Integrated hoisting device and hoisting method for hoisting steel girder of cable-stayed arch bridge
The integrated hoisting device for the main steel beam of the under-bearing arch bridge cable hoisting solves the problems of long hoisting operation cycle, difficulty in guaranteeing welding quality and high risk of high altitude in the existing technology, and improves construction efficiency and safety. It is suitable for the overall hoisting of irregular cantilever steel beams.
Patent Information
- Application Number
- CN202410189320.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-20
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-02-20
AI Technical Summary
Existing technologies for hoisting the main steel beams of under-bearing arch bridges suffer from problems such as long hoisting operation cycles, difficulty in guaranteeing welding quality, high risk to workers at heights, time-consuming and material-intensive cutting of lifting lugs, and large cantilever lengths with significant safety hazards.
The under-deck arch bridge adopts an integrated hoisting device for the steel main beam, which includes parallel main beams, load-bearing beams, load-bearing bracing beams, lifting lugs and steel plate assemblies. The integrated hoisting of the arch bridge steel main beam is achieved by using trenches and cable hoisting, reducing the need for repeated welding and cutting of the lifting lugs.
It improves construction efficiency and safety, saves construction time and hoisting costs, reduces the danger of high-altitude operations, and is suitable for the one-time overall hoisting of irregularly shaped cantilevered steel beams.
Smart Images

Figure CN117947706B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of bridge construction, specifically to an integrated hoisting device and method for cable-stayed steel main beams of a through-arch bridge. Background Technology
[0002] When hoisting the main steel beam of a through-arch bridge, two methods are generally used: First, lifting lugs are installed on the top plate of the main steel beam of the through-arch bridge, and no separate hoisting device is made. The main steel beam is then installed after it is extended outward. Second, lifting lugs are welded to the side of the web of the through-arch bridge. The lifting lugs are connected to a large hanging frame, and the end of the hanging frame is connected to a hook, so as to achieve the overall hoisting of the main beam in one go.
[0003] The first method has the following drawbacks: ① The cantilever is installed later, and the hoisting operation cycle is long; the welding of the cantilever and the main beam requires the use of a basket or other equipment to send personnel to the welding position, the welding quality cannot be guaranteed, and the workers face high risks when working at heights and in water; ② The lifting lugs are directly set on the top plate of the main beam, and welding and cutting the lifting lugs is time-consuming and material-intensive.
[0004] The second method has the following drawbacks: ① Lifting lugs need to be welded to the outside of the web of the main beam. The cutting and grinding of the lifting lugs requires the use of a basket or other equipment to send personnel to the welding position. The quality of grinding and rust prevention is difficult to guarantee, and the workers are working at height, which is highly dangerous; ② Large hanging frames require special design. The cantilever length is large, and the strength and stability requirements are high, which poses a significant safety hazard. Summary of the Invention
[0005] To address the aforementioned shortcomings of existing technologies, an integrated hoisting device and method for cable-stayed steel main beams of under-deck arch bridges are provided. This avoids the repeated construction of work platforms and hoisting platforms, as well as the repeated cutting of lifting lugs, thereby improving construction efficiency and safety.
[0006] The technical solution adopted by the present invention to solve the above-mentioned technical problems is as follows: An integrated hoisting device for the main steel beam of a cable-stayed arch bridge is characterized by comprising: two parallel main beams, several parallel load-bearing beams, load-bearing diagonal bracing beams connecting the main beams and the load-bearing beams, lifting lugs for connecting external cable hoists, and steel plate assemblies laid on the upper part of the load-bearing beams; the load-bearing beams are vertically fixed to the bottom of the main beams, the load-bearing diagonal bracing beams are located on the outer side of the main beams along their length, and the main beams are connected to each load-bearing beam through the load-bearing diagonal bracing beams; the bottom end of the load-bearing diagonal bracing beams is fixed to the load-bearing beams, and the top end of the load-bearing diagonal bracing beams is fixed to the side of the main beams; the lifting lugs are welded to the load-bearing beams; The steel plate assembly forms the construction platform; a trench is provided on the ground at the bottom of the load-bearing beam, the load-bearing beam is placed in the trench, the height of the steel plate assembly is the same as the height of the ground outside the trench, and the gap between the two main beams is greater than the width of the beam transport vehicle.
[0007] According to the above technical solution, the steel plate assembly includes several parallel distribution beams and steel plates laid on top of the distribution beams. The distribution beams are vertically arranged on top of the load-bearing beams and located between the main beams; the steel plates serve as a construction operation platform.
[0008] According to the above technical solution, the main beam adopts a Bailey bridge and is connected by pins; the main beam and the load-bearing beam are connected by a portal frame; the main beam and the load-bearing diagonal brace beam are connected by welding; the load-bearing beam and the distribution beam are connected by welding, and the distribution beam is connected by welding to the steel plate.
[0009] According to the above technical solution, the length of the main beam and the spacing between adjacent sides are adjusted based on the width of the beam transport vehicle and the length of the arch bridge steel main beam.
[0010] A method for integrated hoisting of the steel main beam of a cable-stayed arch bridge, characterized by the following steps: S1: Conduct trench construction on the ground to ensure that the hoisting equipment is embedded in the original foundation; S2: Use a beam transport vehicle to transport the main steel beam of the arch bridge from the ground to the hoisting device embedded in the trench; S3: Use external cable hoists to fix the main steel beam of the arch bridge from the beam transport vehicle to the hoisting device; S4: The cable crane transports the hoisting equipment and the main steel beam of the arch bridge to the design location together, and completes the hoisting and installation of the main steel beam of the arch bridge.
[0011] According to the above technical solution, in step S1, the original foundation refers to the ground in the area below the cable crane's running trajectory, and the ground must be connected to external roads.
[0012] According to the above technical solution, in step S2, when the beam transport vehicle carries the main steel beam of the arch bridge and transports it from the main steel beam stacking area to the hoisting device, the height of the main beam must be less than the height of the lowest point of the main steel beam of the arch bridge from the ground.
[0013] According to the above technical solution, after the beam transport vehicle stops at the construction platform composed of steel plate components, step S3 includes the following steps: S31: Connect the cable to the main steel beam of the arch bridge; S32: Use cable cranes to hoist the main steel beams of the arch bridge to a certain height; S33: The beam transport vehicle will then be driven away from the construction work platform; S34: Lower the cable crane to secure the main steel beam of the arch bridge to the hoisting device.
[0014] According to the above technical solution, in step S4, the cable hoist is fixed on the lifting lugs of the two load-bearing beams located on the leftmost and rightmost sides; then it is lifted and the arch bridge steel main beam is transported to the design position along with the hoisting device; the corresponding arch ribs on the arch bridge steel main beam are connected, and the arch bridge steel main beam is temporarily connected to the front section of the arch bridge steel main beam that has been installed. The cable hoist is released, and the hoisting of a single section of the arch bridge steel main beam is completed.
[0015] The present invention has the following beneficial effects: Because the ground has trenches at the same height as the load-bearing beams, when the hoisting device is lowered onto the ground, the upper surface of the steel plate assembly is flush with the ground, serving as a temporary parking point for the beam transport vehicle. The beam transport vehicle can smoothly travel from the ground to the construction platform formed by the steel plate assemblies, or vice versa. The arch bridge steel main beam is transported from the arch bridge steel main beam stacking area to the construction platform (i.e., the temporary parking point) formed by the steel plate assemblies by the beam transport vehicle, and then lifted to a certain height using an external cable crane. At this point, the arch bridge steel main beam is supported by the cable crane. Subsequently, the beam transport vehicle is moved out from between the two main beams, the height of the cable crane is lowered, the arch bridge steel main beam is placed on the hoisting device, and the arch bridge steel main beam is connected to the hoisting device. Finally, the arch bridge steel main beam is transported to the design location along with the hoisting device using a cable crane; and the installation of the arch bridge steel main beam is completed using the construction platform formed by the steel plate assemblies.
[0016] Based on the above measures, firstly, trenches are used to make the ground and the surface of the construction platform flush, facilitating the movement of the beam transport vehicle between the ground and the construction platform; then, cable hoisting is used to switch the arch bridge steel main beam from the beam transport vehicle to the hoisting device, which facilitates the one-time overall hoisting of arch bridge steel main beam segments (especially suitable for steel beams with irregular overhangs); while saving the construction period of the steel main beam hoisting, the time spent on repeated welding and cutting of the hoisting lugs during the hoisting process can be reduced because the lifting lugs are welded to the hoisting platform.
[0017] In addition, integrating the construction operation platform and the arch bridge steel main beam hoisting device saves on the construction cost of the hoisting device and the construction operation platform, and further shortens the construction period.
[0018] Finally, the hoisting equipment can be reused, saving on platform manufacturing costs. Attached Figure Description
[0019] Figure 1 This is a schematic diagram of the steel main beam of the arch bridge installed under the arch rib; Figure 2 This is a front view of an embodiment provided by the present invention; Figure 3 This is a top view of an embodiment provided by the present invention; Figure 4This is a view of an embodiment provided by the present invention; In the diagram, 1 is the main beam; 2 is the load-bearing beam; 3 is the load-bearing diagonal bracing beam; 4 is the cable-stayed lifting cable; 5 is the lifting lug; 6 is the distribution beam; 7 is the steel plate; 8 is the arch rib; and 9 is the main steel beam of the arch bridge. Detailed Implementation
[0020] The present invention will now be described in detail with reference to the accompanying drawings and embodiments.
[0021] Reference Figures 1-4 As shown, the present invention provides an integrated hoisting device for cable-stayed steel main beams of a lower-bearing arch bridge.
[0022] Example 1 The system includes two parallel main beams 1, several parallel load-bearing beams 2, load-bearing diagonal bracing beams 3 connecting the main beams and the load-bearing beams, lifting lugs 5 for connecting to an external cable crane (as shown in the figure, the lifting lugs are connected to the cable crane lifting cables 4), and steel plate assemblies laid on the upper part of the load-bearing beams; the load-bearing beams are vertically fixed to the bottom of the main beams (as shown in the embodiment in the figure, preferably, the two main beams are fixed to the two ends of the upper surface of the load-bearing beams respectively), the load-bearing diagonal bracing beams are provided on the outer side of the main beams along their length, and the main beams are connected to each load-bearing beam through the load-bearing diagonal bracing beams; the bottom end of the load-bearing diagonal bracing beam is fixed to the load-bearing beam, and the top end of the load-bearing diagonal bracing beam is fixed to the side of the main beam; the lifting lugs are welded to the load-bearing beams; The steel plate assembly forms the construction platform; a trench is provided on the ground at the bottom of the load-bearing beam, the load-bearing beam is placed in the trench, the height of the steel plate assembly is the same as the height of the ground outside the trench, and the gap between the two main beams is greater than the width of the beam transport vehicle.
[0023] In this embodiment, since there is a trench on the ground at the same height as the load-bearing beam, when the hoisting device is placed on the ground, the upper surface of the steel plate assembly is flush with the ground, and the upper surface of the steel plate assembly serves as a temporary parking point for the beam transport vehicle. The beam transport vehicle can smoothly travel from the ground to the construction platform composed of the steel plate assembly, or the construction platform composed of the steel plate assembly can travel to the ground. The arch bridge steel main beam 9 is transported from the arch bridge steel main beam stacking area to the construction platform composed of the steel plate assembly (i.e., the temporary parking point) by the beam transport vehicle, and the arch bridge steel main beam is lifted to a certain height using an external cable crane. At this time, the arch bridge steel main beam is supported by the cable crane. Then, the beam transport vehicle is moved out from between the two main beams, the height of the cable crane is lowered, the arch bridge steel main beam is placed on the hoisting device, and the arch bridge steel main beam is connected to the hoisting device. Finally, the arch bridge steel main beam is transported to the design position along with the hoisting device using a cable crane; and the installation of the arch bridge steel main beam is completed using the construction platform composed of the steel plate assembly.
[0024] Based on the above measures, trenches are used to achieve flush alignment between the ground and the surface of the construction platform, facilitating the movement of the beam transport vehicle between the ground and the construction platform. Subsequently, a cable-stayed crane is used to switch the arch bridge's main steel beam from the beam transport vehicle to the hoisting device, enabling the one-time, integral hoisting of arch bridge main steel beam segments (especially suitable for steel beams with irregular overhangs). This not only saves time in the main steel beam hoisting process but also reduces the time spent on repeated welding and cutting of the lifting lugs during hoisting, as they are welded to the hoisting platform. Furthermore, integrating the construction platform and the arch bridge main steel beam hoisting device saves on the construction costs of the hoisting device and the construction platform, further shortening the construction period. Finally, the hoisting device can be reused, saving on platform manufacturing costs.
[0025] Example 2 The structure and principle of Example 2 are similar to those of Example 1, except that a preferred structural form of the steel plate assembly is provided. Other structural forms of the steel plate assembly can also be used, as long as a platform for the beam transport vehicle to pass through is formed on the upper part of the load-bearing beam.
[0026] The steel plate assembly includes several parallel distribution beams 6 and steel plates 7 laid on top of the distribution beams. The distribution beams are vertically arranged on top of the load-bearing beams and located between the main beams; the steel plates serve as a construction work platform. By utilizing the distribution beams and steel plates to lay the work platform on top of the load-bearing beams, the construction work platform and hoisting device are integrated, saving on the cost of hoisting devices and platforms, and also saving construction time. When the hoisting device is placed in the trench, the upper surface of the steel plate is flush with the ground around the trench, facilitating the movement of the beam transport vehicle from the ground around the trench to the upper surface of the steel plate.
[0027] In Embodiments 1 and 2, preferably, the main beam is a Bailey bridge and connected by pins; the main beam and the load-bearing beam are connected by a portal frame; the main beam and the load-bearing diagonal brace are connected by welding; the load-bearing beam and the distribution beam are connected by welding, and the distribution beam is connected by welding to the steel plate.
[0028] In Examples 1 and 2, preferably, the length of the main beam and the spacing between adjacent sides are adjusted according to the width of the beam transport vehicle and the length of the arch bridge steel main beam. The platform structure dimensions can be flexibly selected, and the dimensions and structural form can be adjusted according to the main beam dimensions, which can reduce the transverse span of the cable-stayed tower to save materials.
[0029] The present invention also provides a method for the integrated hoisting of the steel main beam of a cable-stayed arch bridge.
[0030] Example 1 Includes the following steps: S1: Conduct trench construction on the ground to ensure that the hoisting equipment is embedded in the original foundation; S2: Use a beam transport vehicle to transport the main steel beam of the arch bridge from the ground to the hoisting device embedded in the trench; S3: Use external cable hoists to fix the main steel beam of the arch bridge from the beam transport vehicle to the hoisting device; S4: The cable crane transports the hoisting equipment and the main steel beam of the arch bridge to the design location together, and completes the hoisting and installation of the main steel beam of the arch bridge.
[0031] In this embodiment, a trench design is added to make the ground and the upper surface of the load-bearing beam of the hoisting device flush, facilitating the transport vehicle from the arch bridge steel main beam stacking area to the construction work platform of the hoisting device. Subsequently, the arch bridge steel main beam and the hoisting device are hoisted sequentially using a cable crane. First, the arch bridge steel main beam is hoisted from the transport vehicle onto the hoisting device using a cable crane, and then fixed to the hoisting device. Second, the cable crane is removed from the arch bridge steel main beam and fixed to the hoisting device. The hoisting device and the arch bridge steel main beam fixed to the hoisting device are then hoisted together to the designed position using a cable crane, completing the hoisting and installation of the arch bridge steel main beam.
[0032] This hoisting method fixes the main steel beam of the arch bridge onto the hoisting device, which is then used to hoist the main steel beam and serve as a construction work platform. This method allows for the one-time hoisting of steel beam segments (especially suitable for steel beams with irregular overhangs), saving time on the main steel beam hoisting process. It also integrates the construction work platform and the steel beam hoisting platform, saving on the cost of hoisting devices and platforms, while also saving time.
[0033] Example 2 The steps and principles of Example 2 are similar to those of Example 1, except that in step S1, the original foundation refers to the ground area below the cable crane's running track, and this ground area must be connected to external roads. The purpose of connecting to external roads is to facilitate the transport vehicle from the arch bridge steel main beam storage area to the ground area. The purpose of being located below the cable crane's running track is to utilize the cable crane for hoisting the arch bridge steel main beam.
[0034] In embodiments 1 and 2, preferably, in step S2, when the beam transport vehicle carries the arch bridge steel main beam and transports it from the arch bridge steel main beam stacking area to the hoisting device, the height of the main beam must be less than the height of the lowest point of the arch bridge steel main beam from the ground.
[0035] In embodiments 1 and 2, preferably, after the beam transport vehicle stops at the construction work platform composed of steel plate components, step S3 includes the following steps: S31: Connect the cable to the main steel beam of the arch bridge; S32: Use cable cranes to hoist the main steel beams of the arch bridge to a certain height; S33: The beam transport vehicle will then be driven away from the construction work platform; S34: Lower the cable crane to secure the main steel beam of the arch bridge to the hoisting device.
[0036] In embodiments 1 and 2, preferably, in step S4, the cable hoist is fixed to the lifting lugs of the two load-bearing beams located on the leftmost and rightmost sides; then it is lifted, and the arch bridge steel main beam is transported to the design position along with the hoisting device; the arch bridge steel main beam is connected to the corresponding arch rib 8 on the arch bridge steel main beam, and the arch bridge steel main beam is temporarily connected to the front section of the arch bridge steel main beam that has been installed. The cable hoist is released, and the hoisting of a single section of the arch bridge steel main beam is completed.
[0037] The above are merely preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. Therefore, any equivalent changes made in accordance with the claims of the present invention shall still fall within the protection scope of the present invention.
Claims
1. An integrated hoisting device for the main steel beam of a cable-stayed arch bridge, characterized in that: It includes two parallel main beams, several parallel load-bearing beams, load-bearing diagonal bracing beams connecting the main beams and the load-bearing beams, lifting lugs for connecting external cable cranes, and steel plate assemblies laid on the upper part of the load-bearing beams; the load-bearing beams are vertically fixed to the bottom of the main beams, the load-bearing diagonal bracing beams are located on the outer side of the main beams along their length, and the main beams are connected to each load-bearing beam through the load-bearing diagonal bracing beams; the bottom end of the load-bearing diagonal bracing beam is fixed to the load-bearing beam, and the top end of the load-bearing diagonal bracing beam is fixed to the side of the main beam; the lifting lugs are welded to the load-bearing beams; The steel plate assembly forms the construction platform; a trench is provided on the ground at the bottom of the load-bearing beam, the load-bearing beam is placed in the trench, the height of the steel plate assembly is the same as the height of the ground outside the trench, and the gap between the two main beams is greater than the width of the beam transport vehicle.
2. The integrated hoisting device for cable-stayed steel main beams of a lower-bearing arch bridge according to claim 1, characterized in that: The steel plate assembly includes several parallel distribution beams and steel plates laid on top of the distribution beams. The distribution beams are vertically arranged on top of the load-bearing beams and located between the main beams; the steel plates serve as a construction operation platform.
3. The integrated hoisting device for cable-stayed steel main beams of a lower-bearing arch bridge according to claim 1, characterized in that: The main beams are constructed using Bailey bridges and connected by pins; the main beams and load-bearing beams are connected by portal frames; the main beams and load-bearing diagonal braces are connected by welding; the load-bearing beams are connected to the distribution beams by welding, and the distribution beams are connected to the steel plates by welding.
4. The integrated hoisting device for cable-stayed steel main beams of a lower-bearing arch bridge according to claim 1, characterized in that: Adjust the length of the main beam and the spacing between adjacent sides according to the width of the beam transport vehicle and the length of the arch bridge steel main beam.
5. A method for the integrated hoisting of the steel main beam of a cable-stayed arch bridge, characterized in that: The method employs the integrated hoisting device for cable-stayed steel main beams of under-deck arch bridges as described in any one of claims 1-4; the method includes the following steps: S1: Conduct trench construction on the ground to ensure that the hoisting equipment is embedded in the original foundation; S2: Use a beam transport vehicle to transport the main steel beam of the arch bridge from the ground to the hoisting device embedded in the trench; S3: Use external cable hoists to fix the main steel beam of the arch bridge from the beam transport vehicle to the hoisting device; S4: The cable crane transports the hoisting equipment and the main steel beam of the arch bridge to the design location together, and completes the hoisting and installation of the main steel beam of the arch bridge.
6. The method for integrated hoisting of the steel main beam of a cable-stayed arch bridge according to claim 5, characterized in that: In step S1, the original foundation refers to the ground in the area below the cable crane's running trajectory, and the ground must be connected to external roads.
7. The method for integrated hoisting of the steel main beam of a cable-stayed arch bridge according to claim 5, characterized in that: In step S2, when the beam transport vehicle carries the main steel beam of the arch bridge and transports it from the main steel beam stacking area to the hoisting device, the height of the main beam must be less than the height of the lowest point of the main steel beam of the arch bridge from the ground.
8. The method for integrated hoisting of the steel main beam of a cable-stayed arch bridge according to claim 5, characterized in that: After the beam transport vehicle stops at the construction platform composed of steel plate components, step S3 includes the following steps: S31: Connect the cable to the main steel beam of the arch bridge; S32: Use cable cranes to hoist the main steel beams of the arch bridge to a certain height; S33: The beam transport vehicle will then be driven away from the construction work platform; S34: Lower the cable crane to secure the main steel beam of the arch bridge to the hoisting device.
9. The method for integrated hoisting of the steel main beam of a cable-stayed arch bridge according to claim 5, characterized in that: In step S4, the cable hoist is fixed to the lifting lugs of the two load-bearing beams located on the leftmost and rightmost sides; then it is lifted and transported to the design position along with the hoisting device; the corresponding arch ribs on the arch bridge steel main beam are connected, and the arch bridge steel main beam is temporarily connected to the front section of the arch bridge steel main beam that has been installed. The cable hoist is released, and the hoisting of a single section of the arch bridge steel main beam is completed.
Citation Information
Patent Citations
Rear girder feeding construction method for large-size steel box girder of cable-stayed bridge in narrow terrain
CN115772851A
Construction method of large-span Y-shaped steel box rib arch bridge
CN116024908A