A multi-connected central air conditioning load flexible regulation system
By using a multi-split central air conditioning load flexible control system, which combines control gateways, sensors, and smart meters with data models and algorithms, precise control of air conditioning load is achieved. This solves the problem of pressure on the power grid during peak hours of air conditioning in commercial buildings, improves energy efficiency, and reduces costs.
Patent Information
- Application Number
- CN202410094123.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-23
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-01-23
AI Technical Summary
The central air conditioning load in commercial buildings puts pressure on the power grid during peak hours, and existing technologies are unable to achieve flexible control, resulting in energy waste and equipment overload.
A multi-split central air conditioning load flexible control system is adopted. Through control gateway devices, environmental sensors, smart meters and data models, combined with random forest regression algorithm, load prediction and control scheme generation are carried out, and the air conditioning operation status is dynamically adjusted to optimize energy consumption.
It enables precise control of air conditioning load, improves energy efficiency, reduces energy costs, and provides an adaptive green operation mode, supporting energy conservation and emission reduction in modern buildings.
Smart Images

Figure CN117989674B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of flexible load control technology for air conditioning, specifically a flexible load control system for multi-split central air conditioning. Background Technology
[0002] With the development of urbanization, central air conditioning has become a major electricity consumer in shopping malls and commercial buildings, further widening the peak-valley difference in electricity consumption and putting enormous pressure on the power grid. Against the backdrop of the country's strong advocacy for energy conservation, emission reduction and the development of new energy sources, virtual power plants, as a new type of energy management method, balance energy consumption by accurately responding to the market.
[0003] Central air conditioning load accounts for a significant proportion of the load in commercial buildings, especially during the peak summer season, putting immense pressure on the power grid. Therefore, a flexible control solution is needed to address this issue. Summary of the Invention
[0004] The purpose of this invention is to provide a flexible load control system for multi-split central air conditioning systems to solve the problems mentioned in the background art.
[0005] To achieve the above objectives, the present invention provides the following technical solution: a multi-split central air conditioning load flexible control system, which consists of a control gateway device, environmental sensors, smart meters, data models, model training, scheme generation, and scheme execution.
[0006] Preferably, the control gateway device is used to collect the operating status of the multi-split central air conditioning system and the execution of the control scheme. Through the control gateway device, the operating status of each indoor unit of the multi-split central air conditioning system is continuously monitored on a minute-by-minute basis, and these data are recorded in detail in the control gateway data collection table of the data model for subsequent analysis and decision-making.
[0007] Preferably, the environmental sensor is used to collect the operating environment parameters of the multi-split central air conditioning unit. The environmental sensor continuously collects various data of the environment where the multi-split central air conditioning unit is located, including temperature, humidity, and air quality, on a minute-by-minute basis. It writes these data into the external environment data collection table in the data model in real time, providing the system with comprehensive and real-time environmental information to optimize the operation and energy efficiency of the air conditioning unit.
[0008] Preferably, the smart meter is used to collect the overall operating load of the multi-split central air conditioning system. At the same time, the smart meter accurately monitors the total active power of the multi-split central air conditioning system in minutes. These data are recorded in real time in the meter data collection table in the data model, providing accurate data support for energy management and load control.
[0009] Preferably, the data model is designed to comprehensively record various environmental information and operating statuses of the multi-split central air conditioning system. Five data tables are used: a control gateway data table, an external environment data table, an electricity meter data table, a single indoor unit operating data table, and a multi-split system operating data table. These five tables collectively record the load values corresponding to the air conditioner under different environmental and operating conditions. Specifically, the single indoor unit operating data in the data model is generated by matching the control gateway data and the external environment data. The matching process is based on the device ID and the acquisition time, ensuring the accuracy and consistency of the data and providing strong support for subsequent data analysis and air conditioning operation optimization.
[0010] Preferably, the multi-split unit operation data in the data model is associated data generated by matching the single indoor unit operation data and the electricity meter data in claim 5. This matching process is based on the air conditioner ID and the collection time, ensuring the integrity and accuracy of the data.
[0011] Preferably, the model training is based on the random forest regression algorithm, combined with the multi-split air conditioning operation data in the data model, to train a regression model. This model uses the operating status and external environment as features, and the total active power as the target value. Through this training process, accurate prediction of the load of the multi-split central air conditioning system can be achieved, providing decision support for subsequent energy consumption management and optimization. At the same time, during the model training process, the multi-split air conditioning operation data in the data model is used as the basis, with particular attention paid to the operating status and external environment data as features, and the total active power is used as the target value for training. Through this training method, an accurate regression model can be constructed to predict the load of the multi-split central air conditioning system, thereby optimizing its operating efficiency and energy consumption.
[0012] Preferably, the scheme generation is based on the multi-split air conditioner operation data of the data model, which is used for retrieval and model reasoning to generate targeted control schemes. This process makes full use of the rich operation data and features in the data model, and provides managers with practical control suggestions through intelligent analysis and reasoning, helping them to optimize energy consumption management while ensuring comfort. When generating control schemes, multi-split air conditioner operation data is used for retrieval and model reasoning. The data includes multiple dimensions of data such as the air conditioner's operating status and external environmental information. Through model reasoning, control schemes for different scenarios and needs are generated based on this data.
[0013] Preferably, the proposed scheme involves sending the generated control scheme to a control gateway for execution. During execution, the control gateway continuously monitors the deviation between the power output and the target power, and dynamically adjusts the execution scheme based on the deviation. Simultaneously, during the execution of the scheme, the control gateway continuously monitors the operating status of the central air conditioning system and dynamically adjusts the operating status of the equipment according to actual needs to ensure that the load control achieves the best effect. This dynamic adjustment capability is the key to achieving efficient and accurate energy consumption control, effectively improving energy utilization efficiency and reducing energy costs.
[0014] The beneficial effects of this invention are as follows:
[0015] This invention addresses the need for managers to quickly and accurately formulate control strategies when facing load regulation demands. Utilizing a power prediction algorithm, the system can pre-assess the adjustable capacity of air conditioning resources, providing data support for subsequent control actions. Based on the predicted capacity and control objectives, the system intelligently matches the optimal control behavior. This matching process ensures the effectiveness and accuracy of control, avoiding unnecessary energy waste or equipment overload. Furthermore, the system possesses high adaptability, adjusting strategies in real time according to environmental changes and equipment status, ensuring efficient and stable control. Through this series of intelligent operations, managers can more precisely control loads, improving energy efficiency and contributing to a greener, more sustainable air conditioning operation mode. This intelligent management approach undoubtedly provides strong technical support for energy conservation and emission reduction in modern buildings. Attached Figure Description
[0016] Figure 1 This is a schematic diagram of the Internet of Things (IoT) topology of the present invention;
[0017] Figure 2 This is a schematic diagram of the basic data model of the present invention;
[0018] Figure 3 This is a schematic diagram of the training and inference structure of the machine learning model of the present invention;
[0019] Figure 4 This is a schematic diagram of the control process of the present invention. Detailed Implementation
[0020] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0021] like Figures 1 to 4As shown in the figure, this embodiment of the invention provides a flexible load control system for multi-split central air conditioning systems. The system consists of a control gateway device, environmental sensors, smart meters, data models, model training, scheme generation, and scheme execution.
[0022] The control gateway device is used to collect the operating status of the multi-split central air conditioning system and the execution of the control scheme. Through the control gateway device, the operating status of each indoor unit of the multi-split central air conditioning system is continuously monitored on a minute-by-minute basis, and these data are recorded in detail in the control gateway data collection table of the data model for subsequent analysis and decision-making.
[0023] like Figure 1 As shown, the construction of basic IoT data includes the following steps:
[0024] A1. Data Acquisition and Processing: Real-time data acquisition of operational, environmental, and energy consumption data from the multi-split central air conditioning system is achieved through the control gateway device D1, environmental sensor D2, and smart meter D3. Data format conversion and caching are then performed. The control gateway device D1 parses received air conditioning control messages into control commands, providing a basis for subsequent adjustments.
[0025] A2, Data Integration and Transmission: The load control unit D4 is responsible for collecting and integrating data from the control gateway device D1, environmental sensor D2, and smart meter D3, and reporting it to the IoT cloud platform. Simultaneously, it receives control commands from the IoT cloud platform and distributes them to the control gateway for execution.
[0026] A3, Data Storage and Processing: The IoT cloud platform, as the core brain, collects, cleans, parses, and stores the data reported by the load control unit. After processing, this data will be used for subsequent machine learning training and inference to realize the intelligent load control command delivery.
[0027] A4. Cloud-Edge Collaboration and Precise Control: The load control unit interacts with the IoT cloud platform, receiving control requests and sending control messages to the air conditioning control unit based on these requests. Simultaneously, it periodically collects relevant data and reports it to the IoT cloud platform. This process fully leverages the advantages of cloud-edge collaboration, achieving precise control of the air conditioning load and improving energy efficiency and system stability.
[0028] The load control unit (LCU) interacts efficiently with the IoT cloud platform, receiving and executing control requests from the platform. Simultaneously, it maintains close communication with the central air conditioning control unit (D1), precisely issuing control commands based on the control tasks. Furthermore, the LCU periodically collects multi-source data, including sensing data from the control gateway device (D1), environmental sensor (D2), and smart meter (D3), and reports this data to the IoT cloud platform in real time. Its powerful edge computing capabilities ensure real-time data processing and storage, facilitating precise control of the air conditioning load. Through cloud-edge collaboration, the LCU effectively improves energy efficiency while ensuring stable system operation.
[0029] The environmental sensor is used to collect the operating environment parameters of the multi-split central air conditioning unit. The environmental sensor continuously collects various data of the environment where the multi-split central air conditioning unit is located, including temperature, humidity and air quality, on a minute-by-minute basis. It writes this data into the external environment data collection table in the data model in real time, providing the system with comprehensive and real-time environmental information to optimize the operation and energy efficiency of the air conditioning.
[0030] The smart meter is used to collect the overall operating load of the multi-split central air conditioning system. At the same time, the smart meter accurately monitors the total active power of the multi-split central air conditioning system in minutes. These data are recorded in real time in the meter data collection table in the data model, providing accurate data support for energy management and load control.
[0031] The data model is designed to comprehensively record various environmental information and operating statuses of multi-split central air conditioning systems. It comprises five data tables: a control gateway data table, an external environment data table, an electricity meter data table, a single indoor unit operating data table, and a multi-split system operating data table. These five tables collectively record the load values corresponding to the air conditioner under different environmental and operating conditions. Specifically, the single indoor unit operating data in the data model is generated by matching control gateway data and external environment data. The matching process is based on device ID and acquisition time, ensuring data accuracy and consistency, and providing strong support for subsequent data analysis and air conditioning operation optimization.
[0032] Figure 2 As shown, the basic data model and basic data construction include the following steps:
[0033] B1. Data Acquisition and Storage: First, relevant data from the central air conditioning system is collected through the control gateway device D1, environmental sensor D2, and smart meter D3. The control gateway collects data T1 to record the equipment's operating status, the external environment collects data T2 to record information about the external environment, and the smart meter collects data T3 to record energy consumption indicators. This data is stored in three basic data tables.
[0034] B2, Data Association and Assembly: Based on the control gateway data T1 and the external environment data T2, the device ID and collection time are used as association fields to construct the single indoor unit operation data T4, which contains the minute-by-minute operation status and environmental data of a single indoor unit.
[0035] B3, Derivative Data Generation: Based on the single indoor unit operation data T4 and the electricity meter collection data T3, multi-split unit operation data T5 is constructed by using the air conditioner ID and collection time as associated fields. This data covers the minute-by-minute operation status, environmental data, and energy consumption indicators of the multi-split central air conditioning system.
[0036] B4, Data Analysis and Processing: Analyze and process the multi-split air conditioning system operation data T5 to extract key fields such as average wind speed, average target temperature, average indoor temperature, total number of units in operation, total operating ratio, outdoor temperature, outdoor humidity, wind speed, and total active power.
[0037] B5, Model Training and Prediction: Based on this processed data, the control model is trained, and a correlation model between environmental factors, operating status, and energy consumption is established through machine learning algorithms. This model can predict energy consumption under different environments and operating conditions, thus realizing the first step of the air conditioning control algorithm's capability—energy consumption prediction.
[0038] During the construction of the basic data model, operational data of the central air conditioning system was collected through the control gateway device D1, environmental sensor D2, and smart meter D3. This data was stored in three basic data tables. Subsequently, derived data, including single-unit operation data T4 and multi-split unit operation data T5, were constructed using a computing engine. These data tables record the environmental factors, operational status factors, and corresponding energy consumption data of the central air conditioning system, providing a foundation for training the control model. Through machine learning algorithms, a correlation model between environmental factors, operational status, and energy consumption was established, thus realizing the first step of the air conditioning control algorithm—energy consumption prediction. These data tables are the fundamental elements for training the entire control model and supporting control behavior, providing important basis for subsequent air conditioning control.
[0039] In the data model, the multi-unit operation data is generated by matching the single indoor unit operation data and the electricity meter data in claim 5. This matching process is based on the air conditioner ID and the collection time, which ensures the integrity and accuracy of the data.
[0040] The model training process involves using a random forest regression algorithm combined with multi-split air conditioning system operation data from the data model to train a regression model. This model uses operating status and external environment as features, and total active power as the target value. Through this training process, accurate prediction of the load of multi-split central air conditioning systems can be achieved, providing decision support for subsequent energy management and optimization. Furthermore, during model training, the multi-split air conditioning system operation data from the data model is used as the foundation, with particular attention paid to operating status and external environment data as features, and total active power as the target value. This training method enables the construction of an accurate regression model for predicting the load of multi-split central air conditioning systems, thereby optimizing their operating efficiency and energy consumption.
[0041] like Figure 3 As shown, the power prediction model is constructed by following these steps:
[0042] C1, Feature Extraction and Training Data Preparation:
[0043] Operating status data and external environment data are extracted from the single indoor unit operating data T4 and used as input features for the power prediction model. The total active power is used as the output result to construct the training dataset T5.
[0044] C2, Training and Optimization:
[0045] The training data T5 is modeled using the Random Forest Regression Algorithm A1. This algorithm can comprehensively consider the relationships between multiple features, thereby improving prediction accuracy. The specific algorithm principle is as follows:
[0046] As one implementation method, calculating the importance of sample features based on the sample set first involves determining the sample attributes: the relationship between samples and attributes is represented as X = <x1,x2,x3,......,x n > where X refers to a sample in the sample set, x1, x2, x3, ..., x n This refers to each attribute of a sample, assuming there are n attributes;
[0047] In this patent, the attributes include: average wind speed, average target temperature, average indoor temperature, total number of units turned on, total number of units turned on, outdoor temperature, outdoor humidity, and wind speed.
[0048] Each regression tree determines its optimal parameters by calculating the loss value during the iteration process using negative gradients; each regression tree updates the calculated difference and puts the difference into the next tree;
[0049] Multiple regression trees are accumulated to form a gradient boosting tree model;
[0050] The gradient boosting tree model to which this belongs is:
[0051]
[0052] Where J is the number of leaf nodes, and I represents whether the value of C belongs to the j-th leaf node.
[0053] Multi-unit operation data Input1: Construct multi-unit operation data as input data for model inference;
[0054] Load power prediction Output1: After inputting the Input1 data into the power prediction model M1, the returned load power value is Output1. This value is a floating-point type, retains 2 decimal places, and the unit is kilowatts.
[0055] The training data T5 is fed into the gradient boosting tree model for further training to optimize the model's predictive performance.
[0056] C3, Power Load Prediction Model Establishment:
[0057] After the above training and optimization, the final power prediction model M1 is generated.
[0058] The input to model M1 is the multi-unit operating data (feature Input1), and the output is the predicted load power value Output1.
[0059] The solution generation process involves retrieving and reasoning from multi-split air conditioning unit (MSU) operating data based on a data model to generate targeted control solutions. This process fully utilizes the rich operating data and features within the data model, providing managers with practical control suggestions through intelligent analysis and reasoning. This helps them optimize energy consumption management while ensuring comfort. When generating control solutions, MSU operating data is used for retrieval and model reasoning. The data includes multiple dimensions such as the air conditioning unit's operating status and external environmental information. Through model reasoning, control solutions are generated based on this data for different scenarios and needs.
[0060] The proposed solution involves sending the generated control plan to the control gateway for execution. During execution, the control gateway continuously monitors the deviation between the power output and the target power, and dynamically adjusts the execution plan based on the deviation. Simultaneously, during the execution of the plan, the control gateway continuously monitors the operating status of the central air conditioning system and dynamically adjusts the equipment's operating status according to actual needs to ensure that load control achieves the best results. This dynamic adjustment capability is key to achieving efficient and precise energy consumption control, effectively improving energy utilization efficiency and reducing energy costs.
[0061] like Figure 4 As shown, in Figure 2 and Figure 3 Under the given conditions, load regulation execution includes the following steps:
[0062] S1, Negative Control Command Processing and Target Value Setting:
[0063] When a user initiates a load control command, the system first determines whether there is a clear load control target value Target1.
[0064] If the target value is not clear, environmental data is collected, and the data with the minimum total active power is retrieved from the training data T5 as the current maximum adjustable load value.
[0065] Calculate 80% of the difference between the current total active power and the maximum adjustable load value as the optimal load target for Target1.
[0066] S2, Load Target Retrieval and Indoor Unit Status Acquisition:
[0067] Based on the current environment and the set Target1, retrieve the training data T5 and find the data with total active power within ±3% of Target1 as the reference range for regulation.
[0068] Send a command to the air conditioning control module to read the operating status of all indoor units of the central air conditioning system.
[0069] The indoor unit is used to determine its working status, and its operating status data is processed to form status data for the entire central air conditioning system.
[0070] S3, Similarity Calculation and Model Inference:
[0071] Based on the retrieved data, the Pearson similarity algorithm is used to calculate the similarity S1, S2, S3, ..., S2 between the current environment and the query data. n .
[0072] Sort by similarity score from highest to lowest.
[0073] The running status of the data with the highest similarity is extracted, and combined with the current environment as input data. This data is then submitted to the model for inference to obtain the output data.
[0074] S4, Determining the target's operating state:
[0075] Calculate P1, P2, P3, ..., P n The data that are closest to the Target1 value are sorted from largest to smallest.
[0076] Sort by the minimum difference in the total number of powered-on devices, then sort P1, P2, P3, ..., P n Sort the data and use the running state corresponding to the first data as the State1 running state.
[0077] S5, Optimized Operation Status:
[0078] The target temperature of each indoor unit is optimized and adjusted according to State1: in cooling mode, if the current temperature is lower than the temperature corresponding to State1, the temperature is adjusted; in heating mode, if the current temperature is higher than the temperature corresponding to State1, the temperature is adjusted.
[0079] Adjust the operating fan speed of each indoor unit to the level corresponding to State 1.
[0080] S6, Control command issuance and execution:
[0081] The above adjustments are then transmitted as control commands from the cloud platform to the negative control unit D4.
[0082] The control unit D4 transmits the control mode to the control gateway D1 for execution.
[0083] S7, Continuous Control and Deviation Monitoring:
[0084] During the execution process, the deviation between the total active power load value of the smart meter and the target value Target1 is continuously monitored.
[0085] If the deviation exceeds 1%, randomly select indoor units for temperature control, with each unit controlled no more than 3 times. Continuously collect data and monitor the deviation until the difference is less than 1%, at which point control is complete. This includes processing control commands and setting target values.
[0086] By automatically collecting air conditioning operating parameters and energy load data, combined with advanced calculation and analysis methods, this approach provides strong support for operators, helping them gain a deeper understanding of energy efficiency and implement targeted energy-saving and consumption-reducing measures. This implementation plan significantly improves the load regulation capability of multi-split central air conditioning systems, laying a solid foundation for reducing energy consumption and optimizing operational performance.
[0087] It should be noted that, in this document, relational terms such as "first" and "second" are used only to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus.
[0088] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their likenesses.
Claims
1. A flexible load control system for multi-split central air conditioning, characterized in that: The system consists of a control gateway device, environmental sensors, smart meters, a load control unit, a data model, model training, scheme generation, and scheme execution. The load control unit is used to collect and integrate the data collected by the control gateway device, environmental sensors, and smart meters and report it to the Internet of Things cloud platform. It also receives control commands from the Internet of Things cloud platform and distributes them to the control gateway device for regulation and execution. The implementation of the scheme includes: when a user initiates a load control command, determining whether there is a clear load control target value; if the target value is unclear, collecting environmental data, retrieving the data with the minimum total active power from the training data as the current maximum adjustable load value, and calculating 80% of the difference between the current total active power and the maximum adjustable load value as the optimal load target; based on the current environment and the set target value, retrieving data from the training data where the total active power is within ±3% of the target value as a reference range for control, and reading the operating status of all indoor units of the central air conditioning system; based on the retrieved data, using the Pearson similarity algorithm to calculate the similarity between the current environment and the queried data, sorting them according to the similarity value from largest to smallest, and extracting the highest similarity value. The operating status of the data, combined with the current environmental conditions, is used as input data and submitted to the power prediction model for inference. The data closest to the target value is calculated and sorted by the difference in the total number of units in operation. The operating status corresponding to the first data is taken as the target operating status. The target temperature of each indoor unit is optimized and adjusted according to the target operating status, and the operating speed of each indoor unit is uniformly adjusted to the level corresponding to the target operating status. The adjustment is executed by issuing control commands. During the execution, the deviation between the total active power load value of the smart meter and the target value is continuously monitored. If the deviation exceeds 1%, the indoor unit is randomly selected for temperature control. The number of times each indoor unit is controlled does not exceed 3. Data is continuously collected and the deviation is monitored until the difference is less than 1% and the control is completed.
2. The multi-split central air conditioning load flexible control system according to claim 1, characterized in that: The control gateway device is used to collect the operating status of the multi-split central air conditioning system and the execution of the control scheme. Through the control gateway device, the operating status of each indoor unit of the multi-split central air conditioning system is continuously monitored on a minute-by-minute basis, and this data is recorded in detail in the control gateway data collection table of the data model for subsequent analysis and decision-making.
3. The multi-split central air conditioning load flexible control system according to claim 1, characterized in that: The environmental sensor is used to collect the operating environment parameters of the multi-split central air conditioning unit. The environmental sensor continuously collects various data of the environment where the multi-split central air conditioning unit is located, including temperature, humidity and air quality, on a minute-by-minute basis. It writes this data into the external environment data collection table in the data model in real time, providing the system with comprehensive and real-time environmental information to optimize the operation and energy efficiency of the air conditioning.
4. The multi-split central air conditioning load flexible control system according to claim 1, characterized in that: The smart meter is used to collect the overall operating load of the multi-split central air conditioning system. At the same time, the smart meter accurately monitors the total active power of the multi-split central air conditioning system in minutes. This data is recorded in real time in the meter data collection table in the data model, providing accurate data support for energy management and load control.
5. A multi-split central air conditioning load flexible control system according to claim 1, characterized in that: The data model is designed to comprehensively record various environmental information and operating statuses of multi-split central air conditioning systems. It consists of five data tables: control gateway data table, external environment data table, electricity meter data table, single indoor unit operation data table, and multi-split system operation data table. These five tables collectively record the load values of the multi-split air conditioning system under different environmental and operating conditions. In particular, the single indoor unit operation data in the data model is generated by matching the control gateway data and the external environment data. The matching process is based on the device ID and the acquisition time.
6. A multi-split central air conditioning load flexible control system according to claim 5, characterized in that: The multi-split unit operation data in the data model is generated by matching the single indoor unit operation data and the electricity meter data in claim 5. This matching process is based on the air conditioner ID and the collection time, ensuring the integrity and accuracy of the data.
7. The multi-split central air conditioning load flexible control system according to claim 1, characterized in that: The model training is based on the random forest regression algorithm, combined with the multi-split air conditioning operation data in the data model, to train a regression model. This model uses the operating status and external environment as features, and the total active power as the target value. Through this training process, accurate prediction of the load of multi-split central air conditioning can be achieved, providing decision support for subsequent energy consumption management and optimization. At the same time, in the model training process, the multi-split air conditioning operation data in the data model is used as the basis, with particular attention paid to the operating status and external environment data as features, and the total active power is used as the target value for training. Through this training method, an accurate regression model is constructed.
8. A multi-split central air conditioning load flexible control system according to claim 1, characterized in that: The proposed control scheme is generated based on the multi-split air conditioning system's operating data, which is retrieved and used for model reasoning to create targeted control schemes. Through intelligent analysis and reasoning, it provides managers with practical control suggestions, helping them optimize energy consumption while ensuring comfort. When generating control schemes, multi-split air conditioning system operating data is used for retrieval and model reasoning. The data includes multiple dimensions such as the air conditioning's operating status and external environmental information. Through model reasoning, the optimal control scheme for different scenarios and needs is generated.
9. A multi-split central air conditioning load flexible control system according to claim 1, characterized in that: The proposed scheme involves sending the generated control plan to a control gateway for execution. During execution, the control gateway continuously monitors the deviation between the power output and the target power, and dynamically adjusts the execution plan based on the deviation. Simultaneously, during the execution of the scheme, the control gateway continuously monitors the operating status of the central air conditioning system and dynamically adjusts the equipment's operating status according to actual needs to ensure that load control achieves the best effect. This dynamic adjustment capability is the key to achieving efficient and precise energy consumption control, effectively improving energy utilization efficiency and reducing energy costs.
Citation Information
Patent Citations
Data center central air conditioner chilled water parameter setting method based on AI algorithm
CN114722574A
Virtual power plant dispatching and control system and method based on central air conditioner
CN117249537A