一种滑移式预制拱形陶砖幕墙的施工方法
By using a sliding precast arched terracotta brick curtain wall construction method, the entire arched terracotta brick curtain wall is precast and slid-installed, solving the problems of complexity and low efficiency in traditional construction and achieving highly efficient construction results.
CN117846316BActive Publication Date: 2026-07-17SHANGHAI BAOYE BUILDING DECORATION CO LTD +1
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- SHANGHAI BAOYE BUILDING DECORATION CO LTD
- Filing Date
- 2024-01-08
- Publication Date
- 2026-07-17
AI Technical Summary
Technical Problem
Traditional arched terracotta brick curtain wall construction is complex, difficult, inefficient, and time-consuming.
Method used
The construction method of using a sliding precast arched terracotta brick curtain wall includes laying arched keel and support frame, precasting the arched terracotta brick curtain wall and sliding it as a whole to the installation position, fixing the main keel and removing the support frame, and then carrying out grouting construction.
Benefits of technology
Prefabrication and installation as a whole improves construction efficiency, shortens construction period, and ensures the flatness and firmness of the ceramic brick units.
✦ Generated by Eureka AI based on patent content.
Smart Images

Figure CN117846316B_ABST
Abstract
本发明涉及一种滑移式预制拱形陶砖幕墙的施工方法,包括以下步骤:铺设并焊接拱形龙骨;在所述拱形龙骨内部铺设并焊接拱形支撑架;在所述拱形龙骨与所述拱形支撑架之间铺设陶砖单元,其中,陶砖单元与所述拱形龙骨连接,所述拱形龙骨、所述拱形支撑架以及所述陶砖单元共同构成预制拱形陶砖幕墙;预设时间后,将所述预制拱形陶砖幕墙滑移至待安装位置,将所述拱形龙骨中的主龙骨固定;待所述预制拱形陶砖幕墙稳定后,将所述拱形支撑架撤离,进行拱底勾缝;一方面,通过设置拱形支撑架,保证了陶砖单元的平整度;另一方面,通过将滑移式预制拱形陶砖幕墙作为整体预制而后整体安装,提高了施工效率,缩短了施工工期。