south through each room. Fans can be used without encroaching on the space of the chimney duct, thus solving the technical problem of "a ventilation design that can completely replace air conditioning in both low-density and high-rise residential buildings".
[0010] The objective of this invention is achieved by providing a drafting component for natural ventilation in a building unit, the building unit comprising n floors, a sloping roof, and ventilation corridors, where n is a positive integer greater than or equal to 2, and each floor includes rooms facing south and rooms facing north. The chimney is designed to draw air from the bottom of the chimney, where the air inlet connects to the ventilation corridor, forming a vertical airflow channel from the ventilation corridor to its top. The main air supply channel includes the main air intake duct and the main air outlet duct connecting each room. The main air intake duct is located inside the exhaust chimney and is used to continuously generate positive pressure airflow into each room. The main air outlet duct is connected to the exhaust chimney and is used to generate negative pressure airflow in the main air outlet duct that passes through each room from north to south. The heat accumulation and climbing unit is installed on the sloping roof. The inlet of the heat accumulation and climbing unit is connected to the main air outlet duct, and the outlet is connected in parallel to the exhaust chimney. The heat accumulation and climbing unit is used to accumulate and heat up the air inside to form thermal pressure and draw the air from the main air outlet duct to the exhaust chimney.
[0011] Furthermore, the main air intake duct is located inside the chimney and its lower end connects to the ventilation corridor, which is used to send cold air from the ground into each room of the building unit through the air intake vents at the bottom of each room; the main air outlet duct extends vertically from the top of the first floor to the top floor, which is used to extract the air from each room through the air outlet vents at the top of each room, so that each room forms a cross breeze from north to south through the air intake and air outlet.
[0012] Furthermore, the main air intake duct includes a first air intake duct and a second air intake duct. The first air intake duct is used to deliver outdoor air from the bottom of the building unit into the corresponding rooms on each floor of the shaded side. The second air intake duct is installed inside the chimney. The lower end of the second air intake duct is provided with a first air collection port. The first air collection port is located at the lower air inlet of the chimney. The cross-section of the first air collection port gradually decreases from bottom to top. It is used to deliver outdoor air from the bottom of the building into the corresponding rooms on each floor of the sunny side.
[0013] Furthermore, the feature is that the exhaust chimney includes an exhaust chimney and an optional second exhaust chimney, which extends vertically upward from the ventilation corridor to a height at least one floor above the top of the building unit and is located inside the building unit; the second exhaust chimney is located on the shaded side of the building unit and connects the ventilation corridor and the exhaust chimney.
[0014] Furthermore, a ventilation corridor is a passageway on the ground floor or semi-underground of a building that runs directly from the shaded side to the sunny side; or a ventilation corridor is a passageway on the ground floor or underground of a building unit that is enclosed on the shaded side and connected to the ground-level outdoor area on the shaded side of the building through a cooling mechanism.
[0015] Furthermore, the second air intake duct is installed inside the exhaust chimney; when the second exhaust chimney is selected, the first air intake duct is installed inside the second exhaust chimney, and the lower end of the first air intake duct has the same structure as the lower end of the second air intake duct; when the second exhaust chimney is not installed, the first air intake duct is installed outside the building exterior wall of the room on the shaded side, and the lower end of the first air intake duct is provided with an elbow, and the end of the elbow is provided with a first air inlet. The elbow is located in the ventilation corridor facing the shaded side through the first air inlet.
[0016] Furthermore, the upper part of the exhaust chimney is provided with a sleeve and suction holes spaced apart on the outer peripheral wall. A conical annular suction chamber is formed between the sleeve and the exhaust chimney. The suction holes connect the suction chamber and the exhaust chimney. The upper outlet of the heat collection climbing channel is connected to the suction chamber.
[0017] Furthermore, the heat accumulation climbing channel includes a high-transparency glass tube, a heat-absorbing screen tube, a reflector plate, and a mounting plate. The reflector plate is fixed on the upper surface of the mounting plate, and the heat-absorbing screen tube is fixed on the reflector plate. The high-transparency glass tube covers the heat-absorbing screen tube and the reflector plate and is sealed and fixed on the mounting plate.
[0018] Furthermore, the exhaust chimney outlet may optionally be equipped with a variable frequency fan. The variable frequency fan is installed on the top of the exhaust chimney without occupying channel space through an axial flow mechanism. The axial flow mechanism includes a support pit cover, a lower guide cover, and an upper guide cover. The lower guide cover and the upper guide cover are stacked symmetrically around a middle plate. The middle plate has a connecting hole. The lower guide cover is fixedly connected in the support pit cover, and the support pit cover has a pit cover through hole. The output shaft of the variable frequency fan passes through the top wall of the lower guide cover and is fixed, and the fan blades are placed in the guide cavity of the lower guide cover.
[0019] A building ventilation method that utilizes the aforementioned air-lifting component for natural ventilation of building units and optimizes for human comfort. Each room's air inlet is equipped with a valve. Step S0: Input ventilation mode setting and air volume setting; the controller's default ventilation mode is set to natural ventilation mode, and the default air volume is set to low air volume; ventilation modes include natural ventilation, medium air speed, and high air speed; air volume includes low air volume, medium air volume, and high air volume. Step S1: Accept the room's start signal? If yes, proceed. The human comfort index model is constructed as shown in Formula 1.1. (1.1) Where k is the human comfort index, T is the outdoor temperature, F is the relative humidity, and V is the wind speed in m / s; The suitable range for the human comfort index k is as follows: when 51≤k≤60, the wind speed is 1.5-2m / s, the human body feels warm and cool, which is tolerable and is considered high wind speed; when 61≤k≤70, the wind speed is 1-1.5m / s, which is slightly hot and comfortable and is considered medium wind speed; when 71≤k≤75, it is hotter, the wind speed is 0.25-1m / s, which is relatively comfortable and is considered natural ventilation. No, then wait in a loop; Step S2: Given T, F, and V, calculate the actual human comfort index k1 using formula 1.1. Verify whether the human comfort index k1 falls within the corresponding preset ventilation mode. If the actual human comfort index k1 falls within the natural ventilation speed, proceed to step S3; otherwise, check whether the human comfort index k1 falls within the corresponding preset medium wind speed mode, then proceed to step S3.1; otherwise, check whether the human comfort index k1 falls within the corresponding preset high wind speed mode, then proceed to step S3.2. Step S3: Open the valve (41) of the room air inlet (23) to the preset opening degree, open the automatic sunshade 33 of the corresponding room, and turn on the natural wind speed mode; or Step S3.1: Open the valve 41 of the room air inlet (23) according to the preset opening degree, open the automatic sunshade 33 of the corresponding room, start the variable frequency fan 46, low frequency speed, and turn on the medium wind speed mode; or Step S3.2: Open the valve plate 41 of the room air inlet 23 according to the preset opening degree, open the automatic sunshade 33 of the corresponding room, start the variable frequency fan 46, high frequency speed, and turn on the high wind speed mode.
[0020] A draft member and ventilation method for natural ventilation of building units are disclosed. The draft member establishes thermal pressure ventilation from north to south through each room by means of a heat-accumulating climbing channel. The draft member strengthens the air intake of the thermal pressure ventilation and ensures positive pressure airflow at the air intake of the room. At the same time, the draft member strengthens the air outlet of the thermal pressure ventilation, so that each room forms a continuous airflow. In the northwest region of China, it can replace air conditioning to achieve summer ventilation and has practical value in saving energy. Attached Figure Description
[0021] Figure 1 This is a front sectional view of Embodiment 1 of a building wind-lifting component according to the present invention; Figure 2 This is a front sectional view of the heat accumulation climbing channel of Embodiment 1 of a building wind-lifting component of the present invention. Figure 1 (AA section view); Figure 3 This is an embodiment 1 of a building wind-lifting component of the present invention. Figure 1 A magnified view of a section during natural ventilation (Figure I); Figure 4 This is an embodiment 1 of a building wind-lifting component of the present invention. Figure 1 A magnified view of a section during mechanical ventilation (I); Figure 5 This is a front sectional view of Embodiment 2 of a building wind-lifting component of the present invention; Figure 6 This is a front sectional view of embodiment 3 of the building wind-lifting component of the present invention.
[0022] Figure 7 This is a front sectional view of the heat accumulation climbing channel of Embodiment 4 of a building wind-lifting component of the present invention.
[0023] The reference numerals in the above figure: 10. Exhaust chimney; 11. Ventilation duct; 12. Sleeve; 13. Suction port; 14. Support rod; 15. Suction chamber; 17. Exhaust channel. 20 Main air intake channel, 21 Main air inlet duct, 22 Main air outlet duct, 23 Air inlet, 24 Air outlet, 25 Elbow, 26 First air inlet, 27 First air shroud 21.1 First air inlet duct, 21.2 Second air inlet duct, 22.1 First air outlet duct, 22.2 Second air outlet duct 30. Heat accumulation riser channel; 30.1. First riser channel; 30.2. Second riser channel; 31. High-transparency glass tube; 32. Heat absorption screen tube; 33. Mounting plate; 34. Reflector plate. 40 Flow control, 41 Valve plate, 42 Wind speed sensor, 43 Temperature sensor, 44 Humidity sensor, 45 Controller, 46 Variable frequency fan 50 Second chimney, 51 Lower inlet, 52 Top outlet 60 Axial flow mechanism, 61 Support shroud, 61.1 Shroud through hole, 62 Lower air guide shroud, 63 Upper air guide shroud, 64 Middle plate, 65 Spacing plate, 66 Top plate of the shroud, 67 Lower arc-shaped plate, 68 Connecting hole, 69 Flow guiding cavity, 69.1 Axial flow inlet, 69.2 Flow outlet 70 Cooling mechanism, 71 Above-ground air supply duct, 72 Underground air supply duct, 73 Heat exchange guide plate 80 Second heat accumulation riser channel, 81 Heat accumulation air channel, 82 First thermoelectric unit, 83 Second thermoelectric unit, 84 First heat exchange plate, 85 Second heat exchange plate, 86 Reversing ventilation path, 87 Solar collector, 88 Circuit connection block, 89 Electric heating block Detailed Implementation
[0024] The embodiments of the present invention will be described in detail below with reference to the accompanying drawings, but are not intended to limit the scope of the present invention. Example
[0025] A draft member for natural ventilation of a building unit, the building unit comprising n floors, a sloping roof, and ventilation corridors 11, where n is a positive integer greater than or equal to 2, and each floor includes rooms facing south and rooms facing north. A draft chimney 10 extends vertically upward from the ventilation corridor 11 to a height at least one floor above the top of the building unit and is located within the building unit. Its cross-section is much larger than the heat accumulation climbing channel 30. The air inlet of the draft chimney 10 is connected to the top of the ventilation corridor. The draft chimney 10 is used to allow the air inside it to rise vertically upward from the ventilation corridor to its top to form a draft channel 17. The ventilation corridor 11 extends from the shady side of the building unit to the sunny side and passes through the entire thickness of the building to form a channel wind. The main air intake channel 20 includes a main air intake duct 21 and a main air outlet duct 22. The main air intake duct 21 is located inside the chimney 10 and extends vertically upward from the ventilation corridor to the top floor. It is used to deliver cold air from the ground into each room of the building unit through the air inlets 23 located at the bottom of each room. The main air outlet duct 22 extends vertically upward from the top of the first floor to the top floor. It is used to guide the air from each room to the heat accumulation climbing channel 30 through the air outlets 24 located at the top of each room. Each room forms a cross breeze from north to south through the air inlets and outlets. The heat accumulation climbing channel 30 is installed on the sloping roof and is connected between the main air outlet duct 22 and the exhaust chimney 10. It is used to receive sunlight without obstruction, so that the air inside it is heated to form thermal pressure and draws the air from the main air outlet duct 22 to the exhaust chimney 10.
[0026] More preferably, it also includes airflow control 40, with each room's air inlet 23 equipped with a valve 41 and a wind speed sensor 42, and the ventilation corridor 40 equipped with a temperature sensor 43 and a humidity sensor 44. The wind speed sensor 42, temperature sensor 43, and humidity sensor 44 are respectively connected to the controller 45. The valve 41 is used to control the opening of the air inlet, and the airflow control 40 is used to control the wind speed and flow rate per unit time in the room, thereby controlling the cross ventilation in the corresponding room within the range of human comfort.
[0027] The main air intake duct 21 includes a first air intake duct 21.1 and a second air intake duct 21.2. The first air intake duct 21.1 is located outside the building exterior wall of the room on the shady side and is used to deliver outdoor air from the bottom of the building unit to the corresponding rooms on each floor on the shady side. The second air intake duct 21.2 is located inside the exhaust chimney 10 and is used to deliver outdoor air from the bottom of the building to the corresponding rooms on each floor on the sunny side. The lower end of the main air intake duct 21 is connected to the ventilation corridor 11.
[0028] The first air inlet duct 21.1 has an elbow 25 at its lower end, and a first air inlet 26 at the end of the elbow 25. The elbow 25 is located in the ventilation corridor facing away from the shade through the first air inlet 26. The chimney 10 draws in outside air into the ventilation corridor and into the first air inlet 26 to form air pressure. The second air inlet duct 21.2, in addition to the elbow 25 and the first air inlet 26 at its lower end, also has a first air-gathering hood 27. The first air-gathering hood 27 is located at the lower air inlet of the chimney 10. The cross-section of the first air-gathering hood 27 gradually decreases from bottom to top, preferably in a trumpet shape. The cross-section at the lower end is close to and smaller than the cross-section of the lower air inlet of the chimney, and the cross-section at the upper end is equal to the lower cross-section of the second air inlet duct 22.2. The upper part of the first air-gathering hood 27 is connected to the second air inlet duct 21.2 above the air inlet 23 of the first floor room via a pipe. The first air-gathering hood 27 is used to receive the inlet air from the chimney and send the air into the second air inlet duct 21.2.
[0029] The main air outlet duct 22 includes a first air outlet duct 22.1 and a second air outlet duct 22.2. The first air outlet duct 22.1 is installed inside the smoke extraction chimney 10. The first air outlet duct 22.1 and the second air outlet duct 22.2 are respectively connected to the air inlet of the heat accumulation climbing channel 30.
[0030] The heat accumulation ramp 30 includes a high-transparency glass tube 31, a heat-absorbing screen tube 32, a reflector plate 34, and a mounting plate 33. The reflector plate 34 is fixed to the upper surface of the mounting plate 33, and the heat-absorbing screen tube 32 is fixed on the reflector plate 34. The high-transparency glass tube 31 covers the heat-absorbing screen tube 32 and the reflector plate 34 and is sealed and fixed to the mounting plate 33. The heat-absorbing screen tube 32 is made of tubular aluminum mesh, with a black chrome coating as a selective absorption coating. Air entering the high-transparency glass tube 31 undergoes turbulent heat transfer between the mesh openings of the heat-absorbing screen tube 32, thereby improving the heat exchange efficiency between the air and the heat-absorbing screen tube 32. The length L of the heat accumulation ramp 30 satisfies L≥3m, and the inclination angle α satisfies... The heat collection climbing channel 30 can be any air collector with existing technology. Its function is to heat the air entering from the lower inlet as it passes through the heat collection climbing channel 30 and flows out from the top outlet, ensuring that when the air flow velocity V flows through the heat collection climbing channel 30 at 1m / s to 2m / s, the temperature difference ΔT between the upper outlet air temperature and the lower inlet air temperature is ≥5℃.
[0031] The lower end of the heat collection climbing channel 30 is connected to the main air outlet 22, and its upper end outlet 35 is connected to the exhaust chimney 10. Specifically, the exhaust chimney 10 is provided with a sleeve 12 and suction holes 13 spaced apart on the outer peripheral wall. A conical annular suction cavity 15 is formed between the sleeve 12 and the exhaust chimney 10, and the suction holes 13 connect the suction cavity 15 and the exhaust chimney 10. An automatic sunshade is provided outside the heat collection climbing channel 30.
[0032] The chimney 10 is a hollow body with a gradually decreasing inner cross-section, which can be circular, rectangular, or other hollow shapes. The largest inner cross-section is the chimney inlet, which connects to the ventilation corridor. The chimney outlet at the top of the chimney is equipped with a rainproof cap to prevent both backflow of outdoor wind and rain. The negative pressure suction within the chimney 10 serves two purposes: first, the bottom of the chimney 10 draws air from the bottom of the building into the ventilation corridor and sends it into the main air intake duct 21; second, the upper part of the chimney 10 uses negative pressure suction to draw hot air from the heat accumulation climbing duct 30 to the top chimney outlet, thus creating suction air pressure. The main air intake duct 21, the room, the main air outlet duct 22, and the heat accumulation climbing duct 30 constitute a natural ventilation channel. The natural ventilation channel is connected in parallel with the chimney 17 only at the air intake and outlet points; other sections do not intersect with the chimney 17 and are located outside the chimney 17, forming a parallel air path.
[0033] The chimney 10 is optionally equipped with a variable frequency fan 46 at its outlet to regulate the airflow speed V in each room. A rain cap is provided at the chimney outlet via three support rods 14.
[0034] The variable frequency fan 46 is mounted on the top of the exhaust chimney 10 without occupying the space of the chimney flow channel via the axial flow mechanism 60. The axial flow mechanism 60 includes a support pit cover 61, a lower guide cover 62, and an upper guide cover 63. The support pit cover 61 is fixedly installed on the top of the exhaust chimney, and the lower guide cover 62 is fixedly connected in the support pit cover 61. The lower guide cover 62 and the upper guide cover 63 are stacked symmetrically about the middle plate 64. Specifically, the middle plate 64 and the lower arc-shaped plate and the multiple vertically arranged partition plates 65 between them constitute the lower guide cover 62, and the middle plate 64, the top plate of the hood 66, and the multiple partition plates 65 in the same position constitute the upper guide cover 63. The lower guide cover 62 and the upper guide cover 63 each have a guide cavity 69, which has an axial flow inlet 69.1 and multiple flow outlets 69.2. The multiple flow outlets 69.2 of the flow guide cavity 69 of the lower flow guide 62 are inclined upwards, while the multiple corresponding flow outlets 69.2 of the flow guide cavity 69 of the upper flow guide 63 are inclined downwards, and the corresponding flow outlets are arranged axially symmetrically with the middle plate as the axis of symmetry. The middle plate 64 is provided with a connecting hole 68 connecting the flow guide cavities of the lower flow guide 62 and the upper flow guide 63. The variable frequency fan 46 is fixedly connected to the top plate 66 of the upper flow guide 63, and its output shaft extends through the top plate 66 into the flow guide cavity 69 of the upper flow guide 63. The support pit cover 61 is provided with a pit cover through hole 61.1 connecting the axial flow inlet.
[0035] When the variable frequency fan 46 is not started, the chimney 10 will use the lower guide 62 as the main ventilation path. That is, the axial airflow in the chimney is horizontally guided to the radial direction and blown out of the outer periphery of the chimney through the lower guide 62. Some airflow enters the upper guide 63, but due to the obstruction of the airflow at the downward inclined runoff outlet of the upper guide 63 and the upward inclined runoff outlet of the lower guide 62, the airflow at this point is almost stagnant due to the confining effect.
[0036] When the variable frequency fan 46 starts, the main ventilation path of the chimney 10 is the upper guide shroud 63. The fan in the guide cavity of the upper guide shroud rotates, and the axial air in the chimney 10 is drawn upward and flows into the upper guide shroud through the lower guide shroud. Then it is guided horizontally in the radial direction and blown downward at an angle to the outer periphery of the chimney. The outlet airflow blocks the corresponding runoff outlet of the lower guide shroud, so that the ambient airflow outside the chimney cannot be drawn into the chimney to form a backflow.
[0037] In summary, through the axial flow mechanism 60, during natural ventilation, the upward-sloping airflow from the lower guide shroud's outlet 69.2 blocks the downward-sloping outlet of the upper guide shroud, so only the lower guide shroud 62 functions. However, during fan ventilation, the downward-sloping airflow from the upper guide shroud blocks the upward-sloping outlet of the lower guide shroud, so only the upper guide shroud functions, flowing through the cavity of the lower guide shroud. This arrangement also ensures that the variable frequency fan 46, when installed at the top of the chimney 10, does not occupy the flow channel space of the lower guide shroud 62, nor, as shown in the figure, does it occupy the flow channel space of the chimney 10. In contrast, in existing technologies, at least the fan impeller typically needs to occupy the guide cavity of the lower guide shroud, thus occupying the flow channel space of the chimney.
[0038] Variable frequency fans (VFDs) are used when building height is relatively low, such as in two-story low-density buildings with a height of only 7-8 meters and a chimney height of only 9-11 meters. In such cases, the chimney's air pressure suction is insufficient to provide continuous ventilation and cooling for the rooms. If the chimney is tall enough, there is absolutely no need to install VFDs.
[0039] Ventilation corridor 11 is a passageway on the first floor of a building that runs directly from the shaded side to the sunny side. This passageway can also be located semi-underground, with a ramp leading to the ground to ensure that the air temperature inside the ventilation corridor is lower than the ground air temperature.
[0040] A building ventilation method that utilizes draft-resistant components to optimize human comfort. Step S0: Input ventilation mode settings and airflow settings. The controller's default ventilation mode is set to natural ventilation mode, and the default airflow is set to low airflow.
[0041] Ventilation modes include natural wind speed, medium wind speed, and high wind speed. Air volume includes low air volume, medium air volume, and high air volume. At low air volume, the angle between valve plate 41 and the horizontal plane is 60 degrees; at medium air volume, the angle between valve plate 41 and the horizontal plane is 45 degrees; and at high air volume, the angle between valve plate 41 and the horizontal plane is 0 degrees.
[0042] Step S1: Accept the room's start signal? If yes, proceed. The human comfort index model is constructed as shown in Formula 1.1. (1.1) Where k is the human comfort index, T is the outdoor temperature, F is the relative humidity, and V is the wind speed in m / s.
[0043] An air humidity sensor is installed inside the ventilation corridor to measure the relative humidity F of the outdoor air in real time.
[0044] The suitable range for the human comfort index k is as follows: when 51≤k≤60, the wind speed is 1.5-2m / s, the human body feels warm and cool, which is tolerable and belongs to the high wind speed level; when 61≤k≤70, the wind speed is 1-1.5m / s, which is slightly hot and comfortable and belongs to the medium wind speed level; when 71≤k≤75, it is hotter, the wind speed is 0.25-1m / s, which is relatively comfortable and belongs to the natural ventilation level.
[0045] No, then wait in a loop; Step S2: Given T, F, and V, calculate the actual human comfort index k1 using formula 1.1. Verify whether the human comfort index k1 falls within the corresponding preset ventilation mode. If the actual human comfort index k1 falls within the natural ventilation speed, proceed to step S3; otherwise, check whether the human comfort index k1 falls within the corresponding preset medium wind speed mode, then proceed to step S3.1; otherwise, check whether the human comfort index k1 falls within the corresponding preset high wind speed mode, then proceed to step S3.2. Step S3: Open the valve 41 of the room air inlet 23 to the preset opening degree, open the automatic sunshade 33 of the corresponding room, and turn on the natural wind speed mode; or Step S3.1: Open the valve 41 of the room air inlet 23 to the preset opening degree, open the automatic sunshade 33 of the corresponding room, start the variable frequency fan 46 at low frequency speed, and turn on the medium fan speed mode; or Step S3.2: Open the valve plate 41 of the room air inlet 23 according to the preset opening degree, open the automatic sunshade 33 of the corresponding room, start the variable frequency fan 46, high frequency speed, and turn on the high wind speed mode. Example
[0046] The wind pressure is improved, but other features are the same as in Example 1.
[0047] A draft member for natural ventilation of a building unit, the building unit comprising n floors, a sloping roof, and ventilation corridors 11, where n is a positive integer greater than or equal to 2, and each floor has rooms facing south and rooms facing north. The exhaust chimney 10 extends vertically upward from the ventilation corridor 11 to a height at least one floor above the top of the building unit and is located within the building unit. It is used to draw ambient air into the exhaust component at the bottom of the building and then extract the gas from the top of the heat-accumulating climbing channel 30. The main air passage 20 is used to send ambient air from the bottom of the building into each room, which enters from the bottom of the shaded wall, and draws air from the top of the sunlit wall into the heat accumulation climbing passage 30. A heat accumulation riser 30 is installed on the sloping roof and is located between the main air passage 20 and the exhaust chimney 10. It is used to receive sunlight without obstruction, so that the air inside it is heated to form a first thermal pressure and draws the air from the main air outlet 22 to the exhaust chimney 10. The heat accumulation riser 30 includes a first riser 30.1 and a second riser 30.2. The first air outlet 22.1 is connected to the first riser 30.1, and the second air outlet 22.2 is connected to the second riser 30.2. The second exhaust chimney 50 is located on the shaded side of the building unit and connects the ventilation corridor 11 and the exhaust chimney 10. The first air inlet duct 21.1 is located inside the second exhaust chimney 50 and is used to draw air from the ventilation corridor into the first air inlet duct 21.1. The lower inlet 51 of the second exhaust chimney 50 is located at the top of the ventilation corridor 11 and connects to the ventilation corridor. The second exhaust chimney 50 extends along the exterior wall and sloping roof of the building, and its top outlet 52 connects to the exhaust chimney 10. The top outlet 52 is located below the suction chamber 15.
[0048] Both the first air intake duct 21.1 and the second air intake duct 21.2 are equipped with elbows 25 and first air inlets 26 at their lower ends, which are used to receive the air from the ventilation corridor into the first and second air intake ducts and deliver it to the rooms on the first floor. At the same time, the first air intake duct 21.1 and the second air intake duct 21.2 are also equipped with first air hoods 27 at their lower ends. The first air hoods 27 are located at the lower chimney inlets of the exhaust chimney 10 and the second exhaust chimney 50, which are used to receive the air flow from the lower chimney inlets of the exhaust chimneys into the first and second air intake ducts and deliver it to the rooms on the second floor and above. Example
[0049] The air supply structure is improved, but other features are the same as in Example 1 or 2.
[0050] A drafting component for natural ventilation of a building unit, the building unit comprising an n-story building, a sloping roof and a ventilation corridor 11, where n is a positive integer greater than or equal to 2, each floor having a sunny room and a shady room, the ventilation corridor 11 extending from the first floor or basement of the building unit, that is, the ventilation corridor extending from the shady side to the sunny side of the entire thickness of the building, and the shady side being closed, connected to the ground of the shady side through a cooling mechanism 70.
[0051] It also includes a cooling mechanism 70, which is connected to a ventilation chamber 16 and is used to cool ambient air before sending it into the exhaust fan delay 10 and / or the second exhaust fan chimney 50. The elbows 25 at the lower ends of the first air inlet duct 21.1 and the second air inlet duct 21.2 both extend into the ventilation chamber 16. The exhaust fan chimney 10 and / or the second exhaust fan chimney 50 are connected to the ventilation chamber 16 at their top. The cooling mechanism 70 includes an interconnected above-ground air supply duct 71 and an underground air supply duct 72. The above-ground air supply duct 71 is vertically installed with its air inlet extending a certain height above the ground surface. The underground air supply duct 72 is buried at least 1 meter underground, with its other end extending upwards to connect to the ventilation chamber 16. Multiple heat exchange guide plates 73 are installed inside the underground air supply duct 72.
[0052] The cooling mechanism 70 cools the ambient air and then sends it into each room, making the cooling effect of natural ventilation more noticeable. Example
[0053] The improved heat accumulation ramp 30 has the same features as in Examples 1, 2 or 3.
[0054] A draft member for natural ventilation of building units replaces the heat accumulation riser duct 30 with a second heat accumulation riser duct 80. The second heat accumulation riser duct 80 includes a heat accumulation air duct 81, a first thermoelectric unit 82, and a second thermoelectric unit 83. The first thermoelectric unit 82 and the second thermoelectric unit 83 are respectively arranged on the side walls of the heat accumulation air duct 81. The first side wall of the heat accumulation air duct 81 is provided with a plurality of first heat exchange plates 84 at intervals. The second side wall opposite to the first side wall is provided with second heat exchange plates 85 at intervals from the first heat exchange plates 84, so as to form a return ventilation path 86 in the heat accumulation air duct 81, so that the air can fully exchange heat in the return ventilation path 86. A temperature sensor is provided at the air outlet of the heat accumulation air duct 81. The first thermoelectric unit 82 and the second thermoelectric unit 83 form a thermoelectric switching module. The thermoelectric switching module includes solar collectors 87 arranged side-by-side and a circuit connection block 88. The collector tubes of the solar collector 87 of the first thermoelectric unit 82 on the left are integrally connected to the first heat exchange plate 84, and the collector tubes of the solar collector 87 of the second thermoelectric unit 83 on the right are integrally connected to the second heat exchange plate 85. Electric heating blocks 89 are installed inside the first heat exchange plate 84 and the second heat exchange plate 85, and the electric heating blocks are connected to the circuit connection block 88 via sockets.
[0055] The heat from the first heat exchange plate 84 and the second heat exchange plate 85 can come from the solar collector 87 and / or the electric heating block 89.
[0056] The second heat accumulation ramp 80 achieves true heat accumulation through the reversing ventilation path 86, causing the air flowing through the reversing ventilation path 85 to gradually expand in volume as it is heated. When the heat from the solar collector 82 is insufficient to heat the air flowing through the reversing ventilation path 86, the electric heating block 89 is activated to heat the first and second heat exchange plates 84 and 85 until the flowing air reaches and remains within the preset outlet temperature range. The preset outlet temperature range ensures sufficient thermo-pressure ventilation effect.
[0057] Principle Description: A draft-type component and building ventilation method, aiming to solve the technical problem of "creating excellent ventilation designs that can completely replace air conditioning in both low-density and high-rise residential buildings," adopts the following innovative approach: (1) Thermal pressure ventilation and wind pressure ventilation are coordinated in parallel. The natural ventilation duct and the exhaust duct are connected in parallel only at the air inlet and outlet. The exhaust duct simultaneously increases the positive pressure of the air inlet and the negative pressure of the air outlet. ① Enhanced exhaust suction capacity: The air from each room is extracted through the heat accumulation riser duct 30. However, the heating time of the air by the heat accumulation riser duct 30 is the same as the air passage time, so its thermal pressure cannot be maintained continuously. Therefore, the suction capacity cannot be maintained strongly. The top of the exhaust chimney 10 is connected to the upper part of the heat accumulation riser duct 30, thus applying wind pressure suction force to the outlet of the heat accumulation riser duct 30. The positive pressure of the air inlet is superimposed on the thermal pressure suction force of the air outlet, so that the suction force on the main exhaust duct is maintained at a very strong state. ② Enhanced air inlet capacity: The ventilation corridor 11 forms a channel wind. The exhaust chimney 10 uses the continuous suction force of the wind pressure to draw the air in the ventilation corridor upward. The rising airflow is continuously poured into the main air inlet duct 21, forming positive pressure and increasing the air inlet pressure of the main air inlet duct 21.
[0058] (2) The chimney is installed in conjunction with the ventilation corridor to ensure positive pressure at the air intake and negative pressure at the air outlet.
[0059] The ventilation corridor utilizes the pressure difference between the shaded and sunny sides of the building to create a channel wind, while the pressure difference between the top outlet and bottom inlet of the exhaust chimney creates upward positive pressure ventilation. The bottom inlet of the exhaust chimney is located at the top of the channel, and the channel wind provides the channel wind pressure for positive pressure ventilation. The channel wind pressure, combined with the chimney's suction force, sends air into the exhaust chimney and continuously upwards. This continuously upward airflow ensures the positive pressure of the main air intake duct 21. Meanwhile, the air outlet of the parallel heat-accumulating climbing duct at the top also ensures the negative pressure of the air outlet. The positive pressure of the airflow at the air inlet and the negative pressure of the airflow at the air outlet are the ventilation pressure difference of the natural ventilation airflow passing through each room from north to south. While connecting the top of the rooms to a chimney is a common design in the industry, the combined use of a ventilation corridor and an exhaust chimney is a first. The channel wind, combined with the suction force, generates a greater positive pressure at the exhaust chimney, resulting in a continuously upward airflow. Tests have shown that the western region of Inner Mongolia experiences predominantly northwesterly winds, with a level 1 northwesterly wind of 0.3-1.5 m / s. This wind speed generates approximately 1.2 times the tunnel wind speed of 0.36-1.8 m / s. With the auxiliary effect of this tunnel wind speed, the wind speed of the continuously upward-flowing airflow inside the 10-meter-high chimney is almost close to that of the tunnel wind speed. Therefore, the chimney, in conjunction with the ventilation corridor, ensures positive pressure at the intake and negative pressure at the outlet.
[0060] (3) The air inlet pipe is placed in the chimney to ensure positive pressure air intake while the air inlet of the room is not affected by negative pressure suction.
[0061] The air inlet duct is placed inside the chimney, ensuring positive pressure airflow at the lower end of the duct. This positive pressure airflow is maintained at the air inlet 23 in each room. Because the air inlet duct is isolated from the chimney's flue, the air inlet 23 is not affected by the chimney's draft airflow and is not subject to backflow. In contrast, if the chimney directly opens into each room, the air inlet may become the outlet that draws air from the room into the chimney, resulting in backflow airflow. This is a common problem in existing buildings where bathroom ventilation vents are directly connected to the chimney, leading to odors. Placing the air inlet duct inside the chimney completely avoids this backflow airflow phenomenon.
[0062] (4) The axial flow mechanism 60 enables the axial flow fan to be installed without occupying the space of the chimney flow channel.
[0063] The axial flow mechanism 60 uses a symmetrical arrangement of a lower guide shroud 62 and an upper guide shroud 63. During natural ventilation, the upward-sloping airflow from the lower guide shroud's outlet 69.2 blocks the airflow from the upper guide shroud's outlet, so only the lower guide shroud 62 is active. However, during forced ventilation by the fan, the downward-sloping airflow from the upper guide shroud blocks the upward-sloping airflow from the lower guide shroud, so the axial airflow only flows through the axial inlet of the lower guide shroud and is then drawn upward into the axial inlet of the upper guide shroud. The airflow then flows downward along the upper guide shroud's outlet towards the surrounding environment of the chimney 10, at which point only the upper guide shroud 63 is active.
[0064] A draft member for natural ventilation of building units utilizes the thermal pressure suction effect of the heat-accumulating climbing channel 30 on the sloping roof of the building, combined with the wind pressure suction effect at the top of the draft chimney 10, to help each room form a continuous north-to-south ventilation airflow. This airflow is in the same direction as the airflow of normal door and window ventilation, ensuring that each room maintains continuous ventilation and coolness to the human body in summer. It can replace air conditioning in western Inner Mongolia.
Claims
1. A ventilation member for natural ventilation of a building unit, the building unit comprising n layers of houses, a pitched roof, n being a positive integer equal to or greater than 2, each layer of houses comprising a sun-facing room and a shade-facing room, characterized in that, include The chimney (10) includes a connected ventilation corridor (11), a draft channel (17), and a variable frequency fan (46). The air inlet at the lower end of the draft channel (17) is located in the ventilation corridor (11) and connected to the ventilation corridor (11). The draft channel (17) extends vertically upward from the ventilation corridor to a height at least one floor above the top of the building unit. The ventilation corridor (11) is a passageway on the first floor of the building that runs through the entire thickness of the building from the shaded side to the sunny side. The variable frequency fan (46) is installed without occupying the passage space through an axial flow mechanism. At the top of the blower chimney (10); the axial flow mechanism (60) includes a support pit cover (61), a lower guide cover (62) and an upper guide cover (63). The lower guide cover (62) and the upper guide cover (63) are stacked symmetrically about the middle plate (64). The middle plate (64) is provided with a connecting hole. The lower guide cover (62) is fixedly connected in the support pit cover (61). The support pit cover (61) is provided with a pit cover through hole (61.1). The output shaft of the variable frequency fan (46) passes through the top wall of the lower guide cover (62) and is fixed, and the fan blades are set in the guide cavity of the lower guide cover. The main air intake channel (20) includes a main air intake channel (21) and a main air outlet channel (22) connecting each room. The air intake of the main air intake channel (21) is located in the ventilation corridor (11) to continuously form a positive pressure air intake airflow into each room. The main air outlet channel (22) is connected to the heat accumulation and climbing unit to form a negative pressure air outlet airflow that passes through each room from north to south in the main air outlet channel (22). The heat accumulation and climbing unit is installed on the sloping roof. The main air outlet (22) of the main air channel (20) is connected to the air inlet of the heat accumulation and climbing unit. The upper air outlet of the heat accumulation and climbing unit is connected in parallel to the exhaust channel (17). The heat accumulation and climbing unit is used to make the air inside it accumulate and rise in temperature to form thermal pressure and draw the air from the main air outlet (22) to the exhaust channel (17). The ventilation corridor (11) utilizes the air pressure difference between the shaded and sunny sides of the building to form a roadway wind. The air pressure difference between the top outlet and the bottom inlet of the chimney (10) forms a chimney suction force. The roadway wind superimposed on the chimney suction force forms a positive pressure ventilation that flows continuously upward. This positive pressure ventilation ensures the positive pressure of the main air intake duct (21). At the same time, the chimney suction force generates a negative pressure at the top outlet of the heat accumulation and climbing unit.
2. The draft-exhaust component for natural ventilation of a building unit as described in claim 1, characterized in that, The heat accumulation climbing unit includes a heat accumulation climbing channel (30) and a parallel connecting air extraction channel (17) as follows: the upper part of the air extraction chimney (10) is provided with a sleeve (12) and suction holes (13) spaced apart on the outer peripheral wall. A conical annular suction cavity (15) is formed between the sleeve (12) and the air extraction chimney (10). The suction holes (13) connect the suction cavity (15) and the air extraction chimney (10). The upper outlet (35) of the heat accumulation climbing channel (30) connects to the suction cavity (15).
3. The drafting component for natural ventilation of a building unit as described in claim 1, characterized in that, The main air intake duct (21) is located inside the chimney (10) and its lower end is connected to the ventilation corridor (11). It is used to send cold air from the ground into each room of the building unit through the air intake (23) set at the bottom of each room. The main air outlet duct (22) extends vertically from the top of the first floor to the top floor. It is used to draw the air out of each room through the air outlet (24) set at the top of each room, so that each room forms a cross breeze from north to south through the air intake and air outlet.
4. The drafting component for natural ventilation of a building unit as described in claim 1, characterized in that, The main air intake duct (21) includes a first air intake duct (21.1) and a second air intake duct (21.2). The first air intake duct (21.1) is used to deliver outdoor air from the bottom of the building unit into the corresponding rooms on the shaded side. The second air intake duct (21.2) is installed inside the chimney (10). The lower end of the second air intake duct (21.2) is provided with a first air hood (27). The first air hood (27) is located at the air inlet at the lower end of the chimney (10). The cross-section of the first air hood (27) gradually decreases from bottom to top. It is used to deliver outdoor air from the bottom of the building into the corresponding rooms on the sunny side.
5. The drafting component for natural ventilation of a building unit as described in claim 1, characterized in that, The ventilation corridor (11) is a passageway on the first floor or semi-underground of a building that runs directly from the shaded side to the sunny side; or the ventilation corridor (11) is enclosed by the shaded side of the passageway on the first floor or underground of a building unit and connected to the outdoor area above the shaded side of the building through a cooling mechanism (70).
6. The drafting component for natural ventilation of a building unit as described in claim 4, characterized in that, The second air intake duct (21.2) is set inside the exhaust chimney (10); when the second exhaust chimney (50) is selected, the first air intake duct (21.1) is set inside the second exhaust chimney (50), and the lower end of the first air intake duct (21.1) has the same structure as the lower end of the second air intake duct (21.2); when the second exhaust chimney (50) is not set, the first air intake duct (21.1) is set outside the building wall of the room on the shady side, and the lower end of the first air intake duct (21.1) is provided with an elbow (25), and the end of the elbow (25) is provided with a first air inlet (26). The elbow (25) is set in the ventilation corridor facing the shady side through the first air inlet (26).
7. The drafting component for natural ventilation of a building unit as described in claim 1, characterized in that, The exhaust chimney (10) also includes a second exhaust chimney (50), which is located on the shaded side of the building unit and connects the ventilation corridor (11) and the exhaust chimney (10).
8. The drafting component for natural ventilation of a building unit as described in claim 1, characterized in that, The heat accumulation climbing unit includes a second heat accumulation climbing channel (80), which includes a heat accumulation air channel (81) and thermoelectric units disposed on both sides thereon. Multiple heat exchange plates are alternately and spaced on the two opposite side walls of the heat accumulation air channel (81) to form a foldback ventilation path (86) in the heat accumulation air channel (81). The heat exchange plates are integrally connected to the thermoelectric units on the same side.
9. A building ventilation method utilizing the air-extraction component for natural ventilation of building units as described in any one of claims 1-8, with human comfort as the optimization objective, characterized in that, Each room’s air inlet (23) is equipped with a valve plate (41); Step S0: Input ventilation mode setting and air volume setting; the controller's default ventilation mode is set to natural ventilation mode, and the default air volume is set to low air volume; ventilation modes include natural ventilation, medium air speed, and high air speed; air volume includes low air volume, medium air volume, and high air volume. Step S1: Accept the room's start signal? If yes, proceed. The human comfort index model is constructed as shown in Formula 1.
1. (1.1) Where k is the human comfort index, T is the outdoor temperature, F is the relative humidity, and V is the wind speed in m / s; The suitable range for the human comfort index k is as follows: when 51≤k≤60, the wind speed is 1.5-2m / s, the human body feels warm and cool, which is tolerable and is the high wind speed mode; when 61≤k≤70, the wind speed is 1-1.5m / s, which is slightly hot and comfortable and is the medium wind speed mode; when 71≤k≤75, it is hotter, the wind speed is 0.25-1m / s, which is relatively comfortable and is the natural ventilation mode. No, then wait in a loop; Step S2: Given T, F, and V, calculate the human comfort index k using formula 1.
1. Verify whether the human comfort index k falls within the corresponding preset ventilation mode. If the human comfort index k falls within the natural ventilation mode, proceed to step S3; otherwise, check whether the human comfort index k falls within the corresponding preset medium wind speed mode, then proceed to step S3.1; otherwise, check whether the human comfort index k falls within the corresponding preset high wind speed mode, then proceed to step S3.
2. Step S3: Open the valve (41) of the room air inlet (23) to the preset opening degree, open the automatic sunshade of the corresponding room, and turn on the natural wind speed mode; or Step S3.1: Open the valve (41) of the room air inlet (23) according to the preset opening degree, open the automatic sunshade cloth of the corresponding room, start the variable frequency fan (46) at low frequency speed, and turn on the medium wind speed mode; or Step S3.2: Open the valve plate (41) of the room air inlet (23) according to the preset opening degree, open the automatic sunshade cloth of the corresponding room, start the variable frequency fan (46) at high frequency speed, and turn on the high wind speed mode.
Citation Information
Patent Citations
Solar energy enhanced natural ventilating and green lighting system
CN1844788A
Building
JP2000320031A
Passive type ventilating system of science and technology museum building
CN103644620A
Air conditioner and air outlet control method thereof
CN115264912A
Natural heat dissipating ventilation system of multi-layer or high-rise building
CN204043125U