Construction method for super deep and large diameter rotary drilling of collapse accumulation body

By using large rotary drilling rigs and segmented relay rotary drilling technology, the construction problem of drilling large-diameter concrete piles in rock collapse deposits has been solved, achieving efficient and safe rotary drilling construction and reducing construction risks and costs.

CN117927135BActive Publication Date: 2026-11-20GUIZHOU CONSTR ENG GRP THIRD CONSTR
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410164224.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-05
Publication Date
2026-11-20
Estimated Expiration
2044-02-05

AI Technical Summary

Technical Problem

When constructing large-diameter concrete piles in rock collapse deposits, there are construction problems such as hole collapse, drill bit burial, and drill bit jamming, resulting in high construction risks, low efficiency, and difficulty in meeting the requirements for project quality and safety.

Method used

Large rotary drilling rigs and segmented relay rotary drilling technology are adopted. Through segmented rotary drilling, core extraction and hole enlargement are carried out in stages using rotary drill bits and drill barrels of different diameters. Combined with the use of steel casing, the stability of the pile position and the stability of the hole wall are ensured.

Benefits of technology

It improved the construction efficiency and quality of rotary drilling, reduced the risks of hole collapse, drill bit burial, and drill bit jamming, lowered resource consumption and construction costs, and ensured the safety and progress of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117927135B_ABST
    Figure CN117927135B_ABST
Patent Text Reader

Abstract

The application discloses a construction method for super-deep and large-diameter rotary drilling of collapse accumulation body, and adopts large-scale rotary drilling rig operation, adopts segmented relay rotary drilling hole construction technology for single pile position, and mainly takes the upper soil layer of the hole pile, the collapse accumulation body layer and the rock layer below as the main two vertical segmented boundaries, adopts the 1.4-1.6m rotary drilling bit or the drilling cylinder to carry out core rotary drilling hole operation in the hole forming process of each vertical segment, then sequentially replaces the 2m and 2.5m rotary drilling bits to carry out hole expanding operation, until the hole expanding depth reaches the design depth of the hole pile, and finally the rotary drilling hole construction technology is completed. The application adopts the segmented relay rotary drilling hole of the single pile position rotary drilling rig and other reasonable construction technologies, solves the problem of the super-deep and large-diameter rotary drilling hole construction under the complex geological condition of the collapse accumulation body, and meets the project construction needs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of building construction technology, and in particular relates to a construction method for ultra-deep, large-diameter rotary drilling of collapsed deposits. Background Technology

[0002] In mountainous areas with complex geological conditions, large-diameter cast-in-place concrete piles are frequently used for constructing group buildings and large-scale road and bridge projects. The depth is designed and constructed rationally based on geological and engineering conditions. When used as foundation pit and slope support piles—crucial nodes in construction projects—the requirements for all aspects of construction are high. Traditional drilling techniques for large-diameter cast-in-place concrete piles often employ rotary drilling rigs based on the engineering geology and inherent characteristics. However, when the rockfall deposits are thick, construction is often accompanied by risks such as borehole collapse, drill bit burial, drill bit jamming, and excessive energy consumption, posing significant construction challenges to critical project nodes.

[0003] The site's soil and rock conditions mainly consist of an overlying soil layer and underlying bedrock. The overlying soil layer is primarily plain fill and collapsed deposits, while the underlying bedrock is Silurian Longmaxi Formation argillaceous limestone. The collapsed deposits are composed of clay, gravel, limestone boulders of varying sizes, and disordered rock piles, and are quite thick. In the upper part of the collapsed deposits, boulders are fewer and unevenly distributed, with clay and gravel dominating. As the depth increases, the content of boulders increases, and most have formed a framework, with clay and gravel filling the spaces between them. Locally, there are voids without clay or gravel filling. Small and medium-sized rotary drilling rigs experience significant borehole collapse during drilling, requiring multiple backfillings with low-grade concrete (concrete wall protection). After backfilling, approximately 24 hours must be waited before work can continue, posing risks of drilling difficulties, drill bit jamming, and drill bit burial. Summary of the Invention

[0004] The purpose of this invention is to address the shortcomings of existing technologies by proposing a construction method for ultra-deep, large-diameter rotary drilling in collapsed deposits. This method employs reasonable construction techniques such as segmented relay rotary drilling with a single-pile rotary drilling rig, which solves the problem of ultra-deep, large-diameter rotary drilling in complex geological conditions of collapsed deposits and meets the needs of project construction.

[0005] To achieve the above objectives, the present invention provides the following technical solution: A construction method for ultra-deep, large-diameter rotary drilling in collapsed deposits involves using a large rotary drilling rig. For a single pile location, a segmented relay rotary drilling process is employed. This process primarily uses the upper soil layer and the collapsed deposit layer, along with the underlying rock layer, as the two main vertical segment boundaries. During the drilling process in each vertical segment, a 1.4-1.6m rotary drill bit or drill cylinder is first used for core extraction. Then, 2m and 2.5m rotary drill bits are used in stages to enlarge the hole until the designed depth of the pile is reached, thus completing the rotary drilling construction.

[0006] The above-mentioned construction method for ultra-deep, large-diameter rotary drilling of collapsed deposits has the following process flow: positioning and setting out the original terrain → constructing a construction access road, operating platform, and slope trimming → positioning and setting out → positioning the rotary drilling rig → embedding the steel casing → core drilling → hole enlargement → reaching the bearing layer, where the survey and design unit inspects the trench → replacing the drilling tools and cleaning the bottom → subsequent procedures.

[0007] The above-mentioned construction method for ultra-deep, large-diameter rotary drilling of collapsed deposits specifically includes the following steps: S1, Measurement and Setting Out After the measurement control points provided by the construction unit meet the requirements, secondary control network points are established. After the secondary control network points are re-measured and confirmed to be correct by the supervision unit, the center points of each axis pile are determined. S2. Preparation for steel casing installation Depending on the geological conditions, steel casings with a height of 1-3 meters are installed using the spinning method to fix the position of the pile hole and to protect the stability of the hole opening and the upper soil. After the concrete is poured, a crane is used to pull out the steel casing. S3. Drilling rig installed and in place. The drilling platform base rests on a solid foundation to ensure that it does not tilt or move during construction; the drilling rig must be installed stably, with the drill bit center and the pile hole center in a straight line, and the alignment deviation must not exceed 10mm. S4. Rotary drilling operation When a rotary drilling rig drills for soil extraction, it relies on the weight of the drill rod and drill bit to cut into the soil layer. The inclined bucket teeth cut off soil blocks and push them into the bucket as the drill bucket rotates, thus completing the soil extraction. When encountering hard soil, the weight of the bucket teeth is insufficient to cut into the soil layer. At this time, the drill rod is pressurized by a pressure cylinder to force the bucket teeth to cut into the soil and complete the drilling for soil extraction. S5. Handling of Special Geological Conditions When a rotary drilling rig encounters a collapsed accumulation layer during drilling, causing the borehole to collapse, the rotary drilling rig should first be used to excavate to the collapsed area, and the collapsed rock layer should be quickly removed. The post-collapse treatment method is to backfill with C15 plain concrete, and then drill a second hole after the C15 concrete has reached the required strength. S6. Hole cleaning and acceptance Once the borehole reaches the design elevation or is excavated to the bearing layer of moderately weathered argillaceous limestone or moderately weathered argillaceous limestone, and meets the design requirements, the geological survey unit, supervision unit, and construction unit shall be notified in a timely manner to conduct on-site acceptance, and to check the borehole depth, borehole diameter, borehole wall, verticality, etc. If any defects are found, measures shall be taken to deal with them in a timely manner.

[0008] Furthermore, in step S2, the steel casing can be reused and recycled; however, in special circumstances where the steel casing needs to be permanently buried deep, the geological survey, the client, the supervisor, and the construction unit must jointly discuss and determine the requirements. The specifications of the steel casing are: inner diameter D = d (d is the diameter of the bored pile) + 2 × 100mm (rotary drilling rig working face), thickness H = 15mm, and length generally 1-3 meters (in special cases, the length of the steel casing is determined according to the actual site conditions). The material of the steel casing is Q345B. The burial depth of the steel casing is determined based on the geological survey report and the actual site conditions, and is confirmed upon acceptance.

[0009] Furthermore, in step S4, when performing rotary drilling operations, ZR420L rotary drilling is used for small pile diameters and piles with a diameter of 2.5m or less and a depth of 45m or less; for pile diameters of 2-2.5m and a depth of more than 45m, ZR500L or ZR550L rotary drilling is used for rotary drilling with a larger torque; for the large pile diameter (2.5m pile diameter) on site, four drilling operations were performed, and the drilling method of 1.4m core extraction (1.6m, 2m, 2.5m hole enlargement) was adopted according to the pile diameter on site.

[0010] Further, in step S4, 1-2 rotary drilling rigs are operated in conjunction with 1 medium-sized excavator, using a skip-hole rotary drilling method; the ZR420L rotary drilling rig is used for drilling small-diameter piles and piles up to 45 meters deep; the ZR500L and ZR550L rotary drilling rigs are used for drilling large-diameter piles and piles over 45 meters deep. For rotary drilling of large-diameter, deep-hole piles and rock foundations, a "relay" rotary drilling process is only feasible if the project has a complete set of rotary drilling rigs available, as detailed below: (1) Installation of steel casing on ZR420L rotary drilling rig: positioning and setting out of the pile hole → using ZR420L rotary drilling rig to install a 2.5m diameter sand scooping bucket drill bit to drill to a depth of 1.5m → installing a 2m high steel casing with a diameter of 2.7m, a burial depth of 1.5m, and a height of 0.5m above the ground → repositioning, re-measuring, and correcting the steel casing; (2) Earthwork operations using the ZR420L rotary drilling rig: The process involves using a 1.6m diameter sand-dredging bucket drill bit for core extraction in the earthwork section, extracting cores to the rock collapse layer, then switching to a 2m diameter sand-dredging bucket drill bit for borehole enlargement in the earthwork section, and then switching to a 2.5m diameter sand-dredging bucket drill bit for borehole enlargement in the earthwork section until the rock collapse layer is reached. (3) Operations in rock collapse zones using ZR420L rotary drilling rig: A. Core extraction operation: Replace with a 1.4m diameter core drill for core extraction operation → If encountering loose gravel or rock layers, use a 1.4m diameter sand-dredging bucket drill to excavate the rock debris → Continue to use a 1.4m diameter core drill for core extraction operation, repeatedly using a 1.4m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m; B. Hole Enlargement Operation: Replace with a 1.6m diameter core drill for hole enlargement operation → If encountering loose gravel or rock layers, use a 1.6m diameter sand-dredging bucket drill to excavate the rock debris → Continue using a 1.6m diameter core drill for hole enlargement operation, repeatedly using a 1.6m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m; C. Hole enlargement operation: Replace with a 2m diameter core drill for hole enlargement operation → If a loose gravel layer or rock layer is encountered, use a 2m diameter sand scoop drill to excavate the rock debris → Continue to use a 2m diameter core drill for hole enlargement operation, repeatedly use a 2m diameter core drill in combination with a sand scoop drill for drilling → until the rock collapse layer ends or the depth reaches 45m. D. Hole enlargement operation: Replace with a 2.5m diameter core drill for hole enlargement operation → If encountering loose gravel or rock layers, use a 2.5m diameter sand-dredging bucket drill to excavate the rock debris → Continue to use a 2.5m diameter core drill for hole enlargement operation, repeatedly using a 2.5m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m; (4) The ZR420L rotary drilling rig is used in marl strata, which contain layers of medium-hard rock and hard rock, with a depth limited to within 45m: A. Core extraction operation: Replace with a 1.4m diameter core drill and drill → Core extraction operation ends when the depth reaches 45m; B. Enlargement operation: Replace with a 1.6m diameter core drill for enlargement operation → alternate between using a 1.6m diameter core drill and a sand scooping bucket for drilling → complete the enlargement operation when the hole depth reaches 45m; B. Hole reaming operation: Replace with a 2m diameter core drill for hole reaming operation → alternately use a 2m diameter core drill in combination with a sand scooping bucket for drilling → finish reaming when the hole depth reaches 45m; B. Enlargement operation: Replace with a 2.5m diameter core drill for enlargement operation → alternate between using a 2.5m diameter core drill and a sand scooping bucket for drilling → complete the enlargement operation when the hole depth reaches 45m; (5) Marlstone strata with sub-hard rock and hard rock layers, with a depth greater than 45m, for ZR500L or ZR550L rotary drilling rigs: A. Move the ZR420L rotary drilling rig to other pile hole operations, and arrange for a ZR500L or ZR550L rotary drilling rig to be in place to continue drilling operations using a relay method; B. Core extraction operation: Replace with a 1.4m diameter core drill to perform core extraction drilling → Core extraction operation ends when the designed depth of the pile is reached; C. Enlargement operation: Replace with a 1.6m diameter core drill for enlargement operation → alternately use a 1.6m diameter core drill in combination with a sand scooping bucket for drilling → enlarge the hole to the designed depth of the pile; D. Hole reaming operation: Replace with a 2m diameter core drill for hole reaming operation → alternately use a 2m diameter core drill in combination with a sand scooping bucket for drilling → ream the hole to the designed depth of the pile; E. Hole reaming operation: Replace with a 2.5m diameter core drill for hole reaming operation → alternately use a 2.5m diameter core drill in combination with a sand scooping bucket for drilling → reaming to the designed depth of the pile hole.

[0011] Further, in step S5, the key to treating the collapsed section is soil stabilization to make the borehole wall stable. The method to stabilize the borehole wall is to pour low-grade C15 concrete into the collapsed section using the underwater pouring method. The concrete is backfilled to more than 500mm above the top of the collapsed section. After the concrete has set and reached a certain strength, the drilling rig continues to operate. At this time, the concrete has filled the collapsed section. The rotary drilling rig removes the middle part, and the remaining part will form a concrete wall to prevent the collapse from worsening. If the collapse is more serious, manifested by mud and sand in the collapsed section, incomplete cleaning of rock strata, and rebound of small pile hole advance, then it is necessary to pour C15 concrete in layers and drill until the bottom of the collapsed section is treated.

[0012] Further, in step S6, the borehole inspection method is determined according to the borehole diameter. If groundwater is present in the borehole, a pump-suction reverse circulation method can be used to clean the borehole. After the concrete pouring guide pipe is placed, the borehole depth and bottom sediment are re-measured. If the bottom sediment thickness exceeds the specified limit, reverse circulation cleaning is used with the pouring guide pipe. This is carried out after subsequent operations such as the reinforcement cage and guide pipe are completed. The second cleaning time should be no less than 30 minutes. The cleaning can be stopped only when the bottom sediment is measured to be ≤50mm. The bottom sediment is measured with a heavy hammer test, and the reading of the measuring rope must be accurate. It must be calibrated once every 3 to 5 boreholes. After the cleaning is completed, concrete should be poured as soon as possible, and the interval should not exceed 30 minutes. If the bearing layer of the foundation meets the requirements of the survey and design, the borehole is closed. If it does not meet the requirements, drilling continues according to the opinions of the geological survey and design unit until it is accepted.

[0013] The present invention has the following beneficial effects: This invention, tailored to different rock and soil geological conditions and the design of rotary drilling piles, employs a segmented relay rotary drilling construction process using large rotary drilling rigs. Implemented according to resource matching plans and construction deployments, this technology features high torque, high hole verticality, and flexible relocation, thereby improving the efficiency of rotary drilling construction, reducing the consumption of resources such as rotary drill bits, fuel, power, and labor, and minimizing the risks of hole collapse, drill bit burial, and drill bit jamming. It also helps save construction time and provides a strong guarantee for improving the quality and safety of ultra-deep, large-diameter rotary drilling construction in complex geological conditions such as rock collapse deposits. This invention is applicable to rotary drilling construction in rock collapse deposits and complex geological conditions, and is particularly suitable for ultra-deep, large-diameter (2m-2.5m) rotary drilling operations. Attached Figure Description

[0014] Figure 1 This is a process flow diagram of the present invention. Detailed Implementation

[0015] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0016] Reference Figure 1 This invention employs a large rotary drilling rig for construction operations. The rotary drilling rig itself features fast drilling speed, high torque, high verticality of hole formation, and flexible site relocation. For single pile locations, a segmented relay rotary drilling construction process is adopted. The segmented rotary drilling process mainly uses the upper soil layer and the collapsed accumulation layer and the lower rock layer as the two main vertical segment boundaries. In the process of drilling each vertical segment, a core extraction rotary drilling operation is first performed with a 1.4-1.6m rotary drill bit or drill barrel. Then, 2m and 2.5m rotary drill bits are used in stages to enlarge the hole until the hole depth reaches the designed depth of the pile, thus completing the rotary drilling construction process.

[0017] For rotary drilling operations, ZR420L rotary drilling is used for small pile diameters and piles with a diameter of 2.5m or less and a depth of 45m or less. For piles with a diameter of 2-2.5m or more and a depth of 45m or more, ZR500L or ZR550L rotary drilling is used for rotary drilling operations with a larger torque.

[0018] For the large-diameter piles (2.5m), four drilling processes were used. Based on the pile diameter, a drilling method of 1.4m core extraction and (1.6m, 2m, 2.5m hole enlargement) was adopted.

[0019] The process flow is as follows: original terrain positioning and layout → construction of access road, operating platform, and slope trimming → positioning and layout → positioning of rotary drilling rig → installation of steel casing (diameter 2.7m, height 2m) → core drilling → hole enlargement → reaching the bearing layer, where the survey and design unit inspects the trench → replacing the drilling tool (diameter 2m cleaning drill) and cleaning the bottom thoroughly → subsequent process operations.

[0020] Specifically, the following steps are included: S1, Measurement and Setting Out After the measurement control points provided by the construction unit meet the requirements, secondary control network points are established. The secondary control network points are re-measured and confirmed to be correct by the supervision unit, and the center points of each axis pile are determined. After bidirectional control positioning, steel casings are buried and fixed, and the pile center is controlled by bidirectional cross lines. Before drilling, the center of the drill bit is checked to see if it coincides with the center of the pile position. During the construction process, the position of the drilling tool must be checked frequently to ensure the correctness of the hole position.

[0021] Preparation for steel casing installation Depending on the geological conditions, a steel casing with a height of 1-3 meters is installed using the rotary drilling method. This is used to fix the position of the pile hole and to protect the stability of the hole opening and the upper soil. After the concrete is poured, a crane is used to pull out the steel casing. The steel casing can be reused and recycled. If special circumstances require the steel casing to be permanently buried deep, this needs to be determined through joint consultation between the geological survey team, the client, the supervisor, and the construction unit. The specifications of the steel casing are: inner diameter D = d (d is the diameter of the pile hole) + 2 × 100 mm (rotary drilling rig working face), thickness H = 15 mm, and length is generally 1-3 meters (in special cases, the length of the steel casing is determined according to the actual site conditions). The material of the steel casing is Q345B. The burial depth of the steel casing is determined according to the geological survey report and the actual site conditions, and is confirmed upon acceptance.

[0022] Drilling rig installed and in place The drilling platform base must be placed on a solid foundation to ensure that it does not tilt or move during construction; the drilling rig must be installed stably, with the center of the drill bit and the center of the pile hole in a straight line, and the alignment deviation must not exceed 10mm; the drilling notice can only be issued after checking that all connection parts and safety protection facilities of the drilling rig are complete.

[0023] Rotary drilling operations When a rotary drilling rig drills for soil extraction, it relies on the weight of the drill rod and drill bit to cut into the soil layer. The inclined bucket teeth cut off soil blocks and push them into the bucket as the bucket rotates, thus completing the soil extraction. When encountering hard soil, the weight of the bucket is insufficient to allow the bucket teeth to cut into the soil layer. In this case, a pressure cylinder is used to pressurize the drill rod, forcibly cutting the bucket teeth into the soil to complete the drilling and soil extraction. After the bucket is filled with soil, a crane lifts the drill rod and bucket to the ground. Pulling the switch on the bucket opens the bottom door, and the soil in the bucket is automatically discharged by its own weight. The drill rod is lowered, the bucket door is closed, and the rig rotates back into the hole to excavate the next bucket. During the hole formation process, steel casings are installed to fix the position of the pile hole and protect the stability of the hole opening and the upper soil.

[0024] The specific length of the engineering pile body penetrating the moderately weathered argillaceous limestone or moderately weathered marlstone bearing layer is detailed in the construction drawings. Therefore, drilling must be strictly carried out in accordance with the geological survey report during construction. Construction records must be filled out promptly during hole formation, and soil samples must be collected at points of soil layer change to identify the soil layers for verification against the geological profile. Once the designed rock surface is reached, samples must be taken for analysis. The drilling speed must be controlled according to the soil conditions. To ensure the verticality of the hole meets design requirements, the piling machine must be kept level, and frequent inspections and corrections must be conducted.

[0025] One to two rotary drilling rigs are used in conjunction with one medium-sized excavator, employing a skip-hole rotary drilling method. The ZR420L rotary drilling rig is used for drilling small-diameter piles and piles up to 45 meters deep; the ZR500L and ZR550L rotary drilling rigs are used for drilling large-diameter piles and piles over 45 meters deep. For rotary drilling of large-diameter, deep-hole piles and rock foundations, a complete set of rotary drilling rigs is required on the project site to enable the "relay" rotary drilling process, as detailed below: (1) Installation of steel casing on ZR420L rotary drilling rig: positioning and setting out of the pile hole → using ZR420L rotary drilling rig to install a 2.5m diameter sand scooping bucket drill bit to drill to a depth of 1.5m → installing a 2m high steel casing (diameter 2.7m, burial depth 1.5m, 0.5m above ground) → repositioning, re-measuring, and correcting the steel casing.

[0026] (2) Earthwork operations using the ZR420L rotary drilling rig: The process involves using a 1.6m diameter sand-dredging bucket drill bit for core extraction in the earthwork section, extracting cores to the rock collapse layer, then switching to a 2m diameter sand-dredging bucket drill bit for borehole enlargement in the earthwork section, and then switching to a 2.5m diameter sand-dredging bucket drill bit for borehole enlargement in the earthwork section until the rock collapse layer is reached.

[0027] (3) Operations in rock collapse zones using ZR420L rotary drilling rig: A. Core extraction operation: Switch to a 1.4m diameter core drill for core extraction → If encountering loose gravel or rock layers, use a 1.4m diameter sand-dredging bucket drill to excavate the rock debris → Continue core extraction using a 1.4m diameter core drill, repeatedly using a 1.4m diameter core drill in combination with a sand-dredging bucket → Continue drilling until the rock collapse layer ends or the depth reaches 45m.

[0028] B. Hole Enlargement Operation: Switch to a 1.6m diameter core drill for hole enlargement operation → If encountering loose gravel or rock layers, use a 1.6m diameter sand-dredging bucket drill to excavate the rock debris → Continue using a 1.6m diameter core drill for hole enlargement operation, repeatedly using a 1.6m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m.

[0029] C. Hole Enlargement Operation: Switch to a 2m diameter core drill for hole enlargement operation → If encountering loose gravel or rock layers, use a 2m diameter sand-dredging bucket drill to excavate the rock debris → Continue using a 2m diameter core drill for hole enlargement operation, repeatedly using a 2m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m.

[0030] D. Hole Enlargement Operation: Replace with a 2.5m diameter core drill for hole enlargement operation → If encountering loose gravel or rock layers, use a 2.5m diameter sand-dredging bucket drill to excavate the rock debris → Continue using a 2.5m diameter core drill for hole enlargement operation, repeatedly using a 2.5m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m.

[0031] (4) ZR420L rotary drilling rig in marl strata (sub-hard rock, hard rock), depth limited to within 45m: A. Core extraction operation: Change to a 1.4m diameter core drill and drill → Core extraction operation ends when the depth reaches 45m.

[0032] B. Enlargement operation: Replace with a 1.6m diameter core drill for enlargement operation → alternate between using a 1.6m diameter core drill and a sand scooping bucket for drilling → complete the enlargement operation when the hole depth reaches 45m.

[0033] B. Hole reaming operation: Change to a 2m diameter core drill for hole reaming operation → alternate between using a 2m diameter core drill in combination with a sand scooping bucket for drilling → finish reaming when the hole depth reaches 45m.

[0034] B. Enlargement operation: Replace with a 2.5m diameter core drill for enlargement operation → alternate between using a 2.5m diameter core drill and a sand scooping bucket for drilling → complete the enlargement operation when the hole depth reaches 45m.

[0035] (5) Marlstone (sub-hard rock, hard rock) layer with a depth greater than 45m. ZR500L or ZR500L rotary drilling rig.

[0036] A. Move the ZR420L rotary drilling rig to other pile hole operations, and arrange for a ZR500L or ZR550L rotary drilling rig to be in place, and continue drilling operations by relaying the drilling.

[0037] B. Core extraction operation: Replace with a 1.4m diameter core drill to perform core extraction drilling → Core extraction operation ends when the designed depth of the pile is reached.

[0038] C. Hole reaming operation: Replace with a 1.6m diameter core drill for hole reaming operation → alternately use a 1.6m diameter core drill in combination with a sand scooping bucket for drilling → reaming to the designed depth of the pile hole.

[0039] D. Hole reaming operation: Replace with a 2m diameter core drill for hole reaming operation → alternately use a 2m diameter core drill in combination with a sand scooping bucket for drilling → reaming to the designed depth of the pile hole.

[0040] E. Hole reaming operation: Replace with a 2.5m diameter core drill for hole reaming operation → alternately use a 2.5m diameter core drill in combination with a sand scooping bucket for drilling → reaming to the designed depth of the pile hole.

[0041] Special geological conditions handling When a rotary drilling rig encounters a collapsed layer during drilling, causing a borehole collapse, the rig is first used to excavate to the collapsed area and quickly remove the collapsed rock layer. The post-collapse treatment involves backfilling with C15 plain concrete. Once the C15 concrete reaches the required strength, a second drilling operation is performed. The key to treating the collapsed area is soil stabilization to solidify the borehole wall. This is achieved by pouring low-grade C15 concrete into the collapsed section using underwater grouting, backfilling to at least 500mm above the top of the collapsed section. After the concrete has fully set and reached a certain strength, the drilling rig continues operation. At this point, the concrete has filled the collapsed portion, and the rotary drilling rig removes the middle section, leaving the remaining portion to form a concrete retaining wall to prevent further collapse. If the collapse is more severe, characterized by incomplete removal of mud and rock layers, and rebound in small-diameter pile drilling, then C15 concrete pouring and drilling in layers are necessary until the bottom of the collapsed section is reached.

[0042] Hole cleaning and acceptance Once the borehole reaches the design elevation or is excavated to the moderately weathered argillaceous limestone or moderately weathered argillaceous limestone bearing layer, meeting the design requirements, the geological survey unit, supervision unit, and construction unit should be promptly notified for on-site acceptance. The borehole depth, diameter, wall thickness, and verticality should be checked, and any defects should be addressed promptly. The borehole inspection method depends on the borehole diameter. If groundwater is present in the borehole, reverse circulation grouting can be used to clean it. After the concrete pouring guide pipe is installed, the borehole depth and bottom sediment should be re-measured. If the bottom sediment thickness exceeds the specified limit, [further measures should be taken]. The grouting guide pipe uses reverse circulation for hole cleaning, which is carried out after subsequent processes such as the reinforcement cage and guide pipe are installed. The second hole cleaning time is no less than 30 minutes. Hole cleaning can only be stopped when the sediment at the bottom of the hole is ≤50mm. The sediment at the bottom of the hole is measured with a heavy hammer. The reading of the measuring rope must be accurate. The measurement must be corrected every 3 to 5 holes. After the hole cleaning is completed, concrete should be poured as soon as possible, and the interval between pours should not exceed 30 minutes. If the bearing layer of the foundation meets the requirements of the survey and design, the hole is closed. If it does not meet the requirements, drilling should continue according to the opinions of the geological survey and design unit until it passes the acceptance.

[0043] This invention employs ultra-deep, large-diameter rotary drilling technology for complex geological conditions in collapsed pile bodies. Targeting different rock and soil geological conditions and the design of the rotary piles themselves, it utilizes a segmented relay rotary drilling construction process with large rotary drilling rigs. Implemented according to resource matching plans and construction deployment, this improves the efficiency of rotary drilling construction, reduces the consumption of resources such as rotary drill bits, fuel, power, and labor, lowers construction costs, and scientifically and rationally utilizes multiple drilling operations with machinery, reducing the overload time of construction machinery, thus improving the efficiency of rotary drilling construction, saving construction time, and demonstrating significant economic benefits.

[0044] This invention employs ultra-deep, large-diameter rotary drilling technology for complex geological formations in collapsed deposits. It features a high degree of mechanization, with drilling operations conducted in relays by various machinery. Its characteristics include high torque, high verticality of the drilled holes, and flexible site relocation, reducing the risks of hole collapse, drill bit burial, and stuck drill bits, effectively mitigating safety hazards. This construction technology reduces the consumption of drill bits, drill barrels, and other accessories and machinery during the rotary drilling process, reducing fuel and equipment consumption, thus promoting environmentally friendly and energy-saving construction. Furthermore, it ensures reliable hole quality, significantly improving overall project quality and safety, resulting in substantial social benefits.

[0045] Application examples of this invention The Guizhou Maotai Distillery (Group) Xijiu Co., Ltd. "14th Five-Year Plan" Technological Upgrading (Phase I) Project – Hongtan Qu-making Area Construction Project, undertaken by our company. The project is located in Yuanziyan Group, Dawan Village, Xijiu Town, Xishui County, Zunyi City, Guizhou Province, at the confluence of the Chishui River and the Tongzi River, bordered by the Chishui River to the south and Provincial Highway S208 to the north. The project is 4.5 km from Xijiu Town and 2.4 km from Langjiu Distillery. The project covers an area of ​​73,497 square meters with a total building area of ​​82,752.07 square meters. New buildings include: 4 qu-making workshops, 2 public bathroom buildings, 1 duty room, and parking lots. The total investment for this project is approximately RMB 999.4 million, with a planned construction period from May 2022 to December 2024. This project's slope protection works involve 470 anti-slide piles (335 with a diameter of 2.5m and 135 with a diameter of 2m, at depths of 40-65m) and 716 foundation piles (mainly with diameters of 1.6m to 2m, at depths of 30-55m). The slope protection piles in this project utilize ultra-deep, large-diameter rotary drilling technology in complex geological conditions of collapsed deposits. Considering the different rock and soil geological conditions and the design of the rotary drilling piles themselves, a segmented relay rotary drilling construction process using large rotary drilling rigs was adopted. This improved the efficiency of rotary drilling construction, reduced the consumption of rotary drill bits, fuel, power, and labor, and reduced the risks of hole collapse, drill bit burial, and drill bit jamming. It also saved construction time and provided a strong guarantee for improving the quality and safety of ultra-deep, large-diameter rotary drilling construction in complex geological conditions of collapsed deposits, achieving good economic and social benefits.

Claims

1. A construction method for ultra-deep, large-diameter rotary drilling in collapsed deposits, characterized in that: Large rotary drilling rigs were used for construction. A segmented relay rotary drilling construction process was adopted for single pile positions. The segmented rotary drilling process was based on the vertical segment boundaries of the upper soil layer and the collapsed accumulation layer and the lower rock layer of the pile. In the process of drilling each vertical segment, the core drilling operation was first carried out with 1.4m and 1.6m rotary drill bits or core drills. Then, 2m and 2.5m rotary drill bits were used in stages to enlarge the hole until the hole depth reached the designed depth of the pile, and finally the rotary drilling construction process was completed. Specifically, the following steps are included: S1, Measurement and Setting Out After the measurement control points provided by the construction unit meet the requirements, secondary control network points are established. After the secondary control network points are re-measured and confirmed to be correct by the supervision unit, the center points of each axis pile are determined. S2. Preparation for steel casing installation Depending on the geological conditions, steel casings with a height of 1-3 meters are installed using the spinning method to fix the position of the pile hole and to protect the stability of the hole opening and the upper soil. After the concrete is poured, a crane is used to pull out the steel casing. S3. Drilling rig installed and in place. The drilling platform base rests on a solid foundation to ensure that it does not tilt or move during construction; the drilling rig must be installed stably, with the drill bit center and the pile hole center in a straight line, and the alignment deviation must not exceed 10mm. S4. Rotary drilling operation When a rotary drilling rig drills for soil extraction, it relies on the weight of the drill rod and drill bit to cut into the soil layer. The inclined bucket teeth cut off soil blocks and push them into the bucket as the drill bucket rotates, thus completing the soil extraction. When encountering hard soil, the weight of the bucket teeth is insufficient to cut into the soil layer. At this time, the drill rod is pressurized by a pressure cylinder to force the bucket teeth to cut into the soil and complete the drilling for soil extraction. S5. Handling of Special Geological Conditions When a rotary drilling rig encounters a collapsed accumulation layer during drilling, causing the borehole to collapse, the rotary drilling rig should first be used to excavate to the collapsed area, and the collapsed rock layer should be quickly removed. The post-collapse treatment method is to backfill with C15 plain concrete, and then drill a second hole after the C15 concrete has reached the required strength. S6. Hole cleaning and acceptance Once the borehole reaches the design elevation or is excavated to the moderately weathered argillaceous limestone or moderately weathered argillaceous limestone bearing layer, and meets the design requirements, the geological survey unit, supervision unit, and construction unit shall be notified in a timely manner to conduct on-site acceptance, and to check the borehole depth, borehole diameter, borehole wall, and verticality. If any defects are found, measures shall be taken to deal with them in a timely manner. In step S4, for small pile diameters and piles with a diameter of 2.5m and a depth of 45m or less, ZR420L rotary drilling is used for rotary drilling. For pile diameters of 2-2.5m and a depth of more than 45m, ZR500L or ZR550L with greater torque is used for rotary drilling. For large pile diameters of 2.5m, four drilling operations are used, employing a 1.4m core extraction method, followed by 1.6m, 2m, and 2.5m core extraction and hole enlargement methods, depending on the pile diameter conditions on site. In step S4, 1-2 rotary drilling rigs are operated in conjunction with 1 medium-sized excavator, using a skip-hole rotary drilling method. The ZR420L rotary drilling rig is used for drilling small-diameter piles and piles up to 45 meters deep; the ZR500L and ZR550L rotary drilling rigs are used for drilling large-diameter piles and piles over 45 meters deep. For rotary drilling of large-diameter, deep-hole piles and rock foundations, a complete set of rotary drilling rigs is required for the project to implement the "relay" rotary drilling process, as detailed below: (1) Installation of steel casing on ZR420L rotary drilling rig: positioning and setting out of the pile hole → using ZR420L rotary drilling rig to install a 2.5m diameter sand scooping bucket drill bit to drill to a depth of 1.5m → installing a 2m high steel casing with a diameter of 2.7m, a burial depth of 1.5m, and a height of 0.5m above the ground → repositioning, re-measuring, and correcting the steel casing; (2) Earthwork operations using the ZR420L rotary drilling rig: The process involves using a 1.6m diameter sand-dredging bucket drill bit for core extraction in the earthwork section, extracting cores to the rock collapse layer, then switching to a 2m diameter sand-dredging bucket drill bit for borehole enlargement in the earthwork section, and then switching to a 2.5m diameter sand-dredging bucket drill bit for borehole enlargement in the earthwork section until the rock collapse layer is reached. (3) Operations in rock collapse zones using ZR420L rotary drilling rig: A. Core extraction operation: Replace with a 1.4m diameter core drill for core extraction operation → If encountering loose gravel or rock layers, use a 1.4m diameter sand-dredging bucket drill to excavate the rock debris → Continue to use a 1.4m diameter core drill for core extraction operation, repeatedly using a 1.4m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m; B. Hole Enlargement Operation: Replace with a 1.6m diameter core drill for hole enlargement operation → If encountering loose gravel or rock layers, use a 1.6m diameter sand-dredging bucket drill to excavate the rock debris → Continue using a 1.6m diameter core drill for hole enlargement operation, repeatedly using a 1.6m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m; C. Hole enlargement operation: Replace with a 2m diameter core drill for hole enlargement operation → If a loose gravel layer or rock layer is encountered, use a 2m diameter sand scoop drill to excavate the rock debris → Continue to use a 2m diameter core drill for hole enlargement operation, repeatedly use a 2m diameter core drill in combination with a sand scoop drill for drilling → until the rock collapse layer ends or the depth reaches 45m. D. Hole enlargement operation: Replace with a 2.5m diameter core drill for hole enlargement operation → If encountering loose gravel or rock layers, use a 2.5m diameter sand-dredging bucket drill to excavate the rock debris → Continue to use a 2.5m diameter core drill for hole enlargement operation, repeatedly using a 2.5m diameter core drill in combination with a sand-dredging bucket for drilling → until the rock collapse layer ends or the depth reaches 45m; (4) The ZR420L rotary drilling rig is used in marl strata, which contain layers of medium-hard rock and hard rock, with a depth limited to within 45m: A. Core extraction operation: Replace with a 1.4m diameter core drill and drill → Core extraction operation ends when the depth reaches 45m; B. Enlargement operation: Replace with a 1.6m diameter core drill for enlargement operation → alternately use a 1.6m diameter core drill in combination with a sand scooping bucket for drilling → end the enlargement operation when the hole depth reaches 45m; B. Hole reaming operation: Replace with a 2m diameter core drill for hole reaming operation → alternately use a 2m diameter core drill in combination with a sand scooping bucket for drilling → finish reaming when the hole depth reaches 45m; B. Enlargement operation: Replace with a 2.5m diameter core drill for enlargement operation → alternate between using a 2.5m diameter core drill and a sand scooping bucket for drilling → complete the enlargement operation when the hole depth reaches 45m; (5) Marlstone strata with sub-hard rock and hard rock layers, with a depth greater than 45m, for ZR500L or ZR550L rotary drilling rigs: A. Move the ZR420L rotary drilling rig to other pile hole operations, and arrange for a ZR500L or ZR550L rotary drilling rig to be in place to continue drilling operations using a relay method; B. Core extraction operation: Replace with a 1.4m diameter core drill to perform core extraction drilling → Core extraction operation ends when the designed depth of the pile is reached; C. Enlargement operation: Replace with a 1.6m diameter core drill for enlargement operation → alternately use a 1.6m diameter core drill in combination with a sand scooping bucket for drilling → enlarge the hole to the designed depth of the pile; D. Hole reaming operation: Replace with a 2m diameter core drill for hole reaming operation → alternately use a 2m diameter core drill in combination with a sand scooping bucket for drilling → ream the hole to the designed depth of the pile; E. Hole reaming operation: Replace with a 2.5m diameter core drill for hole reaming operation → alternately use a 2.5m diameter core drill in combination with a sand scooping bucket for drilling → reaming to the designed depth of the pile hole.

2. The construction method for ultra-deep, large-diameter rotary drilling of collapsed deposits as described in claim 1, characterized in that: Step S5: The key to treating the collapsed section is soil stabilization to make the borehole wall stable. The method to stabilize the borehole wall is to pour low-grade C15 concrete into the collapsed section using the underwater pouring method. The concrete is backfilled to more than 500mm above the top of the collapsed section. After the concrete has set and reached a certain strength, the drilling rig continues to operate. At this time, the concrete has filled the collapsed part. The rotary drilling rig removes the middle part, and the remaining part will form a concrete wall to prevent the collapse from worsening. If the collapse is more serious, manifested by mud and sand in the collapsed section, incomplete cleaning of rock strata, and rebound of small pile hole advance, then it is necessary to pour C15 concrete in layers and drill until the bottom of the collapsed section is treated.

3. The construction method for ultra-deep, large-diameter rotary drilling of collapsed deposits as described in claim 1, characterized in that: Step S6: The borehole inspection method depends on the borehole diameter. If groundwater is present in the borehole, reverse circulation grouting is used to clean the borehole. After the concrete pouring guide pipe is installed, the borehole depth and bottom sediment are re-measured. If the bottom sediment thickness exceeds the specified limit, reverse circulation cleaning is used with the pouring guide pipe. This should be done after the reinforcement cage and guide pipe are installed. The second cleaning should take no less than 30 minutes. The cleaning can be stopped only if the bottom sediment is ≤50mm. The bottom sediment is measured with a heavy hammer, and the reading of the measuring rope must be accurate. The measurement must be corrected every 3-5 boreholes. After cleaning, concrete should be poured as soon as possible, with an interval of no more than 30 minutes. If the bearing stratum of the foundation meets the survey and design requirements, the borehole is closed. If it does not meet the requirements, drilling continues according to the opinions of the survey and design unit until acceptance is passed.

Citation Information

Patent Citations

  • Method for using rotary drilling rig to drill into hard rock stratum

    CN104295239A

  • Multi-stage drill bit graded drilling hole-forming method of combined rotary drilling rig

    CN113738266A