A power grid safety and stability control system standardized simulation test system and method

By designing a standardized simulation test system for power grid safety and stability control systems, and adopting a two- or multi-layer architecture and a stability control communication test device, the system solves the problems of interoperability of stability control devices and verification of maximum access capability, and realizes an efficient and standardized test method that is adaptable to various power grid application scenarios.

CN118011861BActive Publication Date: 2026-11-20STATE GRID ELECTRIC POWER RES INST +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410097044.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-23
Publication Date
2026-11-20
Estimated Expiration
2044-01-23

AI Technical Summary

Technical Problem

Existing technologies cannot effectively verify the interoperability and maximum access capability of stabilization devices from different manufacturers, lack third-party impartiality, and traditional testing methods cannot meet standardized design requirements.

Method used

Design a standardized simulation test system for power grid safety and stability control system. Adopt a two-layer or multi-layer architecture. By simulating power grid operation scenarios and abnormal events, and using a stability control communication test device to simulate execution station information, conduct closed-loop simulation tests to verify the interoperability and maximum access capability of the stability control system.

Benefits of technology

It fully verifies the standardization and reliability of the stability control device, reduces the number of test samples and time, and has broad applicability, typicality and efficiency. It meets the requirements of standardized design and is suitable for multi-layer/double-layer architecture and sending/receiving end power grid application scenarios.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118011861B_ABST
    Figure CN118011861B_ABST
Patent Text Reader

Abstract

The application discloses a kind of power grid safety and stability control system standardization simulation test system and method, the system includes sending end power grid stability control system and receiving end power grid stability control system, sending end power grid stability control system and sending end power grid stability control system are double-layer architecture or multilayer architecture, by simulating fault information, closed-loop simulation test is carried out to sending end power grid stability control system and receiving end power grid stability control system;The application can adapt to the stability control system structure of two kinds of multilayer / double layer, compatible sending / receiving end power grid two application scenarios, cover all types of stability control device, and consider substation cascade form, first propose the standardization test method of interoperation ability and maximum communication channel access ability, significantly reduce the workload of test sample production and build test environment, optimize test time, with universality, typicality and compactness features.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of simulation testing of relay protection and safety automatic devices, especially the standardized simulation testing system and method for power grid safety and stability control systems. Background Technology

[0002] A safety and stability control system (stability control system) is a system composed of safety and stability control devices from two or more power plants connected by communication equipment to achieve stable control of a regional or larger power system. The purpose of standardized design for the stability control system is to implement a hierarchical and regional design for power grid stability control functions. The stability control device responsible for regional power grid control decisions and issuing action commands is the master station. It makes decisions based on offline stability analysis and the real-time operating status of the power grid, and issues the strategy functions under the current fault state to the substations. The substations are responsible for allocating the control measures from the master station and issuing the allocated control commands to the lower-level execution stations, which then implement the stability control measures. Execution stations are classified according to the controlled object: DC execution stations, generator tripping execution stations, load shedding execution stations, and new energy execution stations.

[0003] Traditional power stability control devices are treated merely as automatic safety devices, undergoing routine type testing and environmental reliability testing. System-level testing, particularly simulating multiple operating scenarios, is not conducted to fully verify their stability control functions. Real-time digital simulation, utilizing heterogeneous parallel computer systems, can achieve real-time simulation of large-scale power systems. Through protocol conversion, it outputs the simulated system's operating information to the connected device under test in real time, enabling mixed-signal simulation testing. This method is widely used in the standardized testing of relay protection products, but for power stability control systems, it is only used in engineering verification and factory acceptance testing.

[0004] The design specifications clearly define the maximum access capability of the stability control device. Considering that a single master station can connect to a maximum of 16 substations, and a single substation can connect to a maximum of 34 execution stations of the same type, completing this test would require a maximum of 1 × 16 × 34 = 544 sets of devices. Furthermore, considering that each stability control device distinguishes between master (inter-station communication, decision analysis, and command issuance) and slave (information collection) devices, conducting this test with actual physical devices is virtually impossible. Patent (CN115840436A) discloses a simplified simulation method based on a channel self-loop test function to verify the maximum communication access capability of the stability control system. However, the channel self-loop test function proposed in this patent is not part of the design standard specifications and lacks the conditions for widespread application. If the specific design of a device from one manufacturer is used to verify the maximum access capability of devices from other manufacturers, the test results will lack third-party impartiality and persuasiveness. Currently, there is no method proposed to conduct interoperability and maximum access capability tests on stability control devices from different manufacturers to verify the standardization level of the devices. Summary of the Invention

[0005] Purpose of the invention: The purpose of this invention is to provide a standardized simulation test system and method that can fully verify the standardization and reliability of a stability control device.

[0006] Technical solution: The standardized simulation and testing system for power grid safety and stability control system described in this invention.

[0007] It includes a sending-end power grid stability control system and a receiving-end power grid stability control system, wherein the sending-end power grid stability control system and the receiving-end power grid stability control system are in a two-layer architecture or a multi-layer architecture; the two-layer architecture includes a master station stability control device and all types of execution station stability control devices, and the multi-layer architecture includes a master station stability control device, a substation stability control device and all types of execution station stability control devices;

[0008] In the sending-end power grid stability control system and the receiving-end power grid stability control system, multiple execution station stability control devices of the same type are replaced by one execution station stability control device of the same type.

[0009] Closed-loop simulation tests were conducted on the power grid stability control system at both the sending and receiving ends by simulating different power grid operating scenarios and combinations of abnormal events.

[0010] Furthermore, when testing the information transmission capability of cascaded substations in a multi-layer architecture, the tested substation stability control device is connected to a cascaded substation stability control device, a DC execution station stability control device, and a first stability control communication test device. The first stability control communication test device is used to simulate information transmission, including information transmitted by the new energy execution station stability control device and / or the generator tripping execution station stability control device and / or the load shedding execution station stability control device. The cascaded substation stability control device is connected to a second stability control communication test device, which is used to simulate information transmission from the second-level cascaded substations. The tested substation stability control device is connected to the master station stability control device. The master station stability control device issues commands and receives information transmitted by the tested substation stability control device. The information transmission capability of the tested substation stability control device is tested by determining whether the information transmitted by the master station stability control device is consistent with the information simulated by the first stability control communication test device.

[0011] Furthermore, when testing the maximum access capacity of the master station, the test master station stability control device is connected to the third stability control communication test device. In the multi-layer architecture, the third stability control communication test device is used to simulate the information sent by the substation stability control device. In the two-layer architecture, the third stability control communication test device is used to simulate the information sent by the execution station stability control device.

[0012] The master station stability control device sends instructions to the substation stability control device or the execution station stability control device. By checking whether the third stability control communication test device receives the command message, the maximum access capability of the master station under test when accessing the maximum number of substation stability control devices or execution station stability control devices is tested.

[0013] Furthermore, when testing the maximum access capability of a substation, the tested substation stability control device is connected to the master station stability control device, and the tested substation stability control device is connected to a fourth stability control communication test device. The fourth stability control communication test device is used to simulate the information sent by the execution station stability control device. The master station stability control device sends instructions to the tested substation stability control device and then forwards them to the third stability control communication test device. By checking whether the third stability control communication test device receives the command message, the maximum access capability of the tested substation when connecting to the maximum number of execution station stability control devices is tested.

[0014] Furthermore, when conducting interoperability tests on the stability control systems of the first manufacturer and the second manufacturer, both systems have a multi-layered architecture. The first interoperability test system is composed of the first manufacturer's master station stability control device, the second manufacturer's substation stability control device, and the first manufacturer's execution station stability control device. The second interoperability test system is composed of the second manufacturer's master station stability control device, the first manufacturer's substation stability control device, and the second manufacturer's execution station stability control device. Stability control function tests are performed on the first manufacturer's stability control system, the second manufacturer's stability control system, the first interoperability test system, and the second interoperability test system. Interoperability tests are then conducted on the stability control systems of the first manufacturer and the second manufacturer to verify the consistency of the test results.

[0015] Furthermore, when conducting interoperability tests on the stability control systems of the first manufacturer and the second manufacturer, both systems employ a two-layer architecture. A third interoperability test system is formed by combining the master station stability control device of the first manufacturer and the execution station stability control device of the second manufacturer. A fourth interoperability test system is formed by combining the master station stability control device of the second manufacturer and the execution station stability control device of the first manufacturer. Stability control function tests are performed on the stability control systems of the first manufacturer, the second manufacturer, the third interoperability test system, and the fourth interoperability test system. Interoperability tests are then conducted on the stability control systems of the first manufacturer and the second manufacturer to verify the consistency of the test results.

[0016] The standardized hybrid simulation test system for power grid safety and stability control system of the present invention includes a control system under test and a primary power grid model system. The software simulation test model of the control system is built according to the standardized simulation test system for power grid safety and stability control system. The primary power grid model system is connected to the RTDS simulation system via Ethernet and sends simulated operating condition data to the control system. The control system identifies operating faults based on the operating condition data, determines control measures and control quantities, generates control commands and transmits them to the RTDS simulation system to achieve closed-loop experimental verification.

[0017] The standardized simulation test method for power grid safety and stability control system of the present invention includes the following steps:

[0018] Establish a power grid stability control system at the sending end and a power grid stability control system at the receiving end. Conduct closed-loop simulation tests on the power grid stability control system at the sending end and the power grid at the receiving end by simulating different power grid operating scenarios and combinations of abnormal events.

[0019] The sending-end power grid stability control system and the sending-end power grid stability control system are two-layer architectures or multi-layer architectures; the two-layer architecture includes a master station stability control device and all types of execution station stability control devices, and the multi-layer architecture includes a master station stability control device, a substation stability control device and all types of execution station stability control devices;

[0020] In the sending-end power grid stability control system and the receiving-end power grid stability control system, multiple execution station stability control devices of the same type are replaced by one execution station stability control device of the same type.

[0021] The electronic device of the present invention includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the computer program is loaded onto the processor, it implements the standardized simulation test method for the power grid safety and stability control system.

[0022] The computer-readable storage medium of the present invention stores a computer program, which, when executed by a processor, implements the standardized simulation test method for the power grid safety and stability control system.

[0023] Beneficial effects: Compared with the prior art, the advantages of the present invention are: (1) The simulation test system of the present invention can adapt to the two types of stability control system structures, be compatible with the two application scenarios of sending and receiving end power grids, and have the characteristics of wide applicability, typicality and compactness, and meet the requirements of sufficiency and efficiency of the test; by flexibly modifying the model parameters and setting different types of fault simulation power grid operation scenarios, the stability control strategy function can be fully verified; (2) In the simulation test system of the present invention, the stability control system test samples include all seven types of standardized stability control devices, including multi-layer master station, double-layer master station, substation, generator switching execution station, new energy execution station, DC execution station and load switching execution station, strictly implement the relevant standard specifications, meet the standardized test requirements, and have typicality and rationality; (3) For the two test items with a large number of test cases, namely the maximum access capability and interoperability capability test of the device, there are currently no effective and reliable test methods for the test items. The present invention designs test methods that meet the standardized design requirements and constructs an optimized test system design, which greatly reduces the number of test samples and test time. Attached Figure Description

[0024] Figure 1 Power system diagrams for verification of existing stability control system engineering;

[0025] Figure 2This is a diagram of a standardized simulation test system according to an embodiment of the present invention;

[0026] Figure 3 This is a diagram of a standardized mixed-signal simulation test system according to an embodiment of the present invention;

[0027] Figure 4 This is a schematic diagram of the experimental environment for testing the maximum access capability in an embodiment of the present invention;

[0028] Figure 5 This is a schematic diagram of the experimental environment for testing the interoperability of a multi-layer architecture system according to an embodiment of the present invention.

[0029] Figure 6 This is a schematic diagram of the experimental environment for testing the interoperability of a two-layer architecture system according to an embodiment of the present invention. Detailed Implementation

[0030] The technical solution of the present invention will be further described below with reference to the accompanying drawings.

[0031] like Figure 1 The diagram shown is a schematic of the sending-end network of the Yanhuai DC transmission system, which is the prototype system of the standardized simulation test scheme in this embodiment. Figure 2 As shown, the standardized simulation test system of the present invention includes the following improvements: (1) The prototype system only involves the sending-end grid of the DC transmission system. The present invention takes into account both the sending-end grid and the receiving-end grid of the DC transmission system to ensure that the stable control system that passes the test can be compatible with both sending-end and receiving-end grid application scenarios; (2) The number of stable control devices of the same type is reduced. The prototype system includes multiple stable control devices installed at the power plant's generator-switching execution station, which focuses on engineering verification purposes. The present invention simplifies the same type of stable control device to one plant and adds load shedding execution station and new energy execution station, which are installed at transformer #3 and transformer #4 respectively. While reducing the system scale and the number of test samples, the test system ensures that it covers all types of stable control devices; (3) In this embodiment, the sending-end grid stable control system has a multi-layer architecture of master station-substation-execution station. The substation can connect several cascaded substations. Substation, receiving-end power grid stability control system is a master station-execution station dual-layer architecture, which can ensure that one test system covers two architectures (multi-layer / dual-layer architecture) and two power grids (sending-end / receiving-end power grid). At the same time, the power grid structure covers both AC and DC transmission forms, including mainstream voltage levels such as 500kV~220kV~110kV, which greatly simplifies the test system construction process and reduces the test cycle. In actual testing, both the sending-end power grid and the receiving-end power grid can adopt a dual-layer or multi-layer architecture. (4) The stability control system test samples include all types of standardized stability control devices such as multi-layer master station, dual-layer master station, substation (conventional sampling digital trip, conventional sampling and trip 2 types), generator trip execution station, new energy execution station, DC execution station, load trip execution station (conventional sampling and trip, digital sampling digital trip, conventional sampling digital trip 3 types).

[0032] Based on the design of the primary power grid model system and combined with existing hardware-in-the-loop simulation methods, a standardized hybrid numerical simulation test system was built, such as... Figure 3 As shown, the host computer on the control console establishes a primary power grid simulation model, connects to the RTDS simulation system via Ethernet, simulates various operating conditions of the primary power grid, and sends the operating data (including electrical quantities and switching quantities) to the device under test (stability control system) through communication protocol conversion cards (GTAO, GTDO), electrical safety isolation devices (switching quantity conversion devices), and power amplifiers (converting analog small signals into large signals adapted to the acquisition unit of the device under test). At the same time, the decision unit of the stability control equipment under test receives the operating data sent by the acquisition unit, identifies the operating conditions and faults, searches the control strategy table, determines the control measures and control quantities, and transmits the control command communication protocol conversion card (GTDI card) to the simulation system to realize closed-loop experimental verification.

[0033] The simulation test system uses a general communication protocol format to simulate and output DC system operation information and fault status information to the DC actuator under test. The DC actuator judges that a fault has occurred in the DC transmission system based on the information output by the simulation system and sends it to the main control station via the upper-level substation device. The main station retrieves the strategy table, determines the control measures and control quantities (shutdown of generators in the sending-end grid and load shedding in the receiving-end grid), and sends the control command to the corresponding actuator via the substation. The actuator sends the control signal to the simulation test system to simulate the process of disconnecting generators / loads, thus realizing closed-loop simulation test.

[0034] Similarly, the simulation system simulates line / transformer faults (or fault-free trips) that cause frequency or thermal stability problems in the power grid. The substation stability control device collects relevant line and transformer operating information to determine whether power grid components are tripping or overloaded, and sends the judgment information to the master station. The master station retrieves the strategy table, determines the control measures and control quantities, and sends the control commands to the corresponding execution stations via the substations. The execution stations send control signals to the simulation test system to simulate processes such as shedding generators / loads / DC power modulation, thereby achieving closed-loop simulation testing.

[0035] In the two-tier architecture, grid operation information acquisition and fault state identification are completed at the master station's stability control device. After making a decision, the master station directly issues control commands to the relevant execution stations. The simulation system simulates abnormal phenomena such as power reversal, grid frequency deviation, and grid dynamic / static stability failure leading to oscillations, testing whether the stability control system can operate correctly and whether the anti-malfunction measures are effective.

[0036] When conducting maximum access capability tests for stability control devices, the main station stability control device can connect to a maximum of 16 subordinate stations. In a two-layer architecture, it can connect to a maximum of 16 execution station stability control devices, and in a multi-layer architecture, it can connect to a maximum of 16 substation stability control devices. For substation stability control devices, according to standardized design specifications, the maximum scale of substation access includes 1 DC execution station, 1 cascaded substation, 34 load shedding execution stations, 34 new energy execution stations, and 16 generator shedding execution stations. To test the maximum communication processing capability of a substation, a large number of execution station devices are required, making it difficult to build a test environment using actual devices. In the substation communication processing capability test, the main purpose is to test the substation's ability to process communication data and the correctness of logical judgments when a large number of execution stations are connected; it is not necessary to test the execution station functions. Therefore, a stability control communication test device can be used to simulate the information transmission function of the execution station devices, reducing the need for a large number of actual devices. The stability control communication test device sends execution station data to the substation according to the communication protocol specified in the design specifications and receives control commands issued by the substation.

[0037] The stability control communication test device is a general-purpose message simulation device that has passed the test of a third-party testing organization. It strictly follows the communication protocols of different plant stability control devices required by the design standards and can correctly publish / receive messages from the other side's stability control device. A single communication test device can simultaneously support the message publishing / receiving functions of up to 8 stability control devices. When conducting maximum access capacity tests, no modification or special design is required for the functions of the stability control device under test. It is suitable for third-party testing and has the potential for widespread application.

[0038] like Figure 4 The diagram shows a schematic of the experimental environment for conducting maximum access capacity testing.

[0039] (1.1) As Figure 4 As shown in Figure (a), during the test of the substation cascade information transmission capability, the tested substation control device is connected to one cascaded substation control device and one DC execution station control device. At the same time, it is connected to the control communication test device, which simulates the transmission of 34 execution station information (simulating new energy or load shedding execution station or generator shedding execution station) and the control communication test device, which simulates the transmission of 30 substation information (accessed via cascaded substations). The main station can receive and check the information transmitted by the substations and cascaded substations, as well as the simulated execution station information.

[0040] During the test, by viewing the parsed communication messages on the main station's stability control device, the system verifies whether the grid component information, generator set (or load line, new energy collection line) switchability information, and DC system operation information collected by the main station and transmitted through the cascaded substation stability control devices are consistent with the information collected by the lower-level plant station itself or simulated through the stability control communication test device. If they are consistent, the stability control system is deemed to meet the substation cascade information transmission capability required by the design specifications.

[0041] (1.2) such as Figure 4 As shown in (b), during the test of the maximum access capacity of the master station, the stability control communication test device simulates 16 substations sending component information (each substation sends 12 lines and 4 main transformers) and simulated unit switchability information to the master station stability control device. The master station can correctly parse the information sent by the simulated substations. The master station sends a full unit switchover command to the substations according to the test setpoints, checks whether the simulated substations have received the command message, and examines the communication messages collected by the master station from the simulated transmission of the third stability control communication test device. The parsed power grid operation information and switchability information should be completely consistent with the information transmitted by all communication test devices. The test system diagram for testing the maximum access capacity of the master station of the two-layer architecture stability control system is executed with reference to the multi-layer architecture substation test system diagram.

[0042] (1.3) such as Figure 4 As shown in (c), during the test of the maximum access capacity of the substation, the stability control communication test device simulates 36 execution stations sending component information (simulating load shedding execution stations). The substation stability control device can correctly parse the information sent by the simulated execution stations and forward it to the master station. The master station sends a full load shedding command for each round to the substation according to the test setpoint and checks whether the simulated execution station receives the master station command message forwarded by the substation.

[0043] Check the communication messages collected by the main station and forwarded by the substations from the simulated communication test device. The parsed switchable information should be completely consistent with the information collected by the 34 execution station control devices in the simulation. The main station control device sends control commands to the substations. By checking whether the control communication test device receives the command messages, the test substation's maximum communication access capability under the condition of accessing 34 execution stations meets the design requirements.

[0044] like Figure 5 and Figure 6 The diagram illustrates the experimental environment for interoperability testing, using three manufacturers' (Manufacturer A, Manufacturer B, and Manufacturer C) stability control systems as an example. Based on the multi-layered architecture stability control system's substation interchange and the two-layered architecture stability control system's master station interchange channels, it can be ensured that both ends of any communication channel are stability control devices from different manufacturers, enabling interoperability testing of all models of stability control devices from multiple manufacturers.

[0045] (2.1) As Figure 5 As shown, in the multi-layer architecture system, the substations of Manufacturer A and Manufacturer B are interchanged. That is, the substation of Manufacturer A, together with the main station of Manufacturer B and various types of execution stations, forms one set of stability control system, while the substation of Manufacturer B, together with the main station of Manufacturer A and various types of execution stations, forms another set of stability control system. The two systems operate in parallel.

[0046] The experimental environment for conducting interoperability tests between manufacturer C and manufacturers A / B's multi-layer stability control systems is the same as described above. Specifically, the C set of substations is interconnected with the A (or B) set of master stations and various types of execution stations to form one system. The C set of master stations, various types of execution stations, and the A (or B) set of substations form another stability control system, and the two systems operate in parallel.

[0047] (2.2) As Figure 6 As shown, in the two-tier architecture system, the main station of manufacturer A is interconnected with various types of execution stations of manufacturer B to form one stability control system, and the main station of manufacturer B is interconnected with various types of execution stations of manufacturer A to form another stability control system. The two systems operate in parallel.

[0048] The experimental environment for conducting the interoperability test of the dual-layer stability control system of manufacturer C and manufacturers A / B is the same as the above. The C set of master stations and the various types of actuators of A (or B) are interconnected to form one stability control system. The various types of actuators of C and the A (or B) set of master stations form another stability control system. The two systems operate in parallel.

[0049] Two parallel-operation stability control systems were built according to (1.1)-(1.2) above. Relevant stability control function tests were carried out. The test results were compared with the stability control system built by all stability control devices provided by the same manufacturer. If the action results were consistent, the stability control devices of manufacturers A, B and C participating in the test were deemed to meet the interoperability test requirements.

[0050] The standardized simulation test method for power grid safety and stability control system of the present invention includes the following steps:

[0051] Establish a power grid stability control system at the sending end and a power grid stability control system at the receiving end, and conduct stability control function tests; the power grid stability control system at the sending end has a two-layer architecture and the power grid stability control system at the receiving end has a multi-layer architecture, or the power grid stability control system at the sending end has a multi-layer architecture and the power grid stability control system at the receiving end has a two-layer architecture.

[0052] The two-layer architecture includes a master station stability control device and an execution station stability control device, and the multi-layer architecture includes a master station stability control device, a substation stability control device, and an execution station stability control device.

[0053] In the sending-end power grid stability control system and the receiving-end power grid stability control system, multiple execution station stability control devices of the same type are simplified into one execution station stability control device;

[0054] A load shedding execution station and a new energy execution station are respectively set up at any two substations in the multi-layer architecture.

[0055] The electronic device of the present invention includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the computer program is loaded onto the processor, it implements the standardized simulation test method for the power grid safety and stability control system.

[0056] The computer-readable storage medium of the present invention stores a computer program, which, when executed by a processor, implements the standardized simulation test method for the power grid safety and stability control system.

[0057] The computer-readable storage medium may include RAM, ROM, EEPROM, CD-ROM or other optical disc storage devices, magnetic disk storage devices or other magnetic storage devices, flash memory, or any other media that can be used to store desired program code in the form of instructions or data structures and is accessible by a computer.

[0058] The processor is used to execute a computer program stored in memory to implement the various steps in the methods described in the above embodiments.

Claims

1. A standardized simulation and testing system for a power grid safety and stability control system, characterized in that, It includes a sending-end power grid stability control system and a receiving-end power grid stability control system, which are either two-layer or multi-layer architectures. The two-layer architecture includes a master station stability control device and all types of execution station stability control devices, while the multi-layer architecture includes a master station stability control device, a substation stability control device, and all types of execution station stability control devices. In the sending-end power grid stability control system and the receiving-end power grid stability control system, multiple execution station stability control devices of the same type are replaced by one execution station stability control device of the same type. Closed-loop simulation tests were conducted on the sending-end power grid stability control system and the receiving-end power grid stability control system by simulating different power grid operation scenarios and combinations of abnormal events. When conducting interoperability tests on the stability control systems of the first manufacturer and the second manufacturer, both of their stability control systems are multi-layered architectures. The first interoperability test system is composed of the first manufacturer's main station stability control device, the second manufacturer's substation stability control device, and the first manufacturer's execution station stability control device. The second interoperability test system is composed of the second manufacturer's main station stability control device, the first manufacturer's substation stability control device, and the second manufacturer's execution station stability control device. The stability control system of the first manufacturer, the stability control system of the second manufacturer, the first interoperability test system and the second interoperability test system are tested for stability control function. By verifying whether the test results are consistent, the stability control systems of the first manufacturer and the second manufacturer are tested for interoperability. Alternatively, when conducting interoperability tests on the stability control systems of the first manufacturer and the second manufacturer, both the stability control systems of the first manufacturer and the second manufacturer are two-layer architectures; the first manufacturer's master station stability control device and the second manufacturer's execution station stability control device are combined into a third interoperability test system, and the second manufacturer's master station stability control device and the first manufacturer's execution station stability control device are combined into a fourth interoperability test system. The stability control system of the first manufacturer, the stability control system of the second manufacturer, the third interoperability test system, and the fourth interoperability test system were tested for stability control function. By verifying whether the test results were consistent, the stability control systems of the first manufacturer and the second manufacturer were tested for interoperability.

2. The standardized simulation test system for power grid safety and stability control system according to claim 1, characterized in that, When testing the substation cascaded information transmission capability in a multi-layer architecture, the tested substation stability control device is connected to the cascaded substation stability control device, the DC execution station stability control device, and the first stability control communication test device; the first stability control communication test device is used to simulate the transmission of information, including the transmission of information from the new energy execution station stability control device and / or the generator tripping execution station stability control device and / or the load shedding execution station stability control device. The cascaded substation stability control device is connected to the second stability control communication test device, which is used to simulate the information sent up by the second-level cascaded substation. The tested substation stabilization device is connected to the master station stabilization device. The master station stabilization device issues commands and receives information transmitted from the tested substation stabilization device. The ability of the tested substation stabilization device to transmit information is tested by determining whether the information transmitted from the tested substation stabilization device received by the master station stabilization device is consistent with the information transmitted simulated by the first stabilization communication test device.

3. The standardized simulation and testing system for power grid safety and stability control system according to claim 1, characterized in that, When testing the maximum access capacity of the master station, the test master station stability control device is connected to the third stability control communication test device. In the multi-layer architecture, the third stability control communication test device is used to simulate the information sent by the substation stability control device. In the two-layer architecture, the third stability control communication test device is used to simulate the information sent by the execution station stability control device. The master station stability control device sends instructions to the substation stability control device or the execution station stability control device. By checking whether the third stability control communication test device receives the command message, the maximum access capability of the master station under test when accessing the maximum number of substation stability control devices or execution station stability control devices is tested.

4. The standardized simulation test system for power grid safety and stability control system according to claim 1, characterized in that, When testing the maximum access capacity of the substation, the tested substation stability control device is connected to the main station stability control device, and the tested substation stability control device is connected to the fourth stability control communication test device. The fourth stability control communication test device is used to simulate the information sent by the execution station stability control device. The master station stability control device sends instructions to the tested substation stability control device and then forwards them to the third stability control communication test device. By checking whether the third stability control communication test device receives the command message, the maximum access capability of the tested substation when accessing the maximum number of execution station stability control devices is tested.

5. A standardized hybrid numerical simulation test system for power grid safety and stability control systems, characterized in that, The system includes the stability control system under test and the primary power grid model system. The software simulation test model of the stability control system is constructed according to any one of claims 1 to 4, which is a standardized simulation test setup for the power grid safety and stability control system. The primary power grid model system is connected to the RTDS simulation system via Ethernet, and sends the simulated operating condition data to the stability control system. The stability control system identifies operating faults based on the operating condition data, determines control measures and control quantities, generates control commands, and transmits them to the RTDS simulation system to achieve closed-loop experimental verification.

6. A standardized simulation test method for a power grid security and stability control system based on the system described in any one of claims 1 to 4, characterized in that, Includes the following steps: Establish a power grid stability control system at the sending end and a power grid stability control system at the receiving end. Conduct closed-loop simulation tests on the power grid stability control system at the sending end and the power grid at the receiving end by simulating different power grid operating scenarios and combinations of abnormal events. The sending-end power grid stability control system and the receiving-end power grid stability control system are either a two-layer architecture or a multi-layer architecture; the two-layer architecture includes a master station stability control device and all types of execution station stability control devices, and the multi-layer architecture includes a master station stability control device, a substation stability control device, and all types of execution station stability control devices; In the sending-end power grid stability control system and the receiving-end power grid stability control system, multiple execution station stability control devices of the same type are replaced by one execution station stability control device of the same type.

7. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that, When the computer program is loaded into the processor, it implements the standardized simulation test method for the power grid security and stability control system according to claim 6.

8. A computer-readable storage medium storing a computer program, characterized in that, When the computer program is executed by the processor, it implements the standardized simulation test method for the power grid security and stability control system according to claim 6.

Citation Information

Patent Citations

  • Safety and stability control system and test method thereof

    CN115840436A

  • Standardized stability control system test platform and application method thereof

    CN114995332A

  • Strategy table configuration method based on standardized safety and stability control device

    CN115296407A