An electric-ammonia-electric system for large-scale long-period energy storage and rapid peak shaving
By combining water electrolysis to produce hydrogen and synthesize ammonia with a gas turbine and a steam Rankine cycle, the electric-ammonia-electricity system solves the problem of long-term storage and peak shaving of renewable energy, achieves efficient energy conversion and storage, reduces transportation and storage costs, and improves the system's flexibility and stability.
Patent Information
- Application Number
- CN202410175123.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-07
- Publication Date
- 2026-11-24
- Estimated Expiration
- 2044-02-07
AI Technical Summary
How to achieve large-scale, long-term storage of renewable energy, smooth out power generation load fluctuations caused by randomness and instability, and solve the challenges of H₂ transportation and storage.
The system employs a water electrolysis hydrogen production and ammonia synthesis subsystem, a gas turbine subsystem, a steam Rankine cycle subsystem, and a parabolic trough solar collector subsystem. It produces hydrogen and synthesizes ammonia through water electrolysis and converts electrical energy into ammonia for energy storage. The gas turbine generates electricity and high-temperature flue gas by burning liquid ammonia to drive the gas turbine. Combined with the steam Rankine cycle subsystem, it generates power. The parabolic trough solar collector provides thermal energy to support the Rankine cycle.
It enables large-scale, long-term storage and rapid peak shaving of renewable energy, smooths out power fluctuations, provides efficient energy conversion and storage, reduces transportation and storage costs, and improves the decoupling flexibility and operational stability of the system.
Smart Images

Figure CN118049314B_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of synthetic ammonia, and more particularly to an electro-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving. Background Technology
[0002] To reduce reliance on traditional fossil fuels, some regions have begun developing green energy sources such as wind and solar power. However, the randomness and instability of wind and solar resources lead to significant fluctuations in their power generation load. This necessitates the development of large-scale, inter-day and even inter-seasonal energy storage systems to mitigate these fluctuations and increase their share in the energy system. Furthermore, it requires the participation of thermal power generating units for peak shaving.
[0003] Therefore, while striving to increase the penetration rate of fluctuating renewable energy sources such as wind and solar power in the energy system, it is necessary to support this with large-scale, long-term energy storage technologies and flexible and efficient peak-shaving measures to provide structural support for the new power system with a high proportion of renewable energy. Against this backdrop, mature electro-hydrogen production technology holds promise for solving the problem of large-scale storage of fluctuating renewable electricity. Due to its high calorific value and the fact that it only produces H2O after combustion or electrochemical conversion, H2 is widely considered an ideal fuel to replace fossil fuels.
[0004] However, H2 has some problems that cannot be ignored in its use. H2 not only has a low boiling point (-253℃), but also a low volumetric energy density (10.8 kJ·L). -1 H2 has a pressure of 0.1 MPa and is extremely easy to diffuse, as well as being flammable and explosive. This results in extremely high technical requirements and costs for the transportation and storage of H2. Currently, due to the lack of H2 transportation and storage infrastructure, H2 is still far from meeting the actual needs in terms of large-scale use and long-term storage.
[0005] Therefore, how to store renewable energy over a long period of time on a large scale has become an urgent problem to be solved. Summary of the Invention
[0006] This application aims to at least partially address one of the technical problems in the related art.
[0007] Therefore, the first objective of this application is to propose an electric-ammonia-electric system for large-scale, long-term energy storage and rapid peak shaving, so as to realize large-scale, long-term storage of renewable energy, while smoothing out the volatility of renewable electricity caused by randomness and instability.
[0008] The second objective of this application is to propose a control method for an electric-ammonia-electric system for large-scale, long-cycle energy storage and rapid peak shaving.
[0009] To achieve the above objectives, the first aspect of this application proposes an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving, including a water electrolysis hydrogen production and ammonia synthesis subsystem, a gas turbine subsystem, a steam Rankine cycle subsystem, and a trough solar collector subsystem.
[0010] The water electrolysis hydrogen production and ammonia synthesis subsystem includes a first hot water storage tank, an alkaline electrolyzer, a second hot water storage tank, a proton exchange membrane electrolyzer, a hydrogen storage tank, an air separation device, an oxygen storage tank, an ammonia synthesis device, an ammonia upgrading and refrigeration device, and a liquid ammonia storage tank; the alkaline electrolyzer and the proton exchange membrane electrolyzer are used for water electrolysis hydrogen production;
[0011] The gas turbine subsystem includes a compressor, a combustion chamber, a gas turbine, and a first generator; the compressor is connected to the gas turbine through the combustion chamber; the compressor, the gas turbine, and the first generator are coaxially connected, the combustion chamber is connected to the liquid ammonia storage tank, and the first generator is used to produce first electrical energy;
[0012] The parabolic trough solar collector subsystem includes a first solar collector, a first feedwater mixer, a second solar collector, and a second feedwater mixer; the outlet of the first solar collector is connected to the inlet of the first feedwater mixer; one outlet of the first feedwater mixer is connected to the inlet of the second solar collector; and the outlet of the second solar collector is connected to the inlet of the second feedwater mixer.
[0013] The steam Rankine cycle subsystem includes a high-pressure cylinder of a steam turbine, an intermediate-pressure cylinder of a steam turbine, a low-pressure cylinder of a steam turbine, a second generator, a feedwater heat exchanger, a condenser, a low-pressure feedwater pump, an intermediate-pressure feedwater pump, a high-pressure feedwater pump, a triple-pressure reheat waste heat boiler, and a third hot water storage tank; the triple-pressure reheat waste heat boiler is connected to the outlet of the gas turbine.
[0014] Furthermore, when the water electrolysis hydrogen production and ammonia synthesis subsystem is running, electrical energy is converted into ammonia for energy storage. The gas turbine subsystem does not generate electricity. At this time, the third heat energy generated by the ammonia synthesis unit due to the ammonia synthesis operation is provided to the steam Rankine cycle subsystem to drive the steam Rankine cycle subsystem to generate power.
[0015] When the gas turbine subsystem is generating electricity, the liquid ammonia in the liquid ammonia storage tank enters the combustion chamber of the gas turbine subsystem for combustion, generating high-temperature flue gas. This high-temperature flue gas drives the gas turbine to operate and obtain the first electrical energy. At the same time, the gas turbine exhaust gas is used to obtain the first thermal energy, which drives the steam Rankine cycle subsystem to generate power.
[0016] Furthermore, the electrolysis water to hydrogen ammonia synthesis subsystem generates a third heat energy during the ammonia synthesis operation and provides this third heat energy to the steam Rankine cycle subsystem.
[0017] Furthermore, the third hot water storage tank is used to store the hot water generated in the Rankine cycle. The third hot water storage tank is connected to the first hot water storage tank and the second hot water storage tank respectively, and the third hot water storage tank can supply hot water to the first hot water storage tank and the second hot water storage tank.
[0018] Furthermore, the proton exchange membrane electrolyzer and the alkaline electrolyzer are driven by green electricity; the air separation device is also driven by green electricity.
[0019] Furthermore, the alkaline electrolyzer includes an alkaline electrolyzer anode and an alkaline electrolyzer cathode, and the working fluid at the outlet of the alkaline electrolyzer anode and the alkaline electrolyzer cathode is a mixture of steam and water;
[0020] The electrolysis of water to produce hydrogen and synthesize ammonia subsystem further includes a first steam-water separator and a second steam-water separator, which are used to separate the steam-water mixture for storing the hydrogen and oxygen produced in the electrolysis of water to produce hydrogen.
[0021] To achieve the above objectives, a second aspect of this application proposes a control method for an electric-ammonia-electric system for large-scale, long-cycle energy storage and rapid peak shaving, applicable to the aforementioned system, comprising:
[0022] When the water electrolysis hydrogen production and ammonia synthesis subsystem is running, it converts electrical energy into ammonia for energy storage. The gas turbine subsystem does not generate electricity. At this time, the third heat energy generated by the ammonia synthesis unit due to the ammonia synthesis operation is provided to the steam Rankine cycle subsystem to drive the steam Rankine cycle subsystem to generate power.
[0023] When the gas turbine subsystem is generating electricity, the liquid ammonia in the liquid ammonia storage tank enters the combustion chamber of the gas turbine subsystem for combustion, generating high-temperature flue gas. This high-temperature flue gas drives the gas turbine to operate and obtain the first electrical energy. At the same time, the gas turbine exhaust gas is used to obtain the first thermal energy, which drives the steam Rankine cycle subsystem to generate power.
[0024] Furthermore, when the gas turbine subsystem is operating to generate electricity, the trough solar collector subsystem works in conjunction with the gas turbine subsystem to provide the steam Rankine cycle subsystem with first and second thermal energy.
[0025] Furthermore, hydrogen is produced based on water electrolysis technology, and nitrogen is produced based on the air separation device.
[0026] Based on the aforementioned ammonia synthesis apparatus, ammonia is produced by using hydrogen and nitrogen as raw materials to synthesize ammonia.
[0027] The ammonia gas is liquefied using the ammonia upgrading and refrigeration device to obtain liquid ammonia, which is then stored in the liquid ammonia storage tank.
[0028] Furthermore, the third source of heat energy generated during the ammonia synthesis process is obtained;
[0029] The steam Rankine cycle subsystem generates power based on the third thermal energy.
[0030] This application provides an electricity-ammonia-electricity system for large-scale, long-term energy storage and rapid peak shaving. It utilizes an electrolysis-hydrogen-ammonia synthesis subsystem to produce hydrogen through water electrolysis and then liquid ammonia through ammonia synthesis technology, converting electrical energy into chemical energy (ammonia). This achieves long-term storage of green electricity and rational hydrogen storage. A gas turbine subsystem generates a large amount of primary electrical energy and high-temperature flue gas by burning liquid ammonia. The high-temperature flue gas drives the gas turbine to generate electricity. The primary heat energy generated by the gas turbine's exhaust can then be used to promote the steam Rankine cycle subsystem's power generation. Simultaneously, a parabolic trough solar collector subsystem can also provide the necessary secondary heat energy to the steam Rankine cycle subsystem. The operating state of the gas turbine can be adjusted according to actual operating conditions, thereby mitigating the fluctuations in renewable electricity caused by randomness and instability.
[0031] Additional aspects and advantages of this application will be set forth in part in the description which follows, and in part will be obvious from the description, or may be learned by practice of this application. Attached Figure Description
[0032] The above and / or additional aspects and advantages of this application will become apparent and readily understood from the following description of the embodiments taken in conjunction with the accompanying drawings, wherein:
[0033] Figure 1 This is a schematic diagram of the structure of an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving in an embodiment of this application.
[0034] Figure 2 This is a schematic flowchart illustrating a control method for an electric-ammonia-electric system used for large-scale long-cycle energy storage and rapid peak shaving, according to an embodiment of this application.
[0035] Figure 3 This is a flowchart illustrating steps S201-S203 of a control method for an electric-ammonia-electric system used for large-scale long-cycle energy storage and rapid peak shaving, according to an embodiment of this application.
[0036] Explanation of reference numerals in the attached figures:
[0037] 101. First hot water storage tank; 102. Anode of alkaline electrolyzer; 103. Cathode of alkaline electrolyzer; 104. First steam-water separator; 105. Second steam-water separator; 106. Hydrogen mixer; 107. First mixer; 108. Second hot water storage tank; 109. Anode of proton exchange membrane electrolyzer; 110. Cathode of proton exchange membrane electrolyzer; 111. Third steam-water separator; 112. Fourth steam-water separator; 113. Second mixer; 114. Hydrogen storage tank; 115. Third mixer; 116. Air separation unit; 117. Fourth mixer; 118. Oxygen storage tank; 119. Ammonia synthesis unit; 120. Ammonia upgrading and refrigeration unit; 121. Liquid ammonia storage tank; 201. Compressor; 202. Combustion chamber; 203, Gas turbine; 204, First generator; 301, First heat exchanger assembly; 302, First-stage high-pressure economizer; 303, Second heat exchanger assembly; 304, Second-stage high-pressure economizer; 305, Third heat exchanger assembly; 306, High-pressure cylinder of steam turbine; 307, Intermediate-pressure cylinder of steam turbine; 308, Low-pressure cylinder of steam turbine; 309, Second generator; 310, Feedwater heat exchanger; 311, Condenser; 312, Low-pressure feedwater pump; 313, Intermediate-pressure feedwater pump; 314, High-pressure feedwater pump; 315, First solar collector; 316, First feedwater mixer; 317, Second solar collector; 318, Second feedwater mixer; 319, Three-pressure reheat waste heat boiler; 320, Third hot water storage tank. Detailed Implementation
[0038] The embodiments of this application are described in detail below. Examples of these embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary and intended to explain this application, and should not be construed as limiting this application.
[0039] An embodiment of this application of an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving is described below with reference to the accompanying drawings.
[0040] Figure 1 This is a schematic diagram of the structure of an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving provided in an embodiment of this application.
[0041] like Figure 1As shown, the system includes a water electrolysis hydrogen production and ammonia synthesis subsystem, a gas turbine subsystem, a steam Rankine cycle subsystem, and a trough solar collector subsystem. The water electrolysis hydrogen production and ammonia synthesis subsystem includes: a first hot water storage tank 101, an alkaline electrolyzer anode 102, an alkaline electrolyzer cathode 103, a first steam-water separator 104, a second steam-water separator 105, a hydrogen mixer 106, a first mixer 107, a second hot water storage tank 108, a proton exchange membrane electrolyzer anode 109, a proton exchange membrane electrolyzer cathode 110, a third steam-water separator 111, a fourth steam-water separator 112, a second mixer 113, a hydrogen storage tank 114, a third mixer 115, an air separator 116, a fourth mixer 117, an oxygen storage tank 118, an ammonia synthesis unit 119, an ammonia upgrading and refrigeration unit 120, and a liquid ammonia storage tank 121.
[0042] Specifically, the outlet of the first hot water storage tank 101 is connected to the inlet of the anode 102 of the alkaline electrolyzer; the outlet of the anode 102 of the alkaline electrolyzer is connected to the inlet of the first steam-water separator 104; the first outlet of the first steam-water separator 104 is connected to the first inlet of the fourth mixer 117; the outlet of the fourth mixer 117 is connected to the inlet of the oxygen storage tank 118; the outlet of the cathode 103 of the alkaline electrolyzer is connected to the inlet of the second steam-water separator 105; the first outlet of the second steam-water separator 105 is connected to the first inlet of the hydrogen mixer 106; the outlet of the hydrogen mixer 106 is connected to the inlet of the hydrogen storage tank 114; and the outlet of the hydrogen storage tank 114 is connected to the first inlet of the third mixer 115.
[0043] The outlet of the third mixer 115 is connected to the inlet of the ammonia synthesis unit 119; the outlet of the ammonia synthesis unit 119 is connected to the inlet of the ammonia upgrading and refrigeration unit 120; the outlet of the ammonia upgrading and refrigeration unit 120 is connected to the inlet of the liquid ammonia storage tank 121; the outlet of the liquid ammonia storage tank 121 is connected to the second inlet of the combustion chamber 202 of the gas turbine subsystem; the second outlet of the second steam-water separator 105 is connected to the first inlet of the first mixer 107; the second outlet of the first steam-water separator 104 is connected to the second inlet of the first mixer 107; and the outlet of the first mixer 107 is connected to the second inlet of the first hot water storage tank 101.
[0044] The outlet of the second hot water storage tank 108 is connected to the inlet of the anode 109 of the proton exchange membrane electrolyzer; the outlet of the anode 109 of the proton exchange membrane electrolyzer is connected to the inlet of the fourth steam-water separator 112; the first outlet of the fourth steam-water separator 112 is connected to the second inlet of the fourth mixer 117; the second outlet of the fourth steam-water separator 112 is connected to the first inlet of the second mixer 113; and the outlet of the second mixer 113 is connected to the second inlet of the second hot water storage tank 108.
[0045] The outlet of the cathode 110 of the proton exchange membrane electrolyzer is connected to the inlet of the third steam-water separator 111; the first outlet of the third steam-water separator 111 is connected to the second inlet of the hydrogen mixer 106; the second outlet of the third steam-water separator 111 is connected to the second inlet of the second mixer 113; the first outlet of the air separator 116 is connected to the third inlet of the fourth mixer 117; the second outlet of the air separator 116 is connected to the second inlet of the third mixer 115; the first inlet of the first hot water storage tank 101 is connected to the first outlet of the hot water storage tank in the steam Rankine cycle subsystem; the first inlet of the second hot water storage tank 108 is connected to the second outlet of the hot water storage tank in the steam Rankine cycle subsystem; and the inlet of the air separator 116 is connected to an air duct.
[0046] The ammonia synthesis unit 119 of the water electrolysis hydrogen synthesis subsystem uses hydrogen generated by the alkaline electrolyzer and the proton exchange membrane electrolyzer, and nitrogen separated by the air separator 116 as raw materials for ammonia synthesis. The ammonia gas discharged from the ammonia synthesis unit 119 enters the ammonia upgrading and refrigeration unit 120. The liquid ammonia in the ammonia upgrading and refrigeration unit 120 enters the liquid ammonia storage tank 121.
[0047] In addition, the working fluid at the outlet of the anode 102 and cathode 103 of the alkaline electrolysis cell is a mixture of steam and water, which needs to be separated by the first steam-water separator 104 and the second steam-water separator 105 before it can be stored in the storage tank.
[0048] By electrolyzing hydrogen and synthesizing ammonia, electrical energy is ultimately converted into ammonia, enabling large-scale long-term energy storage. At this time, the gas turbine subsystem does not generate electricity, and the waste heat of the ammonia synthesis unit 119 can be directly supplied to the steam Rankine cycle subsystem, i.e., the third thermal energy, so that the steam Rankine cycle subsystem can do work and generate the second electrical energy.
[0049] In addition, the proton exchange membrane electrolyzer and the alkaline electrolyzer are driven by green electricity; the air separation device 116 is driven by green electricity.
[0050] The gas turbine subsystem includes a compressor 201, a combustion chamber 202, a gas turbine 203, and a first generator 204. The compressor 201 is connected to the gas turbine 203 via the combustion chamber 202. The compressor 201, gas turbine 203, and first generator 204 are coaxially connected, and the first generator 204 outputs electrical energy. Simultaneously, the gas turbine 203 generates a large amount of high-temperature flue gas during operation. This high-temperature flue gas provides energy for the steam Rankine cycle. Firstly, the high-temperature flue gas drives the gas turbine 203 to generate electricity. Secondly, within the steam Rankine cycle subsystem, the high-temperature flue gas provides a large amount of primary thermal energy to the heat exchange device for heat exchange.
[0051] When the water electrolysis hydrogen production and ammonia synthesis subsystem is running, electrical energy is converted into ammonia for energy storage. The gas turbine subsystem does not generate electricity. At this time, the third heat energy generated by the ammonia synthesis unit 119 during the ammonia synthesis operation is provided to the steam Rankine cycle subsystem to drive the steam Rankine cycle subsystem to generate power. When the gas turbine subsystem is generating electricity, the liquid ammonia in the liquid ammonia storage tank 121 enters the combustion chamber 202 of the gas turbine subsystem for combustion, generating high-temperature flue gas. The high-temperature flue gas drives the gas turbine 203 to operate and obtain the first electrical energy. At this time, the exhaust gas of the gas turbine 203 still has heat energy. Therefore, the waste heat in the exhaust gas of the gas turbine 203 can be utilized, that is, the first heat energy is obtained based on the exhaust gas of the gas turbine 203, and the steam Rankine cycle subsystem is driven to generate power based on the first heat energy.
[0052] The parabolic trough solar collector subsystem includes: a first solar collector 315, a first feedwater mixer 316, a second solar collector 317, and a second feedwater mixer 318; the outlet of the first solar collector 315 is connected to the inlet of the first feedwater mixer 316; one outlet of the first feedwater mixer 316 is connected to the inlet of the second solar collector 317; and the outlet of the second solar collector 317 is connected to the inlet of the second feedwater mixer 318.
[0053] The carrier of the parabolic trough solar collector subsystem is a triple-pressure reheat waste heat boiler 319; the inlet of the first solar collector 315 is connected to the second outlet of the high-pressure feedwater pump 314; the outlet of the first-stage high-pressure economizer 302 is connected to the inlet of the first feedwater mixer 316; the other outlet of the first feedwater mixer 316 is connected to the inlet of the second-stage high-pressure economizer 304; the outlet of the second-stage high-pressure economizer 304 is connected to the inlet of the second feedwater mixer 318; and the outlet of the second feedwater mixer 318 is connected to the inlet of the high-pressure evaporator in the third heat exchanger group 305.
[0054] The steam Rankine cycle subsystem includes: a first heat exchanger group 301, a first-stage high-pressure economizer 302, a second heat exchanger group 303, a second-stage high-pressure economizer 304, a third heat exchanger group 305, a high-pressure turbine cylinder 306, a medium-pressure turbine cylinder 307, a low-pressure turbine cylinder 308, a second generator 309, a feedwater heat exchanger 310, a condenser 311, a low-pressure feedwater pump 312, a medium-pressure feedwater pump 313, a high-pressure feedwater pump 314, a triple-pressure reheat waste heat boiler 319, and a third hot water storage tank 320. The first heat exchanger group 301 consists of a low-pressure economizer and a low-pressure evaporator; the second heat exchanger group 303 consists of a medium-pressure economizer, a medium-pressure evaporator, and a low-pressure superheater; and the third heat exchanger group 305 consists of a medium-pressure superheater, a high-pressure evaporator, a reheater, and a high-pressure superheater.
[0055] The outlet of the gas turbine 203 is connected to the flue gas inlet of the triple-pressure reheat waste heat boiler 319; the flue gas outlet of the triple-pressure reheat waste heat boiler 319 is connected to the atmosphere; the triple-pressure reheat waste heat boiler 319 is arranged from the flue gas inlet to the flue gas outlet as follows: the third heat exchanger group 305, the second-stage high-pressure economizer 304, the second heat exchanger group 303, the first-stage high-pressure economizer 302, and the first heat exchanger group 301.
[0056] The outlet of the intermediate-pressure superheater in the third heat exchanger group 305 is connected to the inlet of the high-pressure cylinder 306 of the steam turbine; the outlet of the high-pressure cylinder 306 of the steam turbine is connected to the inlet of the reheater in the third heat exchanger group 305; the outlet of the reheater in the third heat exchanger group 305 is connected to the inlet of the intermediate-pressure cylinder 307 of the steam turbine; the outlet of the intermediate-pressure superheater in the third heat exchanger group 305 is connected to the inlet of the reheater; the outlet of the low-pressure superheater in the second heat exchanger group 303 is connected to the inlet of the low-pressure cylinder 308 of the steam turbine; the outlet of the intermediate-pressure cylinder 307 of the steam turbine has two paths, one of which is connected to the inlet of the low-pressure cylinder 308 of the steam turbine, and the other of which is connected to the first inlet of the feedwater heat exchanger 310;
[0057] The second inlet of the feedwater heat exchanger 310 is connected to a normal temperature water pipe; the feedwater heat exchanger 310 includes a first outlet and a second outlet; the first outlet of the feedwater heat exchanger 310 is connected to the inlet of the low-pressure feedwater pump 312; the second outlet of the feedwater heat exchanger 310 is connected to the inlet of the third hot water storage tank 320; the first outlet of the third hot water storage tank 320 is connected to the first inlet of the first hot water storage tank 101 of the water electrolysis hydrogen production and ammonia synthesis subsystem; the second outlet of the third hot water storage tank 320 is connected to the first inlet of the second hot water storage tank 108 of the water electrolysis hydrogen production and ammonia synthesis subsystem.
[0058] The outlet of the low-pressure cylinder 308 of the steam turbine is connected to the inlet of the condenser 311; the outlet of the condenser 311 is connected to the inlet of the low-pressure feedwater pump 312; the outlet of the low-pressure feedwater pump 312 is connected to the inlet of the low-pressure economizer of the first heat exchanger group 301; the high-pressure cylinder 306, the intermediate-pressure cylinder 307, the low-pressure cylinder 308 of the steam turbine, and the second generator 309 are coaxially connected, and the second generator 309 provides electrical output.
[0059] The second outlet of the low-pressure economizer in the first heat exchanger group 301 has two paths, one of which is connected to the inlet of the high-pressure feedwater pump 314, and the other is connected to the inlet of the medium-pressure feedwater pump 313; the outlet of the high-pressure feedwater pump 314 has two paths; the first outlet of the high-pressure feedwater pump 314 is connected to the inlet of the first-stage high-pressure economizer 302; the outlet of the medium-pressure feedwater pump 313 is connected to the inlet of the medium-pressure economizer in the second heat exchanger group 303.
[0060] In the third heat exchanger group 305, the outlet of the high-pressure evaporator is connected to the inlet of the high-pressure superheater; the inlet of the medium-pressure superheater in the third heat exchanger group 305 is connected to the outlet of the medium-pressure evaporator in the second heat exchanger group 303; the outlet of the medium-pressure economizer in the second heat exchanger group 303 is connected to the inlet of the medium-pressure evaporator; the inlet of the low-pressure superheater in the second heat exchanger group 303 is connected to one of the outlets of the low-pressure evaporator in the first heat exchanger group 301; and the first outlet of the low-pressure economizer in the first heat exchanger group 301 is connected to the inlet of the low-pressure evaporator.
[0061] With the above configuration, the steam Rankine cycle subsystem can generate power through the synergistic action of the first, second, and third thermal energies. When the water electrolysis hydrogen production and ammonia synthesis subsystem is running, electrical energy is converted into ammonia for energy storage, and the gas turbine subsystem does not generate power. At this time, the third thermal energy generated by the ammonia synthesis unit 119 during ammonia synthesis is provided to the steam Rankine cycle subsystem to drive it to generate power. When the gas turbine subsystem is generating power, the liquid ammonia in the liquid ammonia storage tank 121 enters the combustion chamber 202 of the gas turbine subsystem for combustion, generating high-temperature flue gas. This high-temperature flue gas drives the gas turbine 203 to operate, obtaining the first electrical energy. Simultaneously, the first thermal energy is obtained from the exhaust gas of the gas turbine 203, which drives the steam Rankine cycle subsystem to generate power.
[0062] During the Rankine cycle, the steam Rankine cycle subsystem also generates hot water, which is then supplied to the water electrolysis for hydrogen production and ammonia synthesis subsystem, enabling the latter to produce hydrogen through water electrolysis. Specifically, the hot water required for the proton exchange membrane electrolyzer in the water electrolysis for hydrogen production and ammonia synthesis subsystem can be obtained by heating the exhaust steam from the intermediate-pressure cylinder 307 of the turbine in the steam Rankine cycle subsystem; similarly, the hot water required for the alkaline electrolyzer can also be obtained by partially heating the exhaust steam from the intermediate-pressure cylinder 307 of the turbine in the steam Rankine cycle subsystem.
[0063] Specifically, when the system operates at a certain solar radiation intensity, the water supply at the outlet of the high-pressure water pump 314 is divided into two lines. In one line, the water supply from the outlet of the high-pressure water pump 314 enters the first solar collector 315 to absorb solar thermal energy. When the water supply temperature at the outlet of the first solar collector 315 is the same as the water supply temperature at the outlet of the first-stage high-pressure economizer 302, the water supply from the outlet of the first solar collector 315 and the water supply from the outlet of the first-stage high-pressure economizer 302 enter the first water mixer 316 for mixing. The water supply at the outlet of the first water mixer 316 is divided into two lines. In one line, the water supply from the outlet of the first water mixer 316 enters the second solar collector 317 to absorb solar thermal energy.
[0064] When renewable energy generation is insufficient or the power grid is at its peak, this embodiment can convert stored chemical energy into electrical energy to participate in grid peak shaving. At this time, the liquid ammonia in the liquid ammonia storage tank 121 enters the combustion chamber 202 for combustion. The high-temperature flue gas generated by combustion first enters the gas turbine 203 to drive the gas turbine 203 to do work. Then, the exhaust gas of the gas turbine 203 enters the triple-pressure reheat waste heat boiler 319 of the steam Rankine cycle subsystem to provide the first heat energy for the triple-pressure reheat waste heat boiler 319, driving the steam Rankine cycle subsystem to do work and generate electricity.
[0065] In this embodiment, hydrogen generated by the alkaline electrolyzer and proton exchange membrane electrolyzer, and nitrogen generated by the air separator 116, are used as raw materials for the ammonia synthesis unit 119. The high-temperature flue gas generated by the combustion of liquid ammonia in the liquid ammonia storage tank 121 first drives the gas turbine 203 to generate electricity. Subsequently, the exhaust gas from the gas turbine 203 enters the triple-pressure reheat waste heat boiler 319 to drive the steam Rankine cycle. The hot water generated by the steam Rankine cycle subsystem can be directly fed into the hot water storage tanks before the anode 102 of the alkaline electrolyzer and before the anode 109 of the proton exchange membrane electrolyzer, respectively. Synthesizing ammonia from fluctuating renewable electricity can achieve large-scale, long-cycle energy storage, smoothing out the fluctuations caused by the randomness and instability of renewable electricity. At the same time, liquid ammonia can be used as an alternative fuel to drive the combined cycle system to convert the energy stored in ammonia into electrical energy, achieving efficient energy release and rapid peak shaving. In addition to liquid ammonia storage tank 121, multiple hot water storage tanks were also installed, improving the system's decoupling flexibility and operational stability. Furthermore, utilizing the system's low-temperature waste heat to heat the electrolytic reactor feedwater significantly reduces the reactor's energy consumption. Therefore, this system possesses efficient, large-capacity energy storage and rapid peak-shaving capabilities, improving upon the current situation where peak-shaving is achieved through thermal power plants.
[0066] To achieve the above embodiments, this application also proposes a control method for an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving.
[0067] Figure 2 This is a schematic flowchart illustrating a control method for an electric-ammonia-electric system used for large-scale long-cycle energy storage and rapid peak shaving, provided in an embodiment of this application.
[0068] like Figure 2 As shown, the method includes:
[0069] S101. When the water electrolysis hydrogen production and ammonia synthesis subsystem is running, electrical energy is converted into ammonia for energy storage. The gas turbine subsystem does not generate electricity. At this time, the third heat energy generated by the ammonia synthesis unit due to the ammonia synthesis operation is provided to the steam Rankine cycle subsystem to drive the steam Rankine cycle subsystem to generate power.
[0070] S102. When the gas turbine subsystem is generating electricity, the liquid ammonia in the liquid ammonia storage tank enters the combustion chamber of the gas turbine subsystem for combustion, generating high-temperature flue gas. The gas turbine is driven by the high-temperature flue gas to obtain the first electrical energy. At the same time, the gas turbine exhaust gas is used to obtain the first thermal energy, which is used to drive the steam Rankine cycle subsystem to generate power.
[0071] In one embodiment of this example, when the gas turbine subsystem is generating electricity, the trough solar collector subsystem works in conjunction with the gas turbine subsystem to provide first and second thermal energy to the steam Rankine cycle subsystem.
[0072] In one embodiment of this example, refer to Figure 3 The method also includes:
[0073] S201. Hydrogen production based on water electrolysis technology and nitrogen production based on an air separation device;
[0074] S202. Based on the ammonia synthesis unit, ammonia is produced by synthesizing ammonia using hydrogen and nitrogen as raw materials.
[0075] S203. Based on the ammonia upgrading and refrigeration device, ammonia gas is liquefied to obtain liquid ammonia, and the liquid ammonia is stored in a liquid ammonia storage tank.
[0076] In one embodiment of this method, the method further includes: acquiring the third thermal energy generated during the ammonia synthesis operation, and using the third thermal energy to drive the steam Rankine cycle subsystem to generate power.
[0077] It should be noted that the foregoing explanation of the embodiment of the electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving also applies to the control method of the electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving in this embodiment, and will not be repeated here.
[0078] Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Any changes, modifications, substitutions and variations made to the above embodiments by those skilled in the art are within the protection scope of the present invention.
Claims
1. An electric-ammonia-electric system for large-scale, long-cycle energy storage and rapid peak shaving, characterized in that, It includes a subsystem for electrolysis of water to produce hydrogen and synthesize ammonia, a gas turbine subsystem, a steam Rankine cycle subsystem, and a parabolic trough solar collector subsystem; The electrolysis water to hydrogen and ammonia synthesis subsystem includes a first hot water storage tank (101), an alkaline electrolyzer, a hydrogen mixer (106), a second hot water storage tank (108), a proton exchange membrane electrolyzer, a hydrogen storage tank (114), an air separator (116), a fourth mixer (117), an oxygen storage tank (118), an ammonia synthesis unit (119), an ammonia upgrading and refrigeration unit (120), and a liquid ammonia storage tank (121). The first hot water storage tank (101) and the alkaline electrolyzer... The alkaline electrolyzer and the proton exchange membrane electrolyzer are connected to the second hot water storage tank (108), the hydrogen mixer (106) is connected to the hydrogen storage tank (114), the fourth mixer (117) is connected to the oxygen storage tank (118), and the air separation device (116) is connected to the fourth mixer (117). The alkaline electrolyzer and the proton exchange membrane electrolyzer are used to electrolyze water to produce hydrogen, and the air separation device is used to separate nitrogen from the air. The gas turbine subsystem includes a compressor (201), a combustion chamber (202), a gas turbine (203), and a first generator (204); the compressor (201) is connected to the gas turbine (203) through the combustion chamber (202); the compressor (201), the gas turbine (203), and the first generator (204) are coaxially connected; the combustion chamber (202) is connected to the liquid ammonia storage tank (121); and the first generator (204) is used to produce first electrical energy. The parabolic trough solar collector subsystem includes a first solar collector (315), a first feedwater mixer (316), a second solar collector (317), and a second feedwater mixer (318); the outlet of the first solar collector (315) is connected to the inlet of the first feedwater mixer (316); one outlet of the first feedwater mixer (316) is connected to the inlet of the second solar collector (317); the outlet of the second solar collector (317) is connected to the inlet of the second feedwater mixer (318); The steam Rankine cycle subsystem includes a high-pressure cylinder (306) of a steam turbine, an intermediate-pressure cylinder (307) of a steam turbine, a low-pressure cylinder (308) of a steam turbine, a second generator (309), a feedwater heat exchanger (310), a condenser (311), a low-pressure feedwater pump (312), an intermediate-pressure feedwater pump (313), a high-pressure feedwater pump (314), a triple-pressure reheat waste heat boiler (319), and a third hot water storage tank (320); the triple-pressure reheat waste heat boiler (319) is connected to the outlet of the gas turbine (203).
2. The electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 1, characterized in that, The electrolysis water to hydrogen synthesis ammonia subsystem also generates a third heat energy during the ammonia synthesis operation, and provides the third heat energy to the steam Rankine cycle subsystem.
3. The electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 2, characterized in that, When the water electrolysis hydrogen production and ammonia synthesis subsystem is running, it converts electrical energy into ammonia for energy storage. The gas turbine subsystem does not generate electricity. At this time, the ammonia synthesis unit (119) provides the third heat energy generated by the ammonia synthesis operation to the steam Rankine cycle subsystem, driving the steam Rankine cycle subsystem to generate power. When the gas turbine subsystem is generating electricity, the liquid ammonia in the liquid ammonia storage tank (121) enters the combustion chamber (202) of the gas turbine subsystem for combustion, generating high-temperature flue gas. The gas turbine (203) is driven to operate based on the high-temperature flue gas to obtain the first electrical energy. At the same time, the first thermal energy is obtained based on the exhaust gas of the gas turbine (203), and the steam Rankine cycle subsystem is driven to generate power based on the first thermal energy.
4. The electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 1, characterized in that, The third hot water storage tank (320) is used to store the hot water generated in the Rankine cycle. The third hot water storage tank (320) is connected to the first hot water storage tank (101) and the second hot water storage tank (108) respectively. The third hot water storage tank (320) can deliver hot water to the first hot water storage tank (101) and the second hot water storage tank (108).
5. The electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 1, characterized in that, The proton exchange membrane electrolyzer and the alkaline electrolyzer are driven by green electricity; the air separation device (116) is driven by green electricity.
6. The electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 1, characterized in that, The alkaline electrolytic cell includes an alkaline electrolytic cell anode (102) and an alkaline electrolytic cell cathode (103), and the working fluid at the outlet of the alkaline electrolytic cell anode (102) and the alkaline electrolytic cell cathode (103) is a mixture of steam and water; The electrolysis water to hydrogen and ammonia synthesis subsystem further includes a first steam-water separator (104) and a second steam-water separator (105), which are used to separate the steam-water mixture for storing the hydrogen and oxygen produced in the electrolysis water to hydrogen production technology.
7. A control method for an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving, applied to the system according to any one of claims 1-6, characterized in that, include: When the water electrolysis hydrogen production and ammonia synthesis subsystem is running, it converts electrical energy into ammonia for energy storage. The gas turbine subsystem does not generate electricity. At this time, the third heat energy generated by the ammonia synthesis unit due to the ammonia synthesis operation is provided to the steam Rankine cycle subsystem to drive the steam Rankine cycle subsystem to generate power. When the gas turbine subsystem is generating electricity, the liquid ammonia in the liquid ammonia storage tank enters the combustion chamber of the gas turbine subsystem for combustion, generating high-temperature flue gas. This high-temperature flue gas drives the gas turbine to operate and obtain the first electrical energy. At the same time, the gas turbine exhaust gas is used to obtain the first thermal energy, which drives the steam Rankine cycle subsystem to generate power.
8. A control method for an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 7, characterized in that, When the gas turbine subsystem is generating electricity, the parabolic trough solar collector subsystem works in conjunction with the gas turbine subsystem to provide the steam Rankine cycle subsystem with first and second thermal energy.
9. A control method for an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 7, characterized in that, Also includes: Hydrogen is produced using water electrolysis technology, and nitrogen is produced using the air separation device. Based on the aforementioned ammonia synthesis apparatus, ammonia is produced by using hydrogen and nitrogen as raw materials to synthesize ammonia. The ammonia gas is liquefied using the ammonia upgrading and refrigeration device to obtain liquid ammonia, which is then stored in the liquid ammonia storage tank.
10. A control method for an electric-ammonia-electric system for large-scale long-cycle energy storage and rapid peak shaving according to claim 9, characterized in that, Also includes: To obtain the third heat energy generated during the ammonia synthesis process; The third thermal energy drives the steam Rankine cycle subsystem to generate power.
Citation Information
Patent Citations
Multi-generation system based on solar energy and biomass energy
CN113340008A
Combined cycle combined cooling heating and power system integrating fuel cell and solar energy
CN115000454A