A test method for safe operation of an automatic driving system of a tower crane

By using no-load, loaded, and overload testing methods for the tower crane automatic driving system, the problem of evaluating the performance and safety of tower cranes under different load conditions is solved, ensuring the stable operation and safety of the system under various conditions and preventing accidents.

CN117873039BActive Publication Date: 2026-11-20中科骊久(济南)机器人有限公司
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410067657.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-17
Publication Date
2026-11-20
Estimated Expiration
2044-01-17

Smart Images

  • Figure CN117873039B_ABST
    Figure CN117873039B_ABST
Patent Text Reader

Abstract

The application provides a test method for safe operation of a tower crane automatic driving system, belonging to the technical field of tower crane testing, comprising tower crane no-load operation testing, tower crane load operation testing and tower crane overload operation testing; the tower crane no-load operation testing: in the no-load state of the tower crane, the automatic operation function of the control terminal is activated to compare the set position with the actual arrival position; the electric operation of the hook is controlled by using a handheld microcontroller, and the running state of the hook is observed, so that the no-load operation testing can verify the performance of the system under different working conditions, the functions in the control precision, safety and efficiency, and the performance of the tower crane unmanned automatic control system can be evaluated through the no-load and load testing; the tests can verify the control precision, safety and performance of the system under different load conditions, thereby providing reliable evaluation of the system effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of tower crane testing, and specifically relates to a testing method for the safe operation of a tower crane automatic driving system. Background Technology

[0002] The no-load and loaded tests of the tower crane's unmanned automatic control system are conducted to verify the system's performance and safety under different load conditions. The testing process involves multiple technologies and equipment, including load pressure sensors, data acquisition systems, test platforms and simulators, control algorithms and software systems, and safety detection systems.

[0003] During testing, load pressure sensors are required to measure the load on the tower crane. These sensors can be installed on the crane's spreaders or other critical locations to monitor load changes in real time. The load pressure sensors need to be highly accurate and reliable, capable of accurately measuring the tower crane's load.

[0004] Simultaneously, for testing purposes, a data acquisition system needs to be installed to collect and record various data from the tower crane under different load conditions, such as load changes, the tower crane's motion status, and sensor readings. The data acquisition system needs to be capable of high-speed data acquisition and real-time data processing and storage.

[0005] To simulate real-world working scenarios, a test platform or simulation software is needed to model the tower crane's operating environment. This could include a simulation of the tower crane's structure and power system, as well as a simulation of the working environment, such as a construction site.

[0006] During testing, pre-designed control algorithms and software systems are required to achieve automatic operation and control of the tower crane. These algorithms and systems should be able to automatically adjust the tower crane's motion control according to load changes, ensuring the stability and safety of the tower crane.

[0007] More importantly, to ensure the safety of the testing process, a safety monitoring system needs to be installed to monitor the status and environment of the tower crane and issue alarms or take appropriate measures in a timely manner to prevent accidents.

[0008] The combined use of these technologies and equipment can provide the necessary support and assurance for system testing and verification.

[0009] Existing tower crane autopilot systems rely on pre-set instructions and sensor-collected information to complete automated operation. During unmanned operation, both empty and loaded states of the tower crane affect the efficiency of the autopilot system. Therefore, a testing method for unloaded and loaded tower cranes is needed to determine the reliability and safety of the tested unmanned autopilot control system.

[0010] When the tower crane is unloaded, the autopilot system is easier to control because no additional load affects the crane's movement and center of gravity, allowing the system to more accurately estimate the crane's motion and position. In this situation, the system's response speed is also faster, and the tower crane's autopilot performance is superior when unloaded.

[0011] However, when a tower crane is loaded, its center of gravity shifts, which can affect the autopilot system. The autopilot system needs to recalculate based on the tower crane's load to ensure no unexpected situations occur during operation. Therefore, when the tower crane is loaded, the autopilot system requires more time to execute more complex algorithms to ensure the stability and safety of the tower crane. Thus, the hook no-load and loaded testing methods based on the unmanned automatic control system of tower cranes are particularly important.

[0012] Tower crane overload testing requires the use of tower crane control technology to achieve autonomous operation and control of the tower crane. This technology involves sensor data processing, modeling, and control algorithms. Overload testing requires sensors to obtain various parameters of the tower crane, including real-time position information such as the current luffing, elevation, and slewing angle of the hook, and current torque and load weight obtained through installed weight and torque sensors. The sensors can electronically transmit the measured values ​​to the tower crane's automatic driving control system. The tower crane's automatic driving control system records, stores, and analyzes the acquired sensor data in real time. It determines whether the tower crane is overloaded or is about to be overloaded, issues corresponding warnings and alarms, and uses the control panel to limit gears, control speed, and brake in time to avoid reaching the overload threshold.

[0013] Overload testing must comply with relevant national standards and industry specifications. These standards and specifications provide technical requirements for the design, installation, operation, and maintenance of tower crane automatic driving systems to ensure the safety and reliability of tower cranes. GB 5144-2006 Safety Regulations for Tower Cranes and GB / T 5031-2019 Tower Cranes require: When the lifting torque is greater than the corresponding rated value but less than 110% of the rated value, the lifting and outward luffing actions should be stopped, but the lowering and inward luffing actions should still be performed.

[0014] For tower cranes with trolley luffing, if the maximum luffing speed exceeds 40 m / min, the luffing speed should automatically switch to a speed not exceeding 40 m / min when the trolley is moving outward and the lifting torque reaches 80% of the rated value.

[0015] When the lifting capacity exceeds the maximum rated lifting capacity but is less than 110% of the rated lifting capacity, the upward movement should be stopped, but the downward movement should still be possible. For cranes with multi-speed transmissions, the limiter should prevent overload at each speed.

[0016] When the tower crane reaches 90% or more of its rated lifting torque and / or rated lifting capacity, it should be able to issue intermittent audible and visual alarms to the operator. When the tower crane reaches 100% or more of its rated lifting torque and / or rated lifting capacity, it should be able to issue continuous and clear audible and visual alarms, and the alarms should only stop when the crane's lifting capacity drops to below 100% of its rated operating capacity. Summary of the Invention

[0017] In view of the problems of the prior art, the present invention provides a test method for the safe operation of a tower crane automatic driving system, including tower crane no-load operation test, tower crane loaded operation test and tower crane overload operation test; The tower crane no-load operation test includes: in the tower crane no-load state, by activating the automatic operation function of the control terminal, comparing the set position with the actual reached position; using a handheld microcontroller to control the electric operation of the hook, observing the hook operation status, and realizing the no-load operation test; The tower crane loading and operation test includes: activating the automatic operation function of the control terminal under the tower crane loading state, comparing the set position with the actual reached position; controlling the lifting and running of the hook, observing the running status of the hoisted object and the trolley; comparing the controlled height when the material is unloaded with the limited height shown by the mobile control terminal; and using a handheld microcontroller to observe the jogging operation of the hook to realize the loading and operation test. The tower crane overload operation test includes: lifting a heavy object exceeding the maximum torque load setting multiple at the base of the tower crane boom, using a handheld micro-controller to control the trolley to move outwards, and comparing the trolley's stopping position with the maximum safe operating limit position displayed on the mobile control terminal to achieve the overload operation test.

[0018] Furthermore, the specific steps for the tower crane no-load operation test include: setting the coordinates of the loading point and unloading point on the mobile control terminal; activating the automatic operation function of the tower crane; comparing the system-set position with the actual position reached by the tower hook; recording the operating parameters; and testing whether the actual position reached is within the error range.

[0019] Furthermore, the specific steps of the tower crane loading and operation test include four test items. The first test item is: setting the coordinates of the loading point and unloading point on the mobile terminal; activating the automatic operation function of the tower crane; recording the operating parameters; and testing whether the actual position of the hook is consistent with the set position. The second test item is: controlling the lifting and movement of the hook; observing the movement of the load and the trolley, and testing whether the movement of the load and the trolley is synchronized. The third test item is: measuring the distance between the bottom of the weight and the material dropping plane during the dropping process; comparing the measured data with the limit height displayed on the moving rod terminal; recording the data of the limit control height displayed by the system; and testing whether the measured data meets the error range. The fourth test item is: using a handheld micro-controller to control the jogging of the hook; observing the jogging operation of the hook; and testing the accuracy of the hook's control operation.

[0020] Furthermore, in the tower crane overload operation test, a load exceeding 1.5 times the maximum torque load is lifted at the base of the tower crane boom. The trolley is controlled to move outward using a handheld micro-controller. The stopping position of the trolley is compared with the maximum safe operating limit position displayed on the mobile control terminal. The test is conducted to determine whether the stopping position of the trolley is within the error range.

[0021] Compared with the prior art, the advantages and positive effects of the present invention are as follows: 1. No-load and loaded tests of the tower crane's unmanned automatic control system are crucial steps in evaluating its performance and reliability. These tests verify the system's performance under different operating conditions, including its functionality in terms of control accuracy, safety, and efficiency.

[0022] 2. In the no-load test, the tower crane's unmanned driving system will perform a series of operations without carrying any load. This test can be used to evaluate the system's accuracy and control response time during operation. The test will examine the system's positioning accuracy, lifting capacity, and operating speed, among other indicators. Furthermore, it can verify the system's adaptability to different environmental conditions, such as wind speed and temperature.

[0023] 3. Load testing is conducted under a certain load on the tower crane's unmanned driving system. This test evaluates the system's performance in actual operation, including stability, safety, and load capacity. During the test, different load conditions are simulated, and indicators such as the system's motion control, working accuracy, and the accuracy of the load sensors are tested. The performance of the tower crane's unmanned automatic control system can be evaluated through no-load and loaded tests. These tests verify the system's control accuracy, safety, and performance under different load conditions, thus providing a reliable assessment of the system's effectiveness.

[0024] 4. During tower crane overload testing, the overload measurement of the tower crane's automatic driving system requires real-time measurement of the current hook's luffing, height, and slewing position using sensors. Load information is obtained from weight and torque sensors, and the maximum torque load is determined from the tower crane's lifting capacity performance table. The stopping position of the trolley is then compared with the maximum safe operating limit position displayed on the mobile control terminal. This process verifies whether the trolley's stopping position is within the error range, thus enabling overload operation testing and improving test reliability and efficiency. Attached Figure Description

[0025] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.

[0026] Figure 1 This is a flowchart of the overload test process of the present invention; Figure 2 This is a diagram illustrating the no-load and loaded testing methods of the present invention; Figure 3 This is a mind diagram of the no-load and loaded testing method of the present invention. Detailed Implementation

[0027] To better understand the above-mentioned objectives, features, and advantages of the present invention, the present invention will be further described below in conjunction with the accompanying drawings and embodiments. It should be noted that, unless otherwise specified, the embodiments and features described in these embodiments can be combined with each other.

[0028] Numerous specific details are set forth in the following description in order to provide a full understanding of the invention. However, the invention may also be practiced in other ways than those described herein, and therefore the invention is not limited to the specific embodiments disclosed in the following specification.

[0029] Example 1, such as Figures 1-3 As shown, this application provides a test method for the safe operation of a tower crane automatic driving system, including tower crane no-load operation test, tower crane loaded operation test, and tower crane overload operation test; The tower crane no-load operation test includes: in the tower crane no-load state, by activating the automatic operation function of the control terminal, comparing the set position with the actual reached position; using a handheld microcontroller to control the electric operation of the hook, observing the hook operation status, and realizing the no-load operation test; The tower crane loading and operation test includes: activating the automatic operation function of the control terminal under the tower crane loading state, comparing the set position with the actual reached position; controlling the lifting and running of the hook, observing the running status of the hoisted object and the trolley; comparing the controlled height when the material is unloaded with the limited height shown by the mobile control terminal; and using a handheld microcontroller to observe the jogging operation of the hook to realize the loading and operation test. The tower crane overload operation test includes: lifting a heavy object exceeding the maximum torque load setting multiple at the base of the tower crane boom, using a handheld micro-controller to control the trolley to move outwards, comparing the trolley's stopping position with the maximum safe operating limit position displayed on the mobile control terminal; and verifying whether the trolley's stopping position is within the error range to achieve the overload operation test.

[0030] The specific steps for the tower crane no-load operation test include: setting the coordinates of the loading point and unloading point on the mobile control terminal; activating the tower crane's automatic operation function; comparing the system-set position with the actual position reached by the tower hook; recording the operating parameters; and testing whether the actual position is within the error range. The specific steps of the tower crane loading and operation test include four test items. The first test item is: setting the coordinates of the loading point and the unloading point on the mobile terminal; activating the automatic operation function of the tower crane; recording the operating parameters; and testing whether the actual position of the hook is consistent with the set position. The second test item is: controlling the lifting and movement of the hook; observing the movement of the load and the trolley, and testing whether the movement of the load and the trolley is synchronized. The third test item is: measuring the distance between the bottom of the weight and the material dropping plane during the dropping process; comparing the measured data with the limit height displayed on the moving rod terminal; recording the data of the limit control height displayed by the system; and testing whether the measured data meets the error range. The fourth test item is: using a handheld micro-controller to control the jogging of the hook; observing the jogging operation of the hook; and testing the accuracy of the hook's control operation.

[0031] In the tower crane overload operation test, a load exceeding 1.5 times the maximum torque load is lifted at the base of the tower crane boom. A handheld micro-controller is used to control the trolley to move outwards, and the stopping position of the trolley is compared with the maximum safe operating limit position displayed on the mobile control terminal. The test is conducted to determine whether the stopping position of the trolley is within the error range.

[0032] The method for testing the hook under no-load and loaded conditions based on the unmanned automatic control system of tower cranes is implemented as follows: 1. Tower crane no-load operation test: Under the no-load state of the tower crane, the coordinates of the loading and unloading points are set using a mobile control terminal, the automatic operation function of the tower crane is activated, the accuracy of the hook reaching the loading and unloading area is verified, and the hook fine-tuning control status is verified using a handheld micro-controller.

[0033] 2. Tower crane loading and operation test: Select an appropriate load weight according to the tower crane model and 100% torque load, set the coordinates of the loading and unloading points on the mobile control terminal, activate the automatic operation function of the tower crane, and verify the accuracy of the hook reaching the loading and unloading area; verify the synchronous operation consistency of the load and trolley during lifting and operation, and the safe distance between the bottom of the load and the unloading plane when dropping the load; and use a handheld micro-motion controller to verify the accuracy of the fine-tuning control of the load operation.

[0034] The following is a table of test items for hook no-load and loaded conditions.

[0035]

[0036] Table 1. Hook No-Load and Load Test Items This solution was derived from research and discussion based on a formula. The formula for calculating the rated torque was determined through research as follows: Rated torque = Maximum amplitude of basic arm corresponding rated lifting capacity When the maximum boom length is less than the basic boom length, the formula for the rated torque can be: Rated torque = Maximum amplitude corresponding rated lifting capacity Taking XCMG XGT7530-20 as an example, when the boom length (m) is 60 and a (multiplier) = 2, R (Cmax) is 31.9 and Cmax is 10000. Therefore, the rated lifting moment of this tower crane is 60m. 4900kg = 29400kg·m.

[0037] In the research and discussion of the plan, the calculation method for the rated lifting capacity is as follows: S1 and S2 are the hoisting distances; W1 and W2 represent the maximum lifting weights under amplitudes S1 and S2, respectively.

[0038] S1, S2, W1, and W2 are all standard data for the lifting performance of tower cranes.

[0039] The maximum lifting weight under the current amplitude variation (s) is W, S1 <S<S2。

[0040] The formula for calculating the maximum lifting weight under the current luffing amplitude is: W = W1 + [(W2 - W1)] (S-S1) / (S2-S1)] The no-load and loaded tests of the tower crane's unmanned automatic control system are the result of research and discussion of derived formulas, fully considering data on boom length, torque, and lifting capacity. All data results are scientifically standardized. Furthermore, the no-load and loaded tests of the tower crane's unmanned automatic control system are also a method for evaluating system performance and reliability. In the field of unmanned technology, the tower crane's no-load and loaded test method also incorporates the autonomous control capabilities and adaptability to various working scenarios of the unmanned automatic control system. This test scheme combines advanced sensor technology, algorithms, and intelligent control systems with the tower crane's autonomous perception, decision-making, and operational capabilities to conduct the tower crane tests.

[0041] In the no-load and loaded tests of the tower crane unmanned automatic control system, the autonomous path planning, obstacle detection and avoidance, and automatic positioning of the tower crane unmanned automatic control system are fully integrated to avoid the impact of the tower crane automatic driving system on the no-load and loaded tests of the tower crane.

[0042] Meanwhile, the no-load and loaded test methods for the unmanned automatic control system of tower cranes are fully designed for testing under unmanned control systems. Therefore, the no-load and loaded test methods have high safety and reliability, avoiding inaccurate test data and preventing accidents.

[0043] Overloading a tower crane can cause excessive stress on its structure, leading to structural damage or overturning, posing a serious threat to the surrounding environment and personnel, and potentially resulting in injuries or fatalities. In tower crane autopilot systems, it is essential to monitor the load on the tower crane during operation, equip it with an effective overload detection and safety control system, and ensure the stable operation of the system.

[0044] This method provides a testing approach for the sensitivity and accuracy of overload detection and safety control systems. Measuring overload in the tower crane's automatic driving system requires real-time measurement of the hook's luffing, height, and slewing positions using sensors, obtaining the tower crane's load information through weight and torque sensors, and determining the tower crane's maximum torque load using a tower crane lifting capacity performance table.

[0045] Maximum safe operating amplitude = maximum torque load of the tower crane / current lifting weight of the cargo (W).

[0046] The mobile control terminal will inform the tower crane remote operator of the current safe operating maximum amplitude (Smax) via the screen.

[0047]

[0048] Table 1. Overload Test Items Table Based on the existing tower crane model and corresponding automatic control system, configure weight and torque sensors on the system. Ensure the sensors are correctly installed and communicate properly with the control system, and that the acquired data is parsed correctly.

[0049] When lifting a load exceeding 1.5 times the maximum torque load at the base of the tower crane boom, the mobile control terminal should display the actual weight of the lifted load and the maximum safe operating limit position of the trolley in real time. Use a handheld micro-controller to control the trolley to move outwards and verify the consistency between the trolley's limit stop position and the maximum safe operating limit position displayed on the mobile control terminal.

[0050] The test requires recording the weight data of each lifted object, the luffing position of the trolley when it stops running, and the maximum luffing limit position information for safe operation displayed on the mobile control terminal.

[0051] If there is an error between the luffing position where the trolley stops and the maximum luffing limit position information displayed on the mobile control terminal, the error is within ±0.5m and it is considered qualified; otherwise, it is considered unqualified.

[0052] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any other way. Any person skilled in the art may make changes or modifications to the above-disclosed technical content to create equivalent embodiments that can be applied to other fields. However, any simple modifications, equivalent changes, and modifications made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the protection scope of the present invention.

Claims

1. A test method for the safe operation of a tower crane automatic driving system, characterized in that, This includes tower crane no-load operation test, tower crane loaded operation test, and tower crane overload operation test; The tower crane no-load operation test includes: in the tower crane no-load state, by activating the automatic operation function of the control terminal, comparing the set position with the actual reached position; using a handheld microcontroller to control the electric operation of the hook, observing the hook operation status, and realizing the no-load operation test; The tower crane loading and operation test includes: activating the automatic operation function of the control terminal under the tower crane loading state, comparing the set position with the actual reached position; controlling the lifting and running of the hook, observing the running status of the hoisted object and the trolley; comparing the controlled height when the material is unloaded with the limited height shown by the mobile control terminal; and using a handheld microcontroller to observe the jogging operation of the hook to realize the loading and operation test. The tower crane overload operation test includes: lifting a heavy object exceeding the maximum torque load setting multiple at the base of the tower crane boom, using a handheld micro-controller to control the trolley to move outwards, and comparing the trolley's stopping position with the maximum safe operating limit position displayed on the mobile control terminal to achieve the overload operation test.

2. The test method for the safe operation of a tower crane automatic driving system according to claim 1, characterized in that, The specific steps for the tower crane no-load operation test include: setting the coordinates of the loading point and unloading point on the mobile control terminal; activating the automatic operation function of the tower crane; comparing the system-set position with the actual position reached by the tower hook; recording the operating parameters; and testing whether the actual position reached is within the error range.

3. The test method for the safe operation of a tower crane automatic driving system according to claim 1, characterized in that, The specific steps of the tower crane loading and operation test include four test items. The first test item is: setting the coordinates of the loading point and the unloading point on the mobile terminal; activating the automatic operation function of the tower crane; recording the operating parameters; and testing whether the actual position of the hook is consistent with the set position. The second test item is: controlling the lifting and movement of the hook; observing the movement of the load and the trolley, and testing whether the movement of the load and the trolley is synchronized. The third test item is: measuring the distance between the bottom of the weight and the material dropping plane during the dropping process; comparing the measured data with the limit height displayed on the moving rod terminal; recording the data of the limit control height displayed by the system; and testing whether the measured data meets the error range. The fourth test item is: using a handheld micro-controller to control the jogging of the hook; observing the jogging operation of the hook; and testing the accuracy of the hook's control operation.

4. The test method for the safe operation of a tower crane automatic driving system according to claim 1, characterized in that, In the tower crane overload operation test, a load exceeding 1.5 times the maximum torque load is lifted at the base of the tower crane boom. A handheld micro-controller is used to control the trolley to move outwards, and the stopping position of the trolley is compared with the maximum safe operating limit position displayed on the mobile control terminal. The test is conducted to determine whether the stopping position of the trolley is within the error range.