一种超长劲性复合桩废桩的处理方法
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- MCC CHENGDU RES INST CO LTD
- Filing Date
- 2024-01-24
- Publication Date
- 2026-07-17
AI Technical Summary
In existing technologies, the failure of ultra-long PHC pipe piles to be properly pressed or the bursting of the pile head can lead to unrepairable piles, affecting the quality and efficiency of the project.
The method of using a down-the-hole hammer for symmetrical pre-drilling, employing thin-skinned PVC pipes for pipe insertion, and backfilling with river sand to treat the waste piles of ultra-long stiff composite piles reduces pile end resistance and pile side friction, protects the borehole, and ensures smooth extraction.
It enables rapid and efficient treatment of waste piles in ultra-long and stiff composite piles, improving the accuracy and efficiency of construction and reducing the risk of borehole collapse in engineering projects.
Smart Images

Figure CN117845926B_ABST