Long-distance air cushion straight-discharge type slurry shield informationized construction method and system

By acquiring and analyzing geological information of shield tunnels, using finite element analysis to formulate construction plans, and adjusting construction parameters in real time, the problem of inaccurate adjustment of construction parameters in long-distance air cushion direct-discharge slurry shield tunnels was solved, thereby improving the safety, quality, and efficiency of construction.

CN117988871BActive Publication Date: 2026-11-24POWERCHINA RAILWAY CONSTR
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410267611.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-08
Publication Date
2026-11-24
Estimated Expiration
2044-03-08

AI Technical Summary

Technical Problem

In long-distance air-cushion direct-discharge slurry shield tunneling, construction workers rely on experience and simple instruments and equipment, which makes it difficult to guarantee construction efficiency, quality and safety, and makes it impossible to adjust construction parameters accurately.

Method used

By acquiring tunnel-related information of the shield tunnel, geological exploration is carried out, geological information is collected, finite element analysis software is used to predict structural response data, construction plans are formulated, and the response data of the geological layer is monitored in real time to adjust construction parameters.

Benefits of technology

It improves the safety, quality, and efficiency of construction, ensures the precision and controllability of the construction process, and reduces construction risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117988871B_ABST
    Figure CN117988871B_ABST
Patent Text Reader

Abstract

This invention relates to the field of subway construction technology, and discloses an information-based construction method and system for long-distance air-cushion direct-discharge slurry shield tunneling. The method includes: acquiring tunnel-related information of the shield tunnel; exploring the geological layers surrounding the shield tunnel based on the tunnel-related information, and collecting geological information around the shield tunnel during the exploration process; analyzing and processing the tunnel-related and geological information, and formulating a construction plan based on the analysis and processing results; setting the construction operating parameters of the slurry shield machine according to the construction plan and geological information; acquiring real-time response monitoring data of the geological layers during slurry shield tunneling, and adjusting the construction operating parameters of the slurry shield machine based on the response monitoring data. This invention improves the quality and efficiency of construction by analyzing tunnel and geological information to formulate a precise construction plan and setting the construction operating parameters of the slurry shield machine accordingly, and by adjusting the construction operating parameters based on real-time monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of subway construction technology, and in particular to an information-based construction method and system for long-distance air cushion direct discharge slurry shield tunneling. Background Technology

[0002] In the construction of long-distance air-cushion direct-discharge slurry shield tunnels, accurate understanding of construction information is crucial to ensuring the safety and quality of construction. Therefore, geological exploration and obtaining geological information around the shield tunnel are essential steps. This information is crucial for formulating reasonable construction plans and setting the construction parameters of the slurry shield machine, so as to improve the accuracy, efficiency and controllability of construction.

[0003] In traditional long-distance air-cushion direct-discharge slurry shield tunneling, construction workers typically rely on experience and simple instruments, making them susceptible to subjective factors and unable to precisely adjust the slurry shield tunneling process, thus compromising construction efficiency, quality, and safety. However, with the development of information technology, information-based construction methods have been applied to long-distance air-cushion direct-discharge slurry shield tunneling, providing comprehensive technical support and management tools for the construction process. Summary of the Invention

[0004] To address the aforementioned technical problems, this invention provides an information-based construction method and system for long-distance air-cushion direct-discharge slurry shield tunneling, comprising: Obtain tunnel-related information of the shield tunnel, explore the geological layers around the shield tunnel based on the tunnel-related information, and collect geological information around the shield tunnel during the exploration process; The tunnel-related and geological information is analyzed and processed, and a construction plan is formulated based on the analysis and processing results; The construction parameters of the slurry shield tunneling machine are set according to the construction plan and geological information. Real-time monitoring data of geological strata response during slurry shield tunneling is acquired, and the construction parameters of the slurry shield tunneling machine are adjusted based on the response monitoring data.

[0005] Furthermore, the acquisition of tunnel-related information of the shield tunnel, the exploration of the geological strata surrounding the shield tunnel based on the tunnel-related information, and the collection of geological information around the shield tunnel during the exploration process include: Obtain tunnel-related information of the shield tunnel, and extract the location information of the shield tunnel from the tunnel-related information; Based on the location information, the geological strata around the shield tunnel are explored, and geological information around the shield tunnel is collected during the exploration process.

[0006] Furthermore, the analysis and processing of the tunnel-related and geological information, and the formulation of a construction plan based on the analysis and processing results, include: Extract the design information of the shield tunnel from the tunnel-related information, construct the geometric model of the shield tunnel based on the design information, and add model information to the geometric model according to the design information; A geological model is constructed based on the geological information, and model information is added to the geological model according to the geological information. The geometric model and the geological model are assembled to form a finite element model of the shield tunnel structure; The finite element model is analyzed using finite element analysis software. Based on the analysis results, the structural response data of the shield tunnel is predicted, and a construction plan is formulated based on the structural response data.

[0007] Furthermore, the assembly of the geometric model and the geological model to form a finite element model of the shield tunnel structure includes: The geometric model is matched with the geological model based on the geological strata and the geometry of the shield tunnel. The matched geometric model and the geological model are then assembled to obtain the finite element model of the shield tunnel structure.

[0008] Furthermore, the step of performing finite element analysis on the finite element model using finite element analysis software, predicting the structural response data of the shield tunnel based on the analysis results, and formulating a construction plan based on the structural response data includes: The finite element model is divided into multiple finite element meshes, and the material parameters and boundary conditions of the finite element meshes are set according to the design information and geological information. The material parameters and boundary conditions of each finite element mesh are combined using formulas, and the formulas are solved to obtain the structural response data of the shield tunnel. A construction plan is developed based on the structural response data.

[0009] Furthermore, the step of developing a construction plan based on the structural response data includes: Calculate each data difference between the structural response data and the preset data, determine the interval range of each data difference, and set a corresponding construction stability parameter requirement based on the interval range of the data difference; All construction stability parameters are combined according to time nodes to form a construction plan.

[0010] Furthermore, setting the construction parameters of the slurry shield tunneling machine based on the construction plan and geological information includes: Analyze the construction stability parameter requirements in the construction plan and the geological conditions in the geological information; Based on the construction stability parameter requirements and geological conditions, the construction operating parameters of the slurry shield tunneling machine are set. The construction operating parameters include the advance speed, thrust, grouting pressure and cutterhead rotation speed of the slurry shield tunneling machine.

[0011] Furthermore, the real-time acquisition of geological layer response monitoring data during slurry shield tunneling construction, and the feedback adjustment of the slurry shield tunneling machine's construction parameters based on the response monitoring data, includes: The response monitoring data of the slurry shield tunneling machine during the slurry shield tunneling construction process is obtained, and the response monitoring data is made into a corresponding curve change graph to determine whether the response monitoring data exceeding the preset change rate exceeds the preset value. Select the response monitoring data that exceed the preset rate of change in the curve change graph, and calculate the difference between the response monitoring data that exceed the preset rate of change and the preset value; Based on the magnitude of the difference, an adjustment coefficient is selected to adjust the construction work parameters corresponding to the response monitoring data that exceed the preset value, and the adjusted construction work parameters are then updated.

[0012] This invention also provides a long-distance air-cushion direct-discharge slurry shield tunneling information construction system, comprising: The acquisition module is used to acquire tunnel-related information of the shield tunnel, explore the geological layers around the shield tunnel based on the tunnel-related information, and collect geological information around the shield tunnel during the exploration process; The planning module is used to analyze and process the tunnel-related and geological information, and to formulate a construction plan based on the analysis and processing results; The parameter setting module is used to set the construction operating parameters of the slurry shield tunneling machine according to the construction plan and geological information. The adjustment module is used to acquire real-time response monitoring data of the geological layer during the slurry shield tunneling process, and to adjust the construction parameters of the slurry shield tunneling machine based on the response monitoring data.

[0013] Compared with existing technologies, the beneficial effects of the information-based construction method and system for long-distance air-cushion direct-discharge slurry shield tunneling according to embodiments of the present invention are as follows: This invention employs a variety of geological exploration techniques to obtain more accurate and comprehensive geological information, which helps to better understand the properties, structure, and changes of the geological strata surrounding the tunnel, thereby improving the accuracy of geological strata exploration. This invention analyzes and processes tunnel-related and geological information, enabling a more comprehensive assessment of the impact of geological conditions on construction and the development of more reasonable construction plans. This helps to reduce construction risks and improve construction efficiency and quality. This invention sets the construction parameters of the slurry shield tunneling machine based on the construction plan and geological information, which helps to adjust parameters such as the advancing speed, thrust, and grouting pressure according to changes in geological conditions, so as to ensure construction safety and quality and improve construction efficiency. This invention acquires real-time response monitoring data of geological layers and adjusts the construction parameters of the slurry shield tunneling machine based on the response monitoring data. This helps to detect changes and problems in the geological layers in a timely manner and adjust the construction parameters accordingly to ensure the safety and quality of construction. This invention improves the safety, quality, and efficiency of shield tunnel construction by accurately acquiring geological information, analyzing and processing geological data, formulating reasonable construction plans, setting construction parameters adapted to geological conditions, and monitoring the geological layer response in real time and adjusting the construction parameters of the slurry shield machine during the construction process. Attached Figure Description

[0014] Figure 1 This is a schematic diagram of the process structure of the long-distance air cushion direct discharge slurry shield tunneling information construction method in an embodiment of the present invention; Figure 2 This is a schematic diagram of the composition of the long-distance air cushion direct discharge slurry shield tunneling information construction system in an embodiment of the present invention. Detailed Implementation

[0015] The specific embodiments of this application will be described in further detail below with reference to the accompanying drawings and examples. The following examples are for illustrative purposes only and are not intended to limit the scope of the invention.

[0016] In the description of this application, it should be understood that the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this application and simplifying the description, and do not indicate or imply that the platform or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this application.

[0017] The terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of this application, unless otherwise stated, "a plurality of" means two or more.

[0018] In the description of this application, it should be noted that, unless otherwise expressly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art can understand the specific meaning of the above terms in this application based on the specific circumstances.

[0019] like Figure 1 As shown in the embodiments of this application, an information-based construction method for long-distance air-cushion direct-discharge slurry shield tunneling is provided, including: S100: acquiring tunnel-related information of the shield tunnel, exploring the geological layers around the shield tunnel based on the tunnel-related information, and collecting geological information around the shield tunnel during the exploration process; S200: analyzing and processing the tunnel-related information and geological information, and formulating a construction plan based on the analysis and processing results; S300: setting the construction working parameters of the slurry shield machine according to the construction plan and geological information; S400: acquiring real-time response monitoring data of the geological layers during the slurry shield construction process, and adjusting the construction working parameters of the slurry shield machine based on the response monitoring data.

[0020] Furthermore, by accurately acquiring geological information, analyzing and processing geological data, formulating reasonable construction plans, setting construction parameters adapted to geological conditions, and monitoring the geological layer response in real time and adjusting the construction parameters of the slurry shield tunneling machine during the construction process, the safety, quality, and efficiency of shield tunnel construction can be improved.

[0021] In the embodiments of this application, an information-based construction control method for long-distance air-cushion direct-discharge slurry shield tunneling is provided. The method involves obtaining tunnel-related information of the shield tunnel, exploring the geological layers around the shield tunnel based on the tunnel-related information, and collecting geological information around the shield tunnel during the exploration process. This includes: obtaining tunnel-related information of the shield tunnel and extracting the location information of the shield tunnel from the tunnel-related information; exploring the geological layers around the shield tunnel based on the location information, and collecting geological information around the shield tunnel during the exploration process.

[0022] Preferably, by collecting and acquiring tunnel-related information, including design drawings, technical specifications, engineering reports, etc., basic information such as tunnel dimensions, geological conditions, and construction stability parameter requirements can be provided.

[0023] Preferably, based on tunnel-related information, geological exploration is designed and carried out. Geological exploration can employ techniques such as drilling, ground-penetrating radar, and seismic exploration to obtain detailed information about the geological layers surrounding the tunnel, including soil type, rock strata properties, and groundwater level.

[0024] Preferably, during the geological exploration process, geological information around the shield tunnel is collected, which may include soil sampling, rock core sampling, groundwater sampling, etc., to ensure that the collected geological information is accurate and comprehensive.

[0025] Preferably, the collected geological information is analyzed and processed, including the properties of soil and rock strata, groundwater level and water quality, in order to obtain a detailed understanding of geological conditions and geological characteristics.

[0026] In an embodiment of this application, an information-based construction control method for long-distance air-cushion direct-discharge slurry shield tunneling is provided. The method involves analyzing and processing tunnel-related and geological information, and formulating a construction plan based on the analysis and processing results. This includes: extracting design information of the shield tunnel from the tunnel-related information; constructing a geometric model of the shield tunnel based on the design information; adding model information to the geometric model based on the design information; constructing a geological model based on the geological information; adding model information to the geological model based on the geological information; assembling the geometric model and the geological model to form a finite element model of the shield tunnel structure; performing finite element analysis on the finite element model using finite element analysis software; predicting the structural response data of the shield tunnel based on the analysis results; and formulating a construction plan based on the structural response data.

[0027] In an embodiment of this application, an information-based construction control method for long-distance air-cushion direct-discharge slurry shield tunneling is provided. The method of assembling the geometric model and the geological model to form a finite element model of the shield tunnel structure includes: mapping the geometric model to the geological model according to the geological layers and the geometry of the shield tunnel; and assembling the mapped geometric model and the geological model to obtain a finite element model of the shield tunnel structure.

[0028] In an embodiment of this application, an information-based construction control method for long-distance air-cushion direct-discharge slurry shield tunneling is provided. The method involves performing finite element analysis on the finite element model using finite element analysis software, predicting the structural response data of the shield tunnel based on the analysis results, and formulating a construction plan based on the structural response data. The method includes: dividing the finite element model into multiple finite element meshes, and setting the material parameters and boundary conditions of the finite element meshes according to design and geological information; combining the material parameters and boundary conditions of each finite element mesh using formulas, solving the formulas to obtain the structural response data of the shield tunnel; and formulating a construction plan based on the structural response data.

[0029] Specifically, firstly, based on design and geological information, the tunnel structure is divided into multiple finite element meshes, each representing a small region where the structural behavior can be simulated and analyzed using the finite element method. Then, based on the design and geological information, material parameters and boundary conditions are set for each finite element mesh. Material parameters include the material's elastic modulus, Poisson's ratio, density, etc., which determine the material's mechanical behavior under stress. Boundary conditions include constraints and loading conditions applied to the structural boundaries, such as fixed boundaries, loading forces, and displacements. Next, the material parameters of each finite element mesh are... By combining formulas with parameters and boundary conditions, the mechanical equations of the finite element model are established. These equations describe the relationship between stress, strain, and displacement within each finite element mesh. Then, using numerical calculation methods (such as iterative methods or matrix operations), the mechanical equations of the finite element model are solved to obtain the response data of the shield tunnel structure. This response data includes stress distribution, displacement changes, etc., reflecting the deformation and response of the structure under stress. Finally, based on the obtained structural response data, a construction plan can be formulated. According to the structural response of the shield tunnel, the stability and safety of the structure can be evaluated, and appropriate construction measures and time nodes can be determined. In summary, by dividing the finite element model into multiple finite element meshes and setting material parameters and boundary conditions according to design and geological information, the structural response data of the shield tunnel can be solved, and a reasonable construction plan can be formulated based on this data. This method can improve the accuracy and efficiency of construction and ensure the structural safety and stability during the construction process.

[0030] In the embodiments of this application, an information-based construction control method for long-distance air-cushion direct-discharge slurry shield tunneling is provided. The step of formulating a construction plan based on the structural response data includes: calculating each data difference between the structural response data and preset data, determining the interval range of each data difference, setting a corresponding construction stability parameter requirement according to the interval range of the data difference, and combining all construction stability parameter requirements according to time nodes to form a construction plan.

[0031] In an embodiment of this application, an information-based construction control method for a long-distance air-cushion direct-discharge slurry shield tunneling machine is provided. The step of setting the construction operating parameters of the slurry shield tunneling machine according to the construction plan and geological information includes: analyzing the construction stability parameter requirements in the construction plan and the geological conditions in the geological information; setting the construction operating parameters of the slurry shield tunneling machine according to the construction stability parameter requirements and geological conditions, wherein the construction operating parameters include the slurry shield tunneling machine's advance speed, thrust, grouting pressure, and cutterhead rotation speed.

[0032] Specifically, based on the required construction stability parameters and geological conditions, a suitable advancing speed is determined. When geological conditions are favorable and construction stability requirements are low, the advancing speed can be appropriately increased to improve construction efficiency. Conversely, when geological conditions are complex or construction stability requirements are high, the advancing speed should be appropriately reduced to ensure construction safety. Based on geological conditions, groundwater level, and water pressure, a suitable thrust is determined. When geological conditions are poor or there is a high groundwater level and water pressure, the thrust needs to be increased to overcome the resistance of water pressure and soil layers. When geological conditions are favorable or the groundwater level is low, the thrust can be appropriately reduced. Based on geological conditions and construction stability requirements, a suitable grouting pressure is determined. When geological conditions are poor and construction stability requirements are high, the grouting pressure needs to be increased to reinforce the strata and prevent water seepage. When geological conditions are favorable and construction stability requirements are low, the grouting pressure can be appropriately reduced. Based on geological conditions and construction stability requirements, a suitable cutterhead rotation speed is determined. When geological conditions are hard and construction stability requirements are low, the cutterhead rotation speed can be appropriately increased to accelerate the advancing speed. When geological conditions are soft and construction stability requirements are high, the cutterhead rotation speed should be appropriately reduced.

[0033] In an embodiment of this application, an information-based construction control method for a long-distance air-cushion direct-discharge slurry shield tunneling machine is provided. The method involves real-time acquisition of geological layer response monitoring data during slurry shield tunneling construction, and feedback adjustment of the slurry shield tunneling machine's construction parameters based on the response monitoring data. This includes: acquiring response monitoring data of the slurry shield tunneling machine during construction; generating a curve graph from the response monitoring data; determining whether response monitoring data exceeding a preset rate of change exceeds a preset value; selecting response monitoring data exceeding the preset rate of change from the curve graph and calculating the difference between the response monitoring data exceeding the preset rate of change and the preset value; selecting an adjustment coefficient based on the magnitude of the difference to adjust the construction parameters corresponding to the response monitoring data exceeding the preset value, and updating the adjusted construction parameters.

[0034] Preferably, during the slurry shield tunneling process, real-time monitoring data of the geological layer's response can be obtained through monitoring equipment such as vibration sensors and displacement sensors.

[0035] Preferably, the construction parameters of the slurry shield tunneling machine are adjusted based on real-time monitoring data, and the advance speed, thrust, grouting pressure and cutterhead speed are adjusted according to the response of the geological layer to ensure the safety and quality of construction.

[0036] like Figure 2As shown in the embodiments of this application, a long-distance air-cushion direct-discharge slurry shield tunneling information construction system is provided, comprising: an acquisition module, used to acquire tunnel-related information of the shield tunnel, explore the geological layers around the shield tunnel based on the tunnel-related information, and collect geological information around the shield tunnel during the exploration process; a planning module, used to analyze and process the tunnel-related information and geological information, and formulate a construction plan based on the analysis and processing results; a parameter setting module, used to set the construction working parameters of the slurry shield machine according to the construction plan and geological information; and an adjustment module, used to acquire real-time response monitoring data of the geological layers during the slurry shield tunneling construction process, and adjust the construction working parameters of the slurry shield machine based on the response monitoring data.

[0037] In summary, this invention provides an information-based construction method and system for long-distance air-cushion direct-discharge slurry shield tunneling, comprising: acquiring tunnel-related information of the shield tunnel; exploring the geological strata surrounding the shield tunnel based on the tunnel-related information, and collecting geological information around the shield tunnel during the exploration process; analyzing and processing the tunnel-related information and geological information, and formulating a construction plan based on the analysis and processing results; setting the construction operating parameters of the slurry shield machine according to the construction plan and geological information; acquiring real-time response monitoring data of the geological strata during the slurry shield tunneling process, and adjusting the construction operating parameters of the slurry shield machine based on the response monitoring data. This invention improves the safety, quality, and efficiency of shield tunneling construction by accurately acquiring geological information, analyzing and processing geological data, formulating reasonable construction plans, setting construction operating parameters adapted to geological conditions, and monitoring the geological strata response and adjusting the construction operating parameters of the slurry shield machine during the construction process in real time.

[0038] Finally, it should be noted that those skilled in the art can obviously make various modifications and variations to this invention without departing from its spirit and scope. Therefore, if these modifications and variations fall within the scope of the claims and their equivalents, this invention also intends to include these modifications and variations.

[0039] The above description is merely one embodiment of the present invention, and should not be construed as limiting the scope of the invention. Any structural changes made based on the present invention, as long as they do not depart from the essence of the invention, should be considered as falling within the protection scope of the present invention and subject to its restrictions. Those skilled in the art will clearly understand that, for the sake of convenience and brevity, the specific working process and related descriptions of the platform described above can be referred to the corresponding processes in the foregoing platform embodiments, and will not be repeated here.

[0040] The term "comprising" or any other similar term is intended to cover non-exclusive inclusion, such that a process, platform, article, or device / platform that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to those processes, platforms, articles, or devices / platforms.

[0041] The technical solutions of the present invention have been described above with reference to the accompanying drawings and further embodiments. However, it will be readily understood by those skilled in the art that the scope of protection of the present invention is obviously not limited to these specific embodiments. Without departing from the principles of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after such changes or substitutions will all fall within the scope of protection of the present invention.

[0042] The above description is merely a preferred embodiment of the present invention and is not intended to limit the scope of protection of the present invention.

Claims

1. A long-distance air cushion straight-discharge slurry shield informationized construction method, characterized in that, include: Obtain tunnel-related information of the shield tunnel, explore the geological layers around the shield tunnel based on the tunnel-related information, and collect geological information around the shield tunnel during the exploration process; The process involves analyzing and processing the tunnel-related and geological information, and formulating a construction plan based on the analysis and processing results. Specifically, this includes extracting design information for the shield tunnel from the tunnel-related information, constructing a geometric model of the shield tunnel based on the design information, and adding model information to the geometric model according to the design information; constructing a geological model based on the geological information, and adding model information to the geological model according to the geological information; assembling the geometric model and the geological model to form a finite element model of the shield tunnel structure; performing finite element analysis on the finite element model using finite element analysis software, predicting the structural response data of the shield tunnel based on the analysis results, and formulating a construction plan based on the structural response data. The formulation of the construction plan based on the structural response data includes: calculating each data difference between the structural response data and preset data, determining the interval range of each data difference, setting a corresponding construction stability parameter requirement based on the interval range of the data difference; and combining all construction stability parameter requirements according to time nodes to form a construction plan. The construction parameters of the slurry shield tunneling machine are set according to the construction plan and geological information. Real-time monitoring data on the response of the geological layer during slurry shield tunneling is acquired, and the construction parameters of the slurry shield tunneling machine are adjusted based on the monitoring data. Specifically, the monitoring data is acquired, and a curve is generated to determine whether any monitoring data exceeding a preset rate of change exceeds a preset value. The monitoring data exceeding the preset rate of change are selected from the curve, and the difference between this difference and the preset value is calculated. An adjustment coefficient is selected based on the magnitude of the difference to adjust the construction parameters corresponding to the monitoring data exceeding the preset value, and the adjusted parameters are then updated.

2. The long-distance air cushion straight-discharge slurry shield informationized construction method according to claim 1, characterized in that, The process of obtaining tunnel-related information about the shield tunnel, exploring the geological strata surrounding the shield tunnel based on this information, and collecting geological information around the shield tunnel during the exploration process includes: Obtain tunnel-related information of the shield tunnel, and extract the location information of the shield tunnel from the tunnel-related information; Based on the location information, the geological strata around the shield tunnel are explored, and geological information around the shield tunnel is collected during the exploration process.

3. The long-distance air cushion straight-discharge slurry shield informationized construction method according to claim 1, characterized in that, The assembly of the geometric model and the geological model to form a finite element model of the shield tunnel structure includes: The geometric model is matched with the geological model based on the geological strata and the geometry of the shield tunnel. The matched geometric model and the geological model are then assembled to obtain the finite element model of the shield tunnel structure.

4. The long-distance air cushion straight-discharge slurry shield information construction method according to claim 3, characterized in that, The process of performing finite element analysis on the finite element model using finite element analysis software, predicting the structural response data of the shield tunnel based on the analysis results, and formulating a construction plan based on the structural response data includes: The finite element model is divided into multiple finite element meshes, and the material parameters and boundary conditions of the finite element meshes are set according to the design information and geological information. The material parameters and boundary conditions of each finite element mesh are combined using formulas, and the formulas are solved to obtain the structural response data of the shield tunnel. A construction plan is developed based on the structural response data.

5. The information-based construction method for long-distance air-cushion direct-discharge slurry shield tunneling according to claim 1, characterized in that, The process of setting the construction parameters of the slurry shield tunneling machine based on the construction plan and geological information includes: Analyze the construction stability parameter requirements in the construction plan and the geological conditions in the geological information; Based on the construction stability parameter requirements and geological conditions, the construction operating parameters of the slurry shield tunneling machine are set. The construction operating parameters include the advance speed, thrust, grouting pressure and cutterhead rotation speed of the slurry shield tunneling machine.

6. A long-distance air-cushion direct-discharge slurry shield tunneling information construction system corresponding to any one of the methods described in claims 1-5, characterized in that, include: The acquisition module is used to acquire tunnel-related information of the shield tunnel, explore the geological layers around the shield tunnel based on the tunnel-related information, and collect geological information around the shield tunnel during the exploration process; The planning module is used to analyze and process the tunnel-related and geological information, and to formulate a construction plan based on the analysis and processing results; The parameter setting module is used to set the construction operating parameters of the slurry shield tunneling machine according to the construction plan and geological information. The adjustment module is used to acquire real-time response monitoring data of the geological layer during the slurry shield tunneling process, and to adjust the construction parameters of the slurry shield tunneling machine based on the response monitoring data.

Citation Information

Patent Citations

  • Long-distance tunneling construction method for big-diameter slurry shield underwater shallow earthing